CN203821925U - Earthquake-proofing house of light steel structure - Google Patents

Earthquake-proofing house of light steel structure Download PDF

Info

Publication number
CN203821925U
CN203821925U CN201420102083.0U CN201420102083U CN203821925U CN 203821925 U CN203821925 U CN 203821925U CN 201420102083 U CN201420102083 U CN 201420102083U CN 203821925 U CN203821925 U CN 203821925U
Authority
CN
China
Prior art keywords
wall
joist
keel
secondary joist
link plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420102083.0U
Other languages
Chinese (zh)
Inventor
霍学朝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201420102083.0U priority Critical patent/CN203821925U/en
Application granted granted Critical
Publication of CN203821925U publication Critical patent/CN203821925U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Abstract

The utility model relates to an earthquake-proofing house of a light steel structure. For walls, light steel keels are adopted as a wall structural system, and for floors, light steel keels are adopted as a floor structural system, wherein the floor structural system and the wall structural system share main keels; the floor structural system further comprises sub keels, wherein the sub keels are arranged between two adjacent main keels, the sub keels are vertically connected with the main keels, the sub keels are mutually parallel, or the sub keels are vertically crossed; the wall structural system further comprises wall keels, wherein the wall keels are vertically connected with the main keels, and the wall keels are mutually parallel. The earthquake-proofing house of the light steel structure has the advantages of reasonable structure, heat preservation, thermal insulation, low energy consumption and good effect; different keel structures are adopted for the walls and the floors, and a keel connecting mode is simple and reliable, so that a building structure is more stable, the installation is simpler, more convenient, rapider and more reasonable, and the requirement on construction operating personnel is lowered. The earthquake-proofing house is suitable for building extensive rural houses.

