CN205973541U - Tower crane is with electronic introduction device that hangs, breaks off relations certainly - Google Patents

Tower crane is with electronic introduction device that hangs, breaks off relations certainly Download PDF

Info

Publication number
CN205973541U
CN205973541U CN201620994494.4U CN201620994494U CN205973541U CN 205973541 U CN205973541 U CN 205973541U CN 201620994494 U CN201620994494 U CN 201620994494U CN 205973541 U CN205973541 U CN 205973541U
Authority
CN
China
Prior art keywords
introduction
rope
rear end
breaks
relations
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620994494.4U
Other languages
Chinese (zh)
Inventor
贺全
田欢
李波
才冰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FUSHUN YONGMAO CONSTRUCTION MACHINERY Co Ltd
Original Assignee
FUSHUN YONGMAO CONSTRUCTION MACHINERY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FUSHUN YONGMAO CONSTRUCTION MACHINERY Co Ltd filed Critical FUSHUN YONGMAO CONSTRUCTION MACHINERY Co Ltd
Priority to CN201620994494.4U priority Critical patent/CN205973541U/en
Application granted granted Critical
Publication of CN205973541U publication Critical patent/CN205973541U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Jib Cranes (AREA)

Abstract

The utility model discloses a tower crane is with electronic introduction device that hangs, breaks off relations certainly who uses when being applicable to the tower crane jacking. It installs the reel mechanism in introduction roof beam rear end including connecting in the introduction roof beam of undersetting, installs the walking wheel carrier on introduction roof beam last quarter orbital plane, installs the guide pulley in introduction roof beam front end and rear end, and rope and back rope before haulage cable is divided into, preceding rope are drawn from reel mechanism upper portion, through rear end guide pulley and the front end guide pulley on introduction roof beam upper portion, and the fixed wheel carrier front end of being expert at, restrict and follow the reel mechanism lower part and draw in the back, the snap -on wheel carrier rear end of being expert at. Special design's board hook and hoist can hoist the direct ground of following of standard festival to introducing liang chu, use manpower sparingly. The utility model discloses simple structure, operation maintenance is convenient. The introduction and the dismantlement that make the standard festival convenient and fast more that becomes. Safe and reliable need not the manpower, and the introduction device can hang certainly, break off relations certainly, saves the jacking greatly and time of falling section operation, reduction intensity of labour.

Description

Derrick crane is with from suspension, from the electronic imported unit that breaks off relations
(One)Technical field
This utility model belongs to derrick crane auxiliary facility and in particular to a kind of electricity of large-scale column crane mast section Dynamic imported unit.
(Two)Background technology
At present, with the continuous development of national large nuclear-power, thermal power project, the performance requirement of large-scale derrick crane is got over Come higher, lead to the tower body sectional dimension of large-scale derrick crane increasing.The standard knot of domestic tower crane introduces form at present It mostly is artificial and pulls form, the shortcoming of this introduction of method is:1. it is unfavorable for construction under rugged environment;2. it is not suitable for Casual labourer's phase engineering;3. poor stability.Therefore, design a kind of new, automatic introduction of standard knot that is being applied to heavy in section size Device becomes urgent problem.
(Three)Content of the invention
The purpose of this utility model is to solve technical deficiency in terms of standard knot introduction for the current large-tonnage tower crane, provides one Plant version rationally, simple to operate, soon, the derrick crane that can save a large amount of manpowers is with from suspension, from unhook for jacking speed Electronic imported unit.
The technical scheme that this utility model is adopted is:Derrick crane is with from suspension, from the electronic imported unit tool that breaks off relations There is introduction beam, be arranged on the drum mechanism built introducing beam rear end, be arranged on the walking round frame introduced in beam lower edge orbital plane, be arranged on Introduce the leading block of beam front-end and back-end, haulage cable is divided into front rope and rear rope, front rope is drawn from drum mechanism built top, lead to Cross the rear end leading block introducing beam top and front end leading block, be fixed on walking round frame front end, restrict afterwards from drum mechanism built Portion draws, and is directly anchored to walking round frame rear end;The plate hook that rope rig connects is adapted with the short axle on suspender both sides, suspender Following steel wire rope sling connection standard section, the short axle the inner on suspender both sides may be stuck in walking round frame.Specially designed plate hook Standard knot directly can be lifted to introduction Liang Chu from ground with suspender.
This utility model compared with prior art, has the advantage that:
1. required size adjustment can be introduced according to standard knot and introduce beam length, have extensive versatility, it is easy to accomplish large-scale The seriation of tower crane imported unit.
2. electronic introduction mechanism is planetary reducer with cycloidal pin teeth, 2 revs/min of this reductor rotating speed(Speed is equivalent to 35mm/ s), it is extremely slow to introduce speed, introducing process more steady safety.Road wheel walking in a horizontal state, no skidding, it is to avoid walking Track and road wheel wear phenomenon, decrease to walking foot wheel abrasion.
3. imported unit is introduced wheel and directly can be introduced from side, easy to disassemble.
4. standard knot can directly be lifted to introducing Liang Chu by specially designed suspender from ground, can certainly be advanced into introduction beam Interior, convenient and swift, save manpower, greatly reduce supernumerary segment and the time of fall section, reduce labor intensity.
(Four)Brief description
Fig. 1 is the structural representation of flat-top tower crane imported unit;
Fig. 2 is the structural representation of movable arm type tower crane imported unit;
Fig. 3 is plate hook of the present utility model and suspender connection diagram;
Fig. 4 is that walking round frame of the present utility model introduces schematic diagram with suspender.
(Five)Specific embodiment
Flat-top tower crane imported unit will be introduced beam 1 by bearing pin and be connected with tower crane undersetting.Drum mechanism built 7 is arranged on draws Enter beam 1 end, drum mechanism built 7 draws the front rope of traction respectively and rear rope is fixed in walking round frame 4.
During lifting, rope rig 2 is bent around tower crane suspension hook, and rope rig 2 two ends are separately fixed on plate hook 3. Steel wire rope sling 6 one end is fixed on suspender 5, and the other end is fixed on standard knot.
After standard knot connects, suspender 5 and standard knot are put in walking round frame 4 by plate hook 3, and plate hook 3 passes through tower crane suspension hook Lifting departs from suspender 5.By drum mechanism built 7 rope traction walking round frame 4, so that standard knot is entered in tower crane stock, realize mark The introduction of quasi- section.
Movable arm type tower crane is longer due to introducing beam, needs to be connected imported unit with phase inversion next time by pull bar 8.It is introduced Process is identical with flat-top tower crane introducing process.
Tower crane fall section, the process removing standard knot is the inverse process introduced.

