CN205501830U - Cable support tower construction removable support - Google Patents

Cable support tower construction removable support Download PDF

Info

Publication number
CN205501830U
CN205501830U CN201620186366.7U CN201620186366U CN205501830U CN 205501830 U CN205501830 U CN 205501830U CN 201620186366 U CN201620186366 U CN 201620186366U CN 205501830 U CN205501830 U CN 205501830U
Authority
CN
China
Prior art keywords
climbing
frame
cable tower
climbing frame
cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201620186366.7U
Other languages
Chinese (zh)
Inventor
谭海雄
李芳锦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Changda Highway Engineering Co Ltd
Original Assignee
Guangdong Changda Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Changda Highway Engineering Co Ltd filed Critical Guangdong Changda Highway Engineering Co Ltd
Priority to CN201620186366.7U priority Critical patent/CN205501830U/en
Application granted granted Critical
Publication of CN205501830U publication Critical patent/CN205501830U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Tents Or Canopies (AREA)

Abstract

本实用新型涉及一种索塔施工移动式支架,该系统包括钢管、爬架、提升架、抱箍、手拉葫芦及保险钢丝绳,其中,钢管设有四根,分别固定在索塔周围,且可竖向接长,作为爬架、提升架固定和爬升的导轨,爬架设有三层,固定在四根钢管上,且每一层爬架均沿索塔周向布设,将索塔包围在内,提升架固定在四根钢管上,沿索塔周向布设,将索塔包围在内,且位于最上层爬架的上方,抱箍设在钢管上,用于支撑爬架或提升架,手拉葫芦连接在相邻两层爬架之间,或连接在爬架与提升架之间,保险钢丝绳连接在相邻两层爬架之间,或连接在爬架与提升架之间。与现有技术相比,本实用新型辅助支架系统能够简化施工过程,降低施工风险。

The utility model relates to a mobile support for cable tower construction. The system includes a steel pipe, a climbing frame, a lifting frame, a hoop, a chain hoist and a safety wire rope, wherein four steel pipes are provided and are respectively fixed around the cable tower, and It can be extended vertically and used as a guide rail for fixing and climbing the climbing frame and lifting frame. The climbing frame has three layers and is fixed on four steel pipes, and each layer of climbing frame is arranged along the circumference of the cable tower to surround the cable tower. , the lifting frame is fixed on four steel pipes, arranged along the circumference of the cable tower, surrounding the cable tower, and located above the uppermost climbing frame, and the hoop is set on the steel pipe to support the climbing frame or lifting frame. The chain hoist is connected between two adjacent climbing frames, or between the climbing frame and the lifting frame, and the safety wire rope is connected between two adjacent layers of climbing frames, or between the climbing frame and the lifting frame. Compared with the prior art, the auxiliary support system of the utility model can simplify the construction process and reduce the construction risk.

Description

索塔施工移动式支架Cable tower construction mobile support

技术领域technical field

本实用新型属于桥梁施工领域,具体涉及一种索塔施工移动式支架。The utility model belongs to the field of bridge construction, in particular to a mobile support for cable tower construction.

背景技术Background technique

目前国内常采用翻模工艺和爬模工艺进行索塔施工。其中翻模施工是以上节段索塔顶节模板作为固定节及承力部分,安装上节段拆除的模板进行施工,需另外搭设脚手架作为施工平台;爬模是由爬升模板、爬架、和爬升设备组成,在已浇节段预埋轨道剪力件,沿着轨道逐节液压顶升施工,在自爬的模板上悬挂脚手架可省去施工过程中的外脚手架。At present, the overturning process and the climbing formwork process are often used in the construction of cable towers in China. Among them, the overturning construction is that the formwork of the top section of the cable tower in the above section is used as the fixed section and the load-bearing part, and the formwork removed from the upper section is installed for construction, and scaffolding needs to be erected as a construction platform; the climbing formwork is composed of climbing formwork, climbing frames, and Climbing equipment is composed of pre-embedded track shear members in the poured section, hydraulic jacking construction section by section along the track, and hanging scaffolding on the self-climbing formwork can save the external scaffolding in the construction process.

目前国内常用的索塔施工辅助支架有脚手架、爬模支架。脚手架是采用钢管、脚手板等逐层搭设而成,由于搭设高度的限制,若用于高塔时需使用转换平台分段搭设和拆除,高空作业控制因素多,施工安全风险大。爬模支架以液压爬升模板作为依托,随爬升模板同步提升,但若用于截面多变的索塔,轨道预埋、安装精度差,施工难度大。At present, the commonly used auxiliary supports for cable tower construction in China include scaffolding and climbing formwork supports. Scaffolding is built layer by layer using steel pipes, scaffolding boards, etc. Due to the limitation of the erection height, if it is used for a high tower, it needs to be erected and dismantled in sections using a conversion platform. There are many control factors for high-altitude operations, and the construction safety risk is great. The climbing formwork support is based on the hydraulic climbing formwork and is lifted synchronously with the climbing formwork. However, if it is used for a cable tower with a variable cross-section, the track is pre-embedded and the installation accuracy is poor, making the construction difficult.

公开号为CN 103898836 A的中国专利公开了一种斜拉桥 H 型索塔高上横梁钢斜腿预应力支架施工方法,用于桥梁施工领域,其采用钢斜腿托架和拱架来施工横梁,避免了现有技术中高支架法施工大量钢管支架的安装和拆除,减少了索塔施工时预埋件的安装及后期修补工作,减少高空焊接工作量和材料,大大降低了高空作业风险,同时也规避了高支架预留压缩量和预埋牛腿托架上拱度设置困难等问题;钢斜腿托架受力明确,上节点将竖向荷载传递给索塔,下节点上斜向下力的水平向外分力靠水平系杆处预应力钢绞线预先施加的预应力抵消,下节点上斜向下力的竖向分力由索塔承受。此外,索塔与横梁异步施工,避免了横梁侧施工索塔的模板及爬架的高空拆除和安装,降低了安全风险,缩短了工期。但是上述施工方法仅适用于斜拉桥 H 型索塔,而对于其他截面形状的索塔施工并不适用。The Chinese patent with the publication number CN 103898836 A discloses a construction method for the steel slanted leg prestressed support of the H-shaped cable tower of the cable-stayed bridge, which is used in the field of bridge construction. It uses steel slanted leg brackets and arch frames for construction The beam avoids the installation and removal of a large number of steel pipe supports in the high-altitude support method in the prior art, reduces the installation of embedded parts and later repair work during cable tower construction, reduces the workload and materials of high-altitude welding, and greatly reduces the risk of high-altitude operations. At the same time, it also avoids the problems of the reserved compression of the high bracket and the difficulty in setting the camber of the pre-embedded corbel bracket; The horizontal outward component of the downforce is offset by the prestressed steel strand pre-applied at the horizontal tie bar, and the vertical component of the oblique downward force on the lower node is borne by the cable tower. In addition, the asynchronous construction of the cable tower and the beam avoids the high-altitude dismantling and installation of the formwork and climbing frame of the beam side construction cable tower, reduces safety risks, and shortens the construction period. However, the above construction method is only applicable to H-type cable towers of cable-stayed bridges, but not applicable to the construction of cable towers with other cross-sectional shapes.

发明内容Contents of the invention

本实用新型的目的就是为了克服上述现有技术存在的缺陷而提供一种简化施工过程、降低施工风险的索塔施工移动式支架。The purpose of this utility model is to provide a mobile tower construction bracket that simplifies the construction process and reduces construction risks in order to overcome the above-mentioned defects in the prior art.

本实用新型的目的可以通过以下技术方案来实现:The purpose of this utility model can be achieved through the following technical solutions:

索塔施工移动式支架,该系统包括钢管、爬架、提升架、抱箍、手拉葫芦和保险钢丝绳,所述钢管设有四根,分别固定在索塔周围,且可竖向接长,作为爬架、提升架固定和爬升的导轨;所述爬架设有三层,固定在四根钢管上,且每一层爬架均沿索塔周向布设,将索塔包围在内;所述提升架固定在四根钢管上,沿索塔周向布设,将索塔包围在内,且位于最上层爬架的上方;所述抱箍设在钢管上,用于支撑爬架或提升架;所述手拉葫芦连接在相邻两层爬架之间,或连接在爬架与提升架之间;所述保险钢丝绳:连接在相邻两层爬架之间,或连接在爬架与提升架之间。Mobile support for cable tower construction. The system includes steel pipes, climbing frames, lifting frames, hoops, chain hoists and safety wire ropes. There are four steel pipes, which are respectively fixed around the cable tower and can be extended vertically. As a guide rail for fixing and climbing the climbing frame and lifting frame; the climbing frame has three layers, fixed on four steel pipes, and each layer of climbing frame is arranged along the circumference of the cable tower to surround the cable tower; the lifting The frame is fixed on four steel pipes, arranged along the circumference of the cable tower, enclosing the cable tower, and located above the uppermost climbing frame; the hoop is arranged on the steel pipe to support the climbing frame or lifting frame; The chain hoist is connected between two adjacent climbing frames, or between the climbing frame and the lifting frame; the safety wire rope: is connected between the adjacent two layers of climbing frames, or between the climbing frame and the lifting frame between.

进一步地,最上层的爬架与中间层的爬架通过桁架连接成整体。Further, the climbing frames on the uppermost layer and the climbing frames on the middle layer are connected as a whole through trusses.

进一步地,最下层的爬架与索塔之间设置型钢平台进行兜底封闭。Further, a shaped steel platform is set between the bottommost climbing frame and the cable tower for bottom closure.

进一步地,还包括设置在相邻两层爬架之间或设置在爬架与提升架之间的活动爬梯。Further, it also includes a movable climbing ladder arranged between two adjacent climbing frames or between the climbing frame and the lifting frame.

进一步地,所述的爬架包括主架体和护栏,护栏设在主架体上;爬架内设有爬梯通道,爬架四周设置钢丝网全封闭。Further, the climbing frame includes a main frame body and a guardrail, and the guardrail is arranged on the main frame body; a ladder channel is provided inside the climbing frame, and a steel wire mesh is arranged around the climbing frame to fully seal it.

进一步地,所述的提升架的平台及护栏采用铁丝网进行封闭。Further, the platform and the guardrail of the lifting frame are closed with barbed wire.

进一步地,在抱箍的底部沿钢管壁焊接4根钢筋作为保险支撑。Further, four steel bars are welded along the steel pipe wall at the bottom of the hoop as a safety support.

与现有技术相比,本实用新型具有以下优点及有益效果:Compared with the prior art, the utility model has the following advantages and beneficial effects:

1、本实用新型辅助支架系统能够适用于变截面形状或变直径的塔索,仅通过该辅助支架系统即可以完成整个塔索不同截面节段的施工,不需要多套辅助支架,因此施工便捷,同时节省安装与操作时间,还能够降低辅助支架的制作成本。1. The auxiliary support system of the utility model can be applied to tower cables with variable cross-sectional shapes or variable diameters. Only through this auxiliary support system, the construction of different cross-section sections of the entire tower cable can be completed without multiple sets of auxiliary supports, so the construction is convenient. , while saving installation and operation time, and can also reduce the production cost of the auxiliary bracket.

2、本实用新型辅助支架主要由可竖向接长的钢管、提升架、爬架、手拉葫芦、保险钢丝绳以及抱箍等组成,结构设置简单,并且在搭建过程中,采用塔吊来提升提升架一个索塔节段的高度,爬架通过手拉葫芦挂在提升架上进行提升,因此上下提升方便,通过锁紧抱箍实现对提升架或爬架的支撑,操作方便。2. The auxiliary support of the utility model is mainly composed of steel pipes that can be extended vertically, a lifting frame, a climbing frame, a chain hoist, a safety wire rope, and a hoop. The structure is simple, and during the construction process, a tower crane is used to lift The height of a cable tower segment is raised, and the climbing frame is lifted by hanging on the lifting frame through a chain hoist, so it is convenient to lift up and down, and the support of the lifting frame or climbing frame is realized by locking the hoop, which is easy to operate.

