CN203856216U - Complete transportation equipment for arc-shaped light-transmitting roof component - Google Patents
Complete transportation equipment for arc-shaped light-transmitting roof component Download PDFInfo
- Publication number
- CN203856216U CN203856216U CN201420099960.3U CN201420099960U CN203856216U CN 203856216 U CN203856216 U CN 203856216U CN 201420099960 U CN201420099960 U CN 201420099960U CN 203856216 U CN203856216 U CN 203856216U
- Authority
- CN
- China
- Prior art keywords
- arc
- transparent roof
- arc transparent
- transported
- transport
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 claims description 9
- 239000010959 steel Substances 0.000 claims description 9
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims description 6
- 239000004677 Nylon Substances 0.000 claims description 5
- 229920001778 nylon Polymers 0.000 claims description 5
- 239000011521 glass Substances 0.000 claims description 3
- 229910052742 iron Inorganic materials 0.000 claims description 3
- 239000000463 material Substances 0.000 claims description 3
- 238000010792 warming Methods 0.000 claims description 3
- 238000010276 construction Methods 0.000 abstract description 21
- 230000000452 restraining effect Effects 0.000 abstract 1
- 238000009434 installation Methods 0.000 description 6
- 238000005516 engineering process Methods 0.000 description 4
- 238000000034 method Methods 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
A complete set of transportation equipment for arc-shaped light-transmitting roof components comprises a vertical hoisting system and a transportation system, wherein the vertical hoisting system is arranged from the ground to an arc-shaped light-transmitting roof, the transportation system is arranged on the surface of the arc-shaped light-transmitting roof, and the vertical hoisting system comprises a winch fixed at the highest point of an arc-shaped light-transmitting roof structure, a hoisting frame connected to the winch and a binding rope for restraining a hoisting path; the transportation system on the arc-shaped light-transmitting roof surface comprises a winch fixed at the highest point of the arc-shaped light-transmitting roof structure, a component transportation tackle running on the arc-shaped light-transmitting roof surface and a slide rail; the next door of hoist engine is provided with and waits to transport the component and stack the platform temporarily, the utility model discloses a self-control hoist and mount frame realizes waiting to transport the vertical hoisting of component, realizes through component transport coaster that arc printing opacity roofing waits to transport the component transportation, simple structure, convenient operation, it is safe high-efficient, reduced construction safety risk when saving manual work and mechanical expense, the component transportation in the arc printing opacity roofing construction of specially adapted large-span.
Description
Technical field
The utility model relates to arc transparent roof installing area, particularly a kind of a kind of component conveying system that facilitates component conveying in the construction of large span arc transparent roof that is applied to.
Background technology
Large span arc transparent roof form of construction work mainly contains two kinds at present, a kind of is to adopt tower crane or big machinery by disposable the member to be transported of the some working face that is transported to, adopting the mode of a dead lift that member sheet to be transported is transported to installation place installs again, its shortcoming is to expend a large amount of artificial and on-the-spot requirements of travelling that is generally difficult to meet crane of practice of construction, the use of crane is subject to very large restriction, is difficult to the position that member to be transported is transported to convenient carrying and installs; Another kind is to adopt tower crane or crane a slice member to be transported of directly slinging to be transported to correspondence position and to install.Its shortcoming is to expend a large amount of mechanical expenses, and workman's construction safety risk is very large.Therefore the shortcoming of existing construction technology is: labor intensive, expend machinery, efficiency of construction is low, construction cost is high.In view of above content, be necessary that utility model is a kind of novel and save artificial, machinery expenses and reduce the component conveying system to be transported of security risk, in order to solve large span arc transparent roof construction problem.
Utility model content
The utility model provides a kind of transport a complete set of equipment of arc transparent roof member, solve available technology adopting tower crane or big machinery by disposablely the member to be transported of some being transported to working face, adopt again the mode of a dead lift that member sheet to be transported is transported to installation place to install, expend the problem that a large amount of artificial and on-the-spot uses that is difficult to travel requirements, the crane that meet crane of practice of construction is subject to very large restriction, is difficult to member to be transported to be transported to the position of convenient carrying and installation; Solve simultaneously and adopt tower crane or crane a slice member to be transported of directly slinging to be transported to that a large amount of machinery expenses is installed, not only expended to correspondence position and workman's construction safety risk is large, efficiency of construction is low, the problem that construction cost is high.
