CN103362235A - Integrally-poured building house with wallboards integrating thermal insulating and templates - Google Patents

Integrally-poured building house with wallboards integrating thermal insulating and templates Download PDF

Info

Publication number
CN103362235A
CN103362235A CN2013102998997A CN201310299899A CN103362235A CN 103362235 A CN103362235 A CN 103362235A CN 2013102998997 A CN2013102998997 A CN 2013102998997A CN 201310299899 A CN201310299899 A CN 201310299899A CN 103362235 A CN103362235 A CN 103362235A
Authority
CN
China
Prior art keywords
wall
plate
riser
board
post
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013102998997A
Other languages
Chinese (zh)
Other versions
CN103362235B (en
Inventor
田仁德
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
YANTAI JINTIAN TECHNOLOGY Co Ltd
Original Assignee
YANTAI JINTIAN TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YANTAI JINTIAN TECHNOLOGY Co Ltd filed Critical YANTAI JINTIAN TECHNOLOGY Co Ltd
Priority to CN201310299899.7A priority Critical patent/CN103362235B/en
Publication of CN103362235A publication Critical patent/CN103362235A/en
Application granted granted Critical
Publication of CN103362235B publication Critical patent/CN103362235B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Bearing And Curtain Walls (AREA)
  • Building Environments (AREA)

Abstract

The invention provides an integrally-poured building house with wallboards integrating thermal insulating and templates. The building house is characterized in that wall bodies, pillar bodies and part of ring beams and roofing boards adopt wallboards integrating thermal insulating and templates; the whole building is formed by integrally pouring concrete. Therefore, the building house has the advantages as follows: the performances of shock resistance, air tightness and thermal insulation are better; the construction cost is further reduced; the construction efficiency is improved.

Description

Form insulation integrated wallboard and integrated poured building
  
Technical field
The present invention relates to a kind of residential building, be specifically related to a kind of form insulation integrated wallboard and integrated poured building.
Background technology
The job practices in existing residential house mainly comprises based on the job practices of reinforced concrete structure with based on the job practices of steel work.In the job practices based on reinforced concrete structure, then the frame construction of generally at first constructing after building foundation is finished fills fragment of brick in framework, and at interior lateral surface construction one deck cement of brick wall.Its major defect is:
The first, building operations program is complicated, and the amount of labour is large, and is long in time limit, produces a large amount of building wastes, and because the site operation amount is difficult to greatly realize strict quality control.
The second, the concrete of whole building body is implemented respectively cast in different construction part, builds rear mutual independence, is difficult to guarantee the bulk strength of building, and anti-seismic performance, sealing performance etc. can not be satisfactory.
Three, need use frequently, in enormous quantities template when construction framework and coating cement, beam, post, plate need maintenance, have increased construction cost and have affected construction efficiency.
Four, main body construction needs after complete the atrial septum to process from, decorating inner and external walls and insulation, and the house building cycle is longer, and construction cost further improves.
Five, need to carry out maintenance to cement, not only prolong construction period, and on-the-spot maintenance construction is difficult to guarantee operation and quality requirement.
Six, wall construction needs after complete other insulation to process, the one side complex operation, long construction period, key issue is: the later stage insulation layer can't lose efficacy prior to body of wall, can't guarantee the same life-span of insulation layer and house, need often to repair insulation layer in the house use procedure, make troubles for the house user.
Summary of the invention
The present invention aims to provide a kind of form insulation integrated wallboard and integrated poured building, in order to overcome existing defective based on the structure of reinforced concrete house, technical problem to be solved is, building operations efficient is higher, cycle is shorter, and being integral structure after the house concreting has better capability and performance, the same life-span of insulation layer and body of wall, and construction is more convenient.
