CN205400043U - Constructional column is funnel combination tool for concreting - Google Patents

Constructional column is funnel combination tool for concreting Download PDF

Info

Publication number
CN205400043U
CN205400043U CN201620164026.4U CN201620164026U CN205400043U CN 205400043 U CN205400043 U CN 205400043U CN 201620164026 U CN201620164026 U CN 201620164026U CN 205400043 U CN205400043 U CN 205400043U
Authority
CN
China
Prior art keywords
template
funnel
constructional column
boats
tree
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620164026.4U
Other languages
Chinese (zh)
Inventor
刘洪延
杨广田
孙朋
陈俊卫
孙文峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fifth Engineering Bureau Co Ltd
Original Assignee
China Construction Fifth Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fifth Engineering Bureau Co Ltd filed Critical China Construction Fifth Engineering Bureau Co Ltd
Priority to CN201620164026.4U priority Critical patent/CN205400043U/en
Application granted granted Critical
Publication of CN205400043U publication Critical patent/CN205400043U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to a two secondary structure construction tool, especially a constructional column is funnel combination tool for concreting. The instrument include the template, template and blockwork form enclosed construction all around, have offered the preformed hole at the template top of blockwork one side, the wood a tree, used in making timber for boats sets up respectively in the four corners of template, and the steel pipe is transversely placed and is corresponded respectively and sets up in the template of blockwork both sides, and the corresponding steel pipe of placing passes through through -wall screw and connects fixedly, be equipped with the slide between the template that is equipped with preformed hole one side and wooden a tree, used in making timber for boats, the steel sheet is placed in the slide, and the funnel corresponds the setting with the preformed hole, and the funnel passes through steel bar connection to be fixed on wooden a tree, used in making timber for boats. The utility model discloses simple structure, convenient operation, construction cost is low, and the efficiency of construction is high, has improved labor efficiency, has eliminated the constructional column and has pour uncompacted mass defect, and it is good to have improved antidetonation effect and appearance quality.