3、在爬架内设置上下层爬梯通道,并在相邻两层爬架之间或在爬架与提升架之间设置活动爬梯,实现不同层之间的活动操作。3. Set the upper and lower ladder passages in the climbing frame, and set up movable ladders between two adjacent layers of climbing frames or between the climbing frame and the lifting frame to realize the movable operation between different layers.

4、最下层的爬架与索塔之间设置型钢平台进行兜底封闭,爬架四周设置钢丝网全封闭,提升架的平台及护栏采用铁丝网进行封闭,在抱箍的底部沿钢管壁焊接4 根钢筋作为保险支撑,因此,本实用新型的辅助支架系统结果稳固安全性高,降低施工风险。4. A shaped steel platform is set between the bottom climbing frame and the cable tower to close the bottom of the pocket, and a steel wire mesh is set around the climbing frame to fully seal it. The platform and guardrail of the lifting frame are closed with barbed wire, and 4 pieces are welded along the steel pipe wall at the bottom of the hoop. Steel bars are used as insurance supports, therefore, the auxiliary support system of the utility model is stable and safe, and reduces construction risks.

附图说明Description of drawings

图1为本实用新型的索塔施工辅助支架系统结构示意图。Fig. 1 is a structural schematic diagram of the auxiliary support system for cable tower construction of the present invention.

图中标号:1为钢管,2为提升架,3为爬架,4为抱箍,5为手拉葫芦,6为保险钢丝绳,7为活动爬梯,8为塔吊,9为爬梯通道,10为电梯,11为索塔节段。Numbers in the figure: 1 is steel pipe, 2 is lifting frame, 3 is climbing frame, 4 is hoop, 5 is chain hoist, 6 is safety wire rope, 7 is movable ladder, 8 is tower crane, 9 is ladder passage, 10 is Elevator, 11 is a cable tower segment.

具体实施方式detailed description

下面结合附图和具体实施例对本实用新型进行详细说明。The utility model will be described in detail below in conjunction with the accompanying drawings and specific embodiments.

实施例Example

如图1所示,一种索塔施工移动式支架,该系统包括钢管1、爬架3、提升架2、抱箍4、手拉葫芦5、保险钢丝绳6及活动爬梯7。钢管1设有四根,分别固定在索塔周围,且可竖向接长,作为爬架3、提升架2固定和爬升的导轨。爬架3设有三层,固定在四根钢管1上,且每一层爬架3均沿索塔周向布设,将索塔包围在内,其中,最上层的爬架3与中间层的爬架3通过桁架连接成整体。最下层的爬架3与索塔之间设置型钢平台进行兜底封闭。爬架3包括主架体与护栏,护栏设在主架体上;爬架3内设置上下层爬梯通道9,爬架3四周设置钢丝网全封闭。提升架2固定在四根钢管1上,沿索塔周向布设,将索塔包围在内,且位于最上层爬架3的上方,提升架2的平台及护栏采用铁丝网进行封闭。抱箍4设在钢管1上,用于支撑爬架3或提升架2,在抱箍4的底部沿钢管壁焊接4 根钢筋作为保险支撑。手拉葫芦5连接在相邻两层爬架3之间,或连接在爬架3与提升架2之间。保险钢丝绳6连接在相邻两层爬架3之间,或连接在爬架3与提升架2之间。活动爬梯7设置在相邻两层爬架3之间或设置在爬架3与提升架2之间。As shown in Figure 1, a mobile support for cable tower construction, the system includes a steel pipe 1, a climbing frame 3, a lifting frame 2, a hoop 4, a chain hoist 5, a safety wire rope 6 and a movable ladder 7. Steel pipe 1 is provided with four, is respectively fixed around the cable tower, and can vertically lengthen, as climbing frame 3, the guide rail that lifting frame 2 fixes and climbs. The climbing frame 3 is provided with three layers, which are fixed on four steel pipes 1, and each layer of climbing frame 3 is arranged along the circumference of the cable tower to surround the cable tower. Frames 3 are connected as a whole by trusses. A profiled steel platform is set between the bottom climbing frame 3 and the cable tower to close the bottom of the pocket. The climbing frame 3 comprises a main frame body and a guardrail, and the guardrail is located on the main frame body; the upper and lower ladder passages 9 are set in the climbing frame 3, and the steel wire mesh is fully enclosed around the climbing frame 3. Lifting frame 2 is fixed on four steel pipes 1, is arranged along cable tower circumferential direction, and cable tower is enclosed in, and is positioned at the top of uppermost climbing frame 3, and the platform of lifting frame 2 and guardrail adopt barbed wire to seal. The hoop 4 is arranged on the steel pipe 1 for supporting the climbing frame 3 or the lifting frame 2, and 4 steel bars are welded along the steel pipe wall at the bottom of the hoop 4 as a safety support. The chain block 5 is connected between two adjacent climbing frames 3 , or between the climbing frame 3 and the lifting frame 2 . The safety wire rope 6 is connected between two adjacent climbing frames 3, or between the climbing frame 3 and the lifting frame 2. Movable climbing ladder 7 is arranged between adjacent two layers of climbing frames 3 or between climbing frame 3 and lifting frame 2 .

