CN205604193U - A high dam reservoir emptying device - Google Patents
A high dam reservoir emptying device Download PDFInfo
- Publication number
- CN205604193U CN205604193U CN201620378158.7U CN201620378158U CN205604193U CN 205604193 U CN205604193 U CN 205604193U CN 201620378158 U CN201620378158 U CN 201620378158U CN 205604193 U CN205604193 U CN 205604193U
- Authority
- CN
- China
- Prior art keywords
- valve
- water
- pipeline
- bypass pipeline
- outlet
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Sewage (AREA)
Abstract
Description
技术领域 technical field
本实用新型涉及一种高坝水库放空装置,属于水利水电工程技术领域。The utility model relates to a venting device for a high dam reservoir, which belongs to the technical field of water conservancy and hydropower engineering.
背景技术 Background technique
闸门作为水电站的一种较常采用的放空设施,以目前的技术水平,通过设置溢洪道、泄洪洞及放空洞等逐层泄水方式最高能将水库放空至正常蓄水位以下150m左右,但对于国内即将在建的不少300m级的高坝大库工程来说,若只能放空到正常蓄水位以下150m左右,还有近150m深的库容无法放空,将会存在发生地震、战争等紧急情况下水库水位降低不足的问题,因此工程仍然存在较大风险,不能满足工程安全运行的需要,所以现有技术还是不够完善。As a commonly used venting facility in hydropower stations, gates can vent the reservoir to about 150m below the normal water level at most by setting up spillways, spillways, vent holes and other layer-by-layer drainage methods at the current technical level. For many 300m-level high dam and large reservoir projects that are about to be built in China, if they can only be emptied to about 150m below the normal water storage level, and the storage capacity of nearly 150m deep cannot be emptied, there will be emergencies such as earthquakes and wars. Under the circumstances, the water level of the reservoir is lowered insufficiently, so the project still has a relatively large risk and cannot meet the needs of safe operation of the project, so the existing technology is still not perfect.
实用新型内容 Utility model content
本实用新型的目的在于,提供一种高坝水库放空装置,在保证放水设施安全的情况下,尽可能将水库的水放空,以确保水利水电工程的The purpose of this utility model is to provide a high dam reservoir emptying device, in the case of ensuring the safety of the water discharge facilities, the water in the reservoir can be emptied as much as possible, so as to ensure the safety of water conservancy and hydropower projects. 安全运行,从而克服现有技术的不足Safe operation, thereby overcoming the deficiencies of existing technologies 。.
本实用新型的技术方案是这样实现的:The technical scheme of the utility model is achieved in that:
本实用新型的一种高坝水库放空装置为,该装置包括设在坝体或山体底部的导流洞,导流洞内设有沿门槽垂直滑动的封堵闸门;所述门槽外侧设有绕过门槽的旁通管路,旁通管路的进水口位于门槽上游侧壁,旁通管路的出水口位于门槽的下游侧壁;所述旁通管路的出水口下游设有泄水堵头,泄水堵头内设有多层泄水管路;旁通管路和泄水管路上均设有组合阀门。A high dam reservoir emptying device of the present utility model is that the device includes a diversion tunnel arranged at the bottom of the dam body or the mountain body, and the diversion tunnel is provided with a blocking gate that slides vertically along the gate slot; There is a bypass pipeline bypassing the door slot, the water inlet of the bypass pipeline is located on the upstream side wall of the door slot, and the water outlet of the bypass pipeline is located on the downstream side wall of the door slot; There is a drain plug, and a multi-layer drain pipeline is arranged in the drain plug; combined valves are arranged on the bypass pipeline and the drain pipeline.
前述装置中,所述组合阀门为偏心半球阀或蝶阀或球阀加活塞阀的组合方式;偏心半球阀或蝶阀或球阀位于活塞阀的进水管路上。In the aforementioned device, the combination valve is an eccentric hemispherical valve or a butterfly valve or a combination of a ball valve and a piston valve; the eccentric hemispherical valve, butterfly valve or ball valve is located on the water inlet pipeline of the piston valve.
前述装置中,所述旁通管路和泄水管路的入水口均设有拦污网。In the aforementioned device, the water inlets of the bypass pipeline and the drain pipeline are all provided with trash traps.
