CN205397785U - Construction elevator attaches wall interval superelevation subassembly - Google Patents

Construction elevator attaches wall interval superelevation subassembly Download PDF

Info

Publication number
CN205397785U
CN205397785U CN201620258572.4U CN201620258572U CN205397785U CN 205397785 U CN205397785 U CN 205397785U CN 201620258572 U CN201620258572 U CN 201620258572U CN 205397785 U CN205397785 U CN 205397785U
Authority
CN
China
Prior art keywords
steel pipe
attached wall
assembly
tower crane
connecting rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620258572.4U
Other languages
Chinese (zh)
Inventor
范水清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hainan Pangyuan Construction Machinery Leasing Co Ltd
Original Assignee
Hainan Pangyuan Construction Machinery Leasing Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hainan Pangyuan Construction Machinery Leasing Co Ltd filed Critical Hainan Pangyuan Construction Machinery Leasing Co Ltd
Priority to CN201620258572.4U priority Critical patent/CN205397785U/en
Application granted granted Critical
Publication of CN205397785U publication Critical patent/CN205397785U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Types And Forms Of Lifts (AREA)

Abstract

The utility model discloses a construction elevator attaches wall interval superelevation subassembly, it includes that the tower crane standard of longitudinal distribution saves, last top -down of this tower crane standard festival transverse distribution in proper order has two auxiliary stay framves, the one end of auxiliary stay frame was fixed on the tower crane standard festival, the other end of auxiliary stay frame is unsettled form and stretches out in the standard of hanging outside the festival, connect through the connection steel pipe of longitudinal distribution between upper and lower two auxiliary stays frame other end, tower crane standard festival department still transversely is provided with attaches wall link bar assembly, should attach the below position that wall link bar assembly is located two auxiliary stay framves. The subassembly adopts the light material, has effectively reduced construction intensity to simplified the construction process, effective monitoring cost reduces the cost, attaches the wall subassembly and adopts the auxiliary stay frame, and adopt and introduce oblique extension steel pipe subassembly and complex auxiliary stay steel pipe with it, has effectively promoted the stability and the security that attach the wall telephone structure when attaching the wall height degree having extended.

