CN106284240A - A kind of power station is in construction time downstream interim water-supply structure and method - Google Patents
A kind of power station is in construction time downstream interim water-supply structure and method Download PDFInfo
- Publication number
- CN106284240A CN106284240A CN201610752749.0A CN201610752749A CN106284240A CN 106284240 A CN106284240 A CN 106284240A CN 201610752749 A CN201610752749 A CN 201610752749A CN 106284240 A CN106284240 A CN 106284240A
- Authority
- CN
- China
- Prior art keywords
- tunnel
- downstream
- water
- diversion tunnel
- temporary
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B9/00—Water-power plants; Layout, construction or equipment, methods of, or apparatus for, making same
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B9/00—Water-power plants; Layout, construction or equipment, methods of, or apparatus for, making same
- E02B9/02—Water-ways
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Sewage (AREA)
Abstract
本发明属于水工建筑物临时供水技术领域,特别是涉及一种水电站在施工期向下游临时供水结构。它包括位于山体上且用于临时卸洪的导流洞,所述导流洞设有导流洞入口,所述导流洞入口处设有控制水流的闸门,所述导流洞入口的上游设有一与导流洞连通的施工支洞,所述施工支洞前期为所述导流洞洞身施工的通道,后期作为向下游供水的旁通洞。本发明采用把导流洞的施工支洞改建成旁通洞,不需要专门再开设放水孔洞,减少工程投资,同时可节省费用,减少投资,节省工期,具有显著的技术经济效益。
The invention belongs to the technical field of temporary water supply for hydraulic structures, in particular to a temporary water supply structure downstream of a hydropower station during the construction period. It includes a diversion tunnel located on the mountain and used for temporary flood discharge. The diversion tunnel is provided with a diversion tunnel entrance, and a gate for controlling water flow is provided at the entrance of the diversion tunnel. There is a construction branch tunnel connected with the diversion tunnel, and the construction branch tunnel is used as a channel for the construction of the diversion tunnel body in the early stage, and as a bypass tunnel for supplying water to the downstream in the later stage. The invention converts the construction branch hole of the diversion tunnel into a bypass hole, and does not need to set up a water discharge hole, which reduces project investment, saves cost, reduces investment, saves construction period, and has significant technical and economic benefits.
Description
技术领域technical field
本发明属于水工建筑物临时供水技术领域,特别是涉及一种水电站在施工期向下游临时供水结构和方法。The invention belongs to the technical field of temporary water supply for hydraulic structures, in particular to a structure and method for temporarily supplying water downstream of a hydropower station during construction.
背景技术Background technique
随着我国大型水电站开发技术的日益成熟,目前电站设计中需充分考虑生态流量对下游的环境影响。对于高坝大库水利水电工程设计中,施工期向下游泄洪的临时泄洪建筑物,待工程完工后,需全部封堵,但受到水工泄洪建筑物的平板门、弧门挡水及控泄能力的限制,工程下闸蓄水期间,通常采用在坝体或山体分层设置临时放水孔洞,形成了目前常用的接力封堵临时孔洞的方法。有些工程甚至没有考虑生态流量对下游的环境影响,在工程下闸蓄水期间出现一段时间下游河段脱流的现象,对河道生态环境短时间内影响较大。采用分层孔洞向下游供水的工程,受到闸门挡水压力的限值,必将增设孔洞,从而增加工程量及费用,影响工程工期。With the development technology of large-scale hydropower stations in my country becoming more and more mature, it is necessary to fully consider the impact of ecological flow on the downstream environment in the design of power stations. For the design of water conservancy and hydropower projects of high dams and large reservoirs, the temporary flood discharge structures that discharge flood downstream during the construction period need to be completely blocked after the completion of the project, but are affected by the water retaining and discharge control of the flat doors and arc doors of the hydraulic flood discharge structures. Due to the limitation of capacity, during the water storage period of the project gate, temporary water discharge holes are usually set up in layers on the dam body or mountain body, forming the current commonly used method of relay sealing temporary holes. Some projects do not even consider the impact of ecological flow on the downstream environment. During the impoundment period of the project, there will be a phenomenon of deflow in the downstream section for a period of time, which will have a great impact on the ecological environment of the river channel in a short period of time. For projects that use layered holes to supply water to the downstream, subject to the limit of the water retaining pressure of the gate, holes must be added, thereby increasing the amount and cost of the project, and affecting the construction period of the project.
