CN202176123U - Assembled box-type integrated house with industrial production - Google Patents

Assembled box-type integrated house with industrial production Download PDF

Info

Publication number
CN202176123U
CN202176123U CN2010205179693U CN201020517969U CN202176123U CN 202176123 U CN202176123 U CN 202176123U CN 2010205179693 U CN2010205179693 U CN 2010205179693U CN 201020517969 U CN201020517969 U CN 201020517969U CN 202176123 U CN202176123 U CN 202176123U
Authority
CN
China
Prior art keywords
house
panel
roof
column
collar tie
Prior art date
Application number
CN2010205179693U
Other languages
Chinese (zh)
Inventor
徐智伟
Original Assignee
徐智伟
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 徐智伟 filed Critical 徐智伟
Priority to CN2010205179693U priority Critical patent/CN202176123U/en
Application granted granted Critical
Publication of CN202176123U publication Critical patent/CN202176123U/en

Links

Abstract

The utility model discloses an assembled box-type integrated house with industrial production, mainly comprising parts such as a main body steel structure, an outer maintaining part, an inner wall board and an antitheft door and the like, wherein the main body steel structure part is a main stressed part of a house and comprises vertical columns, an angle column, ring beams, a ground ring beam, an outer protective board and a roof board and the like, wherein the main nodes (beam columns, ring beams and ground ring beams) are designed to be in bolt connection, most parts of the house can be disassembled and assembled for multiple times without need of replacement, so that the purpose for repeated utilization can be achieved, the installation process of the house does not need high-power power equipment, and most parts can realize electroless installation; in the assembled box-type integrated house, the transportation mode is disassembled transportation, since the connecting mode of all the parts is disassemble, the whole house can be transported to a site in the form of parts and then is assembled completely, so that the space can be saved, the transportation efficiency can be improved, the power support is not needed in the installation process simultaneously, and the installation can be finished by only needing common mechanical tools.