Description

A kind of lightweight steel construction Antiseismic house
Technical field
The utility model relates to earthquake-resistant building structure system, is a kind of lightweight steel construction Antiseismic house specifically.
Background technology
Earthquake in recent years happens occasionally, and harm impact is very large, and building implementation structure antidetonation, building energy conservation integrated design are the developing direction that construction industry is constantly inquired into and pursued.And in modern society, the energy, environment have become the matter of utmost importance that affects Chinese national economy and sustainable development.
Existing building, main structure and the mode of construction of energy saving integrated have: cast-in-situ steel reinforced concrete sandwich energy-saving structural system, block insulation sandwich energy-saving structural system, light steel frame insulation sandwich board energy-saving structure system, inner deposited and outer hung steel concrete insulation sandwich board energy-saving structure system, lightweight structures system etc.For ease of statement, by the mode of construction of this structure and energy saving integrated referred to as structure self-heat-insulation system.
Around the power-saving technology of building maintenance structure, traditional way normally adopts External Thermal Insulation Technology for External, that is: inner side of outer wall or the outside paste heat-preserving heat-barrier material at building forms external thermal insulation, and then reaches the object that thermal insulation reduces energy consumption.Yet the heat preserving and insulating material of domestic a large amount of employings at present, when playing thermal insulation reduction energy consumption, but exists significant deficiency and hidden danger:
One, heat preserving and insulating material is inflammable, causes the fire prevention fire resistance of building very low, once breaking out of fire, its external thermal insulation will become comburant, increase the weight of the condition of a disaster of fire;
Its two, when using in highrise building, the ornament materials such as ceramic tile of external thermal insulation external pasting, are easy to come off because with the passing of time wind, rain erosion etc. cause, and have a strong impact on the person and property safety;
Its three, External Thermal Insulation Technology for External is difficult to accomplish and builds the same life-span;
In addition, the thermal insulation of floor reduction energy consumption lacks corresponding solution.
Housing industry has become one of mainstay of Chinese national economy.Yet, dwelling construction particularly village-town house as the conventional industries of China, long-term in the extensive production phase, the main difficult technical such as village-town house shock resistance is poor, industrialized level is low, labor productivity is low and resource consumption is high, degree of contamination is large is urgently to be resolved hurrily.Therefore, carry out correlation technique research, it is very necessary for the village-town house having a large capacity and a wide range, proposing complete thermal insulation reduction energy consumption solution.
Along with the demand of China market economic development, foreign corporation pours in the introduction with technical equipment, has greatly accelerated the developing steps of China's light-weight structure residence building system.But, because scientific research, design, the execution control work of lightweight steel construction relatively lags behind, so also there are many problems in the process of development.At present, exploitation lightweight steel construction system technology shifts to the marketization, commercial running, though make part achievement through identifying assessment, engineering application research and development lack of staying power.The development scheme that production, teaching & research combines is relatively weak.Marketing application faces many problems, mainly contains:
1, the lightweight steel design theory of computation is comparatively perfect, but the problem of structure and energy saving integrated does not have fine solution; The heat insulating material that lacks the suitable for China of suiting measures to local conditions;
2, difficulty of construction strengthens, and needs professional contingent;
3, design research and development are combined with market not, and engineering application is limited to pilot more;
4, lightweight steel construction system is served urban villa class building more at present, and overall cost is higher, for vast village-town house, is difficult to be suitable for;
5, foam cement or glass bead, can improve insulation, the acoustical effectiveness of building as the insulation layer of body of wall, it is effective that thermal insulation reduces energy consumption, but in light-weight structure residence, not yet apply, universal, in light-weight structure residence, lack complete embodiment.
Utility model content
For the defect existing in prior art, the purpose of this utility model is to provide a kind of lightweight steel construction Antiseismic house, with ecomaterial, new construction and new technology be adopted as principal character, with material property, combined wall board, the force-mechanism of composite floor plate, the anti-seismic performance of structure and energy-saving building technology research are core, with Structural Engineering, material engineering and building energy conservation related discipline crossing research are characteristic, pass through material, the research of element structure and three aspects of building energy conservation, theory analysis and demonstration project construction and application of result are promoted, on the basis of combining closely in production, teaching & research, realize novel light-steel structural seismic room, completed the light steel composite board structural system of novel energy-conserving complete set technology.
For reaching above object, the technical scheme that the utility model is taked is:
A lightweight steel construction Antiseismic house, is characterized in that: its body of wall adopts lightgage steel joist as wall structural system, and its floor adopts lightgage steel joist as floor slab structure system, wherein:
Described floor slab structure system and wall structural system share main joist 2,
Described floor slab structure system also comprises secondary joist 3, and secondary joist 3 is located between two adjacent main joists 2, and secondary joist 3 is connected with main joist 2 is vertical, parallel to each other between secondary joist 3, or square crossing between secondary joist 3,
Described wall structural system also comprises wall keel 1, and wall keel 1 are connected with main joist 2 is vertical, parallel to each other between wall keel 1.
On the basis of technique scheme, described lightgage steel joist material is galvanized sheet, rolls galvanized sheet one-body molded by keel machine.
On the basis of technique scheme, in floor slab structure system region, be provided with the lower floor's fiber cement board 1014 being connected with main joist 2 and/or secondary joist 3,
On floor slab structure system, be provided with the top fiber cement board 1010 that is connected 4 with main joist 2 and/or secondary joist 3,
In floor slab structure system, lower floor's fiber cement board 1014 and top fiber cement board 1010 enclosed spaces, monobloc cast has inorganic light heat insulation material, forms floor insulation layer 1012.
On the basis of technique scheme, in the both sides, front and back of wall keel 1, mount wall link plate as the internal and external ornament sheet material of body of wall,
In wall structural system, internal and external ornament sheet material enclosed space, monobloc cast has inorganic light heat insulation material, forms wall insulating layer 1107.
On the basis of technique scheme, described wall link plate includes but not limited to: cement board, golden nation plate, pottery clay plates, woodwool board.
On the basis of technique scheme, described inorganic light weight thermal insulation material is foam cement or glass bead.
On the basis of technique scheme, wall keel 1 vertically arrange, main joist 2 and the equal along continuous straight runs setting of secondary joist 3,
On main joist 2, be provided with inner core connector 5, described inner core connector 5 is a cuboid,
Wall keel 1 are connected with main joist 2 is vertical by inner core connector 5,
Secondary joist 3 is connected with inner core connector 5 is vertical by corner brace 4 is installed.
On the basis of technique scheme, described secondary joist 3 comprises:
Secondary joist lower shoe 36,
Along the length direction of secondary joist lower shoe 36, symmetrical be provided with extend upward after the secondary joist lower hem 33 of inside 90 degree bendings again,
The end that secondary joist lower hem 33 bends inwards upwards vertically extends to form vertically section 37 of secondary joist,
The secondary joist vertically rear and front end of section 37 is provided with several times keel installation hole 35,
The secondary joist vertically upper end of section 37 bends 90 degree formation secondary joist ribs 31 laterally, is secondary joist opening between secondary joist rib 31.