发明内容Contents of the invention
为了克服大型水电站高坝大库在下闸蓄水期间向下游供水风险大,成本高、影响工期的问题,本发明的目的是提供一种水电站在施工期向下游临时供水结构和方法。In order to overcome the problems of high risk of water supply to the downstream of the high dam and large reservoir of the large-scale hydropower station during the water storage of the lower gate, the high cost and the impact on the construction period, the purpose of the present invention is to provide a temporary water supply structure and method for the downstream of the hydropower station during the construction period.
为实现上述技术目的,本发明采用如下技术方案予以实现:In order to realize the above-mentioned technical purpose, the present invention adopts following technical scheme to realize:
一种水电站在施工期向下游临时供水结构,包括位于山体上且用于临时卸洪的导流洞,所述导流洞设有导流洞入口,所述导流洞入口处设有控制水流的闸门,所述导流洞入口的上游设有一与导流洞连通的施工支洞,所述施工支洞前期为所述导流洞洞身施工的通道,后期作为向下游供水的旁通洞。A temporary water supply structure downstream of a hydropower station during the construction period, including a diversion tunnel located on the mountain and used for temporary flood discharge, the diversion tunnel is provided with a diversion tunnel entrance, and the diversion tunnel entrance is provided with a water flow control channel. The upstream of the entrance of the diversion tunnel is provided with a construction branch tunnel connected with the diversion tunnel. The construction branch tunnel is a channel for the construction of the diversion tunnel body in the early stage and a bypass hole for supplying water to the downstream in the later stage.
优选的,在所述旁通洞内靠近其出口处设有控制闸室,所述控制闸室内设有用以控制上游水位和下泄水量锥阀。Preferably, a control sluice chamber is provided in the bypass hole close to its outlet, and a cone valve for controlling the upstream water level and the downstream water discharge is arranged in the control sluice chamber.
优选的,在所述旁通洞内靠近其出口处还设有消耗水流能量的消能室,所述消能室位于所述控制闸室的后方。Preferably, an energy dissipation chamber for consuming water flow energy is also provided in the bypass hole near its outlet, and the energy dissipation chamber is located behind the control lock chamber.
优选的,所述消能室为椭圆形。Preferably, the energy dissipation chamber is oval.
优选的,所述消能室的长度为7-20m,宽度1-10m,宽度1-10m。Preferably, the energy dissipation chamber has a length of 7-20m, a width of 1-10m, and a width of 1-10m.
优选的,所述控制闸室还连通有外界控制通道,所述外界控制通道一端通向所述控制闸室,另一端通向底面。具体的,所述外界控制通道为竖井或者斜井。Preferably, the control lock chamber is also connected with an external control channel, one end of the external control channel leads to the control lock chamber, and the other end leads to the bottom surface. Specifically, the external control channel is a shaft or an inclined shaft.
本发明的另一目的,提供一种水电站在施工期向下游临时供水的方法,包括以下步骤:Another object of the present invention is to provide a method for temporarily supplying water downstream of a hydropower station during the construction period, comprising the following steps:
步骤1、工程水库完成蓄水;Step 1, the engineering reservoir completes water storage;
步骤2、当上游水位超过旁通洞的所述锥阀进口高程后,所述导流洞入口闸Step 2. When the upstream water level exceeds the inlet elevation of the cone valve of the bypass tunnel, the inlet gate of the diversion tunnel
门下闸;gate under the gate;
步骤3、在所述锥阀的控制下,向下游供水;Step 3, under the control of the cone valve, supply water to the downstream;
步骤4、水位超过水工永久泄洪建筑物进口高程后,关闭锥阀;Step 4. After the water level exceeds the inlet elevation of the hydraulic permanent flood discharge structure, close the cone valve;
步骤5、所述导流洞开始封堵,封堵完成后完成供水。Step 5, the diversion hole starts to be blocked, and the water supply is completed after the sealing is completed.