Description

Construction elevator attached wall spacing superelevation assembly
Technical field
This utility model relates to the technical field of construction, specifically a kind of construction elevator attached wall spacing superelevation assembly, particularly to its mechanical connecting structure.
Background technology
In some engineering projects, the spacing of part floor is relatively larger (beyond 10.5m), and the attached wall spacing of construction elevator can be more taller than the spacing (3 ~ 10.5m) between general attached wall assembly, and existing general attached wall assembly cannot realize the attached wall construction of highly effective and safe.
Summary of the invention
The purpose of this utility model is in that to provide a kind of construction elevator attached wall spacing superelevation assembly, and efficiently solving that the spacing of floor in project is relatively larger cannot the problem of efficient stable attached wall construction.
nullTo achieve these goals: the technical solution of the utility model is: construction elevator attached wall spacing superelevation assembly,It is characterized in that: it includes the standard section of tower crane of genesis analysis,On this standard section of tower crane, cross direction profiles has two auxiliary support frames successively from top to bottom,One end of auxiliary support frame is fixed on standard section of tower crane,The other end of auxiliary support frame is that hanging shape stretches out in and hangs outside standard knot,Connected by the joint steel pipe of genesis analysis between upper and lower two auxiliary support frame other ends,Standard section of tower crane place is also horizontally arranged with attached wall connecting rod assembly,This attached wall connecting rod assembly is positioned at the lower position of two auxiliary support frames,One end of attached wall connecting rod assembly is connected with standard section of tower crane,The other end of attached wall connecting rod assembly is fixing with floorboard to be connected,Diagonally distribute between the other end of joint steel pipe and attached wall connecting rod assembly at least two and stretched steel pipe assembly,An auxiliary supporting steel pipe it is additionally provided with between two stretching steel pipe assemblies,Two stretch between steel pipe assembly in non-parallel shape.
The utility model discloses construction elevator attached wall spacing superelevation assembly, assembly adopts light material, effectively reduce construction intensity, and simplify working procedure, effectively controlling cost, reduce cost, attached wall assembly adopts auxiliary support frame, and adopt introducing oblique extension steel pipe assembly and matched auxiliary supporting steel pipe, while the attached wall height that extended, it is effectively improved stability and the safety of engaged mechanism.
Accompanying drawing explanation
Fig. 1 is this utility model structural representation.
Fig. 2 is this utility model embodiment top view.
Fig. 3 is attached wall connecting rod modular construction schematic diagram.
Fig. 4 is auxiliary support frame structural representation.
Wherein:
1, standard section of tower crane;
2, auxiliary support frame;
3, joint steel pipe;
4, attached wall connecting rod assembly;
5, floorboard;
6, steel pipe assembly is stretched;
7, auxiliary supporting steel pipe;
8, rectangular pipe;
9, short square tube;
10, gusset;
11, single pipe clamp;
12, two-tube card;
13, frame structure.
Detailed description of the invention
With reference to the accompanying drawings, this utility model is further described below.
nullThe utility model discloses construction elevator attached wall spacing superelevation assembly,It is different from prior art and is in that: it includes the standard section of tower crane 1 of genesis analysis,On this standard section of tower crane 1, cross direction profiles has two auxiliary support frames 2 successively from top to bottom,One end of auxiliary support frame 2 is fixed on standard section of tower crane 1,The other end of auxiliary support frame 2 is that hanging shape stretches out in and hangs outside standard knot 1,Connected by the joint steel pipe 3 of genesis analysis between upper and lower two auxiliary support frame 2 other ends,Standard section of tower crane 1 place is also horizontally arranged with attached wall connecting rod assembly 4,This attached wall connecting rod assembly 4 is positioned at the lower position of two auxiliary support frames 2,One end of attached wall connecting rod assembly 4 is connected with standard section of tower crane 1,The other end of attached wall connecting rod assembly 4 is fixing with floorboard 5 to be connected,Diagonally distribute between the other end of joint steel pipe 3 and attached wall connecting rod assembly 4 at least two and stretched steel pipe assembly 6,An auxiliary supporting steel pipe 7 it is additionally provided with between two stretching steel pipe assemblies 6,Two stretch between steel pipe assembly 6 in non-parallel shape.
In the specific implementation, described auxiliary support frame 2 is made up of rectangular pipe 8 and a short square tube 9 of two parallel distributions, wherein, one end of two root length square tubes 8 is each perpendicular to above-mentioned short square tube 9 and arranges, the junction of rectangular pipe 8 and short square tube 9 is provided with the gusset 10 of one piece of right triangular shape, one right-angle side of this gusset 10 is fixed on rectangular pipe 8 outer wall place, and another right-angle side of gusset 10 is fixed and short square tube 9 outer wall place, and short square tube 9 is respectively arranged with a single pipe clamp 11 near the outer wall place at two ends.
In the specific implementation, described joint steel pipe 3 is connected with stretching steel pipe assembly 6 by two-tube card 12, can be effectively increased bonding strength, reduces difficulty of construction.
In the specific implementation, the stage casing of described attached wall connecting rod assembly 4 is frame structure 13.
Above content is in conjunction with concrete preferred implementation further detailed description of the utility model, it is impossible to assert that this utility model is embodied as being confined to these explanations above-mentioned.For this utility model person of an ordinary skill in the technical field, without departing from the concept of the premise utility, it is also possible to make some simple deduction or replace, protection domain of the present utility model all should be considered as belonging to.

Claims (4)

  1. null1. construction elevator attached wall spacing superelevation assembly,It is characterized in that: it includes the standard section of tower crane (1) of genesis analysis,On this standard section of tower crane (1), cross direction profiles has two auxiliary support frames (2) successively from top to bottom,One end of auxiliary support frame (2) is fixed on standard section of tower crane (1),The other end of auxiliary support frame (2) is that hanging shape stretches out in and hangs standard knot (1) outward,Connected by the joint steel pipe (3) of genesis analysis between upper and lower two auxiliary support frame (2) other ends,Standard section of tower crane (1) place is also horizontally arranged with attached wall connecting rod assembly (4),This attached wall connecting rod assembly (4) is positioned at the lower position of two auxiliary support frames (2),One end of attached wall connecting rod assembly (4) is connected with standard section of tower crane (1),The other end of attached wall connecting rod assembly (4) is fixing with floorboard (5) to be connected,Diagonally distribute between the other end of joint steel pipe (3) and attached wall connecting rod assembly (4) at least two and stretched steel pipe assembly (6),Auxiliary supporting steel pipe (7) it is additionally provided with between two stretchings steel pipe assembly (6),Two stretch between steel pipe assembly (6) in non-parallel shape.
  2. 2. construction elevator attached wall spacing superelevation assembly according to claim 1, it is characterized in that: described auxiliary support frame (2) is made up of rectangular pipe (8) and a short square tube (9) of two parallel distributions, wherein, one end of two root length square tubes (8) is each perpendicular to above-mentioned short square tube (9) and arranges, the junction of rectangular pipe (8) and short square tube (9) is provided with the gusset (10) of one piece of right triangular shape, one right-angle side of this gusset (10) is fixed on rectangular pipe (8) outer wall place, another right-angle side of gusset (10) is fixed and short square tube (9) outer wall place, short square tube (9) is respectively arranged with a single pipe clamp (11) near the outer wall place at two ends.
  3. 3. construction elevator attached wall spacing superelevation assembly according to claim 1, it is characterised in that: described joint steel pipe (3) is connected with stretching steel pipe assembly (6) by two-tube card (12).
  4. 4. construction elevator attached wall spacing superelevation assembly according to claim 1, it is characterised in that: the stage casing of described attached wall connecting rod assembly (4) is frame structure (13).
CN201620258572.4U 2016-03-31 2016-03-31 Construction elevator attaches wall interval superelevation subassembly Active CN205397785U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620258572.4U CN205397785U (en) 2016-03-31 2016-03-31 Construction elevator attaches wall interval superelevation subassembly

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620258572.4U CN205397785U (en) 2016-03-31 2016-03-31 Construction elevator attaches wall interval superelevation subassembly

Publications (1)

Publication Number Publication Date
CN205397785U true CN205397785U (en) 2016-07-27

Family

ID=56419218

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620258572.4U Active CN205397785U (en) 2016-03-31 2016-03-31 Construction elevator attaches wall interval superelevation subassembly

Country Status (1)

Country Link
CN (1) CN205397785U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106115512A (en) * 2016-08-26 2016-11-16 甘肃第四建设集团有限责任公司 A kind of fixing device of steel house tower crane attachment detachable steel box beam
CN106185549A (en) * 2016-09-22 2016-12-07 中建八局第四建设有限公司 A kind of wall-attaching equipment of construction elevator
CN106495026A (en) * 2017-01-09 2017-03-15 山东华邦建设集团有限公司 Attachment built temporarily by construction tower crane

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106115512A (en) * 2016-08-26 2016-11-16 甘肃第四建设集团有限责任公司 A kind of fixing device of steel house tower crane attachment detachable steel box beam
CN106115512B (en) * 2016-08-26 2018-01-16 甘肃第四建设集团有限责任公司 A kind of fixing device of steel house tower crane attachment detachable steel box beam
CN106185549A (en) * 2016-09-22 2016-12-07 中建八局第四建设有限公司 A kind of wall-attaching equipment of construction elevator
CN106495026A (en) * 2017-01-09 2017-03-15 山东华邦建设集团有限公司 Attachment built temporarily by construction tower crane

Similar Documents

Publication Publication Date Title
CN204343644U (en) A kind of Novel hanging basket fastening devices for curtain wall construction
CN205397785U (en) Construction elevator attaches wall interval superelevation subassembly
CN206513004U (en) A kind of movable hanger for being easy to roof inner slab to install
CN201598820U (en) Single-point suspension external hanging rack
CN204310644U (en) A kind of single suspension centre cage guide installation and maintenance hanging basket
CN211499713U (en) All-steel attached lifting scaffold
CN207363238U (en) A kind of main frame of universal elevating scaffold
CN108590151A (en) A kind of scalable elevator hanging basket in four sides
CN201284551Y (en) Suspension type simple platform for work high above ground
CN204024013U (en) A kind of self-climbing lifting material platform
CN205634649U (en) Purlin derrick crane girder
CN205397790U (en) A subassembly that is used for construction elevator to attach wall pull rod overlength
CN204400568U (en) Become span hanging basket suspension mechanism
CN207919351U (en) Hanging basket
CN205713050U (en) A kind of scaffold protection network of municipal works
CN206053269U (en) Bamboo ferrum mixing frame for building
CN205840289U (en) A kind of suspension type vertical operating platform
CN211691525U (en) Construction device for overhanging type inclined curtain wall
CN204059909U (en) With the horizontal truss of avoiding structure
CN206667784U (en) The erecting device of glass curtain wall outer visor
CN204174915U (en) Scaffold
CN203394008U (en) Suspension type hanging bracket used on plane truss
CN208844896U (en) A kind of scalable elevator hanging basket in four sides
CN206051211U (en) A kind of special extended type wall-attached frame
CN205901172U (en) Nearly pole of transmission line overhauls corridor hanger device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: 571924 station 050, 1st floor, building a25, Hainan Ecological Software Park, Chengmai County, Haikou City, Hainan Province

Patentee after: Hainan pangyuan Mechanical Engineering Co., Ltd

Address before: 1-1-302, East District, government service center building, No. 8, Yantian Road, Yangpu Economic Development Zone, Hainan Province

Patentee before: HAINAN PANGYUAN CONSTRUCTION MACHINERY LEASING Co.,Ltd.

CP03 Change of name, title or address