CN108442338A - The arrangement of Hydropower Station Underground formula workshop machine set outlet gate - Google Patents
The arrangement of Hydropower Station Underground formula workshop machine set outlet gate Download PDFInfo
- Publication number
- CN108442338A CN108442338A CN201810283522.5A CN201810283522A CN108442338A CN 108442338 A CN108442338 A CN 108442338A CN 201810283522 A CN201810283522 A CN 201810283522A CN 108442338 A CN108442338 A CN 108442338A
- Authority
- CN
- China
- Prior art keywords
- gate
- headstock gear
- hydraulic
- hydropower station
- slot
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000007789 sealing Methods 0.000 claims abstract description 9
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 8
- 239000007788 liquid Substances 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 6
- 238000009412 basement excavation Methods 0.000 abstract description 4
- 238000010586 diagram Methods 0.000 description 2
- 238000005452 bending Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000003673 groundwater Substances 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B7/00—Barrages or weirs; Layout, construction, methods of, or devices for, making same
- E02B7/20—Movable barrages; Lock or dry-dock gates
- E02B7/40—Swinging or turning gates
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B7/00—Barrages or weirs; Layout, construction, methods of, or devices for, making same
- E02B7/20—Movable barrages; Lock or dry-dock gates
- E02B7/54—Sealings for gates
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B8/00—Details of barrages or weirs ; Energy dissipating devices carried by lock or dry-dock gates
- E02B8/04—Valves, slides, or the like; Arrangements therefor; Submerged sluice gates
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B9/00—Water-power plants; Layout, construction or equipment, methods of, or apparatus for, making same
- E02B9/02—Water-ways
- E02B9/06—Pressure galleries or pressure conduits; Galleries specially adapted to house pressure conduits; Means specially adapted for use therewith, e.g. housings, valves, gates
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Barrages (AREA)
Abstract
The invention discloses a kind of arrangements of Hydropower Station Underground formula workshop machine set outlet gate, including the gate in unit lower exit pipeline is arranged, it is prefabricated with storage gate slot in outlet conduit top concrete structure, it is provided with hydraulic switch machine platform above storage gate slot, it is provided with the vertical passageway with vertical guide between hydraulic switch machine platform and storage gate slot, sealing rubber pad is provided between hydraulic headstock gear rack and vertical passageway, the suspending head end of hydraulic headstock gear is provided with slides the directive wheel being connected with vertical track;Gate is hinged close to one end of unit and storage gate slot, and gate upper surface is hinged by the suspending head of connecting rod and hydraulic headstock gear, and gate lower surface side is coated with the water seal rubber with preburied frame sealing cooperation in outlet conduit.Headstock gear operating platform can be arranged under the peak level of downstream in the present invention, greatly reduced cavern excavation amount and gate slot concreting amount, not only improved cavern's stable structure, and saved construction cost.
Description
Technical field
The present invention relates to Hydropower Station Underground formula workshops to go out port strobe technical field, more particularly, to a kind of Hydropower Station Underground formula
The arrangement of workshop machine set outlet gate.
Background technology
Powerhouse of hydropower station is divided into ground type workshop and underground powerhouse.The major advantage of underground powerhouse is that workshop does not take up an area
Face position, less with the interference of ground water conservancy project architecture construction, the duration is relatively short, usually by the group of cavern of crossings on different level
At.It requires geological conditions that can meet cavern's stable calculation using the workshop of this form, reduces cavern excavation amount to the greatest extent, avoid
It excavates excessive influence cavern's stable structure and then generates security risk.Conventional hydropower station underground powerhouse goes out port strobe using vertical
Gate slot mode, usually gate lock is above lock top, when unit needs maintenance by closing gate.It is generally disposed at the top of lock chamber
Headstock gear and electric control equipment, this traditional arrangement mode require lock roof panel to export position higher than downstream highest, avoid tail water
Lock top is flooded, therefore outlet lock chamber excavated volume is larger, increases difficulty of construction, and be unfavorable for the stability of cavern's structure, is
This needs to use a large amount of cavern's reinforcement measure, thereby increases construction investment.