On the basis of technique scheme, along the length direction of secondary joist lower shoe 36, be provided with between two parties at least one secondary joist lower shoe reinforcing rib 34;
Along the length direction of the vertical section 37 of secondary joist, be provided with between two parties vertically section reinforcing rib 32 of at least one secondary joist.
On the basis of technique scheme, the bar shaped cell body of described secondary joist lower shoe reinforcing rib 34 for raising up;
Described secondary joist vertically section reinforcing rib 32 is the bar shaped cell body to the vertical section of secondary joist 37 outside projections.
On the basis of technique scheme, the global shape structure of described main joist 2 and secondary joist 3 is identical, and the two difference is:
Main joist lower shoe is provided with for installing the mounting groove of inner core connector 5.
On the basis of technique scheme, for installing the mounting groove of inner core connector 5, during for site operation, according to concrete definite installation site on-the-spot fluting on main joist 2.
On the basis of technique scheme, described wall keel 1 comprise:
Wall shoe 13,
Along the length direction of wall shoe 13, be symmetrically provided with vertically extending wall side of keel 12,
Wall side of keel 12 forms wall keel flanging 11 away from one end 90 degree bendings laterally of wall shoe 13, is wall keel openings between wall keel flanging 11,
The two ends up and down of wall side of keel 12 are provided with some wall keel installations hole 14.
On the basis of technique scheme, inner core connector 5 is threaded onto in mounting groove, and two ends are exposed to respectively outside main joist 2 up and down,
The front side and the rear side that at inner core connector 5, are exposed to the end outside main joist 2 are respectively provided with wall keel 1;
Pegging graft with corner brace 4 is installed respectively in the rear and front end of secondary joist 3, and fixes with screw or bolt.
On the basis of technique scheme, described installation corner brace 4 comprises:
Corner brace base plate 41 is installed, and its two ends, left and right vertically extend to form corner brace left side wall 42 are installed, corner brace right side wall 43 is installed,
The spacing of corner brace left side wall 42 being installed, installing between corner brace right side wall 43 is slightly less than the vertically spacing between section 37 of secondary joist,
Corner brace left side wall 42 being installed, being installed on corner brace right side wall 43, be equipped with the installation corner brace pilot hole 44 with secondary joist installing hole 35 adaptations.
On the basis of technique scheme, the part of corner brace 4 within being positioned at main joist 2 with inner core connector 5 is installed and by staking nut, is connected, or fix with screw or bolt;
Or:
The part of corner brace 4 outside being exposed to main joist 2 with inner core connector 5 is installed and by staking nut, is connected, or fix with screw or bolt;
Or:
The part that part, the inner core connector 5 of corner brace 4 within being positioned at main joist 2 with inner core connector 5 be respectively exposed to outside main joist 2 is installed and by staking nut, is connected, or fix with screw or bolt.
On the basis of technique scheme, between the wall keel flanging 11 of two wall keel 1 that front and back are oppositely arranged, leave gap.
On the basis of technique scheme, the wall keel opening of wall keel 1 is inserted on inner core connector 5, and the distance between the distance between wall side of keel 12 and inner core connector 5 left and right sidewalls is adaptive, after plug-in mounting:
The wall shoe 13 of wall keel 1 touches with inner core connector 5 front side walls or rear wall,
The wall side of keel 12 of wall keel 1 clamps inner core connector 5 left and right sidewalls,
Screw or bolt be through wall keel installation hole 14, and the end outside the end of wall keel 1 is exposed to main joist 2 with inner core connector 5 is fixedly connected with.
On the basis of technique scheme, described floor comprises:
The floor slab structure system being surrounded by main joist 2 and secondary joist 3,
On secondary joist lower hem 33 and/or main joist lower hem, be provided with lower floor's fiber cement board 1014,
Lower floor's fiber cement board 1014 is fixedly connected with secondary joist lower hem 33 and/or main joist lower hem respectively by screw,
In floor slab structure system and lower floor's fiber cement board 1014 enclosed spaces, build inorganic light heat insulation material, formed floor insulation layer 1012,
The height of building of floor insulation layer 1012 flushes with secondary joist rib 31 and/or main joist rib,
On floor insulation layer 1012, be equipped with layer of steel wire net 1011,
On gauze wire cloth 1011, be coated with one deck anticracking grout,
Anticracking grout is provided with top fiber cement board 1010,
Top fiber cement board 1010 is fixedly connected with secondary joist rib 31 and/or main joist rib respectively by screw.
On the basis of technique scheme, on top fiber cement board 1010, lay wood flooring or ceramic tile.
On the basis of technique scheme, described body of wall comprises:
The wall structural system being surrounded by main joist 2 and wall keel 1,
On main joist 2, be provided with inner core connector 5,
On the wall shoe 13 of wall keel 1 that is positioned at inner core connector 5 front sides, be provided with some spaced bridge cut-off adjustable positioning components 1103,
Bridge cut-off adjustable positioning component 1103 rear ends are connected with the wall keel 1 that are positioned at inner core connector 5 front sides by the inner core 1102 with staking mother,
Bridge cut-off adjustable positioning component 1103 front ends are connected with the link plate keel 1101 that arrange horizontally set or vertical,
On the leading flank of link plate keel 1101, be provided with some link plate parts 1104, as the wall link plate 1105 of outer decoration for vertical face plate, be mounted on link plate part 1104,
On the wall shoe 13 of wall keel 1 that is positioned at inner core connector 5 rear sides, be provided with some link plate parts 1104, as the wall link plate 1106 of inner wall panel, be mounted on link plate part 1104,
In wall structural system, internal and external ornament sheet material enclosed space, monobloc cast has inorganic light heat insulation material, forms wall insulating layer 1107.
On the basis of technique scheme, described link plate part 1104 is supporting with wall link plate.
On the basis of technique scheme, described wall link plate integral body is rectangular, and its upper surface is provided with notch 1401, and soffit is provided with lower notch 1402,
Described upper notch 1401 comprises:
End face 1503, its rear and front end extends to form respectively the first lateral surface 1506, the first medial surface 1504 downwards,
Described the first lateral surface 1506 is vertical with end face 1503, or tilts to wall link plate lateral surface 1502 directions,
Described the first medial surface 1504 is vertical with end face 1503, or tilts to wall link plate medial surface 1501 directions,
The first lateral surface 1506 is connected by the first joint face 1507 with 1502 of wall link plate lateral surfaces,
The first medial surface 1504 is connected by the second joint face 1505 with 1501 of wall link plate medial surfaces,
The level height of described the second joint face 1505 is higher than the level height of the first joint face 1507;
Described lower notch 1402 comprises:
Bottom surface 1511, its rear and front end extends to form respectively the second lateral surface 1510, the second medial surface 1512 downwards,
Described the second lateral surface 1510 is vertical with bottom surface 1511, or tilts to wall link plate lateral surface 1502 directions,
Described the second medial surface 1512 is vertical with bottom surface 1511, or tilts to wall link plate medial surface 1501 directions,
The second lateral surface 1510 is connected by the 3rd joint face 1508 with 1502 of wall link plate lateral surfaces,
The second medial surface 1512 is connected by the 4th joint face 1509 with 1501 of wall link plate medial surfaces,
The level height of described the 4th joint face 1509 is higher than the level height of the 3rd joint face 1508.
On the basis of technique scheme, at one deck of building body, in the turning point of body of wall, be provided with and be embedded in underground concrete stanchion 1601,
The end face of concrete stanchion 1601 is provided with column fixed base plate 1602,
Column 1603 vertically arranges, and the lower end of column 1603 is fixed on column fixed base plate 1602,
Main joist is fixedly connected with main joist 2, column 1603 respectively with column connecting piece 1605.
Lightweight steel construction Antiseismic house described in the utility model, rational in infrastructure, it is effective that thermal insulation reduces energy consumption, for body of wall, floor, adopt respectively different keel structures, and guarantee that keel connected mode is simple, reliable, and make the structure of building more stable, it is more simple and efficient, more reasonable to install, constructing operation personnel are required low, be applicable to vast village-town house construction.
