CN203888020U - Concrete delivery device in precast beam field - Google Patents
Concrete delivery device in precast beam field Download PDFInfo
- Publication number
- CN203888020U CN203888020U CN201420266664.8U CN201420266664U CN203888020U CN 203888020 U CN203888020 U CN 203888020U CN 201420266664 U CN201420266664 U CN 201420266664U CN 203888020 U CN203888020 U CN 203888020U
- Authority
- CN
- China
- Prior art keywords
- portal frame
- gantry
- metal catheter
- precast beam
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000002184 metal Substances 0.000 claims abstract description 29
- 239000000725 suspension Substances 0.000 claims description 7
- 238000004519 manufacturing process Methods 0.000 abstract description 2
- 238000005266 casting Methods 0.000 description 6
- 239000000463 material Substances 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 238000007599 discharging Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 238000005086 pumping Methods 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 238000012857 repacking Methods 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model discloses a concrete delivery device in a precast beam field. The concrete delivery device comprises a gantry. The gantry is provided with a truss vehicle and a lifting hook, the lower portion of the gantry is connected with a pump truck platform, a second metal guide pipe is mounted on the top of the gantry via a rotary platform and is connected with a rubber guide pipe, a first traveling mechanism is arranged at the bottom of the gantry, and the gantry is provided with an operation desk. A first metal guide pipe is movably connected with the second metal guide pipe and is connected to a concrete delivery pump. The concrete delivery device in the precast beam field has the advantages of mobility, convenience in use, high equipment utilization rate and low manufacturing cost.
Description
Technical field
A kind of precast beam of the utility model field appts. for transferring ready-mixed concrete, is applicable to railway or highway engineering large-scale precast beam field concrete and enters mould use.
Background technology
In railway or highway engineering, because the more and same engineering of bridge bridge specification used is consistent.Conventionally adopt the prefabricated mode in beam field to manufacture.When producing, because the single-beam concrete size of large-scale beam is larger with side's amount, therefore concrete transportation problem, is an important problem in Liang Chang beam process processed.Existing solution is all generally to adopt automotive pump pumping or material distributing machine, and the former expense is higher, and the latter moves inconvenience and function singleness.
Summary of the invention
The utility model provides a kind of precast beam field appts. for transferring ready-mixed concrete, and it moves with easy to use, and utilization rate of equipment and installations is high, and cost is lower.
The technical scheme that the utility model is taked is: a kind of precast beam field appts. for transferring ready-mixed concrete, comprise portal frame, portal frame is provided with purlin car, suspension hook, portal frame bottom is connected with pump truck platform, described portal frame top is provided with the second metal catheter by rotation platform, the second metal catheter connects rubber catheter, and described portal frame bottom is provided with the first walking mechanism, and portal frame is provided with operating desk.The first metal catheter is flexibly connected with the second metal catheter, and the first metal catheter is connected to concrete pump.
Described pump truck platform bottom is provided with four universal wheels, forms the second walking mechanism.While guaranteeing that portal frame moves, pump truck platform and portal frame relative position are constant.
A kind of precast beam of the utility model field appts. for transferring ready-mixed concrete, utilizes concrete pump and the repacking of straddle truck system in combination.Portal frame bottom is provided with the first walking mechanism, to guarantee that portal frame can freely walk along beam length direction.Portal frame top is provided with the first metal catheter by rotation platform, rotation platform is closely connected with first metal catheter at portal frame top, first metal catheter at portal frame top is with rotation platform horizontal rotary then horizontally rotate, and its rotating range makes concrete discharging scope can laterally cover whole deck-siding.
Portal frame is provided with the first walking mechanism, to guarantee that portal frame can freely walk along beam length direction.Pump truck platform is reliably connected with the second walking mechanism and with portal frame, and when casting concrete, concrete pump is parked on pump truck platform, and pump truck platform is with portal frame synchronizing moving.When not carrying out concreting, can pass through purlin car and the suspension hook at portal frame top, carry out the lifting work of the materials such as reinforcing bar, to improve the utilization rate of equipment.
The operation such as rise and fall of the walking of the walking of portal frame, the rotation of metal catheter, purlin car and suspension hook, all the operating desk on portal frame carries out.
Accompanying drawing explanation
Fig. 1 is the utility model device facade structures schematic diagram;
Fig. 2 is the utility model device plan structure schematic diagram;
Fig. 3 is the A-A face cutaway view of Fig. 1.
The specific embodiment
As shown in Fig. 1 ~ Fig. 3, a kind of precast beam field appts. for transferring ready-mixed concrete, comprise portal frame 1, portal frame 1 is provided with purlin car 5, suspension hook 7, portal frame 1 bottom is connected with pump truck platform 9, portal frame 1 is fixed with the first metal catheter 3-1, and described portal frame 1 welded top has rotation platform 2, and rotation platform 2 is a metal rotary disk.Rotation platform 2 is closely connected with the second metal catheter 3-2 and is coaxial.The second metal catheter 3-2 upper end is connected with the first metal catheter 3-1, and its interface level, it can level rotate freely.The second metal catheter 3-2 lower end is connected with rubber catheter 4, and described portal frame 1 bottom is provided with the first walking mechanism 6, and portal frame 1 is provided with operating desk 8.Described pump truck platform 9 is reliably connected with portal frame 1, and its bottom welding forms the second walking mechanism by four universal wheels.When portal frame 1 moves, the second walking mechanism can move with portal frame 1, thereby guarantees that portal frame 1, the first metal catheter 3-1 and concrete pump 9 relative positions are constant.
Portal frame 1 is provided with the first walking mechanism 6, and portal frame 1 can freely be walked along beam length direction.Portal frame 1 is provided with rotation platform 2, and rotation platform 2 can be controlled the metal catheter 3 that is positioned at portal frame 1 top and horizontally rotate.