索塔施工移动式支架的搭建方法,包括以下步骤:The construction method of the mobile support for cable tower construction comprises the following steps:

a、通过在承台上的预埋件,安装四根作为整个辅助支架导轨的钢管1,4根钢管1之间通过横联管连成整体,钢管1沿高度方向每24米设置一道横连管,同时钢管1沿高度方向每隔6米设置一道与索塔固定连接的附墙件;相连两根钢管1焊接时,钢管接头满焊,并在钢管接头外侧焊接加劲钢板;a. Through the embedded parts on the bearing platform, install four steel pipes 1 as the guide rails of the entire auxiliary support. The four steel pipes 1 are connected as a whole by cross-connection pipes. The steel pipe 1 is provided with a horizontal connection every 24 meters along the height direction. At the same time, the steel pipe 1 is provided with a wall attachment fixedly connected with the tower every 6 meters along the height direction; when connecting two steel pipes 1 for welding, the joint of the steel pipe is fully welded, and a stiffening steel plate is welded outside the joint of the steel pipe;

b、安装底层爬架:先在钢管上安装4个抱箍4,以锁紧在钢管上的抱箍4作为支撑,分块安装底层的爬架3,同理由下往上安装其余2层爬架3及提升架2;b. Install the bottom climbing frame: first install four hoops 4 on the steel pipe, use the hoops 4 locked on the steel pipe as a support, install the bottom climbing frame 3 in blocks, and install the remaining two layers of climbing frames for the same reason. frame 3 and lifting frame 2;

c、分别在相邻两层爬架3之间,以及爬架3与提升架2间挂设手拉葫芦5作为提升动力装置,并连接保险钢丝绳6;c. Hang a chain hoist 5 as a lifting power device between the two adjacent climbing frames 3, and between the climbing frame 3 and the lifting frame 2, and connect the safety wire rope 6;

d、完成一个节段的索塔施工后,接长4根钢管1,利用塔吊8提升提升架2一个索塔节段的高度,最上层的爬架3通过手拉葫芦5挂在提升架2上进行提升,下层的爬架3通过手拉葫芦5挂在相邻上层爬架3上进行提升,并调整抱箍4位置使抱箍4锁紧在钢管1上并支撑在新高度的爬架3或提升架2下方,完成一次工序循环。d. After completing the cable tower construction of a segment, connect 4 steel pipes 1, use the tower crane 8 to raise the height of a cable tower segment of the lifting frame 2, and the uppermost climbing frame 3 is hung on the lifting frame 2 through the chain hoist 5 For lifting, the lower climbing frame 3 is lifted by hanging on the adjacent upper climbing frame 3 through the hand chain hoist 5, and the position of the hoop 4 is adjusted so that the hoop 4 is locked on the steel pipe 1 and supported at the new height of the climbing frame 3 or below the lifting frame 2 to complete a process cycle.