本发明的有益效果:Beneficial effects of the present invention:
本发明采用把导流洞的施工支洞改建成旁通洞,不需要专门再开设放水孔洞,减少工程投资,同时可节省费用,减少投资,节省工期,具有显著的技术经济效益。The invention converts the construction branch hole of the diversion tunnel into a bypass hole, and does not need to set up a water discharge hole, which reduces project investment, saves cost, reduces investment, saves construction period, and has significant technical and economic benefits.
附图说明Description of drawings
图1是本发明临时供水结构的平面布置示意图;Fig. 1 is the plane layout schematic diagram of temporary water supply structure of the present invention;
图2是本发明导流洞的剖面结构示意图;Fig. 2 is the sectional structure schematic diagram of diversion tunnel of the present invention;
图3是旁通洞和竖井配合的剖面结构示意图。Fig. 3 is a schematic cross-sectional structure diagram of the cooperation between the bypass hole and the shaft.
图中,1-导流洞入口;2-旁通洞;3-竖井;4-锥阀;5-导流洞;6-消能室;7-山体;8-控制闸室。In the figure, 1-entrance of diversion tunnel; 2-bypass tunnel; 3-shaft; 4-cone valve; 5-diversion tunnel; 6-energy dissipation chamber;
具体实施方式detailed description
下面结合附图对本发明作进一步说明:The present invention will be further described below in conjunction with accompanying drawing:
实施例1Example 1
为了克服大型水电站高坝大库在下闸蓄水期间向下游供水风险大,成本高、影响工期的问题,本实施例提供了如图1至3所示的一种水电站在施工期向下游临时供水结构,包括位于山体7上且用于临时卸洪的导流洞5,所述导流洞5设有导流洞入口1,所述导流洞入口1处设有控制水流的闸门,所述导流洞入口1的上游设有一与导流洞5连通的施工支洞,所述施工支洞前期为导流洞5洞身施工的通道,后期作为向下游供水的旁通洞2。In order to overcome the problems of high risk of water supply to the downstream of the high dam and large reservoir of the large-scale hydropower station during the storage period of the gate, the problem of high cost and impact on the construction period, this embodiment provides a temporary water supply to the downstream of the hydropower station during the construction period as shown in Figures 1 to 3 The structure includes a diversion tunnel 5 located on the mountain body 7 and used for temporary flood discharge, the diversion tunnel 5 is provided with a diversion tunnel entrance 1, and a gate for controlling water flow is provided at the diversion tunnel entrance 1. The upstream of the diversion tunnel entrance 1 is provided with a construction branch tunnel connected with the diversion tunnel 5. The construction branch tunnel is used as a channel for the construction of the diversion tunnel 5 in the early stage and as a bypass tunnel 2 for supplying water to the downstream in the later stage.
其中,所述前期和后期以所述导流洞5的施工完成时间来计算,所述导流洞5施工未完成的时间为前期,所述导流洞5施工完成后时间为后期。Wherein, the early stage and the late stage are calculated by the completion time of the construction of the diversion tunnel 5, the time when the construction of the diversion tunnel 5 is not completed is the early stage, and the time after the construction of the diversion tunnel 5 is completed is the late stage.
本发明采用把导流洞5的施工支洞改建成旁通洞2,不需要专门再开设放水孔洞,减少工程投资,同时可节省费用,减少投资,节省工期,具有显著的技术经济效益。In the present invention, the construction branch of diversion tunnel 5 is converted into bypass tunnel 2, and there is no need to set up water discharge holes, which reduces engineering investment, saves costs, reduces investment, saves construction period, and has significant technical and economic benefits.