前述装置中,所述泄水管路的出水口的前端下方设有消力池,泄水管路的出水口向下倾斜对着消力池。In the aforementioned device, a stilling basin is provided below the front end of the water outlet of the drainage pipeline, and the water outlet of the drainage pipeline is inclined downward to face the stilling basin.
由于采用了上述技术方案,本实用新型与现有技术相比,本实用新型利用导流洞改造成放空洞,无须开挖新的放空洞,有效节省了投资。本实用新型在封堵闸门槽内侧设置旁通管路,通过旁通管路可对封堵闸门充水平压,因此封堵闸门可兼作放空洞检修闸门,为泄水堵头及泄水管路阀门相关设施提供检修条件;在封堵闸门后设置泄水堵头,并在泄水堵头内设置多层泄水通路,通过泄水通路实现了高坝水库的放空要求。Due to the adoption of the above technical scheme, compared with the prior art, the utility model utilizes the diversion hole to be transformed into a vent hole, and there is no need to excavate a new vent hole, which effectively saves investment. In the utility model, a bypass pipeline is arranged inside the groove of the blocking gate, through which the blocking gate can be filled with hydraulic pressure, so the blocking gate can also be used as the maintenance gate of the emptying hole, and is used for the drain plug and the valve of the drain pipeline. Relevant facilities provide maintenance conditions; drain plugs are installed after the gates are blocked, and multi-layer drainage channels are set in the drainage plugs, and the venting requirements of the Gaoba reservoir are realized through the drainage channels.
附图说明 Description of drawings
图1是本实用新型的结构示意图;Fig. 1 is the structural representation of the utility model;
图2是图1的A-A剖视图;Fig. 2 is A-A sectional view of Fig. 1;
图3是图2的C-C剖视图;Fig. 3 is a CC sectional view of Fig. 2;
图4是图1的B-B剖视图;Fig. 4 is a BB sectional view of Fig. 1;
图5是坝体或山体上的水流通道示意图。Fig. 5 is a schematic diagram of a water flow channel on a dam body or a mountain body.
图中的标记为:1-导流洞、2-门槽、3-旁通管路、4-封堵闸门、5-泄水堵头、6-上层导流洞、7-泄洪洞、8-溢洪道、9-泄水管路、10-拦污网、11-偏心半球阀或蝶阀或球阀、12-活塞阀、13-出水口、14-消力池。The marks in the picture are: 1- diversion tunnel, 2- door slot, 3- bypass pipeline, 4- blocking gate, 5- discharge plug, 6- upper diversion tunnel, 7- flood discharge tunnel, 8 -spillway, 9-drainage pipeline, 10-trash trap, 11-eccentric hemispherical valve or butterfly valve or ball valve, 12-piston valve, 13-water outlet, 14-stilling basin.
具体实施方式 detailed description
下面结合附图和实施例对本实用新型作进一步的详细说明,但不作为对本实用新型的任何限制。The utility model will be further described in detail below in conjunction with the accompanying drawings and embodiments, but not as any limitation to the utility model.
本实用新型的一种高坝水库导流洞的改造方法,如图1-4所示,该方法是将坝体或山体底部的导流洞改造成放空洞;具体改造方法是在导流洞的封堵闸门的门槽内设置连通封堵闸门上游和下游的旁通管路,通过旁通管路对封堵闸门下游进行充水平压,减小封堵闸门上下游两侧的水压力差;同时在封堵闸门下游的导流洞内设置泄水堵头,泄水堵头内设有多层泄水管路,通过泄水管路将库内的水进一步放空;旁通管路和泄水管路上设有组合阀门。组合阀门采用偏心半球阀+活塞阀的方式,或采用蝶阀+活塞阀的方式;或采用球阀+活塞阀的方式;活塞阀为工作阀,偏心半球阀或蝶阀或球阀为事故检修或保护阀;偏心半球阀或蝶阀或球阀位于活塞阀进水管路上;组合阀门的挡水水头可达300米及以上,动水运行水头可达250米及以上;通过泄水管路及泄水管路上的组合阀门满足300米级大坝的安全放空要求。旁通管路和泄水管路的入水口均设有拦污网,通过拦污网拦截水中较大污物进入管路,避免造成管路堵塞。旁通管路中活塞阀后管路出口向下倾斜,避免充水平压时水流冲击洞室侧墙。泄水管路出口的前端下方设有消力池,泄水管路出口向下倾斜对着消力池;以确保出口水流从上向下冲入消力池,增强消能效果。A method for transforming the diversion tunnel of a high dam reservoir according to the utility model, as shown in Fig. 1-4, the method is to transform the diversion tunnel at the bottom of the dam body or the mountain body into a vent hole; the specific transformation method is in the diversion tunnel A bypass pipeline connecting the upstream and downstream of the blocking gate is installed in the gate slot of the blocking gate, and the downstream of the blocking gate is filled with hydraulic pressure