In order to solve the problems of the technologies described above, the present invention has adopted following technical scheme:
A kind of form insulation integrated wallboard and integrated poured building, comprise reinforced concrete foundation, in the body of wall of steel concrete is arranged, in the structural column of steel concrete is arranged, in the exterior wall collar tie beam of steel concrete is arranged, in have steel concrete Vierendeel girder and in the indoor partition collar tie beam of steel concrete is arranged, it is characterized in that: described RC Continuous everywhere becomes an integral body; Described body of wall comprises the medial and lateral ash wall body plate that be arranged in parallel, and the ash wall body plate of each side is pegged graft mutually by side by several ash wall body plate unit or the mode of overlap joint continues and forms; Wherein the inboard of the ash wall body plate of a side is fixedly connected with wall support, the interior side contacts of the other end of wall support and opposite side ash wall body plate; Also comprise longitudinal reinforcement post and reinforcing bar between the external wall body plate, described reinforcing bar comprises horizontal reinforcement and oblique reinforcing bar; Ash wall body plate is comprised of the face that faces one another insulation layer and the sheet material be fixed together of fitting.
Described sheet material is cement board; Described insulation layer is the composite polyurethane plate that hard bubbles.
Inside and outside each two ash wall body plate of described body of wall are mounted for a construction cell relatively, and each construction cell center is provided with a longitudinal reinforcement post, is provided with two oblique reinforcing bars that cross one another in each construction cell; The up and down two ends of described longitudinal reinforcement post and oblique reinforcing bar all exceed the up and down two ends of interior external wall body plate, wherein, the downward part that exceeds is used for penetrating in the reinforced concrete foundation or in the collar tie beam below the body of wall, and the part that exceeds that makes progress is used for penetrating in the collar tie beam of body of wall top.
Described indoor partition collar tie beam comprises left beam body plate and right beam body plate, left beam body plate comprises left riser and with left riser one and be positioned at the left plate of left riser lower end, left riser and left plate are 90 ° of angles mutually, the left side of left plate is concordant with the left surface of left riser, right beam body plate comprises right riser and with right riser one and be positioned at the right flat board of right riser lower end, right riser and right flat board are 90 ° of angles mutually, the right side of right flat board is concordant with the right flank of right riser, left riser is concordant with right planar bottom surface with the concordant left plate in right riser upper end, sheet material inboard concordant or the inboard that a little inwardly surmounts this outer sheet material outside sheet material inboard concordant or the inboard that a little inwardly surmounts this outer sheet material outside the inner face of left plate and the left wallboard, the inner face of right flat board and right wallboard.
Described exterior wall collar tie beam comprises and is provided with wall support as the outer wall board of wall board and interior wall sheet material between the outer wall board of setting parallel to each other and the interior wall sheet material; The outer wall board upper end is higher than interior wall sheet material upper end, and the two difference in height is the height of exterior wall collar tie beam.
Described Vierendeel girder comprises the structural column of the left and right sides, and described structural column is surrounded by post outer panel, post interior plate, post front side board and post back side panel, and its center pillar outer panel upper end is higher than post interior plate upper end, and the two difference in height is the framework depth of beam; Comprise also that two ends are fixedly mounted on respectively between the structural column of the left and right sides and as front and back two beam bodies riser of beam slab body be fixedly mounted on respectively between the structural column of the left and right sides, two beam body riser lower ends and dull and stereotyped as the beam body of beam slab body before and after being positioned at, before and after two beam body riser shape and size all identical and have identical about, upper-lower position, in front and back two beam bodies riser and space that beam body flat board surrounds, be provided with the beam body reinforcing bar that links to each other with left and right sides post reinforcing bar; Two ends are respectively with the overlap joint hyoplastron about wherein said beam body flat board, and the outer end of overlap joint hyoplastron outwards surpasses described post interior plate but has certain distance with the post outer panel, to reserve the passage at beam body space and cylinder space continuous concrete placing.
Described structural column comprises the dull and stereotyped and cylinder corner board of each two cylinder, the outer side edges of first cylinder flat board is with 45 ° of assembling inclined-planes, the interior outer side edges of second cylinder flat board is respectively with 45 ° of assembling inclined-planes, works in coordination and form the first external corner of cylinder in 45 ° of assembling inclined-planes of 45 ° of assembling inclined-planes of first cylinder flat board and second cylinder flat board; The outer side edges of first corner board is worked in coordination with 45 ° of assembling inclined-planes and by 45 ° of assemblings inclined-plane, inboard of these 45 ° assembling inclined-planes and second cylinder flat board and is formed the second external corner of cylinder; The turning of first corner board is as the first inner corner trim of cylinder; The turning of second corner board is as the second inner corner trim of cylinder.
Can also comprise basement.