For realizing above-mentioned technical purpose, the utility model is being used following concrete technical scheme:
A kind of transport a complete set of equipment of arc transparent roof member, vertical lifting system comprising from ground to arc transparent roof and the transportation system on arc transparent roof face, it is characterized in that: described vertical lifting system comprise be fixed on arc transparent roof structure peak place hoist engine, be suspended in the mast-up on hoist engine by length-adjustable twin-lock, and be located at the binding yarn of controlling vertical lifting path between hoist engine and ground; Described transportation system on arc transparent roof face comprise be fixed on the hoist engine at arc transparent roof structure peak place, by the component conveying coaster moving on arc transparent roof face on length-adjustable drag-line and hoist engine, and be fixed on arc transparent roof face, arc transparent roof peak and and bottom between lay, as the slide rail of component conveying coaster orbit, described component conveying coaster is placed on slide rail; The side of described hoist engine is provided with the interim stacking platform of member to be transported.
As the yes-no decision of technical solutions of the utility model, described mast-up is hoisting platform or lifting cage.
As technical solutions of the utility model can selection scheme, described component conveying coaster comprises the mobile member that carries the sweep of member to be transported and be arranged on sweep bottom, the size of described sweep and the size of member to be transported adapt, and described mobile member is multiple slides or the nylon pulley that size and slide rail size adapt.
As the preferred version of technical solutions of the utility model, described slide rail is the steel work track that i iron, channel-section steel or angle steel are made.
As the preferred version of technical solutions of the utility model, described slide rail is radial arrangement on arc transparent roof.
As the another kind of preferred version of technical solutions of the utility model, described slide rail is removable slide rail, can be using top peak as fixed point, and remainder does corresponding rotation around fixed point, forms new component conveying track to be transported.
As the yes-no decision of technical solutions of the utility model, described member to be transported is glass plate, warming plate, decorative panel or frame material.
Compared with prior art, technical advantage of the present utility model is: the transport a complete set of equipment that a kind of arc transparent roof member is provided, realize the vertical lifting of member to be transported by self-control mast-up, realize arc transparent roof component conveying to be transported by component conveying coaster, simple in structure, easy to operate, safe and efficient, solve available technology adopting tower crane or big machinery by disposable the member to be transported of the some working face that is transported to, adopting the mode of a dead lift that member sheet to be transported is transported to installation place installs again, expend a large amount of artificial and on-the-spot requirements of travelling that is difficult to meet crane of practice of construction, the use of crane is subject to very large restriction, the problem of the position that is difficult to that member to be transported is transported to convenient carrying and install, solve simultaneously and adopt tower crane or crane a slice member to be transported of directly slinging to be transported to that a large amount of machinery expenses is installed, not only expended to correspondence position and workman's construction safety risk is large, efficiency of construction is low, the problem that construction cost is high.
The utility model is specially adapted to the component conveying to be transported in the arc transparent roof construction of large span.
Brief description of the drawings
Fig. 1 is the structural representation of the vertical lifting system of the member to be transported that relates to of the utility model;
Fig. 2 is the structural representation of the transportation system on arc transparent roof face that relates to of the utility model;
Fig. 3 is the partial enlarged drawing of A in the utility model accompanying drawing 2.
Reference numeral: 1-arc transparent roof, 2-hoist engine, the interim stacking platform of 3-member to be transported, 4-mast-up, 5-lifting rope, 6-member to be transported, 7-component conveying coaster, 71-nylon pulley, 72-sweep, 8-slide rail, 9-drag-line, 10-binding yarn, 11-ground or floor.
Detailed description of the invention
As shown in Figures 1 to 3, a kind of transport a complete set of equipment of arc transparent roof member, vertical lifting system comprising from ground to arc transparent roof and the transportation system on arc transparent roof face, it is characterized in that: described vertical lifting system comprises and is fixed on the hoist engine 2 at arc transparent roof structure peak place, is suspended in the mast-up 4 on hoist engine by length-adjustable twin-lock, and is located at the binding yarn 10 of controlling vertical lifting path between hoist engine and ground; Described transportation system on arc transparent roof face comprise be fixed on the hoist engine 2 at arc transparent roof structure peak place, by the component conveying coaster 7 moving on arc transparent roof face on length-adjustable drag-line 9 and hoist engine, and be fixed on arc transparent roof face, arc transparent roof peak and and bottom between lay, as the slide rail 8 of component conveying coaster 7 orbits, described component conveying coaster 7 is placed on slide rail 8; The side of described hoist engine 2 is provided with the interim stacking platform 3 of member to be transported.
As the yes-no decision of technical solutions of the utility model, described mast-up 4 is hoisting platform or lifting cage.
As technical solutions of the utility model can selection scheme, described component conveying coaster 7 comprises the sweep 72 that carries member to be transported and the mobile member that is arranged on sweep bottom, the size of the size of described sweep 72 and member to be transported 6 adapts, described mobile member is multiple slides or the nylon pulley 71 that size and slide rail 8 sizes adapt, and in the utility model accompanying drawing 2 and 3, having embodiment 1 component conveying coaster 7 bottoms is the structural representation of nylon pulley 71.
As the preferred version of technical solutions of the utility model, the steel work track that described slide rail 8 is made for i iron, channel-section steel or angle steel.