Description

A kind of constructional column casting concrete funnel tool kit
Technical field
This utility model relates to secondary structure construction tool, especially a kind of constructional column casting concrete funnel tool kit.
Background technology
It is together important working procedure in secondary structure construction that constructional column is built, and has beam or plate yet with constructional column top, causes constructional column top honeycomb, pitted skin often occur.Traditional method is to make wood funnel on top, concreting is complete reach form removal condition after, form removal, then pick the unnecessary concrete of cutter.Owing to constructional column template plays support concrete effect, wood funnel cannot be removed immediately, and can not be again with after removing, causing significant wastage, and workload is relatively big, field worker processing funnel is wasted time and energy, often it is reluctant to coordinate, there is direct casting concrete, the rear phenomenon mending reserved opening, increase construction cost.
Development along with building trade, during secondary structure construction, the special funnel of constructional column casting concrete is removed after having built constructional column and is recycled in next constructional column concreting, it is possible to increase Constructional Col-umn Construction efficiency, is ensureing that constructional column is built closely knit quality and improved anti seismic efficiency simultaneously.
Utility model content
Problem to be solved in the utility model is to provide a kind of constructional column casting concrete funnel tool kit, described instrument adopts detachable separating type to recycle funnel cooperation steel plate, this funnel is after building constructional column concrete, knock steel plate with hammer and block preformed hole, then being dismountable funnel, this funnel can be recycled in next constructional column casting concrete.
In order to solve above-mentioned technical problem, the technical solution of the utility model is achieved in that
A kind of constructional column casting concrete funnel tool kit, described instrument includes template, and template forms all round closure structure with blockwork, and the die head in blockwork side offers preformed hole;Wood a tree, used in making timber for boats is separately positioned on the corner of template, and steel pipe transverse is placed and is correspondingly arranged in the template of blockwork both sides respectively, and the corresponding steel pipe placed connects fixing by screw rod through walls;Being provided with slideway being provided with between the template of preformed hole side and wood a tree, used in making timber for boats, steel plate is positioned in slideway, and funnel and preformed hole are correspondingly arranged, and funnel is fixed on wood a tree, used in making timber for boats by bar connecting.
Further, described preformed hole is square, and its specification is long 200mm × wide 200mm;
Further, in described slideway, it is provided with lubricant, so that steel plate can upward sliding more smoothly;
Further, being provided with reinforcing rib in the middle part of described steel plate, this reinforcing rib is I-shaped, transverse steel rib plays restriction steel plate off normal, prevents the effect of steel plate deformed, vertical steel rib plays the effect transmitting upwards hammer force, and hammer must be exerted oneself when rising uniformly, can not suddenly strike and hit;
Further, described reinforcing bar has fixed funnel, prevents funnel deformity effect, for preventing funnel deformity serious, is horizontally disposed with reinforcement in the middle part of hopper outlet, and reinforcement is fastened on wood a tree, used in making timber for boats and funnel.
This utility model beneficial effect compared to existing technology:
This utility model simple in construction, easy to operate, construction cost is low, and efficiency of construction is high, improves labor efficiency, eliminates constructional column and build uncompacted mass defect, improves anti seismic efficiency and presentation quality is excellent.Have the advantage that specifically
1, the repeatable utilization of funnel, reduces workman and repeats processing funnel and remove the time of funnel.
2, can remove immediately, recycle, make funnel reuse, improve efficiency of construction.
3, pick cutter amount to be greatly reduced, only pick cutter 15mm thickness concrete, reduce the labor intensity of workman, easy construction.
4, funnel adopts iron plate to make, and removes in time, is hardly damaged, can be used for turnover and allot.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model
Fig. 2 of the present utility model partly cuts open structural representation.
Fig. 3 is the structure for amplifying schematic diagram at this utility model A place.
Fig. 4 is the structural representation of funnel in this utility model.
In figure: 1-structural beams;2-blockwork;3-template;4-preformed hole;5-steel plate;6-wood a tree, used in making timber for boats;7-steel pipe;8-screw rod through walls;9-constructional column;10-funnel;11-reinforcing bar.
Detailed description of the invention
Below in conjunction with accompanying drawing, this utility model is described in further detail.
As shown in Figure 1,2,3, 4, a kind of constructional column casting concrete funnel tool kit, described instrument includes template 3, and template 3 and blockwork 2 form all round closure structure, offer preformed hole 4 at template 3 top of blockwork 2 side;Wood a tree, used in making timber for boats 6 is separately positioned on the corner of template 3, and steel pipe 7 is laterally disposed and is correspondingly arranged in the template 3 of blockwork 2 both sides respectively, and the corresponding steel pipe 7 placed connects fixing by screw rod 8 through walls;Being provided with slideway being provided with between the template 3 of preformed hole 4 side and wood a tree, used in making timber for boats 6, steel plate 5 is positioned in slideway, and funnel 10 and preformed hole 4 are correspondingly arranged, and funnel 10 is fastened on wood a tree, used in making timber for boats 6 by reinforcing bar 11.
Described preformed hole 4 is square, and its specification is long 200mm × wide 200mm;
It is provided with lubricant, so that steel plate 5 can upward sliding more smoothly in described slideway;
It is provided with reinforcing rib in the middle part of described steel plate 5, this reinforcing rib is I-shaped, the effect that transverse steel rib plays restriction steel plate 5 off normal, prevents steel plate 5 from deforming, and vertical steel rib plays the effect transmitting upwards hammer force, hammer must be exerted oneself when rising uniformly, can not suddenly strike and hit;
Described reinforcing bar 11 has fixed funnel 10, prevents funnel 10 metamorphosis, for preventing funnel 10 from deforming seriously, is horizontally disposed with reinforcement at funnel 10 outlet middle part, and reinforcement is fastened on wood a tree, used in making timber for boats 6 and funnel 10.
This utility model can be removed after utilizing constructional column casting concrete immediately, recycles this utility model and replaces traditional wooden funnel tool kit.This utility model is applied in the construction technology process of constructional column casting concrete:
Installation constitution column template 3 preformed hole 4 → on template 3 top are installed steel plate 5, are installed structure spar a tree, used in making timber for boats 6, steel pipe 7, screw rod 8 → casting concrete through walls → hammering steel plate 5 make its rise to bottom structural beams 1 → remove funnel 10, remove steel plate 5 → pick cutter 15mm thickness concrete.
(1) installation constitution column template 3 preformed hole 4
After constructional column 9 both sides lay blockwork 2 by code requirement, the template 3 that can carry out constructional column 9 is installed, and reserves the preformed hole 4 of long 200 × wide 200 when template 3 is installed at an upper portion thereof, is used for installing funnel 10 with casting concrete.
(2) steel plate 5 is installed on template 3 top, installs structure spar a tree, used in making timber for boats 6, steel pipe 7, screw rod through walls 8
Steel plate 5 thickness is 1.5mm, namely steel plate 5 is arranged on while wood a tree, used in making timber for boats 6 and steel pipe 7 are reinforced between template 3 and wood a tree, used in making timber for boats 6, with the space between template 3 and wood a tree, used in making timber for boats 6 for slideway, the steel pipe 7 of steel plate 5 bottom must be reinforced firmly, slideway position can be somewhat lax, but ensure the mould that can not rise, increase lubricant at slideway position, so that steel plate can upward sliding more smoothly.
(3) casting concrete
After template 3 has installed, can carrying out that constructional column 9 is concrete builds work, in casting process, small vibration rod can be adopted at constructional column 9 vibrating bottom, top must vibration compacting.
(4) hammering steel plate 5 makes it rise to bottom structural beams 1
After concreting, namely carrying out the hammer liter work of steel plate 5, the φ 14 transverse steel rib on steel plate 5 plays restriction steel plate 5 off normal and the effect preventing steel plate 5 from deforming, and vertical steel rib plays the effect transmitting upwards hammer force, hammer must be exerted oneself when rising uniformly, can not suddenly strike and hit.
In the process of hammering, and notice whether the concrete observing constructional column 9 top has sagging, if any, then to carry out concrete supplementing, it is ensured that constructional column 9 top concrete compaction, without the mass defect of honeycomb, pitted skin.
(5) remove funnel 10, remove steel plate 5
After steel plate 5 hammer has risen, i.e. dismountable funnel 10, what be immediately made available on next constructional column 9 after funnel 10 dismounting builds work, it is achieved the recycling of funnel 10,
Post 9 concrete to be constructed to remove prefabricated steel 5 after reaching form removal condition in time, never non-disconnectable removed complete, and otherwise steel plate 5 is not easily dismantled, and bad when picking cutter concrete picks cutter, also makes steel plate 5 impaired, it is impossible to recycling.
(6) cutter 15mm thickness concrete is picked
After constructional column 9 concrete final set, the 15mm thickness concrete for having more to carry out picking cutter, to meet the needs of later stage plastering process, as without plastering, also repaired picking cutter position, meet design requirement.
In sum, these are only preferred embodiment of the present utility model, be not intended to limit protection domain of the present utility model.All within spirit of the present utility model and principle, any amendment of making, equivalent replacement, improvement etc., should be included within protection domain of the present utility model.