Lightweight steel construction Antiseismic house described in the utility model, the multidirectional connected mode of lightgage steel joist arranges rationally, and conveniently requirement while meeting construction, requires low, time saving and energy saving to operating personnel.
Accompanying drawing explanation
The utility model has following accompanying drawing:
The assembling schematic diagram of Fig. 1 wall keel and ground joist,
The explosive view of Fig. 2 Fig. 1,
The structural representation of Fig. 3 secondary joist,
The sectional drawing of Fig. 4 secondary joist,
Fig. 5 installs the structural representation of corner brace,
The structural representation of Fig. 6 wall keel,
The structural representation of Fig. 7 floor,
The structural representation of Fig. 8 body of wall,
The structural representation of Fig. 9 link plate part,
The assembling schematic diagram of Figure 10 link plate part and wall link plate,
The sectional drawing of Figure 11 wall link plate,
The sectional drawing of the upper notch of Figure 12 wall link plate,
The sectional drawing of the lower notch of Figure 13 wall link plate,
The assembling schematic diagram of Figure 14 concrete stanchion and main joist.
The specific embodiment
Below in conjunction with accompanying drawing, the utility model is described in further detail.
Lightweight steel construction Antiseismic house described in the utility model, its body of wall adopts lightgage steel joist as wall structural system (wall body structure load-bearing skeleton), its floor adopts lightgage steel joist as floor slab structure system (floor slab structure load-bearing skeleton), wherein, and as shown in Figure 1, 2:
Described floor slab structure system and wall structural system share main joist 2, main joist 2 is generally at least along body of wall setting, in the time need to improving the intensity of floor slab structure system, (such as the region of the large building areas such as hall) also can arrange main joist 2 in the region without body of wall
Described floor slab structure system also comprises secondary joist 3, secondary joist 3 is located between two adjacent main joists 2, secondary joist 3 is connected with main joist 2 is vertical, parallel to each other between secondary joist 3, or square crossing between secondary joist 3, according to varying in size of room Nei Ge region building area, secondary joist 3 may have following several facilities: the first, between several times keel 3 all (such as the region of the Minor Construction areas such as aisle) parallel to each other, the second, 3 of several times keel be arranged in parallel, 3 of several times keel also be arranged in parallel in addition, (ranks intersect to form latticed for described several times keel 3 and in addition 3 square crossings of several times keel, region such as large building areas such as halls), above two kinds of situations are only for giving an example, and the plan of establishment of non-limiting secondary joist 3, meeting building performance (antidetonation, the design objectives such as floor load-bearing) under condition, can be by the concrete plan of establishment of existing lightgage steel joist working design manufacturing process determination secondary joist 3,
Described wall structural system also comprises wall keel 1, and wall keel 1 are connected with main joist 2 is vertical, parallel to each other between wall keel 1.
When practice of construction, for example, when single main joist 2 or the satisfied construction needs of secondary joist 3 length (room or aisle span are greater than single main joist 2 or secondary joist 3 length), between two main joists 2, by lengthening connecting elements, be connected and lengthen main joist 2, between two secondary joists 3, by lengthening connecting elements, be connected and lengthen secondary joist 3, described lengthening connecting elements is square tube or U-shaped fastener, lengthens connecting elements and is fixedly connected with (such as riveting, bolt is connected etc.) with main joist 2 or secondary joist 3.
Described lightgage steel joist material is galvanized sheet, and the thickness of galvanized sheet is determined according to designing requirement and anti-seismic detection data.It is one-body molded that keel (main joist 2, secondary joist 3, wall keel 1) preferably roll galvanized sheet by keel machine, makes that keel intensity is high, long service life.
On the basis of technique scheme, as shown in Figure 7, in floor slab structure system region, be provided with the lower floor's fiber cement board 1014 that is connected (being fixedly connected with) with main joist 2 and/or secondary joist 3,
On floor slab structure system, be provided with the top fiber cement board 1010 that is connected (being fixedly connected with) with main joist 2 and/or secondary joist 3,
In floor slab structure system, lower floor's fiber cement board 1014 and top fiber cement board 1010 enclosed spaces, monobloc cast has inorganic light heat insulation material, forms floor insulation layer 1012.
Build after inorganic light weight thermal insulation material, form the light steel composite board floor of structure and energy saving integrated.
On the basis of technique scheme, as shown in Figure 8, in the both sides, front and back of wall keel 1, mount wall link plate as the internal and external ornament sheet material of body of wall,
In wall structural system, internal and external ornament sheet material enclosed space, monobloc cast has inorganic light heat insulation material, forms wall insulating layer 1107.
Build after inorganic light weight thermal insulation material, form the light steel composite board body of wall of structure and energy saving integrated.
On the basis of technique scheme, described wall link plate includes but not limited to: cement board, golden nation plate, pottery clay plates, woodwool board.Such as: can also be the dalles such as gypsum plank or calcium silicate board.
On the basis of technique scheme, described inorganic light weight thermal insulation material is foam cement or glass bead.
On the basis of technique scheme, as shown in Figure 1, 2, wall keel 1 vertically arrange, main joist 2 and the equal along continuous straight runs setting of secondary joist 3,
On main joist 2, be provided with inner core connector 5, as shown in Figure 2, described inner core connector 5 is a cuboid, and it can be provided with the rectangle endoporus that connects upper and lower surface,
Wall keel 1 are connected with main joist 2 is vertical by inner core connector 5,
Secondary joist 3 is connected with inner core connector 5 is vertical by corner brace 4 is installed.
In Fig. 1, the setting party of wall keel 1 is to being upper and lower, and the setting party of main joist 2 is to being left and right, and the setting party of secondary joist 3 is to being front and back, and the direction of all the other accompanying drawings is all described with reference to Fig. 1.
On the basis of technique scheme, as shown in Figure 2,3, 4, described secondary joist 3 comprises:
Secondary joist lower shoe 36,
Along the length direction of secondary joist lower shoe 36, symmetrical be provided with extend upward after the secondary joist lower hem 33 of inside 90 degree bendings again,
The end that secondary joist lower hem 33 bends inwards upwards vertically extends to form vertically section 37 of secondary joist,
The secondary joist vertically rear and front end of section 37 is provided with several times keel installation hole 35, embodiment illustrated in fig. 3 in, the secondary joist vertically rear and front end of section 37 is respectively provided with 35, two one group of four secondary joist installing hole and is oppositely arranged up and down,
The secondary joist vertically upper end of section 37 bends 90 degree formation secondary joist ribs 31 laterally, is secondary joist opening between secondary joist rib 31.
On the basis of technique scheme, as shown in Figure 3,4, along the length direction of secondary joist lower shoe 36, be provided with between two parties at least one secondary joist lower shoe reinforcing rib 34;
Along the length direction of the vertical section 37 of secondary joist, be provided with between two parties vertically section reinforcing rib 32 of at least one secondary joist.
On the basis of technique scheme, the bar shaped cell body of described secondary joist lower shoe reinforcing rib 34 for raising up, referring to Fig. 4;
Described secondary joist vertically section reinforcing rib 32 is the bar shaped cell body to the vertical section of secondary joist 37 outside projections, referring to Fig. 4.
On the basis of technique scheme, the global shape structure of described main joist 2 and secondary joist 3 is identical, and the two difference is:
On the main joist lower shoe of main joist 2, be provided with for installing the mounting groove of inner core connector 5.
Further, because main joist 2 still forms the part of body of wall, therefore according to actual needs, the material thickness of main joist 2 is equal to or greater than the material thickness of (being slightly larger than) secondary joist 3,