through the bypass pipeline to reduce the water pressure difference between the upstream and downstream sides of the blocking gate At the same time, a drain plug is set in the diversion tunnel downstream of the blocking gate, and a multi-layer drain pipeline is arranged in the drain plug, through which the water in the reservoir is further emptied; the bypass pipeline and the drain pipe There is a combined valve on the road. The combination valve adopts the method of eccentric hemispherical valve + piston valve, or the method of butterfly valve + piston valve; or the method of ball valve + piston valve; the piston valve is the working valve, and the eccentric hemispherical valve or butterfly valve or ball valve is the accident maintenance or protection valve; The eccentric hemispherical valve or butterfly valve or ball valve is located on the piston valve inlet pipe; the water retaining head of the combined valve can reach 300 meters or more, and the head of the dynamic water operation can reach 250 meters or more; Safe venting requirements for 300-meter-class dams. The water inlets of the bypass pipeline and the discharge pipeline are equipped with trash traps, through which large dirt in the water can be intercepted from entering the pipeline to avoid pipeline blockage. The outlet of the pipeline behind the piston valve in the bypass pipeline is inclined downward to avoid the impact of the water flow on the side wall of the cavern when the hydraulic pressure is filled. A stilling pool is provided under the front end of the outlet of the drainage pipeline, and the outlet of the drainage pipeline is inclined downward to face the stilling basin; to ensure that the outlet water flows into the stilling basin from top to bottom to enhance the energy dissipation effect.
根据上述方法构成的本实用新型的一种高坝水库放空装置,包括设在坝体或山体底部的导流洞1,导流洞1内设有沿门槽2垂直滑动的封堵闸门4;所述门槽2外侧设有绕过门槽2的旁通管路3,旁通管路3的进水口位于门槽上游侧壁,旁通管路3的出水口位于门槽2的下游侧壁;所述旁通管路3的出水口下游设有泄水堵头5,泄水堵头5内设有多层泄水管路9;旁通管路3和泄水管路9上均设有组合阀门。组合阀门为偏心半球阀或蝶阀或球阀11加活塞阀12的组合方式;偏心半球阀或蝶阀或球阀11位于活塞阀12的进水管路上。旁通管路3和泄水管路9的入水口均设有拦污网10。泄水管路9的出水口13的前端下方设有消力池14,泄水管路9的出水口13向下倾斜对着消力池14。A kind of venting device for high dam reservoirs of the present invention constituted according to the method described above comprises a diversion tunnel 1 arranged at the bottom of the dam body or a mountain body, and the diversion tunnel 1 is provided with a plugging gate 4 that slides vertically along the gate groove 2; The outside of the door slot 2 is provided with a bypass pipeline 3 bypassing the door slot 2, the water inlet of the bypass pipeline 3 is located on the upstream side wall of the door slot, and the water outlet of the bypass pipeline 3 is located on the downstream side wall of the door slot 2 ; The downstream of the water outlet of the bypass pipeline 3 is provided with a drain plug 5, and a multi-layer drain pipeline 9 is arranged in the drain plug 5; valve. The combined valve is a combination of an eccentric hemispherical valve or a butterfly valve or a ball valve 11 plus a piston valve 12; The water inlets of the bypass pipeline 3 and the drain pipeline 9 are all provided with a trash-stop net 10 . A stilling basin 14 is provided below the front end of the water outlet 13 of the drainage pipeline 9 , and the water outlet 13 of the drainage pipeline 9 is inclined downward facing the stilling basin 14 .