Claims (5)

1. a constructional column casting concrete funnel tool kit, it is characterized in that: described instrument includes template (3), template (3) forms all round closure structure with blockwork (2), offers preformed hole (4) at template (3) top of blockwork (2) side;Wood a tree, used in making timber for boats (6) is separately positioned on the corner of template (3), and steel pipe (7) is laterally disposed and is correspondingly arranged in the template (3) of blockwork (2) both sides respectively, and the corresponding steel pipe (7) placed connects fixing by screw rod through walls (8);Being provided with slideway being provided with between the template (3) of preformed hole (4) side and wood a tree, used in making timber for boats (6), steel plate (5) is positioned in slideway, and funnel (10) and preformed hole (4) are correspondingly arranged, and funnel (10) is fastened on wood a tree, used in making timber for boats (6) by reinforcing bar (11).
2. a kind of constructional column casting concrete funnel tool kit according to claim 1, it is characterised in that: described preformed hole (4) is for square, and its specification is long 200mm × wide 200mm.
3. a kind of constructional column casting concrete funnel tool kit according to claim 1, it is characterised in that: it is provided with lubricant in described slideway.
4. a kind of constructional column casting concrete funnel tool kit according to claim 1, it is characterised in that: described steel plate (5) middle part is provided with reinforcing rib, and this reinforcing rib is I-shaped.
5. a kind of constructional column casting concrete funnel tool kit according to claim 1, it is characterised in that: described funnel (10) outlet middle part is horizontally disposed with reinforcement, and reinforcement is fastened on wood a tree, used in making timber for boats (6) and funnel (10).
CN201620164026.4U 2016-03-04 2016-03-04 Constructional column is funnel combination tool for concreting Expired - Fee Related CN205400043U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620164026.4U CN205400043U (en) 2016-03-04 2016-03-04 Constructional column is funnel combination tool for concreting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620164026.4U CN205400043U (en) 2016-03-04 2016-03-04 Constructional column is funnel combination tool for concreting