Good effect of the present invention is:
The first, heat insulation integrated ash wall body plate of the present invention etc. adopts the batch production manufacturing, and on-the-spot the installation not only has quick for installationly, and the outstanding feature of saving of work and time can realize factorial construction, does not produce building waste, and the quality control of being more convenient for.
The second, whole building adopts integrated pouring concrete, and has adopted steel bar column and oblique reinforcing bar in wallboard, the body of wall load-bearing, and the house classification of waterproof that utilizes the present invention to build reaches one-level, and fire-protection rating one-level, antidetonation reach 9 grades of degree of splitting.And have insulation, wind resistance, protection against the tide, the sound insulation that obviously is better than the existing building house, a longer service life.Be particularly suitable for Urban renewal, new countryside construction, the hilly ground building construction is used in rainy, high wind area, the multiple band building construction of earthquake.
Three, saved template in the construction, and used wallboard, beam slab and post plate to be insulation, waterproof, fire prevention, sound insulation integrated, further reduced construction cost and improved construction efficiency.
Four, adopt job practices of the present invention since used sheet material external surface can process smoothly, attractive in appearance, wall, beam, post needn't maintenances, saved the house decoration link, the house sense is stronger, and is more attractive in appearance, and saved a large amount of human and material resources and financial resources.
Five, can save steel more than 30%, cement consumption is decrease also.
Six, because concrete between sheet material, has saved the cement conservation operation.
Seven, body of wall self does not need to do in addition insulation and processes the same life-span of insulation layer and body of wall with insulation layer.
Description of drawings
Fig. 1 is the structural representation of body of wall of the present invention.Concrete, reinforcing bar and steel bar column have been omitted among the figure.
Fig. 2 shows reinforcing bar of the present invention and steel bar column mounting means schematic diagram.The inboard that has shown two adjacent wall element among the figure.
Fig. 3 is the structural representation (not concreting state) of cylinder of the present invention.
Fig. 4 is the structural representation of indoor partition collar tie beam of the present invention.
Fig. 5 is the structural representation of beam body plate of the present invention.
Fig. 6 is the mounting means schematic diagram of indoor partition collar tie beam of the present invention.
Fig. 7 is the structural representation of exterior wall collar tie beam of the present invention.
Fig. 8 is the structural representation of Vierendeel girder of the present invention.
Fig. 9 is the planform schematic diagram of the steel concrete part in house that the present invention builds.
The specific embodiment
Further specify the present invention below in conjunction with accompanying drawing and construction sequence embodiment.
One, foundation construction: construction reinforced bar concrete foundation 5, longitudinal reinforcement wherein protrudes upward from reinforced concrete foundation 5, be used for wall, post in bar splicing.Can also comprise basement construction.Do waterproofing work at edge joint position after the basement construction.
Two, exterior wall, post construction: at first vertical exterior wall side sheet and mixed lateral column plate also make the exterior wall side sheet and the mixed lateral column integrated circuit board connects, utilize outrigger External Wall side sheet and mixed lateral column plate to carry out temporary supporting, fixing, then colligation wall steel bar and post reinforcing bar, in the slit of wall steel bar, install again suspension end be used for the inner side of outer wall wallboard within the contacted wall support of sidewall, the root of wall support and the medial surface of exterior wall side sheet are fixed, then detain inner side of outer wall wallboard and columnae medialis plate, inner side of outer wall wallboard and columnae medialis integrated circuit board are connect, at last body of wall and cylinder are carried out reinforcement by connection and make body of wall and cylinder become overall structure.
Wherein, described body of wall has following structure:
Comprise the medial and lateral ash wall body plate 1 that be arranged in parallel, the ash wall body plate 1 of each side is pegged graft mutually by side by several ash wall body plate unit or the mode of overlap joint continues and forms.Wherein the inboard of the ash wall body plate 1 of a side is fixedly connected with wall support 2, the interior side contacts of the other end of wall support 2 and opposite side ash wall body plate 1, as shown in Figure 1.