Description

Pin-connected panel box integrated house
(1) technical field: this product relates to a kind of box integrated house, but relates in particular to a kind of batch production of complete assembly unit is produced, convenient transportation quick installation box integrated house.
(2) background technology: but integrated house is a kind of can batch production prefabricated, house of transporting Fast Installation behind the scene to; Building structure is typically designed to lightweight steel construction; The maintenance system that comprises body of wall, roofing can be used various New Building Materials to reach decoration, insulation, sound insulation, requirement such as heat insulation, and through rational design and batch production production, integrated house can be transported to the job site easily; Install fast and remove; Most materials can be reused, and is satisfying under the necessary physical property prerequisite, and integrated house has the incomparable advantage of traditional architecture at aspects such as speed of application, stock utilization, energy-conserving and environment-protective;
The scope of application of integrated house very extensively; According to the purposes in house and the difference of service life, integrated house can be used as that normal domestic is lived, office type building, to face the room that builds a house, commercial facility, tourist attractions supporting with the room etc. as various, also can be used as various industrial single purpose buildings; Equipment like communication, electric power, railway, petrochemical industry is used the room; Mobile laboratory etc., wherein, integrated house as equipment such as communication, electric power with the room replace gradually at present tradition brick, reach concrete building; Particularly require in the short emergency works project at construction period, integrated house has become absolute main force's product;
Be used to communicate by letter, the integrated house in power equipment house mostly is monolithic box integrated house; Be after the main house body structure is produced through batch production, to connect, outer enclosed structure is installed again, and then accomplish the construction in all-in-one-piece house through the form of welding; It is high that this monolithic house has the batch production degree; The advantage that the site work amount is little, but its cost of transportation is higher, and it is big to take up room; On-site hoisting needs the crane gear support, and therefore the ease of use of monolithic integrated house reduces greatly under specific environment.Pin-connected panel box integrated house has solved the above-mentioned shortcoming of box integrated house; Be characterized in and can all parts of house be broken transportation, practiced thrift cost of transportation greatly, improved conevying efficiency; Can artificially at the scene install; Need not to reset and the support of high-power electric equipment, a need is simple manually, electric tools can be accomplished installation, possesses higher environmental suitability;
(3) utility model content
The utility model technical problem to be solved is: be directed against the problem that monolithic box integrated house exists aspect conevying efficiency and mounting condition; The overall structure of box integrated house and node are innovated and optimized; With all being improved to bolt and connecting to be welded as main type of attachment in the past, thereby make the form of structure in house become the purpose that pin-connected panel realizes that the house is broken transportation and is repeatedly used;
The goal of the invention of utility model realizes through following technical scheme:
The pin-connected panel box integrated house that a kind of batch production is produced; Form by main body steel work, outer service portion; Main member comprise column, corner post, roof girder, security door, collar tie beam, collar tie beam, outer casing, inner wall panel, ceiling board, roof panel, top board indent, decorate eaves etc., it is characterized in that said column is welded by two cold-forming shapes, the column bottom is provided with accessory at the bottom of the post; Said accessory is through being bolted on the ground collar tie beam; The column that the house front-back wall is corresponding connects through roof girder, and adjacent two root post tops connect through collar tie beam, between adjacent two root posts outer casing and inner wall panel are installed; Outer casing is positioned at the outside, house, and inner wall panel is positioned at the inboard, house; Between adjacent two roof girders roof panel and ceiling board are installed, roof panel is positioned at the outside, house, and ceiling board is positioned at the inboard, house; The slit is buckled with the top board indent between adjacent two roof panel.
Said column is to be welded by two groups of cold-forming shapes, and two groups of section bars are " protruding " font cross section, and the long side weld of the minor face of heavy in section section bar and small-cross section profiles is connected together; Screw is reserved to be used for that ground collar tie beam and roof girder are installed in column top and bottom, and said geosphere beam section is a notch cuttype, and roof girder is welded by two C shaped steel; Be welded with junction plate at the roof girder two ends; Be used to connect column, screw is all reserved in the roof girder upper and lower, is used to install roof panel and hangs a plate.
Said maintenance system is made up of outer casing and inner wall panel, ceiling board, and wherein, outer casing and roof panel are to be processed by cold-rolled steel sheet, fix through bolt and building structure, can reuse, and can play the effect of security protection; Inner wall panel and ceiling board are metal covering polystyrene sandwiched plate, can pass through ornamental strip and bolt, can realize reusing, and play the effect of thermal insulation; Place, slit between the adjacent roof panel in house is buckled with the top board indent, can play waterproof action, and the roofing in house need not to carry out other waterproofing work; The ground in house is designed to antistatic floor, and this floor system and main house body structure directly are connected, can be after room body installation independent installation.