本实施例中,索塔总高度为107.928m,塔顶高程为+114.502m,桥面以上高度为81.107m。索塔截面由“圆”和“方”组合变换而成,索塔自塔顶向下39.0m 为圆截面 段,由此至塔底为圆截面变化到矩形截面段。塔顶截面直径为6.5m,圆截面开始向矩形截面变化段直径为5.5m塔柱最小尺寸。根据索塔结构特点、牛腿位置和上塔柱斜拉索锚固区段施工要求,将索塔划分为19 个施工节段。索塔1、2节段采用常规双排脚手架进行施工,3~19节段采用本实用新型的辅助支架系统进行施工。In this embodiment, the total height of the cable tower is 107.928m, the elevation of the tower top is +114.502m, and the height above the bridge deck is 81.107m. The section of the cable tower is transformed from a combination of "circle" and "square". The cable tower is a circular section section 39.0m down from the top of the tower, and then changes from a circular section to a rectangular section section at the bottom of the tower. The diameter of the top section of the tower is 6.5m, and the diameter of the section where the circular section begins to change to the rectangular section is 5.5m. The minimum size of the tower column. According to the structural characteristics of the cable tower, the position of the corbel and the construction requirements of the anchorage section of the cable-stayed cables on the upper tower column, the cable tower is divided into 19 construction sections. The 1st and 2nd sections of the cable tower are constructed using conventional double-row scaffolding, and the 3rd to 19th sections are constructed using the auxiliary support system of the utility model.

钢管1采用大直径螺旋钢管如外径80cm以上的钢管。爬架3的高度为3.2m,爬架3中的主架体高2m,护栏高1.2m;提升架2的高度为1.72米,3 个爬架为索塔施工辅助支架的主体。保险钢丝绳6外径采用28mm。抱箍4设置4个牛腿,抱箍内径为Φ820mm,面板为12mm钢板,连接法兰为12mm钢板,肋板为12mm钢板,抱箍法兰采用8颗M20×100 8.8级高强度螺栓连接,螺栓孔为φ22。The steel pipe 1 adopts a large-diameter spiral steel pipe such as a steel pipe with an outer diameter of 80 cm or more. The height of the climbing frame 3 is 3.2m, the main frame body in the climbing frame 3 is 2m high, and the guardrail is 1.2m high; the height of the lifting frame 2 is 1.72 meters, and the three climbing frames are the main bodies of the auxiliary supports for cable tower construction. Insurance wire rope 6 external diameters adopt 28mm. The hoop 4 is provided with 4 corbels, the inner diameter of the hoop is Φ820mm, the panel is 12mm steel plate, the connecting flange is 12mm steel plate, the rib plate is 12mm steel plate, and the hoop flange is connected by 8 M20×100 8.8 grade high-strength bolts. The bolt hole is φ22.

索塔施工完成索塔节段11后,接长钢管1至待施工索塔节段高度,利用塔吊8提升提升架2,并锁紧抱箍4。利用手拉葫芦5分别逐层提升爬架3,并锁紧抱箍4,挂设保险钢丝绳6。完善活动爬梯7及爬梯通道9,方便施工作业人员从电梯10上到爬架后安全上、下作业。After the cable tower construction is completed, the cable tower segment 11 is connected, the steel pipe 1 is connected to the height of the cable tower segment to be constructed, the hoisting frame 2 is lifted by the tower crane 8, and the hoop 4 is locked. Utilize the hand chain hoist 5 to lift the climbing frame 3 layer by layer, and lock the hoop 4, and hang the safety wire rope 6. Improve the movable ladder 7 and the ladder channel 9 to facilitate the construction workers to go up and down safely from the elevator 10 to the climbing frame.