As the preferred version of technical solutions of the utility model, described slide rail 8 is radial arrangement on arc transparent roof 1.
As another preferred version of technical solutions of the utility model, described slide rail 8 can be also removable slide rail, when construction, to not lay many slide rails 8, only need to lay a removable slide rail, then by this slide rail using top peak as fixed point, remainder does corresponding rotation around fixed point, can form new member to be transported 6 conveying tracks.
As the yes-no decision of technical solutions of the utility model, described member 6 to be transported is glass plate, warming plate, decorative panel or frame material.
While utilizing the large span arc transparent roof construction that the transport a complete set of equipment of above-mentioned arc transparent roof member carries out, comprise that member 6 to be transported is carried out to vertical lifting delivers to operation on arc transparent roof 1 and the member to be transported 6 transport operation on 1 of arc transparent roof, its specific implementation method is as follows:
Fig. 1 is that the utility model operation one is carried out vertical lifting by member to be transported and delivered to the schematic diagram on arc transparent roof, and as shown in the figure, concrete operation step is as follows:
Operation one, member 6 to be transported carried out to vertical lifting deliver on arc transparent roof 1:
Step 1, at arc transparent roof 1 structure peak place, lay according to actual needs the hoist engine 2 of appropriate power, and the interim stacking platform 3 of member to be transported be set;
The mast-up 4 that the size of step 2, making and member to be transported 6 matches;
Step 3, mast-up 4 is placed on the ground or floor of hoist engine 2 belows, lifting rope 5 and binding yarn 10 for two ropes liftings are installed between mast-up 4 and hoist engine 2;
Step 4, member to be transported 6 is transported on the ground or floor 11 of hoist engine 2 belows in batches with tower crane
Step 5, member 6 to be transported is placed in mast-up 4 and temporary fixed;
Step 6, startup hoist engine 2 carry out two ropes liftings, mast-up 4 are winched on the platform of arc transparent roof 1 peak plane;
Step 7, unload member 6 to be transported, transfer mast-up 4, carry out the vertical lifting of next group member 6 to be transported according to same method;
Fig. 2 is the schematic diagram that the utility model operation two is carried out the member to be transported transport of member to be transported on arc transparent roof while installing, and as shown in the figure, concrete operation step is as follows:
Operation two, carry out member 6 to be transported member 6 to be transported transport on arc transparent roof 1 while installing:
Step 1, making component conveying coaster 7, place it near the interim stacking platform 3 of member to be transported of arc transparent roof 1 structure peak;
Step 2, between the top peak of arc transparent roof 1 arcuate structure and bottom, lay the slide rail 8 as component conveying coaster 7 orbits, component conveying coaster 7 is placed on slide rail 8;
Step 3, between component conveying coaster 7 and hoist engine 2, drag-line 9 is installed;
Step 4, member 6 to be transported is placed on component conveying coaster 7;
Step 5, startup hoist engine 2, two ropes are held component conveying coasters 7, make component conveying coaster 7 slide to the lowermost end of arc transparent roof 1 arc structure along slide rail 8;
Step 6, unload a slice member 6 to be transported, member 6 to be transported is laid and is arranged on this position, place;
Step 7, up pull component conveying coaster 7, make it slide to second member to be transported 6 installation site, then unload a slice member 6 to be transported, member 6 to be transported is laid and is arranged on this position, place;
Step 8, according to same method, laid successively member 6 to be transported from lower toward eminence;
Step 9, after member to be transported 6 all unload, near the interim stacking platform 3 of member to be transported that component conveying coaster 7 returns arc transparent roof 1 structure peak is reprinted this member 6 to be transported again, until whole installation.
Claims (7)
1. the transport a complete set of equipment of an arc transparent roof member, vertical lifting system comprising from ground to arc transparent roof and the transportation system on arc transparent roof, it is characterized in that: described vertical lifting system comprises and is fixed on the hoist engine (2) at arc transparent roof structure peak place, is suspended in the mast-up (4) on hoist engine by length-adjustable twin-lock, and is located at the binding yarn (10) of controlling vertical lifting path between hoist engine and ground; Described transportation system on arc transparent roof face comprise be fixed on the hoist engine (2) at arc transparent roof structure peak place, by the component conveying coaster (7) moving on arc transparent roof face on length-adjustable drag-line (9) and hoist engine, and be fixed on arc transparent roof face, arc transparent roof peak and and bottom between lay, as the slide rail (8) of component conveying coaster (7) orbit, described component conveying coaster (7) is placed on slide rail (8); The side of described hoist engine (2) is provided with the interim stacking platform of member to be transported (3).
2. the transport a complete set of equipment of a kind of arc transparent roof member according to claim 1, is characterized in that: described mast-up (4) is hoisting platform or lifting cage.