Also comprise longitudinal reinforcement post 3 and reinforcing bar 4 between the external wall body plate 1, described reinforcing bar 4 comprises horizontal reinforcement and oblique reinforcing bar, the junction of longitudinal reinforcement post 3 and reinforcing bar 4 adopts the colligation mode to be connected to each other, the up and down two ends of described longitudinal reinforcement post 3 and oblique reinforcing bar all exceed the up and down two ends of interior external wall body plate 1, wherein, the downward part that exceeds is used for penetrating in the reinforced concrete foundation 5 or in the collar tie beam below the body of wall, and the part that exceeds that makes progress is used for penetrating in the collar tie beam of body of wall top.Fluid concrete 3 between interior external wall body plate 1.During construction, at first install, connect longitudinal reinforcement post 3 and reinforcing bar 4, then inboard ash wall body plate, wall support, outside ash wall body plate are installed, last fluid concrete.
Still such as Fig. 1, ash wall body plate 1 is comprised of the face that faces one another insulation layer 1-2 and the sheet material 1-1 that is fixed together that fit.Wherein, described sheet material 1-1 is generally cement board.The present invention is during as exterior wall, the insulation layer 1-2 composite polyurethane plate that preferably hard bubbles, and the present invention is during as inner wall, and insulation layer 1-2 can be the composite polyurethane plate that hard bubbles, and also can be the warming plate of other material.
In the practice of construction operation, usually inside and outside each two ash wall body plate are installed relatively as a construction cell.In this case, each construction cell center is provided with a longitudinal reinforcement post 3, is provided with two oblique reinforcing bars that cross one another in each construction cell, as shown in Figure 2.
Described cylinder has following structure:
Comprise and erect the cylinder dull and stereotyped 6 that is seated in reinforced concrete foundation 5 upper surfaces and erect the cylinder corner board 7 that is seated in reinforced concrete foundation 5 upper surfaces.Being provided with root in the space that described cylinder dull and stereotyped 6 and cylinder corner board 7 surround is positioned at the reinforcing bar within the reinforced concrete foundation 5 and has built concrete.Such as Fig. 3.
Concrete structure is as follows: the cylinder of this structural column dull and stereotyped 6 and cylinder corner board 7 are each two.The inner side edge band of first cylinder flat board 6 is useful on post plate groove or post plate raised line or the post plate overlap joint mouth of pegging graft and cooperating with ash wall body plate, and outer side edges is with 45 ° of assembling inclined-planes.The interior outer side edges of second cylinder flat board 6 is respectively with 45 ° of assembling inclined-planes, works in coordination and form the first external corner of cylinder in 45 ° of assembling inclined-planes of 45 ° of assembling inclined-planes of first cylinder flat board 6 and second cylinder flat board 6.The outer side edges of first corner board 7 is worked in coordination with 45 ° of assembling inclined-planes and by 45 ° of assemblings inclined-plane, inboard of these 45 ° assembling inclined-planes and second cylinder flat board 6 and is formed the second external corner of cylinder.The turning of first corner board 7 is as the first inner corner trim of cylinder.The inner side edge band of first corner board 7 is useful on groove or raised line or the overlap joint mouth of pegging graft and cooperating with ash wall body plate.Two sides of second corner board 7 are all with being useful on groove or raised line or the overlap joint mouth of pegging graft and cooperating with ash wall body plate.The turning of second corner board 7 is as the second inner corner trim of cylinder.Still such as Fig. 3.
Three, interior wall construction: at first vertical interior wall side sheet also makes the interior wall side sheet and the mixed lateral column integrated circuit board connects, utilize outrigger that the interior wall side sheet is carried out temporary supporting, fixing, then colligation wall steel bar, in the slit of wall steel bar, install again suspension end be used for the interior wall side lining within the contacted wall support of sidewall, the root of wall support and the medial surface of interior exterior wall side sheet are fixed, then detain the interior wall side lining, interior wall side lining and columnae medialis integrated circuit board are connect, at last inner wall is carried out reinforcement by connection and make body of wall and cylinder become overall structure.
Wherein, described inner wall has the structure identical with exterior wall, and only thickness there are differences.Its insulation flaggy also may there are differences as required.