上述的对实施例的描述是为便于该技术领域的普通技术人员能理解和使用实用新型。熟悉本领域技术的人员显然可以容易地对这些实施例做出各种修改,并把在此说明的一般原理应用到其他实施例中而不必经过创造性的劳动。因此,本实用新型不限于上述实施例,本领域技术人员根据本实用新型的揭示,不脱离本实用新型范畴所做出的改进和修改都应该在本实用新型的保护范围之内。The above description of the embodiments is for those of ordinary skill in the technical field to understand and use the utility model. It is obvious that those skilled in the art can easily make various modifications to these embodiments, and apply the general principles described here to other embodiments without creative effort. Therefore, the utility model is not limited to the above-mentioned embodiments, and improvements and modifications made by those skilled in the art according to the disclosure of the utility model without departing from the category of the utility model should be within the protection scope of the utility model.

Claims (7)

1.一种索塔施工移动式支架,其特征在于,该系统包括钢管、爬架、提升架、抱箍、手拉葫芦和保险钢丝绳,所述钢管设有四根,分别固定在索塔周围,且可竖向接长,作为爬架、提升架固定和爬升的导轨;所述爬架设有三层,固定在四根钢管上,且每一层爬架均沿索塔周向布设,将索塔包围在内;所述提升架固定在四根钢管上,沿索塔周向布设,将索塔包围在内,且位于最上层爬架的上方;所述抱箍设在钢管上,用于支撑爬架或提升架;所述手拉葫芦连接在相邻两层爬架之间,或连接在爬架与提升架之间;所述保险钢丝绳:连接在相邻两层爬架之间,或连接在爬架与提升架之间。1. A mobile support for cable tower construction, characterized in that the system includes steel pipes, climbing frames, hoisting frames, hoops, chain blocks and safety wire ropes, and the steel pipes are provided with four, which are respectively fixed around the cable tower , and can be extended vertically, as a guide rail for fixing and climbing the climbing frame and lifting frame; the climbing frame has three layers, fixed on four steel pipes, and each layer of climbing frames is arranged along the circumference of the cable The tower is enclosed inside; the lifting frame is fixed on four steel pipes, arranged along the circumference of the cable tower, surrounding the cable tower, and located above the uppermost climbing frame; the hoop is arranged on the steel pipe for Support the climbing frame or the lifting frame; the chain block is connected between two adjacent layers of climbing frames, or between the climbing frame and the lifting frame; the safety wire rope: connected between two adjacent layers of climbing frames, Or be connected between the climbing frame and the lifting frame. 2.根据权利要求1所述的一种索塔施工移动式支架,其特征在于,最上层的爬架与中间层的爬架通过桁架连接成整体。2. A mobile support for cable tower construction according to claim 1, characterized in that the climbing frame on the uppermost layer and the climbing frame on the middle layer are connected as a whole by trusses. 3.根据权利要求1所述的一种索塔施工移动式支架,其特征在于,最下层的爬架与索塔之间设置型钢平台进行兜底封闭。3. The mobile support for cable tower construction according to claim 1, characterized in that, a shaped steel platform is set between the bottommost climbing frame and the cable tower to close the bottom of the pocket. 4.根据权利要求1所述的一种索塔施工移动式支架,其特征在于,还包括设置在相邻两层爬架之间或设置在爬架与提升架之间的活动爬梯。4. The mobile support for cable tower construction according to claim 1, further comprising a movable ladder arranged between two adjacent climbing frames or between the climbing frame and the lifting frame. 5.根据权利要求1所述的一种索塔施工移动式支架,其特征在于,所述的爬架包括主架体和护栏,护栏设在主架体上;爬架内设有爬梯通道,爬架四周设置钢丝网全封闭。5. A kind of cable tower construction mobile support according to claim 1, is characterized in that, described climbing frame comprises main frame body and guardrail, and guardrail is arranged on the main frame body; Climbing frame is provided with ladder channel, Steel wire mesh is set around the climbing frame and is fully enclosed. 6.根据权利要求1所述的一种索塔施工移动式支架,其特征在于,所述的提升架的平台及护栏采用铁丝网进行封闭。6. A mobile support for cable tower construction according to claim 1, characterized in that, the platform and guardrail of the lifting frame are closed with barbed wire. 7.根据权利要求1所述的一种索塔施工移动式支架,其特征在于,在抱箍的底部沿钢管壁焊接4根钢筋作为保险支撑。7. A mobile support for cable tower construction according to claim 1, characterized in that four steel bars are welded along the steel pipe wall at the bottom of the hoop as a safety support.
CN201620186366.7U 2016-03-11 2016-03-11 Cable support tower construction removable support Expired - Lifetime CN205501830U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620186366.7U CN205501830U (en) 2016-03-11 2016-03-11 Cable support tower construction removable support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620186366.7U CN205501830U (en) 2016-03-11 2016-03-11 Cable support tower construction removable support