实施例 Example
图5是坝体或山体上的水流通道示意图,由图5可见,现有的水坝由上至下一般都设有溢洪道8、泄洪洞7、上层导流洞6和导流洞1等水流通道。本例的方法是利用坝体或山体最底部的导流洞1改造成放空洞。以实现将水库内的水放空的目的。具体方法如图1-4所示,在封堵闸门4的门槽2外侧设置旁通管路9,在封堵闸门4下闸后,在封堵闸门4后设置泄水堵头5,根据泄水流量的要求,在泄水堵头5内从下至上设置相应数量的几层泄水管路9,泄水管路9按顺水流向依次设置拦污网10、偏心半球阀或蝶阀或球阀11及活塞阀12,活塞阀12的出水口13从下至上按与水平线夹角逐渐加大方式布置,在活塞阀12的出水口13下方设置消力池14;其中封堵闸门2在泄水堵头5及泄水管路9的安装调试期间的挡水水头通过上层导流洞6、泄洪洞7或溢洪道8控制泄水,在泄水堵头5及泄水管路9阀门相关设施安装调试完毕后,通过旁通管路3充水平压后可提走封堵闸门2,旁通管路3为U型。由于采用了偏心半球阀或蝶阀或球阀11+活塞阀12的组合方式,挡水水头可达300米及以上,动水运行水头可达250米及以上,因此可将水库放空至200米以下,满足300米级大坝安全放空的要求;此外,偏心半球阀或蝶阀或球阀11作为活塞阀12(工作阀)的事故保护措施,在活塞阀12运行发生故障时,可动水关闭截断水流防止事故扩大,同时也可为泄水管道和活塞阀的检修维护提供条件;另外,门槽2外侧设置旁通管路3,可在泄水堵头及泄水管路阀门相关设施安装调试完毕后,通过旁通管路可对封堵闸门充水平压,因此封堵闸门可兼作放空洞检修闸门,为泄水堵头及泄水管路阀门相关设施提供检修条件;最后,放空设施设置在导流洞的堵头内,利用导流洞改造成放空洞,无须开挖新的放空洞,有效节省了投资。泄水堵头内从下至上设置多层泄水管路9,每层可有多条泄水管路9;在泄水管路9按顺水流向依次设置拦污网10、偏心半球阀或蝶阀或球阀11以及活塞阀12;活塞阀12的出水口13从下至上按与水平线夹角逐渐加大方式布置,在活塞阀12的出水口13下方设置消力池14;前述顺水流向依次设置拦污网10、偏心半球阀或蝶阀或球阀11以及活塞阀12;且活塞阀12的出水口13向下倾斜。Fig. 5 is a schematic diagram of the water flow channel on the dam body or the mountain. It can be seen from Fig. 5 that the existing dams are generally equipped with spillway 8, flood discharge tunnel 7, upper diversion tunnel 6 and diversion tunnel 1 and other water flow channels from top to bottom. . The method of this example is to utilize the diversion tunnel 1 at the bottom of the dam body or the mountain body to be transformed into a venting tunnel. To realize the purpose of emptying the water in the reservoir. The specific method is shown in Figure 1-4. A bypass pipeline 9 is installed outside the door slot 2 of the blocking gate 4. After the blocking gate 4 is lowered, a drain plug 5 is installed after the blocking gate 4. According to According to the requirements of the discharge flow, a corresponding number of several layers of discharge pipelines 9 are arranged from bottom to top in the discharge plug 5, and the discharge pipeline 9 is sequentially provided with a trash stop 10, an eccentric hemispherical valve or a butterfly valve or a ball valve 11 and Piston valve 12, the water outlet 13 of the piston valve 12 is arranged from bottom to top according to the angle gradually increasing with the horizontal line, and a stilling pool 14 is set below the water outlet 13 of the piston valve 12; 5 and the water retaining head during the installation and commissioning of the discharge pipeline 9 are controlled by the upper diversion tunnel 6, the flood discharge tunnel 7 or the spillway 8, and after the installation and commissioning of the discharge plug 5 and the valve related facilities of the discharge pipeline 9 are completed, After the bypass pipeline 3 is filled with hydraulic pressure, the blocking gate 2 can be lifted away, and the bypass pipeline 3 is U-shaped. Due to the combination of eccentric hemispherical valve or butterfly valve or ball valve 11 + piston valve 12, the water retaining head can reach 300 meters and above, and the dynamic water running head can reach 250 meters and above, so the reservoir can be emptied to below 200 meters to meet 300-meter-level dam safety venting requirements; in addition, the eccentric hemispherical valve or butterfly valve or ball valve 11 is used as an accident protection measure for the piston valve 12 (working valve). It can also provide conditions for the repair and maintenance of the drain pipe and piston valve; in addition, a bypass pipe 3 is provided outside the door slot 2, which can pass The bypass pipeline can fill the blockage gate with hydraulic pressure, so the blockage gate can also be used as the maintenance gate of