Further, main joist is the spacing between section vertically, equals the vertically spacing between section of secondary joist, or is at least vertically 1.5 times of the spacing between section of secondary joist.Main joist is the spacing between section vertically, can design according to thickness of wall body.For example: the secondary joist vertically spacing between section is 40mm, the spacing between the vertical section of main joist can be 80mm, can be 100mm.
During keel assembling, secondary joist opening, main joist opening are all upward.
On the basis of technique scheme, for installing the mounting groove of inner core connector 5, during for site operation, according to concrete definite installation site on-the-spot fluting on main joist 2.Described inner core connector 5 has the effect that increases keel intensity concurrently, embodiment illustrated in fig. 1 in, mounting groove is arranged on main joist 2 between two parties, during site operation, can be according to concrete definite installation site on-the-spot fluting on main joist 2.
On the basis of technique scheme, as shown in Figure 6, described wall keel 1 comprise:
Wall shoe 13,
Along the length direction of wall shoe 13, be symmetrically provided with vertically extending wall side of keel 12,
Wall side of keel 12 forms wall keel flanging 11 away from one end 90 degree bendings laterally of wall shoe 13, is wall keel openings between wall keel flanging 11,
The two ends up and down of wall side of keel 12 are provided with some wall keel installations hole 14, embodiment illustrated in fig. 6 in, the two ends up and down of wall side of keel 12 are oppositely arranged before and after being respectively provided with 14, two one group, four wall keel installation holes,
Wall keel installation hole 14 can be used for installing screw or bolt or other connectors of connection wall keel 1 and inner core connector 5.
On the basis of technique scheme, inner core connector 5 is threaded onto in mounting groove, and two ends are exposed to respectively outside main joist 2 up and down, and the spacing between inner core connector 5 front and back sidewalls is slightly less than the vertically spacing between section of main joist,
The front side and the rear side that at inner core connector 5, are exposed to the end outside main joist 2 are respectively provided with wall keel 1;
Pegging graft with corner brace 4 is installed respectively in the rear and front end of secondary joist 3, and fixes (other applicable connectors also can be used for being fixed) herein with screw or bolt.
On the basis of technique scheme, as shown in Figure 5, described installation corner brace 4 comprises:
Corner brace base plate 41 is installed, and its two ends, left and right vertically extend to form corner brace left side wall 42 are installed, corner brace right side wall 43 is installed,
The spacing of corner brace left side wall 42 being installed, installing between corner brace right side wall 43 is slightly less than the vertically spacing between section 37 of secondary joist,
Corner brace left side wall 42 is being installed, is being installed on corner brace right side wall 43, be equipped with the installation corner brace pilot hole 44 with secondary joist installing hole 35 adaptations, for example: the number of positions that corner brace pilot hole 44 is installed is identical with secondary joist installing hole 35.
Corner brace 4 is installed and is plugged between the vertical section 37 of secondary joist, screw or bolt are threaded onto to be installed in corner brace pilot hole 44, secondary joist installing hole 35, corner brace 4 will be installed and be connected with secondary joist 3.
On the basis of technique scheme, the part of corner brace 4 within being positioned at main joist 2 with inner core connector 5 is installed and by staking nut, is connected, or fix with screw or bolt;
Or:
The part of corner brace 4 outside being exposed to main joist 2 with inner core connector 5 is installed and by staking nut, is connected, or fix with screw or bolt;
Or:
The part that part, the inner core connector 5 of corner brace 4 within being positioned at main joist 2 with inner core connector 5 be respectively exposed to outside main joist 2 is installed and by staking nut, is connected, or fix with screw or bolt.
On the basis of technique scheme, between the wall keel flanging 11 of two wall keel 1 that front and back are oppositely arranged (referring to be located at two wall keel 1 of inner core connector 5 front sides and rear side), leave gap.This gap is for the monobloc cast of body of wall.
On the basis of technique scheme, the wall keel opening of wall keel 1 is inserted on inner core connector 5, and the distance between the distance between wall side of keel 12 and inner core connector 5 left and right sidewalls is adaptive, after plug-in mounting:
The wall shoe 13 of wall keel 1 touches with inner core connector 5 front side walls or rear wall,
The wall side of keel 12 of wall keel 1 clamps inner core connector 5 left and right sidewalls,
Screw or bolt be through wall keel installation hole 14, and the end outside the end of wall keel 1 (upper end and/or lower end) is exposed to main joist 2 with inner core connector 5 is fixedly connected with.
On the basis of technique scheme, as shown in Figure 7, described floor comprises:
The floor slab structure system being surrounded by main joist 2 and secondary joist 3,
On secondary joist lower hem 33 and/or main joist lower hem, be provided with lower floor's fiber cement board 1014,
Lower floor's fiber cement board 1014 is fixedly connected with secondary joist lower hem 33 and/or main joist lower hem respectively by screw, and screw does not expose,
In floor slab structure system and lower floor's fiber cement board 1014 enclosed spaces, built inorganic light heat insulation material, formed floor insulation layer 1012, described inorganic light weight thermal insulation material is foam cement or glass bead as previously mentioned,
The height of building of floor insulation layer 1012 flushes with secondary joist rib 31 and/or main joist rib,
On floor insulation layer 1012, be equipped with layer of steel wire net 1011,
On gauze wire cloth 1011, be coated with one deck anticracking grout,
Anticracking grout is provided with top fiber cement board 1010,
Top fiber cement board 1010 is fixedly connected with secondary joist rib 31 and/or main joist rib respectively by screw.
This kind of floor; build foam cement or glass bead; insulation, the soundproof effect of floor have been improved; give a kind of solid sense of people, rational in infrastructure, while building foam cement or glass bead; do not need independent formwork, form removal; conveniently requirement while meeting construction, requires low, time saving and energy saving to operating personnel.
On the basis of technique scheme, on top fiber cement board 1010, lay wood flooring or ceramic tile.
On the basis of technique scheme, as shown in Figure 8, described body of wall comprises:
The wall structural system being surrounded by main joist 2 and wall keel 1,
On main joist 2, be provided with inner core connector 5,
On the wall shoe 13 of wall keel 1 that is positioned at inner core connector 5 front sides, be provided with some spaced bridge cut-off adjustable positioning components 1103,
Bridge cut-off adjustable positioning component 1103 rear ends are connected with the wall keel 1 that are positioned at inner core connector 5 front sides by the inner core 1102 with staking mother,
Bridge cut-off adjustable positioning component 1103 front ends are connected with the link plate keel 1101 that arrange horizontally set or vertical,
Bridge cut-off adjustable positioning component 1103 is for regulating the planeness of link plate keel 1101, and described bridge cut-off adjustable positioning component 1103 preferably adopts building wall panel installation adjustable positioning component described in CN201010291460.6 patent,
On the leading flank of link plate keel 1101, be provided with some link plate parts 1104, as the wall link plate 1105 of outer decoration for vertical face plate, be mounted on link plate part 1104,
On the wall shoe 13 of wall keel 1 that is positioned at inner core connector 5 rear sides, be provided with some link plate parts 1104, as the wall link plate 1106 of inner wall panel, be mounted on link plate part 1104,
At wall structural system, internal and external ornament sheet material, (refer to as the wall link plate 1105 of outer decoration for vertical face plate with as the wall link plate 1106 of inner wall panel, the two can be identical can be different) monobloc cast has inorganic light heat insulation material in enclosed space, forms wall insulating layer 1107.
This kind of body of wall; build foam cement or glass bead; insulation, the soundproof effect of body of wall have been improved; give a kind of solid sense of people, rational in infrastructure, while building foam cement or glass bead; do not need independent formwork (wall link plate 1105, inner wall panel 1106 have the function of building mould concurrently); conveniently requirement while meeting construction, requires low, time saving and energy saving to operating personnel.
On the basis of technique scheme, described link plate part 1104 is supporting with wall link plate, the wall link plate of unlike material, and supporting link plate part is different, and link plate part 1104 can be selected commercially available finished product.Figure 9 shows that a kind of selectable link plate part 1104, it comprises:
Link plate keel junction plate 1201,
In the left and right sides of link plate keel junction plate 1201, be respectively provided with a link plate piece 1202,
On the top of link plate piece 1202, be provided with between two parties a upper notch hook 1203, in the left and right sides of upper notch hook 1203, be respectively provided with a lower notch hook 1204;
Described upper notch hook 1203 is provided with bending part 1205 under downward hook,
Described lower notch hook 1204 is provided with bending part 1206 on hook upwards.
Wall link plate 1105 is connected effect referring to Figure 10 with link plate part 1104.
On the basis of technique scheme, the link plate of wall shown in Fig. 9 1106 is identical with wall link plate 1105 shape and structures, and as shown in Figure 11,12,13, described wall link plate integral body is rectangular, and its upper surface is provided with notch 1401, and soffit is provided with lower notch 1402,
Described upper notch 1401 comprises:
End face 1503, its rear and front end extends to form respectively the first lateral surface 1506, the first medial surface 1504 downwards,
Described the first lateral surface 1506 is vertical with end face 1503, or tilts to wall link plate lateral surface 1502 directions, gradient scope ± 5 degree,
Described the first medial surface 1504 is vertical with end face 1503, or tilts to wall link plate medial surface 1501 directions, gradient scope ± 5 degree,
The first lateral surface 1506 is connected by the first joint face 1507 with 1502 of wall link plate lateral surfaces,
The first medial surface 1504 is connected by the second joint face 1505 with 1501 of wall link plate medial surfaces,
The level height of described the second joint face 1505 is higher than the level height of the first joint face 1507;
Described lower notch 1402 comprises:
Bottom surface 1511, its rear and front end extends to form respectively the second lateral surface 1510, the second medial surface 1512 downwards,
Described the second lateral surface 1510 is vertical with bottom surface 1511, or tilts to wall link plate lateral surface 1502 directions, gradient scope ± 5 degree,
Described the second medial surface 1512 is vertical with bottom surface 1511, or tilts to wall link plate medial surface 1501 directions, gradient scope ± 5 degree,
The second lateral surface 1510 is connected by the 3rd joint face 1508 with 1502 of wall link plate lateral surfaces,
The second medial surface 1512 is connected by the 4th joint face 1509 with 1501 of wall link plate medial surfaces,
The level height of described the 4th joint face 1509 is higher than the level height of the 3rd joint face 1508;
When wall link plate is mounted on the link plate part 1104 shown in Fig. 9, under the hook of upper notch hook 1203, bending part 1205 catches on the first lateral surface 1506;
When wall link plate is mounted on the link plate part 1104 shown in Fig. 9, on the hook of lower notch hook 1204, bending part 1206 catches on the second medial surface 1512.
Described wall link plate, simple in structure, upper notch, lower notch can be through edge polisher machine-shapings, and notch design is convenient to install, and notch intensity is high, attractive in appearance, is easy to processing, and conveniently requirement while meeting construction, requires low, time saving and energy saving to operating personnel.
On the basis of technique scheme, as shown in figure 14, at one deck of building body, in the turning point of body of wall, be provided with and be embedded in underground concrete stanchion 1601,
The end face of concrete stanchion 1601 is provided with column fixed base plate 1602, for example: column fixed base plate 1602 is assemblied in the end face of concrete stanchion 1601 by chemical anchor bolts 1606,
Column 1603 vertically arranges, and the lower end of column 1603 is fixed on column fixed base plate 1602,
Main joist is fixedly connected with main joist 2, column 1603 respectively with column connecting piece 1605, such as: by screw or bolt connection etc.Main joist and column connecting piece 1605 are set as being not easy to, and under the prerequisite meeting design requirement, main joist 2 can directly be fixedly connected with column 1603.
On the basis of technique scheme, the construction sequence of floor following (omit the construction sequence of concrete stanchion, column, omit the Connection Step of main joist and column):
The 1st step: main joist is set by body of wall trend;
The 2nd step: on-the-spot offering for installing the mounting groove of inner core connector on main joist;
The 3rd step: installation corner brace is fixedly connected with secondary joist;
The 4th step: inner core connector is packed into for installing the mounting groove of inner core connector;
The 5th step: installation corner brace is fixedly connected with inner core connector; Form floor slab structure system;
The 6th step: be fixedly installed lower floor's fiber cement board on secondary joist lower hem and/or main joist lower hem;
The 7th step: build foam cement or glass bead in floor slab structure system and lower floor's fiber cement board enclosed space, form floor insulation layer; The height of building of insulation layer flushes with secondary joist rib, main joist rib;
The 8th step: after waiting foam cement or glass bead to solidify, lay layer of steel wire net on insulation layer;
The 9th step: smear one deck anticracking grout on gauze wire cloth;
The 10th step: after anticracking grout solidifies, lay top fiber cement board on anticracking grout;
The 11st step: top fiber cement board is fixedly connected with secondary joist rib, main joist rib respectively by screw.
Further, also comprise the 12nd step: on top fiber cement board, lay wood flooring or ceramic tile.
On the basis of technique scheme, the construction sequence of body of wall following (omit the construction sequence of concrete stanchion, column, omit the Connection Step of main joist and column, omit the construction sequence of inner core connector):
The 1st step: after main joist and inner core connector are all in place, the front side and the rear side that are exposed to the end outside main joist at inner core connector are respectively established wall keel; Form wall structural system;
The 2nd step: on the wall shoe of wall keel that is positioned at inner core connector front side, some spaced bridge cut-off adjustable positioning components are set;
The 3rd step: bridge cut-off adjustable positioning component front end is connected with the link plate keel that arrange horizontally set or vertical;
The 4th step: utilize bridge cut-off adjustable positioning component, the planeness that completes link plate keel regulates;
The 5th step: on the leading flank of link plate keel, some link plate parts are set;
The 6th step: the wall link plate as outer decoration for vertical face plate is mounted on link plate part; Complete the installation of outer decoration for vertical face plate;
The 7th step: on the wall shoe of wall keel that is positioned at inner core connector rear side, some link plate parts are set;
The 8th step: the wall link plate as inner wall panel is mounted on link plate part; Complete the installation of interior decoration for vertical face plate;
The 9th step: monobloc cast has inorganic light heat insulation material in wall structural system, internal and external ornament sheet material enclosed space, forms wall insulating layer 1107.
The utility model has provided a kind of novel light-steel structural seismic room, for body of wall, floor, adopts respectively different lightweight steel construction structures:
(1) body of wall, by light steel as load-bearing skeleton, and safeguards that by two-sided curtain wall and light steel form cavity, inside water the light heat insulation materials such as foam cement or glass bead and jointly form.This body of wall integrates the functions such as load-bearing, partition space, thermal insulation, and the Experimental Study on Seismic Behavior that complete three slice bodies of wall in Tsing-Hua University in April, 2013 shows, this structure can reach the target of providing fortification against earthquakes of " no damage in small earthquake, middle shake can be repaiied, no collapsing with strong earthquake ".
(2) floor, by special light steel load-bearing, is laid the sheet materials such as cement board as bed die in its bottom, and foam cement or glass bead are built in centre, and the formation plane structures such as the pea gravel concreten of arrangement of steel wires net sheet, shared vertical load are built in upper strata.The floor that complete in September, 2013 in Beijing Jiaotong University is tested and is shown, under the serviceability limit state of test specimen (L/200), the uniform live load value of test is 6.5kN/m 2, meet the requirement of civilian construction bearing capacity of floor slab.
Its connected mode of novel light-steel structure is simple, reliable, makes building structure aseismatic performance good, and Structural Tectonics is reasonable, and simple installation is quick, and energy-saving effect is good, is applicable to the construction of 1~3 layer of building such as villa, village-town house and tourism house.
The content not being described in detail in this manual belongs to the known prior art of professional and technical personnel in the field.