Invention content
The present invention provides a kind of arrangement of Hydropower Station Underground formula workshop machine set outlet gate, it is therefore intended that solves existing
Underground powerhouse exports lock chamber and excavates the problem that difficulty is big, construction investment is big.
To achieve the above object, the present invention can take following technical proposals:
The arrangement of Hydropower Station Underground formula workshop machine set outlet gate of the present invention, including be arranged in unit lower exit
Gate in pipeline is prefabricated with the storage gate slot for horizontal gate, the storage door in the outlet conduit top concrete structure
It is provided with hydraulic switch machine platform above slot, is provided with vertical guide between the hydraulic switch machine platform and storage gate slot
Vertical passageway is provided with caulking gum between the hydraulic headstock gear rack and the vertical passageway on hydraulic switch machine platform
Pad, the suspending head end of the hydraulic headstock gear is provided with slides the directive wheel being connected with the vertical track;The gate is close
One end of unit is hinged with storage gate slot, and gate upper surface is hinged by the suspending head of connecting rod and hydraulic headstock gear, gate following table
Face side is coated with the water seal rubber with preburied frame sealing cooperation in outlet conduit.
The hydraulic headstock gear rack is sealing structure.
The hydraulic switch machine platform is located under the peak level of unit downstream.
The arrangement of Hydropower Station Underground formula workshop machine set outlet gate provided by the invention, by the way that sealing hydraulic is arranged
The modes such as headstock gear rack, turning hinge formula open-close sluice gate and embedded gate arrangement, enable headstock gear operating platform to be arranged in down
It swims under peak level, space is used in the operation to reduce gate, greatly reduces cavern excavation amount and gate slot concrete
The amount of pouring not only improves cavern's stable structure, and has saved construction cost.
Description of the drawings
Fig. 1 is the structural schematic diagram of the present invention(Gate opening state).
Fig. 2 is the structural schematic diagram of the present invention(Closing gate state).
Specific implementation mode
As shown in Figure 1, the arrangement of Hydropower Station Underground formula workshop machine set outlet gate of the present invention, including use
The upper horizontal turning hinge open-close type gate 2 being arranged in unit lower exit pipeline 1.Specifically, 1 top concrete knot of outlet conduit
Storage gate slot 3 is prefabricated in structure, 3 inside of storage gate slot is close to one end of unit(It is left end in figure)Embedded turning hinge free bearing, to hinged
Gate 2, gate 2 can be rotated around hinged shaft, can be completely embedded into when in horizontality in the storage gate slot 3 and are used as outlet conduit 1
A part for roof does not influence passing through for normal flow;Hydraulic switch machine platform 4 has been built in 3 top of storage gate slot, the hydraulic switch
It is connected by the vertical passageway 6 with vertical guide 5 between machine platform 4 and storage gate slot 3;It is installed on hydraulic switch machine platform 4
There is hydraulic headstock gear 7, the rack of the hydraulic headstock gear 7 is provided with caulking gum between sealed structure, with vertical passageway 6
Pad 8, and be bolted together, to ensure that higher than when opening and closing machine platform water leak accident does not occur for the level of tail water;In order to
The hydraulic stem for ensuring hydraulic headstock gear 7 axially movable, avoids hydraulic pressure rod bending or destroys sealing, in hanging for hydraulic headstock gear 7
Head end is equipped with slides the directive wheel 9 being connected with vertical track 5, it is made vertically to be run along track;Meanwhile hydraulic headstock gear
7 suspending head is hinged by connecting rod 10 and 2 upper surface of gate, and 2 rotating folding of gate is driven by hydraulic headstock gear 7;In addition, gate
2 lower surfaces(That is gate panel)Side is also wrapped on water seal rubber 12, for making gate 2 be in closed state as shown in Figure 2
When, excellent sealing can be formed with 11 palette of preburied frame being arranged in outlet conduit 1, to stop that downstream water enters
Unit provides nonirrigated farmland for unit and overhauls condition.