The column in said house, corner post, roof girder, collar tie beam, the connected mode of collar tie beam, outer casing, inner wall panel, ceiling board and roof panel all be that bolt connects, the house is dismounting repeatedly.
The body of wall in said house is made up of two parts, and the outside is the outer casing of steel, and inboard heat preserving and insulating material is the polystyrene sandwiched plate.
The roof in said house is made up of two parts, and what be positioned at roof girder top, the house outside be the roof panel of steel, and the heat preserving and insulating material that is positioned at roof girder bottom, inboard, house is the polystyrene sandwiched plate.
The means of transportation of the utility model is for breaking transportation; Because the type of attachment of each parts all is removable; Therefore house integral body can be transported to the scene and accomplish assembling again with the form of parts; Thereby can save the space, improve conevying efficiency, installation process need not the electric power support simultaneously, only needs common machine tool can accomplish installation;
All component weight of the utility model all are no more than 100kg, and the installation in house can rely on manpower to carry out fully, need not professional crane gear, are adapted to the installation in the abominable area of outdoor environment especially;
(4) description of drawings:
Fig. 1 is the utility model front elevation view;
Fig. 2 is the utility model side elevational view;
Fig. 3 is the stereogram of the utility model;
Fig. 4 is the sectional drawing of the utility model;
Fig. 5 is the utility model column node diagram;
Fig. 6 is the utility model corner post node diagram;
Fig. 7 is the utility model foot joint figure;
Fig. 8 is the utility model bean column node figure;
Fig. 9 uses novel capital drawing for this;
Figure 10 is the utility model ceiling board node diagram;
Accompanying drawing number:
1. column 2 corner posts 3. collar tie beams 4. ground collar tie beams 5. roof girders
6. top board indent 7. outer casings 8. gable outer casings 9. special-shaped outer casing 10. security doors
11. inner wall panel 12. gable inner wall panels 13. ceiling boards 14 roof panel 15. are decorated eaves
16. gable is decorated eaves 17. antistatic floors 18. bolts 19 wallboard ornamental strip 1#
20. accessory at the bottom of wallboard ornamental strip 2# 21. wallboard ornamental strip 3# 22. wallboard ornamental strip 4# 23. posts
24. top board keel 1# 25. top board keel 2#
(5) specific embodiment:
Like Fig. 1, Fig. 3, Fig. 6, Fig. 7 Fig. 8 and shown in Figure 9; At first lay ground collar tie beam 4, column 1 and corner post 2; Be connected 18 through bolt between ground collar tie beam 4 and column 1, the corner post 2; Ground collar tie beam 4 is fixed through accessory at the bottom of the post 22 and ground, at the bottom of the post accessory 22 be positioned at column 1 under, be connected with column through bolt; The appropriate to the occasion paired installation of the installation of column 1, promptly the column of house front-back wall correspondence position connects this column through roof girder 5 again; With same procedure another adjacent column is installed, is got in touch through collar tie beam 3 between two columns; Repeat above-mentioned installation process, until install all columns 1 of forming the house, corner post 2, collar tie beam 3, collar tie beam 4.
Like Fig. 1, Fig. 2, Fig. 3, Fig. 5, installation outer casing 7 shown in Figure 6, outer casing 7 is between adjacent two root posts 1, or between corner post 2 and the column 1, outer casing is connected with column 1 or corner post 2 through spiral shell 18 bolts; There is the position of security door 10 that special-shaped outer casing 9 is installed, repeats the installation that above process is accomplished all outer casings.
Like Fig. 4, Fig. 5, Fig. 6, shown in Figure 7, inner wall panel 11 is installed, the position of inner wall panel such as Fig. 5; Be installed between adjacent two root posts 1 or between corner post 2 and the column; The inboard of outer casing 7 at first is positioned over column 1 both sides to adjacent two inner wall panels 11 during installation, is buckled on the slit of 11 of two inner wall panels with wallboard ornamental strip 1#19 then; With bolt 18 that itself and column 1 is fixing, at last wallboard ornamental strip 2#20 is buckled on the wallboard ornamental strip 1#19; Elbow place wallboard install with above similar, use wallboard ornamental strip 3#21 to be buckled in place, corner inner wall panel slit at last, be fixed on the wallboard with pulling rivet, be buckled on the wallboard ornamental strip 3#21 with wallboard ornamental strip 4#22 again; Repeat above process until the installation of accomplishing left and right sides inner wall panel.
Like Fig. 9 and shown in Figure 10, ceiling board 13 is installed, at first be fixed in roof girder 5 bottoms to top board keel 1#24; Top board keel 2#25 is inserted wherein; Be fixed on top board keel 2#25 bottom to wallboard ornamental strip 1#19 again, in the space between ceiling board 13 insertion top board keel 1#24 and wallboard ornamental strip 1#19, buckle wallboard ornamental strip 2#20 at last; Repeat above installation steps, install all ceiling boards.
Like Fig. 3, Fig. 4, shown in Figure 10, roof panel 14 is installed, roof panel is connected with roof girder 5 through bolt 18, and its position is between two adjacent roof girders 5, and the seam crossing of adjacent two roof panel 14 is buckled with top board indent 6; Repeat above installation steps, accomplish the installation of all roof panel 14; Roof panel installation back wall was installed around the roof and is decorated eaves 15 and gable decoration eaves 16 in one week.
As shown in Figure 4, at indoor installation antistatic floor 17, floor and main house body structure are not contacted directly.
In sum, it is simple and reasonable, sturdy and durable that this product has, and environmental suitability is strong, fully batch production production, parts are from heavy and light, install simple, fast, need not advantages such as power supply and crane gear dress.