实施例2Example 2
在实施例1的基础上,如图3所述,在所述旁通洞2内靠近其出口处设有控制闸室8,所述控制闸室8内设有用以控制上游水位和下泄水量锥阀4,所锥阀4具有消能率高、施工简单,占用空间小,维修要求低的优点。所述锥阀4可选用市场上常见的锥阀,在此不再详细描述。On the basis of Embodiment 1, as shown in Figure 3, a control lock chamber 8 is provided in the bypass hole 2 close to its outlet, and the control lock chamber 8 is provided with a cone valve for controlling the upstream water level and the amount of water discharged. 4. The cone valve 4 has the advantages of high energy dissipation rate, simple construction, small space occupation and low maintenance requirements. The poppet valve 4 can be a common poppet valve in the market, which will not be described in detail here.
在所述旁通洞2内靠近其出口处还设有消能室6,所述消能室6位于所述控制闸室8的后方,所述消能室6用以消耗由锥阀4放出的高速水流的能量。本发明采用所述锥阀4和消能室6的结构用以连续排放流量控制,适应高水头、各级流量,可解决高水头、高流速、连续运行时间长、下游泄洪消能等问题。An energy dissipating chamber 6 is also provided near the outlet of the bypass hole 2, the energy dissipating chamber 6 is located behind the control lock chamber 8, and the energy dissipating chamber 6 is used to consume the energy released by the cone valve 4. The energy of high-speed water flow. The present invention adopts the structure of the cone valve 4 and the energy dissipation chamber 6 for continuous discharge flow control, adapts to high water head and flows at all levels, and can solve the problems of high water head, high flow rate, long continuous operation time, downstream flood discharge and energy dissipation.
所述消能室6为椭圆形,设置成椭圆形对水流过流条件较好,并限制水流的方向,形成对冲来消能水能。所述消能室6的长度为7-20m,宽度1-10m,宽度1-10m,在这个范围内能够达到更好的消能效果。The energy dissipating chamber 6 is elliptical, and the elliptical shape has better conditions for water flow, and limits the direction of water flow to form a hedge to dissipate water energy. The energy dissipation chamber 6 has a length of 7-20m, a width of 1-10m, and a width of 1-10m, within which a better energy dissipation effect can be achieved.
所述控制闸室8还连通有外界控制通道3,所述外界控制通道3一端通向所述控制闸室8,另一端通向底面,通过该外界控制通道3实现控制闸室8与外接的联系,方便锥阀4的维修和观察。具体地,所述外界控制通道为竖井或者斜井,竖井或者斜井的选择根据地质情况来决定。The control lock chamber 8 is also connected with an external control channel 3, one end of the external control channel 3 leads to the control lock chamber 8, and the other end leads to the bottom surface, and the control lock chamber 8 and the external connection are realized through the external control channel 3. Contact, convenient maintenance and observation of cone valve 4. Specifically, the external control channel is a vertical shaft or an inclined shaft, and the selection of the vertical shaft or the inclined shaft is determined according to geological conditions.
实施例3Example 3
为了克服现有技术中现有坝体浸润线抬高,且无法检修,严重影响坝体安全的缺陷,本发明提供了一种水电站在施工期向下游临时供水的方法,包括以下步骤:In order to overcome the defects in the prior art that the wetting line of the existing dam body is raised and cannot be repaired, which seriously affects the safety of the dam body, the present invention provides a method for temporarily supplying water downstream of a hydropower station during the construction period, which includes the following steps:
步骤1、工程水库完成蓄水;Step 1, the engineering reservoir completes water storage;
步骤2、当上游水位超过旁通洞2的所述锥阀4进口高程后,所述导流洞入口1闸门下闸;Step 2. When the upstream water level exceeds the inlet elevation of the cone valve 4 of the bypass tunnel 2, the gate of the diversion tunnel entrance 1 is lowered;
步骤3、在所述锥阀4的控制下,向下游供水;Step 3, under the control of the cone valve 4, supply water downstream;
步骤4、水位超过水工永久泄洪建筑物进口高程后,关闭锥阀4;Step 4, after the water level exceeds the inlet elevation of the hydraulic permanent flood discharge structure, close the cone valve 4;
步骤5、所述导流洞5开始封堵,封堵完成后完成供水。Step 5, the diversion tunnel 5 starts to be blocked, and the water supply is completed after the sealing is completed.
