CN103171975A - Method for transporting slope engineering material - Google Patents

Method for transporting slope engineering material Download PDF

Info

Publication number
CN103171975A
CN103171975A CN201310030607XA CN201310030607A CN103171975A CN 103171975 A CN103171975 A CN 103171975A CN 201310030607X A CN201310030607X A CN 201310030607XA CN 201310030607 A CN201310030607 A CN 201310030607A CN 103171975 A CN103171975 A CN 103171975A
Authority
CN
China
Prior art keywords
parts
rope
slope
collection dress
cableway
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310030607XA
Other languages
Chinese (zh)
Other versions
CN103171975B (en
Inventor
刘照朗
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGDONG ANYUAN MINING TECHNOLOGY SERVICE Co Ltd
Original Assignee
GUANGDONG ANYUAN MINING TECHNOLOGY SERVICE Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGDONG ANYUAN MINING TECHNOLOGY SERVICE Co Ltd filed Critical GUANGDONG ANYUAN MINING TECHNOLOGY SERVICE Co Ltd
Priority to CN201310030607.XA priority Critical patent/CN103171975B/en
Publication of CN103171975A publication Critical patent/CN103171975A/en
Application granted granted Critical
Publication of CN103171975B publication Critical patent/CN103171975B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention discloses a method for transporting a slope engineering material. Slope base materials are transported to any position of a slope through a wire cableway and a winding engine, which are randomly moved and portable.

Description

A kind of method of slope project material transportation
Technical field
The invention belongs to the Geotechnical Engineering field
Background technology
State of the art is at present: the slope project material transportation is limited by complex-terrain, there is no standardized equipment, generally adopts scaffold man-handling of materials method, tower crane method, crane method, slope track method etc., cut both ways, but convenient not enough with alerting ability; The objective of the invention is to adopt easy, the most practical method to carry out the side slope material transportation, realize saving and produce.
Summary of the invention
Material transport system of the present invention is comprised of 11 kinds of parts: 1. parts are acrochordal road, slope rope permanent seats, are anchored on firm ground; 2. parts are cableway rope (steel ropes), its interspersed parts top becket bridle 4., and 1. an end is fixed in parts, other end link (11); 4. parts are traversing carriages, are shifted by support, make the cableway rope be in different discharging line positions, fix with digonal link (rope) or other means after the support displacement; Parts (11) are hypochord road, slope rope regulating controls, and it is a cover combined member, the base anchoring, and function is to adapt to the support displacement and retractable and tensioner cableway rope; 6. parts are universal standard part pulley suspension hooks, and the pulley sleeve of its upper end hangs on the cableway rope, and lower end suspension hook link 7.; 7. parts are suspension gears, can be simple and easy ropes, also can make combined member, make length adjustable, to adapt to discharge heights different on side slope; 8. the parts 7. lower parts of hanging are simple and easy collection dress baskets (bag), are used for loaded material; 10. parts are twin drum winch, are positioned at bed material field, slope; 3. parts are leading sheaves, are hung on the traversing carriage of top, slope; 5. parts are to promote head rope (steel rope), and rope stretching is connected in rising edge or the pulley suspension hook lower end of collection dress basket after by track adjusting wheel, is used for promoting collection dress basket; 9. parts are to promote tail rope, and the direct-connected collection dress of rope stretching basket trailing edge is used for transferring collection dress basket; Winch rotates like this, can pull collection dress basket to move up and down along the cableway rope, realizes material transfer.
The Figure of description explanation:
Fig. 1 is the transport systems schematic diagram, and in figure, the mark symbolic significance is as follows:
1.---acrochordal road, slope rope permanent seat, 2.---cableway rope (steel rope), 3.---leading sheave,
4.---traversing carriage, 5.---promote head rope (steel rope), 6.---the pulley suspension hook,
7.---suspension gear, 8.---simple and easy collection dress basket (bag), 9.---promote tail rope (steel rope),
10.---twin drum winch, (11)---hypochord road, slope rope is regulated end device, (12)---side slope,

Claims (1)