Claims (8)

1. pin-connected panel box integrated house, main member comprise column, corner post, roof girder, security door, collar tie beam, collar tie beam, outer casing, inner wall panel, ceiling board, roof panel, top board indent, decorate eaves etc., it is characterized in that said column is welded by two cold-forming shapes; Column bottom is provided with accessory at the bottom of the post, and said accessory is through being bolted on the ground collar tie beam, and the column that the house front-back wall is corresponding connects through roof girder; Adjacent two root post tops connect through collar tie beam; Between adjacent two root posts outer casing and inner wall panel are installed, outer casing is positioned at the outside, house, and inner wall panel is positioned at the inboard, house; Between adjacent two roof girders roof panel and ceiling board are installed; Roof panel is positioned at the outside, house, and ceiling board is positioned at the inboard, house, and the slit is buckled with the top board indent between adjacent two roof panel.
2. pin-connected panel box integrated house as claimed in claim 1; It is characterized in that said column is to be welded by two groups of cold-forming shapes; Two groups of section bars are " protruding " font cross section; The long side weld of the minor face of heavy in section section bar and small-cross section profiles is connected together, and screw is reserved to be used for installing ground collar tie beam and roof girder in column top and bottom.
3. pin-connected panel box integrated house as claimed in claim 1 is characterized in that said roof girder is to be welded by two C shaped steel, is welded with junction plate at the roof girder two ends, is used to connect column, and screw is all reserved in the roof girder upper and lower.
4. pin-connected panel box integrated house as claimed in claim 1, it is characterized in that said house column, corner post, roof girder, collar tie beam, the connected mode of collar tie beam, outer casing, inner wall panel, ceiling board and roof panel all be that bolt connects.
5. pin-connected panel box integrated house as claimed in claim 1 is characterized in that the body of wall in said house is made up of two parts, and the outside is the outer casing of steel, and inboard heat preserving and insulating material is the polystyrene sandwiched plate.
6. pin-connected panel box integrated house as claimed in claim 1; The roof that it is characterized in that said house is made up of two parts; What be positioned at roof girder top, the house outside be the roof panel of steel, and the heat preserving and insulating material that is positioned at roof girder bottom, inboard, house is the polystyrene sandwiched plate.
7. pin-connected panel box integrated house as claimed in claim 1 is characterized in that the place, slit between the adjacent roof panel in said house is buckled with the top board indent.
8. pin-connected panel box integrated house as claimed in claim 1 is characterized in that the collar tie beam section bar cross section, ground in said house is stepped.
CN2010205179693U 2010-09-06 2010-09-06 Assembled box-type integrated house with industrial production CN202176123U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010205179693U CN202176123U (en) 2010-09-06 2010-09-06 Assembled box-type integrated house with industrial production

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010205179693U CN202176123U (en) 2010-09-06 2010-09-06 Assembled box-type integrated house with industrial production

Publications (1)

Publication Number Publication Date
CN202176123U true CN202176123U (en) 2012-03-28

Family

ID=45866008

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010205179693U CN202176123U (en) 2010-09-06 2010-09-06 Assembled box-type integrated house with industrial production

Country Status (1)

