Utility model content
In order to solve at least one above-mentioned technical problem, the purpose of this utility model is that providing a kind of installs effect
Rate is high, cost of manufacture is low and can effectively ensure that the combination type integral wall of surface of wall quality.
In view of this, this utility model provides a kind of combination type integral wall, including: multiple panels, use
Combined wall panel is formed in mutual split;And fixed frame, described fixed frame is fixing with multiple described panels to be connected,
So that multiple described panels form described combined wall panel, and described fixed frame is fixed on described combined wall panel
A plate face on, and circumferentially disposed along described combined wall panel.
The combination type integral wall that this utility model provides, fixes multiple panel by arranging fixed frame, makes
In-site installation is transported in multiple panel splits again after becoming an entirety, then the assembled process of wallboard can be complete in factory
Become, so on the one hand avoid monolithic in-site installation of the prior art, considerably reduce field erected
Workload;On the other hand wallboard can be played a protective role by fixed mount, it is to avoid the damage of colliding with of wallboard corner,
Reduce the breakage rate of wallboard, and be easy to lifting and install, thus further increase installation effectiveness;Additionally,
The quality of wallboard can also be controlled, to improve the yields of product further by batch production centralized production.
As for hoisting process, can directly by rope hook on framework, it is also possible to preset hole position on framework, will rope
Rope is hooked in inside hole, is all capable of lifting.
It addition, the combination type integral wall in above-described embodiment of this utility model offer can also have as follows
Additional technical feature:
In technique scheme, described combination type integral wall also includes: connect securing member, described connection
Securing member sequentially passes through multiple described panel, so that multiple described panel is fixedly linked.
In any of the above-described technical scheme, described combination type integral wall includes multiple described connection securing member.
Specifically, described connection securing member is for drawing reinforcing bar, tensioning screw or threaded rod etc..
Connect the setting of securing member, on the basis of fixed frame is fixing, multiple panels are served further
Fastening effect so that be connected as a single entity between multiple panels, reduces and produces dislocation or bigger between panel
The probability in gap, further increases intensity and the surface quality of wallboard.Preferably, securing member is connected horizontal
Arranging, two ends are provided with fastening bolt and are fixed;Further, connect securing member and be provided with multiple, so that wall
Intensity and the surface quality at each position of plate all can be guaranteed.
In any of the above-described technical scheme, being provided with connector in described panel, described fixed frame is provided with connection
Hole, securing member is connected through described connecting hole with described connector, so that described panel is solid with described fixed frame
Fixed connection.
By securing member, panel is tightened together with fixed frame, fixed, and assembling is simple.Preferably,
One panel itself is provided with multiple connector, and multiple connectors are uniformly distributed, to guarantee the tight of panel and fixed frame
It is solidly connected.Specifically, securing member is bolt.
In any of the above-described technical scheme, described fixed frame is provided with the transfer hole matched with adaptor, tightly
Firmware connects girder steel, so that described combination type integral wall is with described through described transfer hole and described adaptor
Girder steel is fixing to be connected.
Make wallboard realize securing member with girder steel by adaptor and be connected fixing, it is to avoid the construction of Site Welding
Journey, further reduces field erected workload, improves installation effectiveness, accelerate project progress.Tool
Body ground, securing member is bolt.Further, combination type integral wall and adjacent upper strata or bottom wall panel it
Between, realize bolt also by adaptor and connect fixing, it is firm to connect, and install convenient.
In any of the above-described technical scheme, described combination type integral wall also includes: pre-buried pipeline, described pre-
Pipe laying road is arranged in described panel, is used for installing water power circuit.
By arranging pre-buried pipeline in panel so that the water power of wallboard arranges and also achieves factorial praluction,
In wallboard, offer the work progress of pipeline when avoiding in-site installation, thus further reduce in-site installation
Workload, further increase installation effectiveness.
In any of the above-described technical scheme, described combination type integral wall also includes: decorative layer, described decoration
Layer is arranged on described combined wall panel to deviate from the plate face of described fixed frame.
By arranging decorative layer so that the face finish of wallboard also achieves factorial praluction, it is to avoid existing
Technology deadlight carries out the work progress fitted up again after installing, thus also further increases installation effectiveness, enters
One step improves speed of application.
In any of the above-described technical scheme, described fixed frame is C-type steel framework.
Fixed frame uses C-type steel framework, and C-type steel is lighter than same size angle steel weight, and intensity is bigger.Specifically
Ground, the side plate of C-type steel framework is fixing with the plate face of panel to be connected, and this side plate is provided with and connector and spiral shell
The connecting hole that the securing members such as bolt match, relative another on the base plate adjacent with this side plate and/or with this side plate
Side plate is provided with the transfer hole matched with the securing member such as adaptor and bolt.Certainly, the technology of this area
Personnel should be appreciated that employing angle steel or other kinds of channel-section steel, also can realize the purpose of this utility model,
This will not enumerate, but these technical schemes are all without departing from design philosophy of the present utility model and objective, because of
This is also in protection domain of the present utility model.
It is understood that C-type steel is formed by steel plate bending, the height of its two side plates being oppositely arranged can
With equal, it is also possible to unequal.Preferably, the height fixing the side plate being connected with panel plate face is of a relatively high,
To increase the intensity of this side plate, and then increase the bonding strength of C-type steel framework and panel.Certainly, when separately
When offering transfer hole on side plate, it should also suitably increase its height, with ensure combination type integral wall with
Bonding strength between steel structure girder.
In any of the above-described technical scheme, in the groove of described C-type steel framework, it is provided with reinforcement.
Owing to fixed frame fixes whole wallboard, span is relatively large, therefore in the groove of C-type steel framework
Reinforcement is set, it is possible to be effectively improved the intensity of fixed frame, reduces the probability that fixed frame deforms, and then
Improve the intensity of combination type integral wall, improve the dependability of product.
In any of the above-described technical scheme, described panel is ALC panel.
ALC (Autoclaved Lighweight Concrete, ALC) sheet material has material
Gently, intensity is high, soundproof effect is good, the advantage of low cost, and has the heat insulation property of excellence, fire-resistant resistance to
The performances such as long property.Certainly, the panel of this programme is not limited to ALC sheet material, it would however also be possible to employ other materials
The lightweight panels of matter, will not enumerate at this, it is understood by those skilled in the art that these technology
Scheme is also in protection domain of the present utility model.
Additional aspect of the present utility model and advantage will become obvious in following description part, or by this
The practice of utility model is recognized.
Detailed description of the invention
In order to be more clearly understood that above-mentioned purpose of the present utility model, feature and advantage, below in conjunction with attached
This utility model is further described in detail by figure and detailed description of the invention.It should be noted that not
In the case of conflict, the feature in embodiments herein and embodiment can be mutually combined.
Elaborate a lot of detail in the following description so that fully understanding this utility model, but,
This utility model can be implemented to use other to be different from other modes described here, therefore, and this practicality
Novel protection domain is not limited by following public specific embodiment.
Describe according to the combination type integral wall described in some embodiments of this utility model referring to Fig. 1 to Fig. 4
Plate.
As shown in Figures 1 to 4, the combination type integral wall that this utility model provides, including: multiple panels
10 and fixed frame 20.
Specifically, multiple panels 10 form combined wall panel for mutual split;Fixed frame 20 with multiple
Plate 10 is fixing to be connected, so that multiple panel 10 forms combined wall panel, and fixed frame 20 is fixed on combination
On one plate face of formula wallboard, and circumferentially disposed along combined wall panel.
The combination type integral wall that this utility model provides, fixes multiple panel by arranging fixed frame 20
10, make the split of multiple panel 10 after becoming an entirety, transport to in-site installation again, then the assembled process of wallboard exists
Factory can complete, and so on the one hand avoids monolithic in-site installation of the prior art, considerably reduces
Field erected workload;On the other hand wallboard can be played a protective role by fixed mount, it is to avoid wallboard corner
Damage of colliding with, reduce the breakage rate of wallboard, and be easy to lifting and install, thus further increase peace
Dress efficiency;Additionally it is possible to controlled the quality of wallboard by batch production centralized production, to improve further
The yields of product.
As for hoisting process, can directly by rope hook on framework 20, it is also possible on framework 20 preset
Kong Wei, by rope hook inside hole, is all capable of lifting.
In an embodiment of the present utility model, as it is shown in figure 1, combination type integral wall also includes: even
Connect securing member 30, connect securing member 30 and sequentially pass through multiple panel 10, so that phase fixed by multiple panel 10
Even.
Further, as it is shown in figure 1, combination type integral wall includes multiple connection securing member 30.
Specifically, securing member 30 is connected for drawing reinforcing bar, tensioning screw or threaded rod etc..
In the above-described embodiments, connect the setting of securing member 30, on the basis of fixed frame 20 is fixing, right
Multiple panels 10 serve further fastening effect so that be connected as a single entity between multiple panels 10,
Reduce between panel 10 produce dislocation or the probability in bigger gap, further increase wallboard intensity and
Surface quality.Preferably, connecting securing member 30 horizontally set, two ends are provided with fastening bolt 50 and are fixed;
Further, connect securing member 30 and be provided with multiple, so that the intensity at each position of wallboard and the equal energy of surface quality
Access guarantee.
In an embodiment of the present utility model, as shown in Figures 1 to 4, in panel 10, it is provided with connection
Part 11, fixed frame 20 is provided with connecting hole, and securing member is connected through connecting hole with connector 11, so that
Panel 10 is fixing with fixed frame 20 to be connected.
By securing member, panel 10 is tightened together with fixed frame 20, fixed, and assembling is simple.
Specifically, as shown in Figures 1 to 4, securing member is bolt 50.
Preferably, as it is shown in figure 1, a panel 10 is internal is provided with multiple connector 11, multiple connectors 11
It is uniformly distributed, to guarantee being fastenedly connected of panel 10 and fixed frame 20.
In an embodiment of the present utility model, as shown in Figure 4, fixed frame 20 is provided with and adaptor
60 transfer hole matched, securing member connects girder steel 70 through transfer hole and adaptor 60, so that combination type
Integral wall is fixing with girder steel 70 to be connected.
In this embodiment, make wallboard realize securing member with girder steel 70 by adaptor 60 and be connected fixing, keep away
Exempt from the work progress of Site Welding, further reduced field erected workload, improve installation effectiveness,
Accelerate project progress.Specifically, as shown in Figure 4, securing member is bolt 50.
Further, as shown in Figure 4, between combination type integral wall with adjacent upper strata or bottom wall panel,
Realizing bolt also by adaptor 60 and connect fixing, it is firm to connect, and install convenient.
In an embodiment of the present utility model, as it is shown in figure 1, combination type integral wall also includes: pre-
Pipe laying road 40, pre-buried pipeline 40 is arranged in panel 10, is used for installing water power circuit.
In this embodiment, by arranging pre-buried pipeline 40 in panel 10 so that the water power of wallboard is arranged
Also achieve factorial praluction, it is to avoid in wallboard, during in-site installation, offer the work progress of pipeline, thus
Further reduce field erected workload, further increase installation effectiveness.
In an embodiment of the present utility model, combination type integral wall also includes: decorative layer, decorative layer
It is arranged on combined wall panel to deviate from the plate face of fixed frame 20.
In this embodiment, by arranging decorative layer so that the face finish of wallboard also achieves factory's metaplasia
Produce, it is to avoid prior art deadlight carries out the work progress fitted up again after installing, thus improves the most further
Installation effectiveness, further increases speed of application.
In an embodiment of the present utility model, as shown in Figures 2 to 4, fixed frame 20 is C-type steel
Framework.
In this embodiment, fixed frame 20 uses C-type steel framework, and C-type steel is than same size angle steel weight more
Gently, intensity is bigger.