显然,本领域的技术人员可以对本发明进行各种改动和变型而不脱离本发明的精神和范围。这样,倘若本发明的这些修改和变型属于本发明权利要求及其等同技术的范围之内,则本发明也意图包括这些改动和变型在内。Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and equivalent technologies thereof, the present invention also intends to include these modifications and variations.
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610752749.0A CN106284240A (en) | 2016-08-29 | 2016-08-29 | A kind of power station is in construction time downstream interim water-supply structure and method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610752749.0A CN106284240A (en) | 2016-08-29 | 2016-08-29 | A kind of power station is in construction time downstream interim water-supply structure and method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN106284240A true CN106284240A (en) | 2017-01-04 |
Family
ID=57674274
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201610752749.0A Pending CN106284240A (en) | 2016-08-29 | 2016-08-29 | A kind of power station is in construction time downstream interim water-supply structure and method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN106284240A (en) |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106968227A (en) * | 2017-05-16 | 2017-07-21 | 中国电建集团成都勘测设计研究院有限公司 | The maintenance arrangement of the permanent plug of induced joint diversion tunnel |
| CN108677892A (en) * | 2018-07-27 | 2018-10-19 | 中国电建集团成都勘测设计研究院有限公司 | Diversion tunnel working tunnel is used as reconstruction structure of the ecology for water hole |
| CN109356124A (en) * | 2018-11-21 | 2019-02-19 | 中国电建集团成都勘测设计研究院有限公司 | Cavern usual friendship fork structure |
| CN113338236A (en) * | 2021-05-26 | 2021-09-03 | 中国电建集团西北勘测设计研究院有限公司 | Structure and method for discharging ecological water to downstream in initial storage of reservoir |
| CN113481928A (en) * | 2021-07-27 | 2021-10-08 | 中国三峡建工(集团)有限公司 | High-water-level water storage method for construction period of high-dam large reservoir and at initial operation stage |
| CN116427368A (en) * | 2023-04-07 | 2023-07-14 | 中国电建集团北京勘测设计研究院有限公司 | A stepped layout structure for continuous discharge of ecological flow in water conservancy and hydropower projects |
Citations (14)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| SU1240824A1 (en) * | 1985-01-08 | 1986-06-30 | Тбилисское Отделение Всесоюзного Ордена Ленина Проектно-Изыскательского И Научно-Исследовательского Института "Гидропроект" Им.С.Я.Жука | Unit for matching spillways of hydraulic structure |
| CN1888322A (en) * | 2006-08-02 | 2007-01-03 | 四川大学 | Method for rebuilding diversion tunnel to pressure expanded aerated flood-discharge tunnel |
| JP2008144361A (en) * | 2006-12-06 | 2008-06-26 | Furutochi Kensetsu:Kk | Water management device of dam |
| CN101215830A (en) * | 2007-12-29 | 2008-07-09 | 四川大学 | The hydraulic form of vertical shaft swirling flood discharge tunnel and emptying tunnel or diversion tunnel |
| CN101280557A (en) * | 2008-05-23 | 2008-10-08 | 水利部交通部电力工业部南京水利科学研究院 | Method for rebuilding guide current hole to jet flow internal energy dissipating drilled shaft flood discharge hole |
| CN203594007U (en) * | 2013-11-12 | 2014-05-14 | 中国水电顾问集团成都勘测设计研究院有限公司 | Power station hub downstream water supply structure |
| CN104005387A (en) * | 2014-05-26 | 2014-08-27 | 中国电建集团成都勘测设计研究院有限公司 | Emptying tunnel or special flood discharging tunnel arranging system and opening and closing method thereof |
| CN104912043A (en) * | 2015-06-19 | 2015-09-16 | 中国电建集团成都勘测设计研究院有限公司 | Diversion drainage structure for tunnel inside in water conservancy and hydropower project and construction method of diversion drainage structure |
| CN204715315U (en) * | 2015-06-08 | 2015-10-21 | 中国电建集团贵阳勘测设计研究院有限公司 | Disconnect-type water inlet arrangement structure |