Four, construction indoor partition collar tie beam: the indoor partition collar tie beam comprises left beam body plate and right beam body plate, left beam body plate comprises left riser and with left riser one and be positioned at the left plate of left riser lower end, left riser and left plate are 90 ° of angles mutually, the left side of left plate is concordant with the left surface of left riser, right beam body plate comprises right riser and with right riser one and be positioned at the right flat board of right riser lower end, right riser and right flat board are 90 ° of angles mutually, the right side of right flat board is concordant with the right flank of right riser, left riser is concordant with right planar bottom surface with the concordant left plate in right riser upper end, sheet material inboard concordant or the inboard that a little inwardly surmounts this outer sheet material outside sheet material inboard concordant or the inboard that a little inwardly surmounts this outer sheet material outside the side sheet in the inner face of left plate and the interior wall, the inner face of right flat board and inner wall panel.
Concrete structure is as follows:
Such as Fig. 4,6, indoor partition collar tie beam of the present invention comprises as the left beam body plate of beam body plate 8 and right beam body plate.Between left beam body plate and right beam body plate, reinforcing bar is installed and is filled with concrete.
Left beam body plate comprises left riser and with left riser one and be positioned at the left plate of left riser lower end, left riser and left plate are 90 ° of angles mutually, and the left side of left plate is concordant with the left surface of left riser.Right beam body plate comprises right riser and with right riser one and be positioned at the right flat board of right riser lower end, right riser and right flat board are 90 ° of angles mutually, and the right side of right flat board is concordant with the right flank of right riser.Left riser is concordant with right planar bottom surface with the concordant left plate in right riser upper end.
Such as Fig. 5, left riser comprises collar tie beam sheet material 8-1 and is fixed in the collar tie beam insulation layer 8-2 of collar tie beam sheet material 8-1 inboard that left plate also comprises collar tie beam sheet material 8-1 and is fixed in the collar tie beam insulation layer 8-2 of collar tie beam sheet material 8-1 inboard.Right riser comprises collar tie beam sheet material 8-1 and is fixed in the collar tie beam insulation layer 8-2 of collar tie beam sheet material 8-1 inboard that right flat board also comprises collar tie beam sheet material 8-1 and is fixed in the collar tie beam insulation layer 8-2 of collar tie beam sheet material 8-1 inboard.
The inboard sheet material of left riser and left plate upside sheet material is one each other, left riser outside sheet material and left plate downside sheet material is one each other, similarly, the inboard sheet material of right riser and right dull and stereotyped upside sheet material is one each other, and right riser outside sheet material and right dull and stereotyped downside sheet material is one each other.
Still shown in Fig. 4,6, in the building operations, the flat board of beam body plate 8 is seated on the indoor partition 9 as load bearing wall, and the riser lateral surface leans against trend and intersects with indoor partition on the body of wall of (such as square crossing).
Such as Fig. 6, described indoor partition 9 comprises as the left wallboard of wallboard 9-1 and right wallboard, and reinforcing bar is installed and is filled with concrete between left wallboard and right wallboard.Wallboard 9-1 has double-layer structure parallel to each other: outer sheet material and applying are fixed on the insulation layer of outer sheet material inboard.Sheet material inboard concordant or the inboard that a little inwardly surmounts this outer sheet material outside the inner face of left plate and the left wallboard, sheet material inboard concordant or the inboard that a little inwardly surmounts this outer sheet material outside the inner face of right flat board and the right wallboard, purpose is fluid concrete and the insulation layer in wallboard 9-1, to guarantee that connection is more firm between beam, the wall, the junction has better sealing.
Five, the construction Vierendeel girder is also installed floor: the Vierendeel girder of at first constructing, the whole floor in each room, be placed in wall by lifting mode, on the post, the edge of floor is seated on side lining and the columnae medialis plate to be held, sheet material inboard concordant or the inboard that a little inwardly surmounts this outer sheet material outside the inner face of left plate and the left wallboard, the inner face of floor or the inboard that a little inwardly surmount this side lining or columnae medialis plate concordant with side lining or columnae medialis plate, inwardly to reserve, between the side sheet and in, the passage of fluid concrete between the mixed lateral column plate, at last reinforcement by connection between body of wall and floor and cylinder and floor.
Six, lay the floor insulation layer.
Seven, build stair: stair are lifted the installation that puts in place, and stair reinforcing steel bars exposed end is used for overlapping with ring beam reinforcing steel bar.