Publications (1)

Publication Number Publication Date
CN205501830U true CN205501830U (en) 2016-08-24

Family

ID=56731404

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620186366.7U Expired - Lifetime CN205501830U (en) 2016-03-11 2016-03-11 Cable support tower construction removable support

Country Status (1)

Country Link
CN (1) CN205501830U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105755959A (en) * 2016-03-11 2016-07-13 广东省长大公路工程有限公司 Auxiliary bracket system suitable for construction of cable towers with different sections and building method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105755959A (en) * 2016-03-11 2016-07-13 广东省长大公路工程有限公司 Auxiliary bracket system suitable for construction of cable towers with different sections and building method
CN105755959B (en) * 2016-03-11 2017-07-28 广东省长大公路工程有限公司 Suitable for the Sarasota construction auxiliary stand system and building method of different cross section

Similar Documents

Publication Publication Date Title
CN102864936B (en) Combination lifting construction method for large-scale high hollow building roof of steel structure
CN103291076B (en) Multilayer steel truss fragmented reverse hoisting construction method in arc-shaped frame
CN102661054B (en) Lateral reinforcing structure in whole lifting of plane steel truss and whole lifting method
CN101435276B (en) Hydraulic lifting and positioning device for steel beam at top of silo structure and construction method thereof
CN102535845A (en) Construction method of bearing frame of corridor structure
CN103410101B (en) Tower crane conversion method for construction of parabola-shaped ultrahigh pier
CN113401815B (en) High-altitude conversion system of core tube tower crane of super high-rise building and construction method thereof
CN207919363U (en) A kind of Filled Steel Tubular Arch Bridge low level assembly lifting system
CN104695337A (en) Self-lifting sliding and turnover construction system and construction method
CN106400951A (en) Synchronous construction method for horizontal and vertical structures of super high-rise building
CN104847102A (en) Wall attaching method and device of attached self-lifting scaffold on retraction section of building outer wall
CN111809528B (en) A pier column vertical cage platform channel construction method and cage platform channel device
CN107575032A (en) A kind of bolt-ball net frame roofing installation method
CN206495142U (en) A kind of overhead pier column operation platform of assembled
CN105888227B (en) Superelevation is tubaeform steel structure exterior finish operation platform and its building method
CN104989092B (en) A kind of construction method of high-altitude overhanging superposed type steel truss bearing platform
CN201908447U (en) Lift-type horizontal safety net
CN206267031U (en) A kind of solid pier climbing support of bridge construction
CN203547125U (en) Column type overall steel platform hydraulic creeping formwork
CN205501830U (en) Cable support tower construction removable support
CN107268971B (en) A double self-elevating external climbing frame of a super high-rise building and its application method
CN113062584A (en) Multipoint elevator shaft construction lifting platform and construction method
CN112723094A (en) Integrated wall-attached device based on synchronous climbing of light steel platform
CN108797350B (en) Tower column inner and outer stiff skeleton device and construction method thereof
CN201915614U (en) Integral electric climbing frame suitable for shear wall structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20160824