| CN105155484A (en) * | 2015-06-23 | 2015-12-16 | 四川大学 | Method for reconstructing temporary diversion tunnel into permanent flood discharge facility |
| CN105178268A (en) * | 2015-08-11 | 2015-12-23 | 中国电建集团贵阳勘测设计研究院有限公司 | Construction method and structure for combining diversion tunnel and flood discharge tunnel |
| CN205035779U (en) * | 2015-09-29 | 2016-02-17 | 浙江省水利水电勘测设计院 | Construction branch tunnel suitable for pressure regulating of water delivery tunnel and maintenance traffic |
| CN105369784A (en) * | 2015-11-27 | 2016-03-02 | 中国电建集团成都勘测设计研究院有限公司 | Drainage hole structure and drainage method for ditchwater treatment |
| CN205501957U (en) * | 2016-04-11 | 2016-08-24 | 中国电建集团成都勘测设计研究院有限公司 | Retaining phase downstream water supply system |
-
2016
- 2016-08-29 CN CN201610752749.0A patent/CN106284240A/en active Pending
Patent Citations (14)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| SU1240824A1 (en) * | 1985-01-08 | 1986-06-30 | Тбилисское Отделение Всесоюзного Ордена Ленина Проектно-Изыскательского И Научно-Исследовательского Института "Гидропроект" Им.С.Я.Жука | Unit for matching spillways of hydraulic structure |
| CN1888322A (en) * | 2006-08-02 | 2007-01-03 | 四川大学 | Method for rebuilding diversion tunnel to pressure expanded aerated flood-discharge tunnel |
| JP2008144361A (en) * | 2006-12-06 | 2008-06-26 | Furutochi Kensetsu:Kk | Water management device of dam |
| CN101215830A (en) * | 2007-12-29 | 2008-07-09 | 四川大学 | The hydraulic form of vertical shaft swirling flood discharge tunnel and emptying tunnel or diversion tunnel |
| CN101280557A (en) * | 2008-05-23 | 2008-10-08 | 水利部交通部电力工业部南京水利科学研究院 | Method for rebuilding guide current hole to jet flow internal energy dissipating drilled shaft flood discharge hole |
| CN203594007U (en) * | 2013-11-12 | 2014-05-14 | 中国水电顾问集团成都勘测设计研究院有限公司 | Power station hub downstream water supply structure |
| CN104005387A (en) * | 2014-05-26 | 2014-08-27 | 中国电建集团成都勘测设计研究院有限公司 | Emptying tunnel or special flood discharging tunnel arranging system and opening and closing method thereof |
| CN204715315U (en) * | 2015-06-08 | 2015-10-21 | 中国电建集团贵阳勘测设计研究院有限公司 | Disconnect-type water inlet arrangement structure |
| CN104912043A (en) * | 2015-06-19 | 2015-09-16 | 中国电建集团成都勘测设计研究院有限公司 | Diversion drainage structure for tunnel inside in water conservancy and hydropower project and construction method of diversion drainage structure |
| CN105155484A (en) * | 2015-06-23 | 2015-12-16 | 四川大学 | Method for reconstructing temporary diversion tunnel into permanent flood discharge facility |
| CN105178268A (en) * | 2015-08-11 | 2015-12-23 | 中国电建集团贵阳勘测设计研究院有限公司 | Construction method and structure for combining diversion tunnel and flood discharge tunnel |
| CN205035779U (en) * | 2015-09-29 | 2016-02-17 | 浙江省水利水电勘测设计院 | Construction branch tunnel suitable for pressure regulating of water delivery tunnel and maintenance traffic |
| CN105369784A (en) * | 2015-11-27 | 2016-03-02 | 中国电建集团成都勘测设计研究院有限公司 | Drainage hole structure and drainage method for ditchwater treatment |
| CN205501957U (en) * | 2016-04-11 | 2016-08-24 | 中国电建集团成都勘测设计研究院有限公司 | Retaining phase downstream water supply system |
Cited By (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106968227A (en) * | 2017-05-16 | 2017-07-21 | 中国电建集团成都勘测设计研究院有限公司 | The maintenance arrangement of the permanent plug of induced joint diversion tunnel |
| CN108677892A (en) * | 2018-07-27 | 2018-10-19 | 中国电建集团成都勘测设计研究院有限公司 | Diversion tunnel working tunnel is used as reconstruction structure of the ecology for water hole |