Country Link
CN (1) CN202176123U (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102913002A (en) * 2012-11-22 2013-02-06 北京城乡建设集团有限责任公司 Integrated steel structure movable room and mounting method thereof
CN102936932A (en) * 2012-11-23 2013-02-20 武汉理工大学 Combined wall with angle steel keel combined with light concrete
CN103397653A (en) * 2013-07-17 2013-11-20 徐子朗 Base structure of integrated housing and construction method of base structure
CN103898977A (en) * 2014-03-18 2014-07-02 万华集成房屋(烟台)有限公司 Modularized integrated house
CN104775522A (en) * 2014-01-15 2015-07-15 大连中集物流装备有限公司 Detachable house box
CN104963430A (en) * 2014-12-05 2015-10-07 北新集团建材股份有限公司 Steel structural wall provided with door opening and installation method for same
CN105780927A (en) * 2016-03-14 2016-07-20 耿家伟 Industrially assembled type recyclable mobile steel structure house
CN106193661A (en) * 2016-08-27 2016-12-07 东莞市微筑住宅科技有限公司 A kind of spliced aluminum alloy container house
WO2018176638A1 (en) * 2017-03-27 2018-10-04 青岛矢车菊设计有限公司 Assembly for construction house and cabinet system

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102913002A (en) * 2012-11-22 2013-02-06 北京城乡建设集团有限责任公司 Integrated steel structure movable room and mounting method thereof
CN102913002B (en) * 2012-11-22 2015-07-29 北京城乡建设集团有限责任公司 Integral steel structure prefabricated house and mounting method thereof
CN102936932A (en) * 2012-11-23 2013-02-20 武汉理工大学 Combined wall with angle steel keel combined with light concrete
CN103397653B (en) * 2013-07-17 2016-12-28 徐子朗 The base structure of integrated house and construction method thereof
CN103397653A (en) * 2013-07-17 2013-11-20 徐子朗 Base structure of integrated housing and construction method of base structure
CN104775522B (en) * 2014-01-15 2018-10-12 大连中集特种物流装备有限公司 A kind of detachable house box
CN104775522A (en) * 2014-01-15 2015-07-15 大连中集物流装备有限公司 Detachable house box
CN103898977B (en) * 2014-03-18 2016-02-24 万华集成房屋(烟台)有限公司 A kind of modular integrated house
CN103898977A (en) * 2014-03-18 2014-07-02 万华集成房屋(烟台)有限公司 Modularized integrated house
CN104963430A (en) * 2014-12-05 2015-10-07 北新集团建材股份有限公司 Steel structural wall provided with door opening and installation method for same
CN105780927A (en) * 2016-03-14 2016-07-20 耿家伟 Industrially assembled type recyclable mobile steel structure house
CN105780927B (en) * 2016-03-14 2019-03-19 耿家伟 Movable steel structure house can be recycled in industrialization assembled
CN106193661A (en) * 2016-08-27 2016-12-07 东莞市微筑住宅科技有限公司 A kind of spliced aluminum alloy container house
CN106193661B (en) * 2016-08-27 2019-11-19 东莞市微筑住宅科技有限公司 A kind of spliced aluminum alloy container house
WO2018176638A1 (en) * 2017-03-27 2018-10-04 青岛矢车菊设计有限公司 Assembly for construction house and cabinet system
US10779651B2 (en) 2017-03-27 2020-09-22 Qingdao Centaury Design Co., Ltd Assembly for assembled container house system