Specifically, a sidewall of C-type steel framework is fixing with the plate face of panel 10 to be connected, and this sidewall is provided with
The connecting hole matched with securing members such as connector 11 and bolts 50, on the diapire adjacent with this sidewall and/
Or another sidewall relative with this sidewall is provided with turning of matching with the securing member such as adaptor 60 and bolt 50
Connect hole.
It is understood that C-type steel is formed by steel plate bending, the height of its two side plates being oppositely arranged can
With equal, it is also possible to unequal.Preferably, relative with the height of the side plate that connection is fixed in panel 10 plate face
Higher, to increase the intensity of this side plate, and then increase the bonding strength of C-type steel framework and panel 10.When
So, when offering transfer hole on another side plate, it should also suitably increase its height, to ensure that combination type is whole
Bonding strength between body wallboard and girder steel 70.
Certainly, it will be understood by those of skill in the art that employing angle steel or other kinds of channel-section steel, also can be real
Existing the purpose of this utility model, will not enumerate at this, but these technical schemes are new all without departing from this practicality
The design philosophy of type and objective, the most also in protection domain of the present utility model.
In an embodiment of the present utility model, in the groove of C-type steel framework, it is provided with reinforcement.
In this embodiment, owing to fixed frame 20 fixes whole wallboard, span is relatively large, therefore at C
In the groove of structural steel frame, reinforcement is set, it is possible to be effectively improved the intensity of fixed frame 20, reduces fixed frame
20 probability deformed, and then improve the intensity of combination type integral wall, improve the use of product
Reliability.
In an embodiment of the present utility model, panel 10 is ALC panel 10.
In this embodiment, ALC (Autoclaved Lighweight Concrete, ALC)
Sheet material has that material is light, intensity is high, soundproof effect is good, the advantage of low cost, and has the thermal insulation separation of excellence
The performances such as hot, fire-resistant durability.
Certainly, the panel 10 of this programme is not limited to ALC sheet material, it would however also be possible to employ other materials light
Matter panel 10, will not enumerate at this, it is understood by those skilled in the art that these technical sides
Case is also in protection domain of the present utility model.
In sum, the combination type integral wall that this utility model provides, fix many by arranging fixed frame
Individual panel, makes multiple panel split transport to in-site installation after becoming an entirety again, then the assembled process of wallboard exists
Factory can complete, and so on the one hand avoids monolithic in-site installation of the prior art, considerably reduces
Field erected workload;On the other hand wallboard can be played a protective role by fixed mount, it is to avoid wallboard corner
Damage of colliding with, reduce the breakage rate of wallboard, and be easy to lifting and install, thus further increase peace
Dress efficiency;Additionally it is possible to controlled the quality of wallboard by batch production centralized production, to improve further
The yields of product.
In this utility model, term " multiple " then refers to two or more, unless otherwise clear and definite restriction.
Term " is installed ", " being connected ", " connection ", the term such as " fixing " all should be interpreted broadly, such as, and " connection "
It can be fixing connection, it is also possible to be to removably connect, or be integrally connected;" being connected " can be direct phase
Even, it is also possible to be indirectly connected to by intermediary.For the ordinary skill in the art, Ke Yigen
Above-mentioned term concrete meaning in this utility model is understood according to concrete condition.
In the description of this specification, term " embodiment ", " some embodiments ", " specific embodiment "
Deng description means to combine this embodiment or example describes specific features, structure, material or feature be contained in
In at least one embodiment of the present utility model or example.In this manual, schematic to above-mentioned term
Statement is not necessarily referring to identical embodiment or example.And, the specific features of description, structure, material
Or feature can combine in any one or more embodiments or example in an appropriate manner.
The foregoing is only preferred embodiment of the present utility model, be not limited to this utility model,
For a person skilled in the art, this utility model can have various modifications and variations.All in this practicality
Within novel spirit and principle, any modification, equivalent substitution and improvement etc. made, should be included in this
Within the protection domain of utility model.