| CN108677892B (en) * | 2018-07-27 | 2024-04-19 | 中国电建集团成都勘测设计研究院有限公司 | Reconstruction structure for ecological water supply tunnel by diversion tunnel construction branch tunnel |
| CN109356124A (en) * | 2018-11-21 | 2019-02-19 | 中国电建集团成都勘测设计研究院有限公司 | Cavern usual friendship fork structure |
| CN109356124B (en) * | 2018-11-21 | 2023-11-21 | 中国电建集团成都勘测设计研究院有限公司 | Chamber level crossing fork structure |
| CN113338236A (en) * | 2021-05-26 | 2021-09-03 | 中国电建集团西北勘测设计研究院有限公司 | Structure and method for discharging ecological water to downstream in initial storage of reservoir |
| CN113481928A (en) * | 2021-07-27 | 2021-10-08 | 中国三峡建工(集团)有限公司 | High-water-level water storage method for construction period of high-dam large reservoir and at initial operation stage |
| CN116427368A (en) * | 2023-04-07 | 2023-07-14 | 中国电建集团北京勘测设计研究院有限公司 | A stepped layout structure for continuous discharge of ecological flow in water conservancy and hydropower projects |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106284240A (en) | A kind of power station is in construction time downstream interim water-supply structure and method | |
| CN202440803U (en) | Air-entraining structure for flood releasing building | |
| CN203546687U (en) | Hydropower station tail water surge chamber capable of automatically adapting to changes in tail water level | |
| CN104179159B (en) | Power station bright flowing full tail water system | |
| CN107740389B (en) | Diversion tunnel structure and plugging construction method thereof | |
| CN106368185A (en) | Hydropower station water inlet gallery desilting system and method | |
| CN205501957U (en) | Retaining phase downstream water supply system | |
| CN105155484B (en) | By the method that the reconstruction of temporary diversion hole is permanent release floodwatering facility | |
| CN205501944U (en) | To downstream water supply structure suitable for high arch dam | |
| CN104195997A (en) | Aerated flip bucket arrangement structure suitable for high water head flood discharge hole | |
| CN207919510U (en) | Diversion tunnel blocks arrangement using lock under permanent plug first section joint gate | |
| CN117188413A (en) | A layout method combining power generation tailrace tunnel and diversion tunnel | |
| CN110258458B (en) | Structure of diversion tunnels for ultra-high rockfill dam | |
| CN104099909B (en) | Based on the flood discharge generating sync energy dissipater of flood-discharge tunnel | |
| CN108316259A (en) | Diversion tunnel sets up lock under interim plug joint gate and blocks arrangement and method | |
| CN100392193C (en) | Method of rebuilding diversion tunnel into flood discharge tunnel with sudden expansion under pressure and aeration | |
| CN207092033U (en) | A kind of flood discharging tunnel | |
| CN209277132U (en) | A kind of hydraulic and hydroelectric engineering water conservancy diversion, tail water, emptying tunnel structure | |
| CN205742110U (en) | A kind of arrangement improving long diversion system power station unit operational flexibility | |
| CN104164858A (en) | Diversion tunnel sequential blocking method for realizing continuous stream of down stream of high arch dam in storage period | |
| CN204676504U (en) | The emptying maintenance structure of a kind of long tailwater tunnel group without gravity flow ejectment condition | |
| CN204715318U (en) | Diversion tunnel gate shaft structure in mountain | |
| CN206143743U (en) | Husky corridor system is arranged to power station water inlet | |
| CN103821115B (en) | A kind of method solving power station free-flow tunnel and occur free pressure flow | |
| CN115613529A (en) | Layout structure of a high head ecological flow discharge tunnel |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170104 |