1. the specific practice of a kind of method of slope project material transportation is:
Material transport system is comprised of 11 kinds of parts: 1. parts are acrochordal road, slope rope permanent seats, are anchored on firm ground; 2. parts are cableway rope (steel ropes), its interspersed parts top becket bridle 4., and 1. an end is fixed in parts, other end link (11); 4. parts are traversing carriages, are shifted by support, make the cableway rope be in different discharging line positions, fix with digonal link (rope) or other means after the support displacement; Parts (11) are hypochord road, slope rope regulating controls, and it is a cover combined member, the base anchoring, and function is to adapt to the support displacement and retractable and tensioner cableway rope; 6. parts are universal standard part pulley suspension hooks, and the pulley sleeve of its upper end hangs on the cableway rope, and lower end suspension hook link 7.; 7. parts are suspension gears, can be simple and easy ropes, also can make combined member, make length adjustable, to adapt to discharge heights different on side slope; 8. the parts 7. lower parts of hanging are simple and easy collection dress baskets (bag), are used for loaded material; 10. parts are twin drum winch, are positioned at bed material field, slope; 3. parts are leading sheaves, are hung on the traversing carriage of top, slope; 5. parts are to promote head rope (steel rope), and rope stretching is connected in rising edge or the pulley suspension hook lower end of collection dress basket after by track adjusting wheel, is used for promoting collection dress basket; 9. parts are to promote tail rope, and the direct-connected collection dress of rope stretching basket trailing edge is used for transferring collection dress basket; Winch rotates like this, can pull collection dress basket to move up and down along the cableway rope, realizes material transfer.
CN201310030607.XA 2013-01-17 2013-01-17 Method for transporting slope engineering material Expired - Fee Related CN103171975B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310030607.XA CN103171975B (en) 2013-01-17 2013-01-17 Method for transporting slope engineering material

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310030607.XA CN103171975B (en) 2013-01-17 2013-01-17 Method for transporting slope engineering material

Publications (2)

Publication Number Publication Date
CN103171975A true CN103171975A (en) 2013-06-26
CN103171975B CN103171975B (en) 2015-04-22

Family

ID=48632264

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310030607.XA Expired - Fee Related CN103171975B (en) 2013-01-17 2013-01-17 Method for transporting slope engineering material

Country Status (1)

Country Link
CN (1) CN103171975B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104707846A (en) * 2015-03-11 2015-06-17 广东安元矿业勘察设计有限公司 Method for solving urban refuse landfill through building material resource development
CN106184237A (en) * 2015-05-08 2016-12-07 中国石油化工股份有限公司天然气川气东送管道分公司 A kind of Light-duty Quick-installation cableway
CN108128589A (en) * 2017-12-27 2018-06-08 俞钟晓 A kind of bamboo shoots hillside fields carrier
CN108792675A (en) * 2018-06-28 2018-11-13 广东安元矿业勘察设计有限公司 The loading counterweight of opencut ramp automobile hoisting way and step method for arranging
CN110510527A (en) * 2019-08-01 2019-11-29 中国建筑土木建设有限公司 A kind of installation system and its construction method of high slope variable cross-section side slope prefabricated section
CN110775852A (en) * 2019-10-30 2020-02-11 徐州中能电力科技有限公司 Communication tower equipment hoisting method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB190613213A (en) * 1906-06-07 1907-06-07 William Pelham Bullivant Improvements in Overhead Ropeways, or Railways, and Gear for Hauling, or Traversing, and Raising and Lowering Loads.
GB269095A (en) * 1926-12-01 1927-04-14 George Alexander Main Improvements relating to ropeways
US3011653A (en) * 1955-11-21 1961-12-05 Larsen Botolv System for operating rail- or cablecrane carriages
JPH01285590A (en) * 1988-05-12 1989-11-16 Sadao Shimonaka Carrying device
JPH084307A (en) * 1994-06-16 1996-01-09 Shimizu Corp Ropeway system for horizontal transportation
CN201209090Y (en) * 2008-03-07 2009-03-18 中铁十三局集团有限公司 Ropeway cable crane using single machine traction and lifting at steep terrain
CN201494438U (en) * 2009-10-13 2010-06-02 中国石油天然气股份有限公司 Simple and fast installation cableway for maintenance and rush repair of mountain pipeline
CN102020206A (en) * 2010-12-17 2011-04-20 长江水利委员会长江勘测规划设计研究院 Ropeway transport system of long-span steep terrain wind power device
JP2011219226A (en) * 2010-04-09 2011-11-04 Sentan Gijutsu Kenkyusho:Kk Ropeway device