Publications (1)

Publication Number Publication Date
CN205400043U true CN205400043U (en) 2016-07-27

Family

ID=56444613

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620164026.4U Expired - Fee Related CN205400043U (en) 2016-03-04 2016-03-04 Constructional column is funnel combination tool for concreting

Country Status (1)

Country Link
CN (1) CN205400043U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106481082A (en) * 2016-11-17 2017-03-08 云南省建设投资控股集团有限公司 A kind of improvement casting method of constructional column
CN108999407A (en) * 2018-09-29 2018-12-14 北京首钢建设集团有限公司 A kind of constructional column concreting top uses the construction method of funnel
CN109113338A (en) * 2018-09-13 2019-01-01 中铁十六局集团城市建设发展有限公司 A kind of tool-type mould bases of constructional column top one-piece casting
CN110528874A (en) * 2019-09-27 2019-12-03 山西运城建工集团有限公司 Constructional column column cap concreting mould bases in a kind of filling wall
CN112376904A (en) * 2020-11-13 2021-02-19 罗奕舵 Feeding funnel of constructional column pouring mold and constructional column pouring method
CN113565465A (en) * 2021-07-19 2021-10-29 中铁十九局集团第六工程有限公司 Filling and pouring device for lining coring hole and construction method thereof

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106481082A (en) * 2016-11-17 2017-03-08 云南省建设投资控股集团有限公司 A kind of improvement casting method of constructional column
CN109113338A (en) * 2018-09-13 2019-01-01 中铁十六局集团城市建设发展有限公司 A kind of tool-type mould bases of constructional column top one-piece casting
CN109113338B (en) * 2018-09-13 2024-03-19 中铁十六局集团城市建设发展有限公司 Tool type die carrier for integrally pouring top of constructional column
CN108999407A (en) * 2018-09-29 2018-12-14 北京首钢建设集团有限公司 A kind of constructional column concreting top uses the construction method of funnel
CN110528874A (en) * 2019-09-27 2019-12-03 山西运城建工集团有限公司 Constructional column column cap concreting mould bases in a kind of filling wall
CN112376904A (en) * 2020-11-13 2021-02-19 罗奕舵 Feeding funnel of constructional column pouring mold and constructional column pouring method
CN113565465A (en) * 2021-07-19 2021-10-29 中铁十九局集团第六工程有限公司 Filling and pouring device for lining coring hole and construction method thereof

Similar Documents

Publication Publication Date Title
CN205400043U (en) Constructional column is funnel combination tool for concreting
CN107263684A (en) The entirety of PC wallboard moulds and the application mould enters mould method
CN104074314A (en) Pre-buried shear key connector box for precast facade panel and machining method of pre-buried shear key connector box
CN201891260U (en) Hanging template
CN105569333A (en) Construction formwork of cantilever layer outer wall preformed hole, and construction method
CN101906875A (en) Hollow slab template for buildings
CN207048312U (en) Tool-type post formwork for Large area reinforced concrete post
CN208343121U (en) Prefabricated assembled steel structure concrete wallboard mould
CN207177286U (en) Add region mould after fabricated shear wall is reserved
CN207314830U (en) A kind of shear wall negative and positive angle construction mould
CN210976630U (en) Repeatedly-usable construction column bell mouth concrete pouring device free of chiseling
CN204571289U (en) A kind of construction formwork of overhang layer exterior wall preformed hole
CN201095866Y (en) Elevator barrel formwork
CN111236623A (en) Novel construction method for formwork reinforcement system
CN203429798U (en) Embedded bar structure for horizontal secondary structure of super high-rise
CN101173530A (en) Construction method of concrete wall panel
CN104908148A (en) Cable trough cover plate prefabricated template and construction method thereof
CN107214819B (en) Building constructional column shaping moulding box
CN105625708B (en) A kind of aluminum wood composite shuttering system for building
CN211849566U (en) Roughing mill body reserved bolt hole support-free template
CN114704080A (en) Aluminum template and PC (polycarbonate) component combined mold hanging system and construction method
CN105239770B (en) Integrated casting steel framework plastic building template system
CN105971269A (en) Wallboard structure with template screw hole positions standardized
CN210828837U (en) Prefabricated window component that wafts of assembled building
CN104453235B (en) Current conversion station fire wall construction technology

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160727

Termination date: 20190304

CF01 Termination of patent right due to non-payment of annual fee