Eight, assembling reinforcement: colligation inner, external wall ring beam reinforcing steel bar forms the collar tie beam main body, and makes floor bar and ring beam reinforcing steel bar overlap joint, post reinforcing bar and ring beam reinforcing steel bar overlap joint, ring beam reinforcing steel bar and stair bar splicing.
Nine, fluid concrete: adopt by the self-flowing dense concrete of high strength cement preparation and pour into a mould, body of wall, cylinder, floor, collar tie beam are become one.Then the last layer of constructing building.
Ten, roofing construction: after the typical floor construction is complete, at the superiors' reinforcement placing concrete roof beam, the reinforcing bar of roof girder is connected respectively with body of wall, cylinder, ring beam reinforcing steel bar; lay roof panel at roof girder, reinforcement by connection, water detection is flat; construction waterproof layer and topping thereof are installed photovoltaic panel at last.
Exterior wall collar tie beam of the present invention has following structure:
Such as Fig. 7, the exterior wall collar tie beam comprises as the outer wall board of wall board and interior wall sheet material, be provided with wall support 2 between the outer wall board of setting parallel to each other and the interior wall sheet material, also be provided with wall steel bar between outer wall board and the interior wall sheet material and be cast with walls concrete.The outer wall board upper end is higher than interior wall sheet material upper end, and the two difference in height is the height of exterior wall collar tie beam.Be useful on the beam body reinforcing bar that is connected with the reinforcing bar of wall steel bar and floor 14 respectively in the outer wall board installed inside, and be provided with the beam body concrete of pouring into a mould with described walls concrete one in the outer wall board inboard.
Vierendeel girder of the present invention has following structure:
Such as Fig. 8, Vierendeel girder comprises the structural column of the left and right sides, described structural column is surrounded by post outer panel 10, post interior plate 11, post front side board and post back side panel, its center pillar outer panel 10 upper ends are higher than post interior plate 11 upper ends, the two difference in height is the framework depth of beam, is provided with the post reinforcing bar and has built the post concrete in column body.This Vierendeel girder comprises also that two ends are fixedly mounted on respectively between the structural column of the left and right sides and as front and back two beam bodies riser 12 of beam slab body be fixedly mounted on respectively between the structural column of the left and right sides, two beam body riser 12 lower ends and as the beam body flat board 13 of beam slab body before and after being positioned at, before and after two beam body riser 12 shape and size all identical and have identical about, upper-lower position, in front and back two beam bodies riser 12 and space that beam body flat board 13 surrounds, be provided with the beam body reinforcing bar that links to each other with left and right sides post reinforcing bar and the beam body concrete of pouring into a mould with post concrete one arranged.Two ends are respectively with overlap joint hyoplastron 13-1 about wherein said beam body flat board 13, the outer end of overlap joint hyoplastron 13-1 outwards surpasses described post interior plate 11 but has certain distance with post outer panel 12, to reserve the passage at beam body space and cylinder space continuous concrete placing.
If remove ash wall body plate, beam body plate, cylinder plate, the steel concrete of whole building is continuous integrated state shown in Figure 9.

Claims (10)

1. a form insulation integrated wallboard and integrated poured building, comprise reinforced concrete foundation (5), in the body of wall of steel concrete is arranged, in the structural column of steel concrete is arranged, in the exterior wall collar tie beam of steel concrete is arranged, in have steel concrete Vierendeel girder and in the indoor partition collar tie beam of steel concrete is arranged, it is characterized in that: described RC Continuous everywhere becomes an integral body; Described body of wall comprises the medial and lateral ash wall body plate (1) that be arranged in parallel, and the ash wall body plate of each side (1) is pegged graft mutually by side by several ash wall body plate unit or the mode of overlap joint continues and forms; Wherein the inboard of the ash wall body plate of a side (1) is fixedly connected with wall support (2), the interior side contacts of the other end of wall support (2) and opposite side ash wall body plate (1); Also comprise the longitudinal reinforcement post (3) and the reinforcing bar (4) that are positioned between the external wall body plate (1), described reinforcing bar (4) comprises horizontal reinforcement and oblique reinforcing bar; Ash wall body plate (1) is comprised of the face that faces one another insulation layer (1-2) and the sheet material (1-1) be fixed together of fitting.