Claims (24)

1. a lightweight steel construction Antiseismic house, is characterized in that: its body of wall adopts lightgage steel joist as wall structural system, and its floor adopts lightgage steel joist as floor slab structure system, wherein:
Described floor slab structure system and wall structural system share main joist (2),
Described floor slab structure system also comprises secondary joist (3), secondary joist (3) is located between adjacent two main joists (2), and secondary joist (3) and vertical connection of main joist (2) are parallel to each other between secondary joist (3), or square crossing between secondary joist (3)
Described wall structural system also comprises wall keel (1), and wall keel (1) and vertical connection of main joist (2) are parallel to each other between wall keel (1).
2. lightweight steel construction Antiseismic house as claimed in claim 1, is characterized in that: described lightgage steel joist material is galvanized sheet, rolls galvanized sheet one-body molded by keel machine.
3. lightweight steel construction Antiseismic house as claimed in claim 1, is characterized in that: in floor slab structure system region, be provided with the lower floor's fiber cement board (1014) being connected with main joist (2) and/or secondary joist (3),
On floor slab structure system, be provided with the top fiber cement board (1010) that is connected (4) with main joist (2) and/or secondary joist (3),
In floor slab structure system, lower floor's fiber cement board (1014) and top fiber cement board (1010) enclosed space, monobloc cast has inorganic light heat insulation material, forms floor insulation layer (1012).
4. lightweight steel construction Antiseismic house as claimed in claim 1, is characterized in that: in the both sides, front and back of wall keel (1), mount wall link plate as the internal and external ornament sheet material of body of wall,
In wall structural system, internal and external ornament sheet material enclosed space, monobloc cast has inorganic light heat insulation material, forms wall insulating layer (1107).
5. lightweight steel construction Antiseismic house as claimed in claim 4, is characterized in that: described wall link plate includes but not limited to: cement board, golden nation plate, pottery clay plates, woodwool board.
6. the lightweight steel construction Antiseismic house as described in claim 3 or 4 or 5, is characterized in that: described inorganic light weight thermal insulation material is foam cement or glass bead.
7. the lightweight steel construction Antiseismic house as described in claim 1 or 2 or 3 or 4 or 5, is characterized in that: wall keel (1) vertically arrange, all along continuous straight runs settings of main joist (2) and secondary joist (3),
On main joist (2), be provided with inner core connector (5), described inner core connector (5) is a cuboid,
Wall keel (1) pass through inner core connector (5) and vertical connection of main joist (2),
Secondary joist (3) is by installing corner brace (4) and vertical connection of inner core connector (5).
8. lightweight steel construction Antiseismic house as claimed in claim 7, is characterized in that, described secondary joist (3) comprising:
Secondary joist lower shoe (36),
Along the length direction of secondary joist lower shoe (36), symmetrical be provided with extend upward after the secondary joist lower hem (33) of inside 90 degree bendings again,
The end that secondary joist lower hem (33) bends inwards upwards vertically extends to form vertically section (37) of secondary joist,
The secondary joist vertically rear and front end of section (37) is provided with several times keel installation hole (35),
The secondary joist vertically upper end of section (37) bends 90 degree formation secondary joist ribs (31) laterally, between secondary joist rib (31), is secondary joist opening.
9. lightweight steel construction Antiseismic house as claimed in claim 8, is characterized in that: along the length direction of secondary joist lower shoe (36), be provided with between two parties at least one secondary joist lower shoe reinforcing rib (34):
Along the length direction of the vertical section of secondary joist (37), be provided with between two parties vertically section reinforcing rib (32) of at least one secondary joist.
10. lightweight steel construction Antiseismic house as claimed in claim 9, is characterized in that: the bar shaped cell body of described secondary joist lower shoe reinforcing rib (34) for raising up;
Described secondary joist vertically section reinforcing rib (32) is the bar shaped cell body to the vertical section of secondary joist (37) outside projection.
11. lightweight steel construction Antiseismic houses as described in claim 8 or 9 or 10, is characterized in that: described main joist (2) is identical with the global shape structure of secondary joist (3), and the two difference is:
Main joist lower shoe is provided with for installing the mounting groove of inner core connector (5).
12. lightweight steel construction Antiseismic houses as claimed in claim 11, is characterized in that: for installing the mounting groove of inner core connector (5), during for site operation, according to concrete definite installation site, at the upper scene of main joist (2), slot.
13. lightweight steel construction Antiseismic houses as claimed in claim 11, is characterized in that, described wall keel (1) comprising:
Wall shoe (13),
Along the length direction of wall shoe (13), the symmetrical vertically extending wall side of keel (12) that is provided with,
Wall side of keel (12) forms wall keel flangings (11) away from one end 90 degree bendings laterally of wall shoe (13), is wall keel openings between wall keel flanging (11),
The two ends up and down of wall side of keel (12) are provided with some wall keel installations holes (14).
14. lightweight steel construction Antiseismic houses as claimed in claim 13, is characterized in that: inner core connector (5) is threaded onto in mounting groove, and two ends are exposed to respectively outside main joist (2) up and down,
The front side and the rear side that at inner core connector (5), are exposed to the end outside main joist (2) are respectively provided with wall keel (1);
Pegging graft with corner brace (4) is installed respectively in the rear and front end of secondary joist (3), and fixes with screw or bolt.
15. lightweight steel construction Antiseismic houses as claimed in claim 14, is characterized in that, described installation corner brace (4) comprising:
Corner brace base plate (41) is installed, and its two ends, left and right vertically extend to form corner brace left side wall (42) are installed, corner brace right side wall (43) is installed,
The spacing of corner brace left side wall (42) being installed, installing between corner brace right side wall (43) is slightly less than the vertically spacing between section (37) of secondary joist,
Corner brace left side wall (42) being installed, corner brace right side wall (43) being installed above, be equipped with the installation corner brace pilot hole (44) adaptive with secondary joist installing hole (35).
16. lightweight steel construction Antiseismic houses as claimed in claim 14, is characterized in that: the part of corner brace (4) within being positioned at main joist (2) with inner core connector (5) is installed and by staking nut, is connected, or fix with screw or bolt;
Or:
The part of corner brace (4) outside being exposed to main joist (2) with inner core connector (5) is installed and by staking nut, is connected, or fix with screw or bolt;
Or:
The part of corner brace (4) within being positioned at main joist (2) with inner core connector (5) is respectively installed, the part that inner core connector (5) is exposed to outside main joist (2) is connected by staking nut, or fixes with screw or bolt.
17. lightweight steel construction Antiseismic houses as claimed in claim 14, is characterized in that: between the wall keel flanging (11) of two wall keel (1) that front and back are oppositely arranged, leave gap.
18. lightweight steel construction Antiseismic houses as claimed in claim 14, it is characterized in that: the wall keel opening of wall keel (1) is inserted on inner core connector (5), distance between distance between wall side of keel (12) and inner core connector (5) left and right sidewall is adaptive, after plug-in mounting:
The wall shoe (13) of wall keel (1) touches with inner core connector (5) front side wall or rear wall,
The wall side of keel (12) of wall keel (1) clamps inner core connector (5) left and right sidewall,
Screw or bolt be through wall keel installation hole (14), and the end outside the end of wall keel (1) is exposed to main joist (2) with inner core connector (5) is fixedly connected with.
19. lightweight steel construction Antiseismic houses as claimed in claim 14, is characterized in that, described floor comprises:
The floor slab structure system being surrounded by main joist (2) and secondary joist (3),
On secondary joist lower hem (33) and/or main joist lower hem, be provided with lower floor's fiber cement board (1014),
Lower floor's fiber cement board (1014) is fixedly connected with secondary joist lower hem (33) and/or main joist lower hem respectively by screw,
In floor slab structure system and lower floor's fiber cement board (1014) enclosed space, build inorganic light heat insulation material, formed floor insulation layer (1012),
The height of building of floor insulation layer (1012) flushes with secondary joist rib (31) and/or main joist rib,
On floor insulation layer (1012), be equipped with layer of steel wire net (1011),
On gauze wire cloth (1011), be coated with one deck anticracking grout,
Anticracking grout is provided with top fiber cement board (1010),
Top fiber cement board (1010) is fixedly connected with secondary joist rib (31) and/or main joist rib respectively by screw.
20. lightweight steel construction Antiseismic houses as claimed in claim 19, is characterized in that: on top fiber cement board (1010), lay wood flooring or ceramic tile.
21. lightweight steel construction Antiseismic houses as claimed in claim 14, is characterized in that, described body of wall comprises:
The wall structural system being surrounded by main joist (2) and wall keel (1),
On main joist (2), be provided with inner core connector (5),
On the wall shoe (13) of wall keel (1) that is positioned at inner core connector (5) front side, be provided with some spaced bridge cut-off adjustable positioning components (1103),
Bridge cut-off adjustable positioning component (1103) rear end is connected with the wall keel (1) that are positioned at inner core connector (5) front side by the inner core with staking mother (1102),
Bridge cut-off adjustable positioning component (1103) front end is connected with the link plate keel (1101) that arrange horizontally set or vertical,
On the leading flank of link plate keel (1101), be provided with some link plate parts (1104), as the wall link plate (1105) of outer decoration for vertical face plate, be mounted on link plate part (1104) upper,
Upper at the wall shoe (13) of wall keel (1) that is positioned at inner core connector (5) rear side, be provided with some link plate parts (1104), as the wall link plate (1106) of inner wall panel, be mounted on link plate part (1104) upper,
In wall structural system, internal and external ornament sheet material enclosed space, monobloc cast has inorganic light heat insulation material, forms wall insulating layer (1107).
22. lightweight steel construction Antiseismic houses as claimed in claim 21, is characterized in that: described link plate part (1104) is supporting with wall link plate.
23. lightweight steel construction Antiseismic houses as described in claim 4 or 21, is characterized in that: described wall link plate integral body is rectangular, and its upper surface is provided with notch (1401), and soffit is provided with lower notch (1402),
Described upper notch (1401) comprising:
End face (1503), its rear and front end extends to form respectively the first lateral surface (1506), the first medial surface (1504) downwards,
Described the first lateral surface (1506) is vertical with end face (1503), or tilts to wall link plate lateral surface (1502) direction,
Described the first medial surface (1504) is vertical with end face (1503), or tilts to wall link plate medial surface (1501) direction,
Between the first lateral surface (1506) and wall link plate lateral surface (1502), by the first joint face (1507), be connected,
Between the first medial surface (1504) and wall link plate medial surface (1501), by the second joint face (1505), be connected,
The level height of described the second joint face (1505) is higher than the level height of the first joint face (1507);
Described lower notch (1402) comprising:
Bottom surface (1511), its rear and front end extends to form respectively the second lateral surface (1510), the second medial surface (1512) downwards,
Described the second lateral surface (1510) is vertical with bottom surface (1511), or tilts to wall link plate lateral surface (1502) direction,
Described the second medial surface (1512) is vertical with bottom surface (1511), or tilts to wall link plate medial surface (1501) direction,
Between the second lateral surface (1510) and wall link plate lateral surface (1502), by the 3rd joint face (1508), be connected,
Between the second medial surface (1512) and wall link plate medial surface (1501), by the 4th joint face (1509), be connected,
The level height of described the 4th joint face (1509) is higher than the level height of the 3rd joint face (1508).
24. lightweight steel construction Antiseismic houses as claimed in claim 14, is characterized in that: at one deck of building body, in the turning point of body of wall, are provided with and are embedded in underground concrete stanchion (1601),
The end face of concrete stanchion (1601) is provided with column fixed base plate (1602),
Column (1603) vertically arranges, and it is upper that the lower end of column (1603) is fixed on column fixed base plate (1602),
Main joist is fixedly connected with main joist (2), column (1603) respectively with column connecting piece (1605).
CN201420102083.0U 2014-03-07 2014-03-07 Earthquake-proofing house of light steel structure Expired - Lifetime CN203821925U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420102083.0U CN203821925U (en) 2014-03-07 2014-03-07 Earthquake-proofing house of light steel structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420102083.0U CN203821925U (en) 2014-03-07 2014-03-07 Earthquake-proofing house of light steel structure

