CN204298825U - 基坑浇筑溜管支撑调节装置 - Google Patents
基坑浇筑溜管支撑调节装置 Download PDFInfo
- Publication number
- CN204298825U CN204298825U CN201420740116.4U CN201420740116U CN204298825U CN 204298825 U CN204298825 U CN 204298825U CN 201420740116 U CN201420740116 U CN 201420740116U CN 204298825 U CN204298825 U CN 204298825U
- Authority
- CN
- China
- Prior art keywords
- elephant trunk
- regulating device
- supporting
- foundation ditch
- screw rod
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Sewage (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
- Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
Abstract
本实用新型提供了一种基坑浇筑溜管支撑调节装置,基坑的底面铺设有钢筋笼,钢筋笼上设立有支撑架,溜管架设于支撑架上,该支撑调节装置包括:螺杆,旋置于支撑架的顶端;顶托,固设于螺杆的顶端,溜管支撑于顶托上。本实用新型对支撑固定后的溜管做高度上的精确调整,进而解决了分段式溜管架设于支撑架后不能准确对接的问题,并进一步提高施工效率。
Description
技术领域
本实用新型涉及一种支撑调节装置,具体涉及一种基坑浇筑溜管支撑调节装置。
背景技术
目前,在基坑混凝土浇筑施工时,一般会采用在基坑内布置若干条木质溜槽或者分段连接的溜管浇筑混凝土,并在溜槽或溜管下方采用钢管搭设支撑架体。但是,支撑架体本身的高度在出厂后即已固定,一旦当溜管架设于支撑架体上之后,需将各段溜管对接形成一体,就很有可能遇到不能准确对接的情况,此时,便难以再对溜管做高度上的调整。
实用新型内容
为克服现有技术所存在的缺陷,现提供一种基坑浇筑溜管支撑调节装置,以对支撑固定后的溜管做高度上的精确调整,进而解决分段式溜管架设于支撑架后不能准确对接的问题,并进一步提高施工效率。
为实现上述目的,提供一种基坑浇筑溜管支撑调节装置,基坑的底面铺设有钢筋笼,钢筋笼上设立有支撑架,溜管架设于支撑架上,该支撑调节装置包括:
螺杆,旋置于支撑架的顶端;
顶托,固设于螺杆的顶端,溜管支撑于顶托上。
本实用新型基坑浇筑溜管支撑调节装置的有益效果在于,通过在支撑架顶端设置螺杆同时配合顶托对溜管进行高度上的精确调整。
优选地,支撑架的顶端开设有螺纹孔,螺杆螺合于螺纹孔内。
优选地,支撑架的顶端两侧固设有挡板,螺杆位于两侧的挡板之间,两侧的挡板与顶托形成一承托空间,溜管支撑调节于承托空间内。
附图说明
图1为本实用新型基坑浇筑溜管支撑调节装置的整体结构示意图;
图2为对应于图1中A区域的放大结构示意图。
具体实施方式
为利于对本实用新型的结构的了解,以下结合附图及实施例进行说明。
参照图1,为本实用新型基坑浇筑溜管支撑调节装置的整体结构示意图。如图1所示,本实用新型提供了一种基坑浇筑溜管支撑调节装置,基坑1的底面铺设有钢筋笼2,钢筋笼2上设立有支撑架3,溜管4架设于支撑架3上,该支撑调节装置5包括:螺杆50,旋置于支撑架3的顶端;顶托52,固设于螺杆50的顶端,溜管4支撑于该顶托52上。
参照图2,为对应于图1中A区域的放大结构示意图。如图2所示,具体地,支撑架3的顶端开设有螺纹孔,螺杆50螺合于该螺纹孔内。支撑架3的顶端两侧固设有挡板54,螺杆50位于两侧的挡板54之间,两侧的挡板54与顶托52形成一承托空间56,溜管4支撑调节于该承托空间56内。
在具有上述实施过程后,本实用新型可按以下过程进行实施:
如图1,先在基坑1的底面铺设包括上下两层钢筋以形成待浇筑的钢筋笼2,再可选用格构柱作为支撑架3,在钢筋笼2上固定支撑架3。
结合图2,将上述的支撑调节装置5安装于支撑架3的顶端。具体地,将螺杆50螺合于支撑架3顶端的螺纹孔内,螺杆50的顶端固设有顶托52,再在螺杆50的两侧固设两块挡板54,以形成上述的承托空间56。
随后,在基坑1的侧壁安装形成一条斜向设置的溜管4,将该溜管4的底端对应架接于支撑架3顶端的顶托52上。
当实施溜管4的各段连接工作时,若发现某一段溜管4与相邻段溜管4的高度不能匹配,便可人为上下调整螺杆50,使得该段溜管4在承托空间56内到达相匹配的连接高度。
以上结合附图实施例对本实用新型进行了详细说明,本领域中普通技术人员可根据上述说明对本实用新型做出种种变化例。因而,实施例中的某些细节不应构成对本实用新型的限定,本实用新型将以所附权利要求书界定的范围作为保护范围。
Claims (3)
1.一种基坑浇筑溜管支撑调节装置,所述基坑的底面铺设有钢筋笼,所述钢筋笼上设立有支撑架,溜管架设于所述支撑架上,其特征在于,所述支撑调节装置包括:
螺杆,旋置于所述支撑架的顶端;
顶托,固设于所述螺杆的顶端,所述溜管支撑于所述顶托上。
2.根据权利要求1所述的支撑调节装置,其特征在于,
所述支撑架的顶端开设有螺纹孔,所述螺杆螺合于所述螺纹孔内。
3.根据权利要求2所述的支撑调节装置,其特征在于,
所述支撑架的顶端两侧固设有挡板,所述螺杆位于两侧的所述挡板之间,两侧的所述挡板与所述顶托形成一承托空间,所述溜管支撑调节于所述承托空间内。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420740116.4U CN204298825U (zh) | 2014-11-18 | 2014-12-01 | 基坑浇筑溜管支撑调节装置 |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410659409 | 2014-11-18 | ||
CN201420740116.4U CN204298825U (zh) | 2014-11-18 | 2014-12-01 | 基坑浇筑溜管支撑调节装置 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204298825U true CN204298825U (zh) | 2015-04-29 |
Family
ID=52848453
Family Applications (8)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201420740116.4U Expired - Fee Related CN204298825U (zh) | 2014-11-18 | 2014-12-01 | 基坑浇筑溜管支撑调节装置 |
CN201420740120.0U Expired - Fee Related CN204298827U (zh) | 2014-11-18 | 2014-12-01 | 基坑混凝土浇筑组合串管结构 |
CN201420742538.5U Expired - Fee Related CN204298828U (zh) | 2014-11-18 | 2014-12-01 | 基坑混凝土浇筑溜管缓冲控制结构 |
CN201420740119.8U Expired - Fee Related CN204298826U (zh) | 2014-11-18 | 2014-12-01 | 深基坑混凝土底板浇筑分支溜管结构 |
CN201420740133.8U Expired - Fee Related CN204298831U (zh) | 2014-11-18 | 2014-12-01 | 基坑混凝土浇筑转接缓冲结构 |
CN201420740118.3U Expired - Fee Related CN204299185U (zh) | 2014-11-18 | 2014-12-01 | 浇筑管道钢筋缓冲结构 |
CN201410717256.4A Active CN104532845B (zh) | 2014-11-18 | 2014-12-01 | 深基坑超厚混凝土底板浇筑系统及施工方法 |
CN201420740100.3U Expired - Fee Related CN204298824U (zh) | 2014-11-18 | 2014-12-01 | 基坑混凝土浇筑管道缓冲结构 |
Family Applications After (7)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201420740120.0U Expired - Fee Related CN204298827U (zh) | 2014-11-18 | 2014-12-01 | 基坑混凝土浇筑组合串管结构 |
CN201420742538.5U Expired - Fee Related CN204298828U (zh) | 2014-11-18 | 2014-12-01 | 基坑混凝土浇筑溜管缓冲控制结构 |
CN201420740119.8U Expired - Fee Related CN204298826U (zh) | 2014-11-18 | 2014-12-01 | 深基坑混凝土底板浇筑分支溜管结构 |
CN201420740133.8U Expired - Fee Related CN204298831U (zh) | 2014-11-18 | 2014-12-01 | 基坑混凝土浇筑转接缓冲结构 |
CN201420740118.3U Expired - Fee Related CN204299185U (zh) | 2014-11-18 | 2014-12-01 | 浇筑管道钢筋缓冲结构 |
CN201410717256.4A Active CN104532845B (zh) | 2014-11-18 | 2014-12-01 | 深基坑超厚混凝土底板浇筑系统及施工方法 |
CN201420740100.3U Expired - Fee Related CN204298824U (zh) | 2014-11-18 | 2014-12-01 | 基坑混凝土浇筑管道缓冲结构 |
Country Status (1)
Country | Link |
---|---|
CN (8) | CN204298825U (zh) |
Families Citing this family (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105003077B (zh) * | 2015-07-17 | 2017-07-18 | 中国建筑第二工程局有限公司 | 一种密闭空间混凝土浇筑装置及施工方法 |
CN105442609B (zh) * | 2015-11-20 | 2017-06-23 | 山东送变电工程公司 | 基础混凝土浇筑自支撑溜槽装置 |
CN108894231A (zh) * | 2018-09-19 | 2018-11-27 | 北京城建集团有限责任公司 | 一种混凝土溜筒结构体系及其施工方法 |
CN110904852A (zh) * | 2019-12-18 | 2020-03-24 | 诚通凯胜生态建设有限公司 | 一种桥梁施工方法 |
CN111456011A (zh) * | 2020-03-24 | 2020-07-28 | 中国五冶集团有限公司 | 一种地下室底板混凝土装配式钢溜槽 |
CN112376567A (zh) * | 2020-11-05 | 2021-02-19 | 中国建筑土木建设有限公司 | 一种大体积混凝土溜管浇筑体系及其施工方法 |
CN112982467A (zh) * | 2021-02-08 | 2021-06-18 | 中铁二十局集团第六工程有限公司 | 混凝土浇筑装置及筏板基础浇筑方法 |
CN113653060A (zh) * | 2021-07-28 | 2021-11-16 | 中国建筑第八工程局有限公司 | 多支撑梁的深基坑底板混凝土浇筑系统及其施工方法 |
CN113638420B (zh) * | 2021-09-26 | 2022-05-24 | 中铁十八局集团第五工程有限公司 | 深基坑自流消能混凝土浇筑方法及混凝土自流消能结构 |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6098014A (ja) * | 1983-11-04 | 1985-06-01 | Ohbayashigumi Ltd | 水中コンクリ−ト打設用トレミ−管先端位置測定装置 |
CN101294387B (zh) * | 2008-06-17 | 2011-09-07 | 中国葛洲坝集团股份有限公司 | 一种缓坡地形的碾压混凝土输送方法 |
CN102936896B (zh) * | 2012-12-04 | 2015-07-08 | 中铁二十三局集团有限公司 | 一种向下输送混凝土的装置 |
CN103089015B (zh) * | 2013-02-01 | 2015-07-22 | 河南省水利第二工程局 | 缓降器 |
-
2014
- 2014-12-01 CN CN201420740116.4U patent/CN204298825U/zh not_active Expired - Fee Related
- 2014-12-01 CN CN201420740120.0U patent/CN204298827U/zh not_active Expired - Fee Related
- 2014-12-01 CN CN201420742538.5U patent/CN204298828U/zh not_active Expired - Fee Related
- 2014-12-01 CN CN201420740119.8U patent/CN204298826U/zh not_active Expired - Fee Related
- 2014-12-01 CN CN201420740133.8U patent/CN204298831U/zh not_active Expired - Fee Related
- 2014-12-01 CN CN201420740118.3U patent/CN204299185U/zh not_active Expired - Fee Related
- 2014-12-01 CN CN201410717256.4A patent/CN104532845B/zh active Active
- 2014-12-01 CN CN201420740100.3U patent/CN204298824U/zh not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
CN204298828U (zh) | 2015-04-29 |
CN204299185U (zh) | 2015-04-29 |
CN204298826U (zh) | 2015-04-29 |
CN104532845B (zh) | 2016-06-29 |
CN204298827U (zh) | 2015-04-29 |
CN104532845A (zh) | 2015-04-22 |
CN204298824U (zh) | 2015-04-29 |
CN204298831U (zh) | 2015-04-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204298825U (zh) | 基坑浇筑溜管支撑调节装置 | |
CN204163115U (zh) | 一种后浇带吊模板施工装置 | |
CN108661313A (zh) | 一种工具式混凝土叠合板现浇连接段模板支撑装置 | |
CN103031892A (zh) | 钢桁架支柱及钢桁架平台制造方法 | |
CN102926537A (zh) | 一种固定外墙模板根部的方法及装置 | |
CN204252083U (zh) | 拱坝牛腿全倒悬模板装置 | |
CN203755676U (zh) | 一种墙柱垂直度控制工具 | |
CN203200719U (zh) | 悬空式倒坡模板装置 | |
CN206267520U (zh) | 一种自支撑后浇带浇筑用吊模 | |
CN105781159A (zh) | 一种电厂主厂房钢筋混凝土煤漏斗施工工艺 | |
CN202031309U (zh) | 一种结构混凝土施工用悬空作业平台 | |
CN204959790U (zh) | 一种弹簧隔振基础施工模板调平装置 | |
CN204920244U (zh) | 大跨度钢结构分段吊装的支撑结构 | |
CN105350719A (zh) | 大跨度后浇带早拆模增设临时构造柱施工方法 | |
CN203008232U (zh) | 钢桁架支柱 | |
CN202370545U (zh) | 止水带安装模具 | |
CN204199691U (zh) | 一种螺旋楼梯的扶手浇筑模板结构 | |
CN202181728U (zh) | 基础剪力墙及附墙柱钢筋无接头施工结构 | |
CN201437580U (zh) | 高架箱梁模板支撑体系 | |
CN204589996U (zh) | 钢筋调节装置 | |
CN205476444U (zh) | 一种基于低位顶升模架系统的轻型支撑立柱 | |
CN205012226U (zh) | 一种钢管支撑架顶端承重的方形砂筒 | |
CN205259215U (zh) | 明挖隧道敞开型主体结构侧墙贝雷架支模 | |
CN105781200A (zh) | 一种电厂主厂的房屋钢筋混凝用土煤漏斗分段支模浇筑施工工艺 | |
CN205243012U (zh) | 一种单侧模板加固结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150429 Termination date: 20201201 |