During concreting, concrete pump is parked on pump truck platform 9, and pump truck platform 9 is with portal frame 1 synchronizing moving.Concrete pump 9 and the first metal catheter 3-1 lower end are connected and fixed, concrete is transported to concrete pump 9 by concrete transportation place, concrete by concrete pump 9 and the first metal catheter 3-1, the second metal catheter 3-2, rubber catheter 4 by concrete conveyance to casting beams 10.
During concreting, staff, in operating desk 8, rotates by controlling the second metal catheter 3-2 at rotation platform 2, control portal frame 1 top, makes blanking scope can cover the deck-siding of whole casting beams 10.By controlling the first walking mechanism 6, make whole device along the walking of beam length direction, make blanking scope can cover the beam length of whole casting beams 10.After a slice beam has been built, by controlling the first walking mechanism 6, make whole device move to next casting beams to continue to build, realization is worked continuously.
When not carrying out concreting, can control the first walking mechanism 6 along the beam length direction of casting beams 10 move, purlin car 5, suspension hook 7 along deck-siding direction move, suspension hook 7 moves up and down work such as carrying out material handling, to improve utilization rate of equipment and installations.
Claims (2)
1. a precast beam field appts. for transferring ready-mixed concrete, comprise portal frame (1), portal frame (1) is provided with purlin car (5), suspension hook (7), it is characterized in that, portal frame (1) bottom is connected with pump truck platform (9), described portal frame (1) top is provided with the second metal catheter (3-2) by rotation platform (2), the second metal catheter (3-2) connects rubber catheter (4), described portal frame (1) bottom is provided with the first walking mechanism (6), portal frame (1) is provided with operating desk (8), the first metal catheter (3-1) is flexibly connected with the second metal catheter (3-2), the first metal catheter (3-1) is connected to concrete pump (9).
2. a kind of precast beam field appts. for transferring ready-mixed concrete according to claim 1, is characterized in that, described pump truck platform (9) bottom is provided with four universal wheels, forms the second walking mechanism.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420266664.8U CN203888020U (en) | 2014-05-23 | 2014-05-23 | Concrete delivery device in precast beam field |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420266664.8U CN203888020U (en) | 2014-05-23 | 2014-05-23 | Concrete delivery device in precast beam field |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203888020U true CN203888020U (en) | 2014-10-22 |
Family
ID=51714466
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201420266664.8U Expired - Fee Related CN203888020U (en) | 2014-05-23 | 2014-05-23 | Concrete delivery device in precast beam field |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203888020U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105429058A (en) * | 2015-12-09 | 2016-03-23 | 国家电网公司 | Anti-pollution mobile construction device for cable channel |
-
2014
- 2014-05-23 CN CN201420266664.8U patent/CN203888020U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105429058A (en) * | 2015-12-09 | 2016-03-23 | 国家电网公司 | Anti-pollution mobile construction device for cable channel |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104895584B (en) | A kind of modularization steel form carrier and construction technology thereof | |
CN104790977B (en) | Tunnel just serves as a contrast formwork jumbo and its construction method | |
CN207415658U (en) | A kind of concrete material transfering device and preform production line | |
CN106593469B (en) | A kind of trolley for inverted arch construction | |
CN207415665U (en) | A kind of preform production line | |
CN104564102A (en) | Tunnel lining concrete grouting device | |
CN207415657U (en) | A kind of distribution device | |
CN204455738U (en) | Subway solid concrete roabed is built and is used movable concrete cloth device | |
CN202064243U (en) | Transporting and laying device of track boards | |
CN103982200A (en) | Full-face inner sliding rail moving steel mould trolley | |
CN203888020U (en) | Concrete delivery device in precast beam field | |
CN209381053U (en) | Building concrete wallboard prefabricated components production line Tai Moche ferry-boat system | |
CN204627629U (en) | Fully automatic hydraulic concrete-liner steel formwork trolley | |
CN110173281A (en) | A kind of sliding mode system for circular tunnel concreting | |
CN103527218A (en) | Multifunctional combined type concrete lining trolley | |
CN102720102B (en) | Construction trolley | |
CN205743934U (en) | Self-propelled tunnel inverted arch reinforcing bar spelling installs chassis | |
CN209760820U (en) | Blanking and mixed vibrating device for self-moving type regeneration block | |
CN206186077U (en) | Prefab production line | |
CN202250105U (en) | Integral hydraulic steel formwork trolley | |
CN204097880U (en) | A kind of self-propelled transverse-moving trolley | |
CN209440480U (en) | Concrete distributing device and preform production line | |
CN204324739U (en) | XJ type manual gate type hoisting crane | |
CN204173804U (en) | A kind of inside-climbing tower crane of structural beams bearing-type is installed and climbing structure | |
CN101775990B (en) | Three-dimensional space curved surface steel mould trolley |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C56 | Change in the name or address of the patentee |
Owner name: CHINA GEZHOUBA GROUP NO. 6 ENGINEERING CO., LTD. Free format text: FORMER NAME: GEZHOUBA GROUP NO. 6 ENGINEERING CO., LTD. |
|
CP01 | Change in the name or title of a patent holder |
Address after: 443002 Xiling, Hubei Province sheep mountain road, No. 29, No. Patentee after: CHINA GEZHOUBA GROUP NO.6 ENGINEERING Co.,Ltd. Address before: 443002 Xiling, Hubei Province sheep mountain road, No. 29, No. Patentee before: GEZHOUBA GROUP NO.6 ENGINEERING Co.,Ltd. |
|
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20141022 |
|
CF01 | Termination of patent right due to non-payment of annual fee |