the vent hole, providing maintenance conditions for the related facilities of the discharge plug and the valve of the discharge pipeline; finally, the vent facility is set at the diversion tunnel In the plug, the diversion hole is used to transform it into a vent hole, and there is no need to dig a new vent hole, which effectively saves investment. A multi-layer drainage pipeline 9 is arranged in the drainage plug from bottom to top, and each layer may have multiple drainage pipelines 9; a trash net 10, an eccentric hemispherical valve or a butterfly valve or a ball valve 11 are arranged in sequence in the drainage pipeline 9 according to the flow direction of the water And the piston valve 12; the water outlet 13 of the piston valve 12 is arranged from bottom to top according to the angle gradually increasing with the horizontal line, and a stilling pool 14 is set below the water outlet 13 of the piston valve 12; , eccentric hemispherical valve or butterfly valve or ball valve 11 and piston valve 12; and the water outlet 13 of the piston valve 12 is inclined downward.
本实用新型具有如下特点:The utility model has the following characteristics:
(1)放空及旁通管路充水平压设施采用偏心半球阀(或蝶阀或球阀)+活塞阀组合方式,偏心半球阀、蝶阀、球阀及活塞阀挡水水头可达300米及以上,动水运行水头可达250米及以上,因此可将水库放空至200米以下,满足300米级大坝安全放空及特高水头充水平压的技术要求。(1) The hydraulic pressure facilities for venting and bypass pipelines adopt the combination of eccentric hemispherical valve (or butterfly valve or ball valve) + piston valve. The head of eccentric hemispherical valve, butterfly valve, ball valve and piston valve can reach 300 meters and above The water running head can reach 250 meters and above, so the reservoir can be emptied to below 200 meters, which meets the technical requirements of 300-meter-level dam safety venting and super-high water head filling water pressure.
(2)偏心半球阀或蝶阀或球阀作为活塞阀(工作阀)的事故保护措施,在活塞阀运行发生故障时,可动水关闭截断水流防止事故扩大,同时也可为泄水管道和活塞阀的检修维护提供条件。(2) The eccentric hemispherical valve or butterfly valve or ball valve is used as an accident protection measure for the piston valve (working valve). Conditions for overhaul and maintenance are provided.
(3)导流洞封堵闸门槽内侧设置旁通管路,可在泄水堵头及泄水管路阀门相关设施安装调试完毕后,通过旁通管路可对导流洞封堵闸门充水平压,因此导流洞封堵闸门可兼作放空洞检修闸门,为泄水堵头及泄水管路阀门相关设施提供检修条件。(3) Bypass pipelines are installed inside the diversion hole blocking gate slot, and after the installation and commissioning of the drainage plug and drainage pipeline valve related facilities, the bypass pipeline can fill the diversion hole sealing gate Therefore, the plugging gate of the diversion tunnel can also be used as the maintenance gate of the vent hole, providing maintenance conditions for the drainage plug and related facilities of the drainage pipeline valve.
(4)放空设施设置在导流洞的堵头内,利用导流洞改造成放空洞,无须开挖新的放空洞,有效节省了投资。(4) The venting facility is set in the plug of the diversion tunnel, and the diversion hole is used to transform it into a vent hole, without excavating a new vent hole, which effectively saves investment.
(5)泄水管路及旁通管路前端设置拦污网,可防止较大污物进入管道。(5) The front end of the drainage pipeline and the bypass pipeline is provided with a trash net to prevent large dirt from entering the pipeline.
(6)活塞阀出口的管道下方设置消力池,活塞阀出口的管道从下至上按与水平线夹角逐渐加大方式布置,可使活塞阀出口水流从上对下冲击,增强消能效果。(6) A stilling pool is installed under the pipeline at the outlet of the piston valve, and the pipeline at the outlet of the piston valve is arranged in such a way that the angle with the horizontal line gradually increases from bottom to top, so that the water flow at the outlet of the piston valve can impact from top to bottom and enhance the energy dissipation effect.