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB190613213A (en) * 1906-06-07 1907-06-07 William Pelham Bullivant Improvements in Overhead Ropeways, or Railways, and Gear for Hauling, or Traversing, and Raising and Lowering Loads.
GB269095A (en) * 1926-12-01 1927-04-14 George Alexander Main Improvements relating to ropeways
US3011653A (en) * 1955-11-21 1961-12-05 Larsen Botolv System for operating rail- or cablecrane carriages
JPH01285590A (en) * 1988-05-12 1989-11-16 Sadao Shimonaka Carrying device
JPH084307A (en) * 1994-06-16 1996-01-09 Shimizu Corp Ropeway system for horizontal transportation
CN201209090Y (en) * 2008-03-07 2009-03-18 中铁十三局集团有限公司 Ropeway cable crane using single machine traction and lifting at steep terrain
CN201494438U (en) * 2009-10-13 2010-06-02 中国石油天然气股份有限公司 Simple and fast installation cableway for maintenance and rush repair of mountain pipeline
JP2011219226A (en) * 2010-04-09 2011-11-04 Sentan Gijutsu Kenkyusho:Kk Ropeway device
CN102020206A (en) * 2010-12-17 2011-04-20 长江水利委员会长江勘测规划设计研究院 Ropeway transport system of long-span steep terrain wind power device

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104707846A (en) * 2015-03-11 2015-06-17 广东安元矿业勘察设计有限公司 Method for solving urban refuse landfill through building material resource development
CN106184237A (en) * 2015-05-08 2016-12-07 中国石油化工股份有限公司天然气川气东送管道分公司 A kind of Light-duty Quick-installation cableway
CN108128589A (en) * 2017-12-27 2018-06-08 俞钟晓 A kind of bamboo shoots hillside fields carrier
CN108128589B (en) * 2017-12-27 2019-12-31 奉化市中新阀门有限公司 Bamboo shoots sloping field carrier
CN108792675A (en) * 2018-06-28 2018-11-13 广东安元矿业勘察设计有限公司 The loading counterweight of opencut ramp automobile hoisting way and step method for arranging
CN110510527A (en) * 2019-08-01 2019-11-29 中国建筑土木建设有限公司 A kind of installation system and its construction method of high slope variable cross-section side slope prefabricated section
CN110775852A (en) * 2019-10-30 2020-02-11 徐州中能电力科技有限公司 Communication tower equipment hoisting method

Also Published As

Publication number Publication date
CN103171975B (en) 2015-04-22

Similar Documents

Publication Publication Date Title
CN103171975B (en) Method for transporting slope engineering material
CN205366908U (en) Self -discharging formula hoisting device
CN107500109A (en) A kind of overhead crane with electric hoists
CN108002229B (en) A kind of low clearance box culvert part loop wheel machine with turn over function
CN204098952U (en) A kind of coal mine roadway centre mounted type container handling equipment
CN203889011U (en) Material transporting device of drilling platform
CN204432946U (en) The transport of foundation pile and lifting device
CN204506935U (en) Mining cross-country traveling ability heavier load transport hutching
CN204186314U (en) For the induction system that drilling rod or sleeve pipe are carried
CN204038914U (en) A kind of mountain region logging sling cart
CN204474191U (en) The jib body dumping mechanism of tower crane
CN207241554U (en) The hanging bar beam carrier loader of abdomen and electric pole transport vehicle
CN204569122U (en) Building tower crane cargo hook gear
CN209908537U (en) A handling device for tunnel lining cutting platform truck rail
CN205527498U (en) Utilize pulley system's hoist and mount and conveyer
CN204847997U (en) Manual winch of adjustable height
CN201228193Y (en) Disjointed universal shaft guide conveying enclasping machine
CN203020135U (en) Special hanger for metal tubes and vehicle provided with hanger
CN203781713U (en) High slope support material transport device
CN206841277U (en) Lifting and delivery head base device for electric pole conveying
CN103072511B (en) Hanger for metal pipe and vehicle with hanger
CN202245807U (en) Lifting appliance for rear shaft of automobile
CN202429900U (en) Turnover pulley for coiled plate
CN201212004Y (en) Wheel center spreader
CN202107424U (en) Three-jaw sling

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 516211 Guangdong city of Huizhou province Huiyang aimn road 3 homes 2 block B room 1805

Applicant after: GUANGDONG ANYUAN MINING TECHNOLOGY SERVICE Co.,Ltd.

Address before: 516211 Guangdong city of Huizhou province Huiyang aimn road 3 homes 2 block B room 1805

Applicant before: GUANGDONG ANYUAN MINING TECHNOLOGY SERVICE Co.,Ltd.

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: GUANGDONG ANYUAN MINING TECHNOLOGY SERVICE CO., LTD. TO: GUANGDONG ANYUAN MINING SURVEY AND DESIGN CO., LTD.

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150422

Termination date: 20220117

CF01 Termination of patent right due to non-payment of annual fee