Claims (3)

1. a kind of derrick crane is with from suspension, from the electronic imported unit that breaks off relations, is characterized in that:It has introduction beam(1), install Introducing beam(1)The drum mechanism built of rear end(7), it is arranged on introduction beam(1)Walking round frame in lower edge orbital plane(4), it is arranged on Introduce beam(1)The leading block of front-end and back-end, haulage cable is divided into front rope and rear rope, and front rope is from drum mechanism built(7)Top Draw, by introducing beam(1)The rear end leading block on top and front end leading block, are fixed on walking round frame(4)Front end, restricts afterwards From drum mechanism built(7)Bottom is drawn, and is directly anchored to walking round frame(4)Rear end;Rope rig(2)The plate hook connecting(3)With Suspender(5)The short axle on both sides is adapted, the steel wire rope sling below suspender(6)Connection standard section, suspender(5)In the short axle on both sides End may be stuck in walking round frame(4)On.
2. derrick crane according to claim 1 is with from suspension, from the electronic imported unit that breaks off relations, is characterized in that:Pass through Bearing pin will introduce beam(1)It is connected with tower crane undersetting.
3. derrick crane according to claim 1 is with from suspension, from the electronic imported unit that breaks off relations, is characterized in that:To draw Enter device and pass through pull bar(8)It is connected with phase inversion next time.
CN201620994494.4U 2016-08-31 2016-08-31 Tower crane is with electronic introduction device that hangs, breaks off relations certainly Active CN205973541U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620994494.4U CN205973541U (en) 2016-08-31 2016-08-31 Tower crane is with electronic introduction device that hangs, breaks off relations certainly

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620994494.4U CN205973541U (en) 2016-08-31 2016-08-31 Tower crane is with electronic introduction device that hangs, breaks off relations certainly

Publications (1)

Publication Number Publication Date
CN205973541U true CN205973541U (en) 2017-02-22

Family

ID=58041763

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620994494.4U Active CN205973541U (en) 2016-08-31 2016-08-31 Tower crane is with electronic introduction device that hangs, breaks off relations certainly

Country Status (1)

Country Link
CN (1) CN205973541U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107055344A (en) * 2017-02-28 2017-08-18 南通庞源机械工程有限公司 One kind maintenance tower crane jacking pumping plant hanging method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107055344A (en) * 2017-02-28 2017-08-18 南通庞源机械工程有限公司 One kind maintenance tower crane jacking pumping plant hanging method

Similar Documents

Publication Publication Date Title
CN201458596U (en) Crane with self-dismounting device
CN207339088U (en) Transmission line of electricity straight line pole aerial earth wire overhauls stent
CN201559671U (en) Automatic decoupling device for mine car
CN103708360B (en) Swing arm tower crane, standard knot introduction system thereof and standard knot introduction method
CN103171975A (en) Method for transporting slope engineering material
CN205973541U (en) Tower crane is with electronic introduction device that hangs, breaks off relations certainly
CN202358850U (en) Light lift-type cantilever crane
CN213171204U (en) Construction equipment hoisting device
CN201183702Y (en) Novel silo hoisting device using movable pulley
CN204474191U (en) The jib body dumping mechanism of tower crane
CN202542743U (en) Auxiliary reeving mechanism for mounting tower crane
CN106809764A (en) Rack built-in device is carried and takes machine
CN202917897U (en) Cable hoisting horizontal pulley
CN203143964U (en) Device for quickly changing blast furnace air-tight box
CN104724615A (en) Penetrating and winding method of large-diameter variable-amplitude steel wire rope of large moving-arm type tower crane
CN201762053U (en) Simple automatic hoisting rod
CN205114823U (en) Supplementary instrument that lifts by crane that head sheave or leading wheel were used
CN201647851U (en) Multifunctional building crane
CN201105958Y (en) Rope holding carriage system of tower crane
CN204750193U (en) Automatic decoupling device device in sub -inclined shaft pittop
CN204173830U (en) Pumping plant travelling hoist
CN202131996U (en) Steel wire rope traction device of rotary drilling machine
CN207313007U (en) A kind of pulley arrangements form of conveying trolley used in inclined shaft trailer system
CN201473171U (en) Moving and lifting dual-purpose hanging device of cableway device
CN202785203U (en) Movable pulley hook head for vertical shaft sinking and hoisting

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant