CN204202616U - Concrete structure settlement monitoring mark - Google Patents

Concrete structure settlement monitoring mark Download PDF

Info

Publication number
CN204202616U
CN204202616U CN201420602577.5U CN201420602577U CN204202616U CN 204202616 U CN204202616 U CN 204202616U CN 201420602577 U CN201420602577 U CN 201420602577U CN 204202616 U CN204202616 U CN 204202616U
Authority
CN
China
Prior art keywords
monitoring
round steel
spanner
concrete structure
mobile jib
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420602577.5U
Other languages
Chinese (zh)
Inventor
刘记帅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201420602577.5U priority Critical patent/CN204202616U/en
Application granted granted Critical
Publication of CN204202616U publication Critical patent/CN204202616U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

A kind of pit retaining monitoring or New Buildings main body monitoring in for monitoring the concrete structure settlement monitoring mark of concrete structure sedimentation.Its mobile jib is round steel, upper end is a spheroid, for standing up levelling staff, the below of spheroid is free segment, the length of free segment is determined according to the exterior decoration thickness of buildings, lower end is a hemisphere, be screw thread (without screw thread on the hemisphere of lower end) in the scope of distance lower end 162.5mm, be round steel spanner ear apart from the position of lower end 200mm, block round steel spanner ear with spanner and rotate monitoring mark, during laying monitoring mark, electricity consumption is drilled on concrete structure and punches, drilling diameter 2mm less of mobile jib diameter, the lower end that this monitoring indicates is placed in hole, block round steel spanner ear rotation monitoring mark extruded concrete formation internal thread with spanner and enter at the bottom of hole, lay simple, make monitoring mark be combined with buildings firmly simultaneously, block round steel spanner ear with spanner after monitoring completes monitoring mark is backed out for next monitoring works.

Description

Concrete structure settlement monitoring mark
Technical field
It is reusable that the utility model relates to concrete structure settlement monitoring in a kind of pit retaining monitoring or the monitoring of New Buildings main body, and lay simple, and be combined with concrete structure and firmly monitor mark.
Background technology
At present, the method laying concrete structure settlement monitoring mark in pit retaining monitoring or the monitoring of New Buildings main body is that electricity consumption is drilled on concrete structure and punches, φ 18 × 200mm mark concrete is embedded in hole, lay loaded down with trivial details, with buildings in conjunction with insecure, and not reproducible use, in monitoring afterwards, monitor mark be easily pulled out and destroy.
Summary of the invention
Loaded down with trivial details degree is laid in order to simplify concrete structure settlement monitoring mark, increase the fastness combined between itself and buildings, solve the not re-usable problem of concrete structure settlement monitoring mark, the utility model provides a kind of concrete structure settlement monitoring mark, this concrete structure settlement monitoring mark is not only laid simply, and be combined firmly with buildings, can reuse.
The utility model solves the technical scheme that its technical matters adopts: the mobile jib of this monitoring mark is round steel, upper end is a spheroid, for standing up levelling staff, the below of spheroid is free segment, the length of free segment is determined according to the exterior decoration thickness of buildings, lower end is a hemisphere, be screw thread (without screw thread on the hemisphere of lower end) in the scope of distance lower end 162.5mm, be round steel spanner ear apart from the position of lower end 200mm, block round steel spanner ear with spanner and rotate monitoring mark, during laying monitoring mark, electricity consumption is drilled on concrete structure and punches, drilling diameter 2mm less of mobile jib diameter, the lower end that this monitoring indicates is placed in hole, block round steel spanner ear rotation monitoring mark extruded concrete formation internal thread with spanner and enter at the bottom of hole, lay simple, it is combined with buildings firmly, block round steel spanner ear with spanner after monitoring completes monitoring mark is backed out for next monitoring works.
The beneficial effects of the utility model are: can lay simple, increase its be combined firmly with buildings while, can reuse.
Accompanying drawing explanation
Fig. 1 is front view of the present utility model; Fig. 2 is side view; Fig. 3 is round steel spanner ear place three-dimensional effect diagram.
In figure, 1 is spheroid, and 2 is free segment, and 3 is round steel spanner ear, and 4 is screw thread, and 5 is hemisphere.
Embodiment
In the drawings, mobile jib of the present utility model is round steel, upper end is a spheroid (1), for standing up levelling staff, the below of spheroid (1) is free segment (2), the length of free segment (2) is determined according to the exterior decoration thickness of buildings, lower end is a hemisphere (5), be screw thread (4) (hemisphere (5) of lower end is upper without screw thread) in the scope of distance lower end 162.5mm, be round steel spanner ear (3) apart from the position of lower end 200mm, blocking round steel spanner ear with spanner and rotate monitoring mark.
During laying concrete structure settlement monitoring mark, electricity consumption is drilled on concrete structure and punches, drilling diameter 2mm less of mobile jib diameter, the lower end of monitoring mark is placed in hole, block round steel spanner ear (3) with spanner and rotate monitoring mark, screw thread (4) extruded concrete forms internal thread and makes monitoring mark enter at the bottom of hole, thus make it be combined with concrete structure firmly, lay simple.
Block round steel spanner ear (3) rotation monitoring mark with spanner after monitoring completes monitoring mark to be backed out, for next monitoring works.