Above-mentioned hydraulic switch machine platform can be arranged under the peak level of downstream, reduce the operation of gate with empty
Between, cavern excavation amount and gate slot concreting amount are greatly reduced, not only improves cavern's stable structure, and saved and be constructed into
This, can promote the use of hydraulic and hydroelectric engineering underground power house machine set outlet gate and be arranged in the indoor technical field in hole.
Claims (3)
1. a kind of arrangement of Hydropower Station Underground formula workshop machine set outlet gate, including be arranged in unit lower exit pipeline
(1)Interior gate(2), it is characterised in that:The outlet conduit(1)It is prefabricated in top concrete structure for horizontal gate
(2)Storage gate slot(3), the storage gate slot(3)Top is provided with hydraulic switch machine platform(4), the hydraulic switch machine platform(4)
With storage gate slot(3)Between be provided with vertical guide(5)Vertical passageway(6), it is located at hydraulic switch machine platform(4)On liquid
Press headstock gear(7)Rack and the vertical passageway(6)Between be provided with sealing rubber pad(8), the hydraulic headstock gear(7)Hang
Head end is provided with and the vertical track(5)The connected directive wheel of sliding(9);The gate(2)Close to unit one end with
Store up gate slot(3)It is hinged, gate(2)Upper surface passes through connecting rod(10)With hydraulic headstock gear(7)Suspending head be hinged, gate(2)
Lower surface side is coated with and outlet conduit(1)Interior preburied frame(11)Seal the water seal rubber of cooperation(12).
2. the arrangement of Hydropower Station Underground formula workshop machine set outlet gate according to claim 1, it is characterised in that:Institute
State hydraulic headstock gear(7)Rack is sealing structure.
3. the arrangement of Hydropower Station Underground formula workshop machine set outlet gate according to claim 1, it is characterised in that:Institute
State hydraulic switch machine platform(4)Under the peak level of unit downstream.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810283522.5A CN108442338A (en) | 2018-04-02 | 2018-04-02 | The arrangement of Hydropower Station Underground formula workshop machine set outlet gate |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810283522.5A CN108442338A (en) | 2018-04-02 | 2018-04-02 | The arrangement of Hydropower Station Underground formula workshop machine set outlet gate |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108442338A true CN108442338A (en) | 2018-08-24 |
Family
ID=63198700
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810283522.5A Pending CN108442338A (en) | 2018-04-02 | 2018-04-02 | The arrangement of Hydropower Station Underground formula workshop machine set outlet gate |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108442338A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110594240A (en) * | 2019-10-14 | 2019-12-20 | 常州液压成套设备厂有限公司 | Waterproof sealing frame |
CN111997002A (en) * | 2020-08-24 | 2020-11-27 | 中建环能科技股份有限公司 | Drainage gate and weir crest with sealing structure |
CN113186880A (en) * | 2021-04-02 | 2021-07-30 | 中国长江电力股份有限公司 | Automatic pressurizing and depressurizing method for deep-hole arc door water seal of high-head power station and construction method |
CN114396028A (en) * | 2021-12-01 | 2022-04-26 | 国网福建省电力有限公司 | Water-blocking door for main traffic hole of power station |
CN114822890A (en) * | 2022-02-28 | 2022-07-29 | 中国建筑第二工程局有限公司 | Nuclear power station equipment gate installation method |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001123434A (en) * | 1999-10-25 | 2001-05-08 | Ebara Corp | Semi-lift type pump gate |
US20030026660A1 (en) * | 2001-08-01 | 2003-02-06 | Chun-Ching Wu | Automatically opened and closed water gate |
CN101851908A (en) * | 2010-04-19 | 2010-10-06 | 黄河勘测规划设计有限公司 | Two-way water blocking gate valve type working gate |
CN102322043A (en) * | 2011-06-10 | 2012-01-18 | 天津大学 | Double-guideway inclined-plane steel gate system |
