CN203924353U - Screw built-in fitting - Google Patents

Screw built-in fitting Download PDF

Info

Publication number
CN203924353U
CN203924353U CN201420390544.9U CN201420390544U CN203924353U CN 203924353 U CN203924353 U CN 203924353U CN 201420390544 U CN201420390544 U CN 201420390544U CN 203924353 U CN203924353 U CN 203924353U
Authority
CN
China
Prior art keywords
base
screw
column tube
fitting
built
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420390544.9U
Other languages
Chinese (zh)
Inventor
林明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201420390544.9U priority Critical patent/CN203924353U/en
Application granted granted Critical
Publication of CN203924353U publication Critical patent/CN203924353U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model relates to the pre-buried of securing member, especially screw built-in fitting.Its structural feature is, comprises annular base, and a plurality of column tubes on one of base center and base, between center column tube and column tube on base, has rib to be connected.Column tube is respectively as fixing hole and securing member embedded hole.By fixing hole, this product is fixed in the template that need to use screw point position, after floor completes fluid concrete, this screw built-in fitting completes with regard to pre-buried, and floor presents screw embedded hole, and for tightening up a screw, object is installed in hanging.Avoid redrilling in the future to cause damage to metope floor.The utility model science simple in structure, pre-buried easy, stretching resistance is strong, firmly.

Description

Screw built-in fitting
Technical field
The utility model relates to the pre-buried of securing member, especially screw built-in fitting.
Background technology
The house that finishing has been whitewashed, needs mounted lamp, hangs adapted tool etc., normally takes electric drill or hammering to get hole and installs.Like this floor or metope are caused to damage, be sometimes even corrupted to the pipeline being embedded in body of wall, cause wire short-circuiting, or the serious consequence such as Water pipe leaking.
Utility model content
The purpose of this utility model is to overcome prior art deficiency, and the screw being embedded in floor or body of wall built-in fitting is provided.In major structure of construction framework engineering, complete template formwork, before placing of concrete, on its template face screw point of application, bury this product.Can on the some position of screw, carry out pre-buriedly with being intended to estimate to use, reserve screw hole position, avoid destructive and install, for unnecessary no preformed hole, can whitewash to fill and lead up and leave no trace.
The purpose of this utility model realizes by following approach.
Screw built-in fitting, its structural feature is to comprise annular base, and a plurality of column tubes on one of base center and base, between center column tube and column tube on base, has rib to be connected.
Described base center column tube can be used as fixing hole, column tube on base is as securing member embedded hole, or the column tube of base center is as securing member embedded hole, and the column tube on base is as fixing hole, and the described column tube as fixing hole is spaghetti.
At building body floor concrete formwork, complete, while not carrying out casting and compacting of concrete, with reference to construction drawing, use on the some position of screw estimating, as lamp installation position, hang the positions such as adapted tool, screw built-in fitting is carried out pre-buried.Screw built-in fitting base is kept flat on template millet cake position, with member, by fixing hole, built-in fitting is fixed in template and is positioned, during disturbing concrete, it is embedded in concrete structure layer, pull down after formwork pre-buried completing.On floor face, just reserve securing member embedded hole.During use, be combined with usefulness, at embedded hole, screw in the securing members such as self-tapping screw, expansion bolt.
The utility model prioritization scheme is also:
Described fixing hole is logical heart cylindrical tube, the polygon prism pipe that securing member embedded hole is upper end closed.
Circular fixing hole facilitates the location of built-in fitting, only need through fixing hole, built-in fitting be followed closely on formwork with iron nail; Securing member embedded hole is polygon prism pipe, like this, has increased frictional force between securing member embedded hole and securing member, has also increased built-in fitting and concrete Contact face simultaneously, in securing member processes such as DRIVE SCREWSs, avoids skidding; When on embedded hole, end closure is avoided fluid concrete by embedded hole landfill.
Described base center column tube is as securing member embedded hole, and its caliber is reducing, and epimere caliber is greater than hypomere caliber.
Like this, column tube hypomere closes the more concrete of bag than epimere, and hypomere form to support epimere, when body is subject to pulling force, the epimere body application of force below concrete on, strengthened the stretching resistance of built-in fitting.While especially hanging weight on ceiling, use this built-in fitting can bear heavier object.
Described base is annulus or elliptical ring.
Like this, poured into a mould after concrete, concrete fills up ring internal pore, makes built-in fitting and concrete inlay to such an extent that more reinforce, and has very strong stretching resistance.
Column tube on described base is equally spaced, and makes embedded part structure stable.
In sum, the utility model is rational in infrastructure, and stretching resistance is strong, is embedded in advance in concrete floor, has solved while needing hung articles after house decoration flooring is caused to damage problem.
Accompanying drawing explanation
Fig. 1 is embodiment 1 structural representation
Fig. 2 is most preferred embodiment structural representation
Below in conjunction with accompanying drawing, the utility model is described in further detail.
The specific embodiment
Embodiment 1
As Fig. 1, screw built-in fitting, comprises built-in fitting annular base 1, and two pentagonal prism shape embedded holes 2 that are equally spaced on the circular spaghetti fixing hole 3 in one of base center and base, and fixing hole 2 has rib 4 to be connected with securing member embedded hole 3 interdigits.
At building body floor concrete formwork, complete, while not carrying out casting and compacting of concrete, with reference to construction drawing, on expectation use screw point position, carry out pre-buried.Screw built-in fitting base 1 is kept flat on template millet cake position, on the fixing hole 2 of base center, with iron nail, screw built-in fitting is fixed on formwork.During disturbing concrete, it is embedded in concrete structure layer, pulls down after formwork, two screw embedded hole positions 3 on base just present.While needing hanging that object is installed, in embedded hole position, 3 screw in little self-tapping screw, the object that suspended erection weight is lighter; Pack expansion bolt into, suspended weight.
Most preferred embodiment
As Fig. 2, screw built-in fitting, comprise built-in fitting base 1, and upper semisection aperture, one of base center is greater than the pentagonal prism shape embedded hole 3 in lower semisection aperture and two circular spaghetti fixing holes 2 that base is equally spaced, fixed hole position 2 has rib 4 to be connected with 3 of embedded hole positions.
At building body floor concrete formwork, complete, while not carrying out casting and compacting of concrete, with reference to construction drawing, on expectation use screw point position, carry out pre-buried.Screw built-in fitting base 1 is kept flat on template millet cake position, on base, on two fixed hole positions 2, with iron nail, screw built-in fitting is fixed on formwork.During disturbing concrete, it is embedded in concrete structure layer, pulls down after formwork, left the screw embedded hole position 3 of base center.While needing hanging that object is installed, in embedded hole position, screw in a little bigger self-tapping screw suspended heavier object is installed.
It is same as the prior art that the utility model is not stated part.

Claims (6)

1. screw built-in fitting, is characterized in that, comprises annular base (1), and a plurality of column tubes on one of base center and base, between center column tube and column tube on base, has rib (4) to be connected.
2. screw built-in fitting according to claim 1, it is characterized in that, described base center column tube can be used as fixing hole (3), column tube on base is as securing member embedded hole (2), or the column tube of base center is as securing member embedded hole, column tube on base is as fixing hole, and the described column tube as fixing hole is spaghetti.
3. screw built-in fitting according to claim 2, is characterized in that, described fixing hole (3) is logical heart cylindrical tube, the polygon prism pipe that securing member embedded hole (2) is upper end closure.
4. screw built-in fitting according to claim 2, is characterized in that, described base (1) center column tube is reducer pipe as the caliber of embedded hole, and its epimere caliber is greater than hypomere caliber.
5. screw built-in fitting according to claim 1, is characterized in that, described base (1) is annulus or elliptical ring.
6. screw built-in fitting according to claim 1, is characterized in that, the column tube on described base is equally spaced.
CN201420390544.9U 2014-07-15 2014-07-15 Screw built-in fitting Expired - Fee Related CN203924353U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420390544.9U CN203924353U (en) 2014-07-15 2014-07-15 Screw built-in fitting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420390544.9U CN203924353U (en) 2014-07-15 2014-07-15 Screw built-in fitting

Publications (1)

Publication Number Publication Date
CN203924353U true CN203924353U (en) 2014-11-05

Family

ID=51820203

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420390544.9U Expired - Fee Related CN203924353U (en) 2014-07-15 2014-07-15 Screw built-in fitting

Country Status (1)

Country Link
CN (1) CN203924353U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107476443A (en) * 2017-07-03 2017-12-15 武汉城市空间壹加壹科技发展有限公司 Cast-in-place concrete floor hanging built-in fitting and technique
CN108468389A (en) * 2018-03-30 2018-08-31 天津住宅集团建设工程总承包有限公司 A kind of elimination construction error wall lacing wire component
CN110017405A (en) * 2019-03-25 2019-07-16 广东蕉岭建筑工程集团有限公司 Fixing means and fixed device for floor supplying drainage
CN111457803A (en) * 2020-05-19 2020-07-28 华侨大学 Underground space model circulating blasting test pre-buried blast hole and manufacturing method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107476443A (en) * 2017-07-03 2017-12-15 武汉城市空间壹加壹科技发展有限公司 Cast-in-place concrete floor hanging built-in fitting and technique
CN108468389A (en) * 2018-03-30 2018-08-31 天津住宅集团建设工程总承包有限公司 A kind of elimination construction error wall lacing wire component
CN110017405A (en) * 2019-03-25 2019-07-16 广东蕉岭建筑工程集团有限公司 Fixing means and fixed device for floor supplying drainage
CN111457803A (en) * 2020-05-19 2020-07-28 华侨大学 Underground space model circulating blasting test pre-buried blast hole and manufacturing method

Similar Documents

Publication Publication Date Title
CN203924353U (en) Screw built-in fitting
CN103061504A (en) Concrete board pipeline installation reserved hole construction mould and construction method
CN108818879B (en) Weight hanging structure of prefabricated inner partition plate and construction process of weight hanging structure
CN202596184U (en) Lifting node for assembly type large wallboard
CN203961322U (en) Prefabricated panel installation adjusting device
CN203475824U (en) Mould hanging device for reserved hole of building construction water power pipeline
CN204061461U (en) EXPANSION ANCHOR BOLTS embedded part
CN204199688U (en) Floor slab preformed hole hangs mould mounting structure
CN202273420U (en) Suspended mould location and supporting device
CN204009336U (en) A kind of hard ball curtain
CN217000950U (en) Assembly type building wall body quick hoisting installation mechanism based on building engineering
CN204059918U (en) scaffold and wall connecting piece
CN208415519U (en) A kind of metope pre-embedded formula connection component
CN201539100U (en) Simple mould fitting for construction floor prepared holes
CN202517709U (en) Polyvinyl chloride (PVC) wire pipe bending tool
CN204164607U (en) A kind of para-seismic support of building interior electromechanical equipment
CN204510688U (en) A kind of temporary fixing structure of precast wall panel
CN204435421U (en) A kind of assembling manhole
CN204370564U (en) Underfloor constructional column concrete pouring structure
CN206033024U (en) Pipeline hoist and mount mould
CN204202616U (en) Concrete structure settlement monitoring mark
CN202299353U (en) Building scaffold
CN202530518U (en) Embedded device at sewer line in toilet
CN205840329U (en) A kind of novel pipeline reserves sleeve pipe
CN205857713U (en) Hole mould is hung in a kind of canalization

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141105

Termination date: 20160715

CF01 Termination of patent right due to non-payment of annual fee