Claims (1)

1. a concrete structure settlement monitoring mark, for monitoring the monitoring mark of concrete structure sedimentation, it is characterized in that: its mobile jib is round steel, the upper end of mobile jib round steel is a spheroid, for standing up levelling staff, the lower end of mobile jib round steel is a hemisphere, mobile jib round steel within the scope of the lower end hemisphere 162.5mm of distance mobile jib round steel there is screw thread, without screw thread on the lower end hemisphere of mobile jib round steel, on mobile jib round steel, the position of the lower end hemisphere 200mm of distance mobile jib round steel is round steel spanner ear, mobile jib round steel between the upper end spheroid of mobile jib round steel and round steel spanner ear is free segment, the length of free segment is determined according to the exterior decoration thickness will monitoring concrete structure.
CN201420602577.5U 2014-10-17 2014-10-17 Concrete structure settlement monitoring mark Expired - Fee Related CN204202616U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420602577.5U CN204202616U (en) 2014-10-17 2014-10-17 Concrete structure settlement monitoring mark

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420602577.5U CN204202616U (en) 2014-10-17 2014-10-17 Concrete structure settlement monitoring mark

Publications (1)

Publication Number Publication Date
CN204202616U true CN204202616U (en) 2015-03-11

Family

ID=52660563

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420602577.5U Expired - Fee Related CN204202616U (en) 2014-10-17 2014-10-17 Concrete structure settlement monitoring mark

Country Status (1)

Country Link
CN (1) CN204202616U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105891453A (en) * 2016-04-08 2016-08-24 山东建泽混凝土有限公司 Device and method for testing apparent mass of bare concrete

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105891453A (en) * 2016-04-08 2016-08-24 山东建泽混凝土有限公司 Device and method for testing apparent mass of bare concrete

Similar Documents

Publication Publication Date Title
IN2015DN02350A (en)
CN204001720U (en) Service sleeve in a kind of constructional column
CN204081445U (en) To encorbelment i iron anchor device
CN204202616U (en) Concrete structure settlement monitoring mark
CN203924353U (en) Screw built-in fitting
MX367895B (en) Method for producing a precast concrete segment of a wind turbine tower, and a precast concrete tower segment formwork.
CN204612719U (en) A kind of settlement observer
CN205387949U (en) Engineering slip casting stock
CN204139521U (en) A kind of wall curtain brick suspension member with barb
CN204282382U (en) A kind of equipment by decompression drainage quick blocking precipitation pipe well
CN203639892U (en) Ground anchor device of static sounding machine
CN201937217U (en) Inner line box heightening ring electrician accessory for building or structure
CN203096597U (en) Bridge suspender connecting device
CN203741837U (en) Ground anchor
CN205478764U (en) Concrete structure main part settlement monitoring sign
CN204370564U (en) Underfloor constructional column concrete pouring structure
CN204139168U (en) For installing the protective device of steel pipe earth anchor
CN202769217U (en) Roadway hanging ceiling set screw structure
CN204237492U (en) Telescopic well testing top sheave
CN204942180U (en) A kind of plastic dowel sleeve
CN104790578A (en) Manufacturing device of preformed hole in building floor concrete construction and construction method thereof
CN203572477U (en) Assembled settlement observation point
CN204282605U (en) A kind of wall curtain brick suspension member
CN204494561U (en) A kind of indoor radiator heating is for return pipe embedded device
CN203160239U (en) Anchor rod construction device for civil engineering

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150311

Termination date: 20161017