CN203684176U (en) * | 2014-01-28 | 2014-07-02 | 四川东方水利水电工程有限公司 | Horizontal type flood gate |
CN204023516U (en) * | 2014-08-27 | 2014-12-17 | 中工武大设计研究有限公司 | A kind of steel dam anchor gate on-off structure |
-
2018
- 2018-04-02 CN CN201810283522.5A patent/CN108442338A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001123434A (en) * | 1999-10-25 | 2001-05-08 | Ebara Corp | Semi-lift type pump gate |
US20030026660A1 (en) * | 2001-08-01 | 2003-02-06 | Chun-Ching Wu | Automatically opened and closed water gate |
CN101851908A (en) * | 2010-04-19 | 2010-10-06 | 黄河勘测规划设计有限公司 | Two-way water blocking gate valve type working gate |
CN102322043A (en) * | 2011-06-10 | 2012-01-18 | 天津大学 | Double-guideway inclined-plane steel gate system |
CN203684176U (en) * | 2014-01-28 | 2014-07-02 | 四川东方水利水电工程有限公司 | Horizontal type flood gate |
CN204023516U (en) * | 2014-08-27 | 2014-12-17 | 中工武大设计研究有限公司 | A kind of steel dam anchor gate on-off structure |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110594240A (en) * | 2019-10-14 | 2019-12-20 | 常州液压成套设备厂有限公司 | Waterproof sealing frame |
CN111997002A (en) * | 2020-08-24 | 2020-11-27 | 中建环能科技股份有限公司 | Drainage gate and weir crest with sealing structure |
CN113186880A (en) * | 2021-04-02 | 2021-07-30 | 中国长江电力股份有限公司 | Automatic pressurizing and depressurizing method for deep-hole arc door water seal of high-head power station and construction method |
CN114396028A (en) * | 2021-12-01 | 2022-04-26 | 国网福建省电力有限公司 | Water-blocking door for main traffic hole of power station |
CN114396028B (en) * | 2021-12-01 | 2024-01-26 | 国网福建省电力有限公司 | Water blocking door for main traffic hole of electric station |
CN114822890A (en) * | 2022-02-28 | 2022-07-29 | 中国建筑第二工程局有限公司 | Nuclear power station equipment gate installation method |
CN114822890B (en) * | 2022-02-28 | 2024-01-16 | 中国建筑第二工程局有限公司 | Nuclear power station equipment gate installation method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108442338A (en) | The arrangement of Hydropower Station Underground formula workshop machine set outlet gate | |
CN102162230B (en) | Design method for reconstructing diversion tunnel into flood discharge tunnel in 'tail-raising' mode | |
CN204456008U (en) | Vertical axle rotating type steel-slag sand | |
CN201874614U (en) | Drainage structure for emptying overhaul of derivation tunnel | |
CN201473933U (en) | Combination layout structure of tail water emergency gate and tail water surge shaft in pumped storage power station | |
CN107740389A (en) | A kind of diversion tunnel structure and its plugging construction method | |
CN208056018U (en) | The arrangement of Hydropower Station Underground formula workshop machine set outlet gate | |
CN208857807U (en) | It is a kind of to fill sluicing and water charging system for large scale ship | |
CN105133552A (en) | Balance type hydraulic barrage | |
CN201056682Y (en) | Water sealing device of high water head radial gate | |
CN204940217U (en) | A kind of ultra-large type plane splits arc triangle gate | |
CN207092033U (en) | A kind of flood discharging tunnel | |
CN103290824A (en) | Dam hydraulic power ship lifter | |
CN203684173U (en) | Dam freeing port | |
CN202644491U (en) | Urban landscape steel gate | |
CN103510492A (en) | Automatic switch of rotary type plane gate | |
CN203603121U (en) | Full-automatic hydraulic horizontal dam gate | |
CN205604193U (en) | High dam reservoir emptying device | |
CN207176904U (en) | The integrated pump lock that a kind of aperture automatically adjusts | |
CN205530153U (en) | Integration multifunction board floodgate | |
CN201245832Y (en) | Side self-operated sluice | |
CN203834435U (en) | Bottom hole water draining sluice gate | |
CN206784335U (en) | Hydraulic gate headstock gear | |
CN107130568A (en) | More than 200 meters superelevation dam reservoir emptying tunnel structures and its arrangement and application method | |
CN203247566U (en) | Closed gate device of dam waterpower ship lift |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180824 |
|
RJ01 | Rejection of invention patent application after publication |