Publications (1)

Publication Number Publication Date
CN203821925U true CN203821925U (en) 2014-09-10

Family

ID=51477438

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420102083.0U Expired - Lifetime CN203821925U (en) 2014-03-07 2014-03-07 Earthquake-proofing house of light steel structure

Country Status (1)

Country Link
CN (1) CN203821925U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104047457A (en) * 2014-03-07 2014-09-17 霍学朝 Light steel structure anti-seismic house
CN115387520A (en) * 2022-09-29 2022-11-25 苏州美瑞德建筑装饰有限公司 Interlayer floor design structure based on assembled steel framework

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104047457A (en) * 2014-03-07 2014-09-17 霍学朝 Light steel structure anti-seismic house
CN115387520A (en) * 2022-09-29 2022-11-25 苏州美瑞德建筑装饰有限公司 Interlayer floor design structure based on assembled steel framework
CN115387520B (en) * 2022-09-29 2024-03-15 苏州美瑞德建筑装饰有限公司 Interlayer floor slab design structure based on assembled steel skeleton

Similar Documents

Publication Publication Date Title
CN203821627U (en) Wall structure system with light steel keels, and wall
CN106638963B (en) A kind of fast assembled integrated house and its method of construction
US20100024323A1 (en) Energy Saving House
US9797137B2 (en) Fully assembled, fully cast-in-place, composite-type house and construction method thereof
CN105421818B (en) Built-in steel Standard house
CN103015623A (en) Prefabricated slab and fixed mounting structure thereof
US20140338283A1 (en) House constructed from finished product components and constructing method thereof
CN106703201A (en) Fabricated integrated building and production method thereof
CN105649196A (en) Modularized building system
CN207794290U (en) A kind of multilayer light gauge cold-formed steel shape-concrete composite structure building construction system
CN104047457A (en) Light steel structure anti-seismic house
Rahman et al. Comparative study of IPS & PPVC precast system—A case study of public housing buildings project in Singapore
CN103790424B (en) A kind of lightweight steel joist system of Antiseismic house
CN105064551B (en) Removable board wall system
CN203821925U (en) Earthquake-proofing house of light steel structure
CN203821669U (en) Floor slab structure system with light steel keels, and floor slab
US10253511B2 (en) Multi-flex forming system
CN105421656B (en) External wall board installation structure of embedded type steel structure assembled house
CN205296607U (en) Embedded steel construction assembly house roof boarding mounting structure
CN203821926U (en) Light steel keel structure system of earthquake-proof house
CN204139316U (en) A kind of steel structure shear wall structure system
CN103362235A (en) Integrally-poured building house with wallboards integrating thermal insulating and templates
CN203412312U (en) Thermal-insulating integrated template wallboard construction building
Hossain IPS & PPVC precast system in construction–A case study in Singaporean housing building project
CN111155681B (en) Steel concrete composite connection multilayer prefabricated section steel concrete shear wall structure and preparation and construction method thereof

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20140910

CX01 Expiry of patent term