3. the transport a complete set of equipment of a kind of arc transparent roof member according to claim 1, it is characterized in that: described component conveying coaster (7) comprises the mobile member that carries the sweep (72) of member to be transported and be arranged on sweep bottom, the size of the size of described sweep (72) and member to be transported (6) adapts, and described mobile member is multiple slides or the nylon pulley (71) that size and slide rail (8) size adapt.
4. the transport a complete set of equipment of a kind of arc transparent roof member according to claim 1, is characterized in that: described slide rail (8) is the steel work track that i iron, channel-section steel or angle steel are made.
5. the transport a complete set of equipment of a kind of arc transparent roof member according to claim 1, is characterized in that: described slide rail (8) is radial arrangement on arc transparent roof.
6. the transport a complete set of equipment of a kind of arc transparent roof member according to claim 1, it is characterized in that: described slide rail (8) is removable slide rail, can, using top peak as fixed point, thereby doing corresponding rotation around fixed point, remainder form new component conveying track to be transported.
7. according to the transport a complete set of equipment of a kind of arc transparent roof member described in claim 1~6 any one, it is characterized in that: described member to be transported (6) is glass plate, warming plate, decorative panel or frame material.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420099960.3U CN203856216U (en) | 2014-03-06 | 2014-03-06 | Complete transportation equipment for arc-shaped light-transmitting roof component |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420099960.3U CN203856216U (en) | 2014-03-06 | 2014-03-06 | Complete transportation equipment for arc-shaped light-transmitting roof component |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203856216U true CN203856216U (en) | 2014-10-01 |
Family
ID=51606078
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201420099960.3U Expired - Fee Related CN203856216U (en) | 2014-03-06 | 2014-03-06 | Complete transportation equipment for arc-shaped light-transmitting roof component |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203856216U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103790390A (en) * | 2014-03-06 | 2014-05-14 | 中国建筑第二工程局有限公司 | Glass plate hoisting system for large-span dome glass curtain wall construction and construction method thereof |
CN113213085A (en) * | 2021-05-14 | 2021-08-06 | 深圳市三鑫科技发展有限公司 | Material transportation system applied to arched roof building |
-
2014
- 2014-03-06 CN CN201420099960.3U patent/CN203856216U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103790390A (en) * | 2014-03-06 | 2014-05-14 | 中国建筑第二工程局有限公司 | Glass plate hoisting system for large-span dome glass curtain wall construction and construction method thereof |
CN103790390B (en) * | 2014-03-06 | 2015-11-18 | 中国建筑第二工程局有限公司 | Glass plate hoisting system for large-span dome glass curtain wall construction and construction method thereof |
CN113213085A (en) * | 2021-05-14 | 2021-08-06 | 深圳市三鑫科技发展有限公司 | Material transportation system applied to arched roof building |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103790390B (en) | Glass plate hoisting system for large-span dome glass curtain wall construction and construction method thereof | |
CN201377184Y (en) | Ultra-long roofing contour plate vertical lifting transporting device | |
CN104192735B (en) | A kind of minor crane | |
CN202248941U (en) | Integral lifting, positioning and mounting device for large-scale steel members | |
CN201980880U (en) | Hoisting device | |
CN205387453U (en) | Cubical switchboard hoisting device | |
CN203856216U (en) | Complete transportation equipment for arc-shaped light-transmitting roof component | |
CN203794533U (en) | Light portable mobile lifting equipment | |
CN206562264U (en) | A kind of hanging device for transport outside high-rise building | |
CN103821084B (en) | Operational method at the bottom of implement at the bottom of beam and beam | |
CN107313356B (en) | A kind of fortune beam method that double-decker bridge is built | |
CN104401887B (en) | A kind of micro lifter | |
CN107720652A (en) | A kind of construction method for hanging of frame structure large scale equipment | |
CN204609308U (en) | A kind of passage limited position concrete rail transporter | |
CN215046305U (en) | Material transportation system applied to arched roof building | |
CN205527498U (en) | Utilize pulley system's hoist and mount and conveyer | |
CN203781713U (en) | High slope support material transport device | |
CN106087756A (en) | The erecting device of Wavelike steel webplate and installation method | |
CN202544409U (en) | High-rise building construction material discharging device | |
CN211366784U (en) | Integral hoisting system in narrow space | |
CN202208625U (en) | Hydraulic lifting platform of hydraulic control system | |
CN209179426U (en) | A kind of elevator shaft steel construction section construction device | |
CN207747906U (en) | A kind of small precast cover board installation carriage | |
CN104192469A (en) | Electric tower sliding and conveying device and application method thereof | |
CN206827837U (en) | The cable windings timber of hydraulic elevator platform is installed |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20141001 Termination date: 20150306 |
|
EXPY | Termination of patent right or utility model |