Similar Documents

Publication Publication Date Title
CA2730329C (en) Transportable, modular self contained shipping container building
US7941975B2 (en) Affordable, sustainable buildings comprised of recyclable materials and methods thereof
AU2013100444A4 (en) A prefabricated panel and its fixed installation structure
US4162595A (en) Prefabricated roof structure and erection method
CN102433955B (en) Assembling prefabricated light steel composite load-bearing wall panel
JP3218530U (en) Central assembly steel structure
CN107148540A (en) The floor used between floors and ceiling panel
US7040066B2 (en) Structure formed of foaming cement and lightweight steel and a structural system and method of forming the structural system
US8286391B2 (en) Portable building
CN202248964U (en) Novel integrated house
CN101748903B (en) Structural system of industrial low storied dwelling
US20110162293A1 (en) Modular Housing
US20140041321A1 (en) Building Systems
MX2013003931A (en) Modular building system.
CN104563288A (en) Reinforced concrete frame gridding slab prefabricated energy-saving house
JP2003521603A (en) Panel building systems and methods
US9587399B2 (en) Insulating wall, a column assembly therefore and a method of constructing such an insulating wall
GB1477754A (en) Prefabricated buildings
CN201665915U (en) Movable house with detachable single-layer lightweight steel structure
CN204627053U (en) A kind of multiple field steel work ITS
LT4783B (en) A method for buiding construction
KR100643075B1 (en) A modular type prefabricated building and its construction method
US8429871B2 (en) Affordable, sustainable buildings comprised of recyclable materials and methods thereof
CN204571086U (en) The filling high-strength wallboard of a kind of ripple
RU2522359C2 (en) Element of multilayer light-weight construction panel, and its manufacturing method

Legal Events

Date Code Title Description
DD01 Delivery of document by public notice

Addressee: Xu Zhiwei

Document name: Notification to Make Rectification

Addressee: Xu Zhiwei

Document name: Notification to Make Rectification

DD01 Delivery of document by public notice

Addressee: Xu Zhiwei

Document name: Notification to Go Through Formalities of Registration

Addressee: Xu Zhiwei

Document name: Notification to Go Through Formalities of Registration

C14 Grant of patent or utility model
GR01 Patent grant
DD01 Delivery of document by public notice

Addressee: Xu Zhiwei

Document name: Notification that Application Deemed not to be Proposed

Addressee: Xu Zhiwei

Document name: Notification that Application Deemed not to be Proposed

EE01 Entry into force of recordation of patent licensing contract

Assignee: Beijing Chengdong International Modular Housing Co., Ltd.

Assignor: Xu Zhiwei

Contract record no.: 2013110000003

Denomination of utility model: Assembled box-type integrated house with industrial production

Granted publication date: 20120328

License type: Exclusive License

Record date: 20130123

Assignee: Beijing Chengdong International Modular Housing Co., Ltd.

Assignor: Xu Zhiwei

Contract record no.: 2013110000003

Denomination of utility model: Assembled box-type integrated house with industrial production

Granted publication date: 20120328

License type: Exclusive License

Record date: 20130123

LICC Enforcement, change and cancellation of record of contracts on the licence for exploitation of a patent or utility model
C41 Transfer of patent application or patent right or utility model
ASS Succession or assignment of patent right

Owner name: BEIJING CHENGDONG INTERNATIONAL MODULAR HOUSING CO

Free format text: FORMER OWNER: XU ZHIWEI

Effective date: 20150120

TR01 Transfer of patent right

Effective date of registration: 20150120

Address after: 101118 No. 6 South Street, Songzhuang Town, Beijing, Tongzhou District

Patentee after: Beijing Chengdong International Modular Housing Co., Ltd.

Address before: 101100, 51-141 orchard East Avenue, Beijing, Tongzhou District

Patentee before: Xu Zhiwei

Effective date of registration: 20150120

Address after: 101118 No. 6 South Street, Songzhuang Town, Beijing, Tongzhou District

Patentee after: Beijing Chengdong International Modular Housing Co., Ltd.

Address before: 101100, 51-141 orchard East Avenue, Beijing, Tongzhou District

Patentee before: Xu Zhiwei

COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 101100 TONGZHOU, BEIJING TO: 101118 TONGZHOU, BEIJING

DD01 Delivery of document by public notice

Addressee: Xu Zhiwei

Document name: Notification of Passing Examination on Formalities

Addressee: Xu Zhiwei

Document name: Notification of Passing Examination on Formalities

CX01 Expiry of patent term

Granted publication date: 20120328

CX01 Expiry of patent term