(7)旁通管路中活塞阀后管道出口向下倾斜,可防止充水平压时水流冲击洞室侧墙。(7) The outlet of the pipeline behind the piston valve in the bypass pipeline is inclined downward, which can prevent the water flow from impacting the side wall of the cavern when the hydraulic pressure is filled.
Claims (4)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201620378158.7U CN205604193U (en) | 2016-04-29 | 2016-04-29 | A high dam reservoir emptying device |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201620378158.7U CN205604193U (en) | 2016-04-29 | 2016-04-29 | A high dam reservoir emptying device |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN205604193U true CN205604193U (en) | 2016-09-28 |
Family
ID=56967947
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201620378158.7U Expired - Lifetime CN205604193U (en) | 2016-04-29 | 2016-04-29 | A high dam reservoir emptying device |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN205604193U (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109469026A (en) * | 2018-12-21 | 2019-03-15 | 中国电建集团贵阳勘测设计研究院有限公司 | A concora crush pipe that is used for high dam manger plate to let off air system step by step |
| CN109667248A (en) * | 2018-12-21 | 2019-04-23 | 中国电建集团贵阳勘测设计研究院有限公司 | A multistage manger plate emptying system for high dam engineering |
-
2016
- 2016-04-29 CN CN201620378158.7U patent/CN205604193U/en not_active Expired - Lifetime
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109469026A (en) * | 2018-12-21 | 2019-03-15 | 中国电建集团贵阳勘测设计研究院有限公司 | A concora crush pipe that is used for high dam manger plate to let off air system step by step |
| CN109667248A (en) * | 2018-12-21 | 2019-04-23 | 中国电建集团贵阳勘测设计研究院有限公司 | A multistage manger plate emptying system for high dam engineering |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN201762694U (en) | Dam flow guiding device | |
| CN206928252U (en) | A kind of small water conservancy gate of energy-conserving and environment-protective | |
| CN107326879A (en) | Transformation method and device for diversion tunnel of high dam reservoir | |
| CN102162230A (en) | Design method for reconstructing diversion tunnel into flood discharge tunnel in 'tail-raising' mode | |
| CN107288104A (en) | A kind of cradle-type checkdam structure | |
| CN105369784B (en) | Ditch water process scupper structure and ditch water process water discharge method | |
| CN205604193U (en) | A high dam reservoir emptying device | |
| CN107119643A (en) | A kind of dam for being capable of the anti-alluvial of floating row sand discharge | |
| CN105040648B (en) | More than 200 meters superelevation dam reservoir emptying tunnels and its method for arranging, purposes | |
| CN207919510U (en) | Diversion tunnel blocks arrangement using lock under permanent plug first section joint gate | |
| CN110258458A (en) | Extra-high rock-fill dams diversion tunnel group structure | |
| CN105421312B (en) | Ventilation hole and layout method after the diversion tunnel is rebuilt into arc gate control | |
| CN207032177U (en) | Cradle-type checkdam structure | |
| CN202440787U (en) | Riverway diversion device | |
| CN202157297U (en) | Gate control type urban rain and flood regulation, control and utilization system | |
| CN108316259A (en) | Diversion tunnel sets up lock under interim plug joint gate and blocks arrangement and method | |
| CN204849708U (en) | 200 superelevation dam reservoir unloading hole more than rice | |
| CN112982319A (en) | Structure and method for conducting diversion, emptying and water taking through dam foundation culvert | |
| CN202718071U (en) | Barrage structure capable of lowering silt of reservoir area | |
| CN103614986B (en) | It a kind of is applicable to the pressure free current inlet method that Tailings Dam drains off floodwaters | |
| CN107893406B (en) | A blocking procedure for the lower gate of a diversion tunnel group | |
| CN102747706A (en) | Section steel frame cage stone-dumping closure construction method | |
| CN106988400A (en) | It is a kind of keep off it is damp, anti-blocking, maintenance it is convenient, can sand washing desilting hondo formula closure works system and method | |
| CN215329800U (en) | A Navigation Facility Clearance Filling and Horizontal Pressure Device | |
| CN206752427U (en) | A kind of power station ground power house tailrace outlet structure and its power station |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant |