CN203572477U - Assembled settlement observation point - Google Patents
Assembled settlement observation point Download PDFInfo
- Publication number
- CN203572477U CN203572477U CN201320678510.5U CN201320678510U CN203572477U CN 203572477 U CN203572477 U CN 203572477U CN 201320678510 U CN201320678510 U CN 201320678510U CN 203572477 U CN203572477 U CN 203572477U
- Authority
- CN
- China
- Prior art keywords
- observation point
- settlement observation
- assembly type
- shaft
- service sleeve
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
The utility model discloses an assembled settlement observation point. The assembled settlement observation point comprises a rod body, a rod cap, a pre-buried casing and a fixed wing, wherein the rod cap is arranged at one end of the rod body; the other end of the rod body is connected with the pre-buried casing; the rod body is in threaded connection with the pre-buried casing; one end, which is connected with the rod body, of the pre-buried casing is fixedly connected with the fixed wing. The assembled settlement observation point is easy to install and detach. Artificial damages to the settlement observation point are reduced, so that the accuracy of observation data is ensured.
Description
Technical field
The utility model belongs to building engineering construction field, is specifically related to a kind of assembly type settlement observation point.
Background technology
A period of time in Building Construction and after completion of works, need to, by the settlement observation point being installed on buildings, regularly building settlement deformation be observed.
In engineering construction at present, common settlement observation point has following several:
The first is to adopt round steel to make, and after buildings concrete construction is complete, first electricity consumption is drilled on concrete holes, and then by structure glue, settlement observation point is anchored to design attitude.Although this settlement observation point simple structure is iron not antirust.Owing to being rear installation, during boring, easily buildings is caused to certain damage, even run into the intensive place of reinforcing bar, there is the unsuccessful phenomenon of boring.Some successful installations, but be exposed in work progress, easily workmen is damaged, therefore this kind of settlement observation point used and has certain limitation.
The second is the settlement observation point of making of stainless steel, but owing to being also that rear boring is installed, is the same with the first installation method, while installing equally, buildings is had to damage, also has certain use restriction.
Traditional settlement observation point generally adopts round steel to make, and electricity consumption is drilled on buildings and holes, and adopts structure glue to be anchored on buildings; Or adopt stainless steel to make, but be also by installing again after boring on buildings.Above two kinds of settlement observation points, because be rear installation, have a bit and damage buildings when mounted, encounter building structure reinforcing bar while sometimes holing, and install and also have any problem, or position is inaccurate, installs crooked.What is more, and Drill Crack also has injury to the person.Thereby, need a kind of novel, settlement observation point simple, attractive in appearance is installed to address the above problem.
Therefore, need a kind of new settlement observation point to address the above problem.
Utility model content
The utility model is in Building Construction in prior art, and settlement observation point is installed inconvenient defect, and a kind of assembly type settlement observation point easy to install is provided.
For solving the problems of the technologies described above, the technical scheme that assembly type settlement observation point of the present utility model adopts is:
A kind of assembly type settlement observation point, comprise shaft, pole cap, service sleeve and fixed-wing, one end of described shaft is provided with described pole cap, the other end of described shaft connects described service sleeve, described shaft is threaded with described service sleeve, and one end that described service sleeve is connected with described shaft is fixedly connected with described fixed-wing.
Further, to be provided with one end of described pole cap be 90 ° of crotches to described shaft.Facilitate observation data.
Further, described shaft is stainless steel round steel.Adopt stainless steel to avoid exposing overlong time and corrosion.
Further, described service sleeve is stainless-steel tube.Adopt stainless-steel tube to avoid exposing overlong time and corrosion.
Further, a side of described pole cap is plane, and opposite side is sphere.Facilitate data observation, avoid construction period exposed parts to injure workmen.
Further, on described fixed-wing, be provided with through hole.Facilitate shaft to connect service sleeve by through hole.
Further, the surrounding of described through hole is provided with fixed orifice.For fixed-wing is fixed on to template.
Beneficial effect: assembly type settlement observation point of the present utility model, installing/dismounting is simple, reduces artificial destruction settlement observation point, thereby guarantees that observation data is accurate.
Accompanying drawing explanation
Fig. 1 is assembly type settlement observation point application schematic diagram of the present utility model;
Fig. 2 is assembly type settlement observation point overall perspective view of the present utility model;
Fig. 3 is assembly type settlement observation point shaft of the present utility model, pole cap stereographic map;
Fig. 4 is assembly type settlement observation point shaft stereographic map of the present utility model;
Fig. 5 is assembly type settlement observation point pole cap stereographic map of the present utility model;
Fig. 6 is assembly type settlement observation point service sleeve of the present utility model and fixed-wing stereographic map;
Fig. 7 is assembly type settlement observation point fixed-wing stereographic map of the present utility model.
Embodiment
Below in conjunction with the drawings and specific embodiments, further illustrate the utility model, should understand these embodiment and only for the utility model is described, be not used in restriction scope of the present utility model, after having read the utility model, those skilled in the art all fall within the application's claims limited range to the modification of the various equivalent form of values of the present utility model.
Refer to shown in Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5, Fig. 6 and Fig. 7, assembly type settlement observation point of the present utility model, comprises shaft 1, pole cap 2, service sleeve 3 and fixed-wing 4.One end of shaft 1 is provided with pole cap 2, and the other end of shaft 1 connects service sleeve 3, and shaft 1 is threaded with service sleeve 3.Installing/dismounting is all more convenient.
One end that service sleeve 3 is connected with shaft 1 is fixedly connected with fixed-wing 4.Fixed-wing 4 is a block plate, facilitates shaft to connect service sleeve by through hole.Fixed-wing 4 welds together with service sleeve 3.On fixed-wing 4, be provided with through hole.The surrounding of through hole is provided with fixed orifice 5.For fixed-wing and service sleeve are fixed on to template.
One end that shaft 1 is provided with pole cap 2 is 90 ° of crotches.One side of pole cap 2 is plane, and opposite side is sphere, is welded in one end of shaft 1, avoids construction period exposed parts to injure workmen, facilitates observation data.
The stainless steel that shaft 1 is 20mm for diameter, shaft 1 is round steel.Service sleeve 3 is the stainless-steel tube of diameter 25mm.Adopt stainless steel to avoid exposing overlong time and corrosion.One end that shaft 1 is connected with service sleeve 3 is provided with the long screw thread of 50mm, and the inner side of service sleeve 3 is provided with the screw thread matching with shaft 1 screw thread, and length is 80mm.Adopt round steel and the stainless-steel tube of size of the present invention, material be easy to get and intensity enough, can effectively realize object of the present invention.
Before concreting, service sleeve 3 and fixed-wing 4 are fixed in template with iron nail to form removal when concrete reaches some strength.During settlement observation, only shaft 1 need be installed to be anchored in service sleeve 3 and can carry out data observation.
Use principle:
Assembly type settlement observation point of the present utility model, feature part is, on service sleeve, fixed-wing is set, and by wire nail, fixed-wing is fixed in template, and concrete reaches intensity, after the demoulding, shaft is arranged in service sleeve, can carry out building subsidence observation.
Assembly type settlement observation point of the present utility model, installs dismantle simple, adopts stainless steel to avoid exposing overlong time and corrosion, avoids construction period exposed parts to injure workmen, reduces artificial destruction settlement observation point, thereby guarantees that observation data is accurate.
Claims (8)
1. an assembly type settlement observation point, it is characterized in that, comprise shaft (1), pole cap (2), service sleeve (3) and fixed-wing (4), one end of described shaft (1) is provided with described pole cap (2), the other end of described shaft (1) connects described service sleeve (3), and one end that described service sleeve (3) is connected with described shaft (1) is fixedly connected with described fixed-wing (4).
2. assembly type settlement observation point as claimed in claim 1, is characterized in that, described shaft (1) is threaded with described service sleeve (3).
3. assembly type settlement observation point as claimed in claim 1, is characterized in that, one end that described shaft (1) is provided with described pole cap (2) is 90 ° of crotches.
4. assembly type settlement observation point as claimed in claim 1, is characterized in that, described shaft (1) for diameter be stainless steel round steel.
5. assembly type settlement observation point as claimed in claim 1, is characterized in that, described service sleeve (3) is stainless-steel tube.
6. assembly type settlement observation point as claimed in claim 1, is characterized in that, a side of described pole cap (2) is plane, and opposite side is sphere.
7. assembly type settlement observation point as claimed in claim 1, is characterized in that, the middle part of described fixed-wing (4) is provided with through hole.
8. assembly type settlement observation point as claimed in claim 7, is characterized in that, the surrounding of described through hole is provided with fixed orifice (5).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320678510.5U CN203572477U (en) | 2013-10-30 | 2013-10-30 | Assembled settlement observation point |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320678510.5U CN203572477U (en) | 2013-10-30 | 2013-10-30 | Assembled settlement observation point |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203572477U true CN203572477U (en) | 2014-04-30 |
Family
ID=50540205
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201320678510.5U Expired - Fee Related CN203572477U (en) | 2013-10-30 | 2013-10-30 | Assembled settlement observation point |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203572477U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104316023A (en) * | 2014-08-28 | 2015-01-28 | 张美娇 | Tunnel initial-stage settlement measure tool |
-
2013
- 2013-10-30 CN CN201320678510.5U patent/CN203572477U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104316023A (en) * | 2014-08-28 | 2015-01-28 | 张美娇 | Tunnel initial-stage settlement measure tool |
CN104316023B (en) * | 2014-08-28 | 2016-09-14 | 张美娇 | A kind of tunnel initial-stage settlement measurement instrument |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204781970U (en) | Template fixing device with adjustable | |
CN204612719U (en) | A kind of settlement observer | |
CN203572477U (en) | Assembled settlement observation point | |
CN103147572A (en) | Complete water-stopping screw rod and mounting method | |
CN203499017U (en) | Wall tie bar pre-embedded positioning device | |
CN204139622U (en) | Adjustable segmented column steel bar positioning fixture | |
CN206191059U (en) | Prefabricated piping lane pipeline support installation device for component | |
CN204001665U (en) | A kind of scaffold assembling wall-connecting piece | |
CN204388854U (en) | A kind of assembled folding formula settlement observation point | |
CN203559586U (en) | PVC (Polyvinyl chloride) electric wire pipe embedded direct connector for concrete | |
CN203429621U (en) | Stress application self-drilling pile | |
CN203531361U (en) | Embedded type lifting ring bolt for being connected with scaffold | |
CN102141466A (en) | Boundary simulation device and method for thin-walled cylindrical shell structure experiment | |
CN202734828U (en) | Novel settlement observation point embedded element | |
CN201671339U (en) | Fixing device for wall bodies and beam column templates of buildings | |
CN204941579U (en) | The pre-buried orifice tube of a kind of pit shaft borehole wall grouting | |
CN205138436U (en) | Inflation formula L shape deformation monitoring prism support | |
CN203924718U (en) | A kind of formwork reinforcement combination tool | |
CN210221061U (en) | Settlement observation point mounting structure | |
CN207376966U (en) | A kind of sleeve barrel fixing device | |
CN104359599A (en) | Photoelastic stress meter mounting and guiding device | |
CN204255541U (en) | A kind of instrument for installing photoelastic taseometer | |
CN206113946U (en) | A repeatedly usable monitoring point device for concrete structure component | |
CN203008197U (en) | Fixing device for fixing suspender on roof | |
CN202882114U (en) | Cast-in-place concrete prearranged pull connection piece |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20140430 Termination date: 20141030 |
|
EXPY | Termination of patent right or utility model |