2. form insulation integrated wallboard as claimed in claim 1 and integrated poured building, it is characterized in that: described sheet material (1-1) is cement board; Described insulation layer (1-2) is the composite polyurethane plate that hard bubbles.
3. form insulation integrated wallboard as claimed in claim 1 and integrated poured building, it is characterized in that: inside and outside each two ash wall body plate of described body of wall are mounted for a construction cell relatively, each construction cell center is provided with a longitudinal reinforcement post (3), is provided with two oblique reinforcing bars that cross one another in each construction cell; The up and down two ends of described longitudinal reinforcement post (3) and oblique reinforcing bar all exceed the up and down two ends of interior external wall body plate, wherein, the downward part that exceeds is used for penetrating in the reinforced concrete foundation (5) or in the collar tie beam below the body of wall, and the part that exceeds that makes progress is used for penetrating in the collar tie beam of body of wall top.
4. such as claim 1 or 2 or 3 described form insulation integrated wallboard and integrated poured buildings, it is characterized in that: described indoor partition collar tie beam comprises left beam body plate and right beam body plate, left beam body plate comprises left riser and with left riser one and be positioned at the left plate of left riser lower end, left riser and left plate are 90 ° of angles mutually, the left side of left plate is concordant with the left surface of left riser, right beam body plate comprises right riser and with right riser one and be positioned at the right flat board of right riser lower end, right riser and right flat board are 90 ° of angles mutually, the right side of right flat board is concordant with the right flank of right riser, left riser is concordant with right planar bottom surface with the concordant left plate in right riser upper end, sheet material inboard concordant or the inboard that a little inwardly surmounts this outer sheet material outside sheet material inboard concordant or the inboard that a little inwardly surmounts this outer sheet material outside the inner face of left plate and the left wallboard, the inner face of right flat board and right wallboard.
5. such as claim 1 or 2 or 3 described form insulation integrated wallboard and integrated poured buildings, it is characterized in that: described exterior wall collar tie beam comprises and is provided with wall support (2) between the outer wall board of setting parallel to each other and the interior wall sheet material as the outer wall board of wall board and interior wall sheet material; The outer wall board upper end is higher than interior wall sheet material upper end, and the two difference in height is the height of exterior wall collar tie beam.
6. such as claim 1 or 2 or 3 described form insulation integrated wallboard and integrated poured buildings, it is characterized in that: described Vierendeel girder comprises the structural column of the left and right sides, described structural column is surrounded by post outer panel (10), post interior plate (11), post front side board and post back side panel, its center pillar outer panel (10) upper end is higher than post interior plate (11) upper end, and the two difference in height is the framework depth of beam; Comprise also that two ends are fixedly mounted on respectively between the structural column of the left and right sides and as front and back two beam bodies risers (12) of beam slab body be fixedly mounted on respectively between the structural column of the left and right sides, two beam body riser (12) lower ends and as the beam body dull and stereotyped (13) of beam slab body before and after being positioned at, before and after two beam body risers (12) shape and size all identical and have identical about, upper-lower position, in front and back two beam bodies risers (12) and space that beam body flat board (13) surrounds, be provided with the beam body reinforcing bar that links to each other with left and right sides post reinforcing bar; Two ends are respectively with overlap joint hyoplastron (13-1) about wherein said beam body dull and stereotyped (13), the outer end of overlap joint hyoplastron (13-1) outwards surpasses described post interior plate (11) but has certain distance with post outer panel (12), to reserve the passage at beam body space and cylinder space continuous concrete placing.
7. such as claim 1 or 2 or 3 described form insulation integrated wallboard and integrated poured buildings, it is characterized in that: described structural column comprises each two cylinder flat board (6) and cylinder corner board (7), the outer side edges of first cylinder flat board (6) is with 45 ° of assembling inclined-planes, the interior outer side edges of second cylinder flat board (6) is respectively with 45 ° of assembling inclined-planes, work in coordination the first external corner of formation cylinder of 45 ° of first cylinder flat board (6) assembling inclined-planes and 45 ° of assembling inclined-planes of second cylinder flat board (6); The outer side edges of first corner board (7) is worked in coordination with 45 ° of assembling inclined-planes and by 45 ° of assemblings inclined-plane, inboard of these 45 ° assembling inclined-planes and second cylinder flat board (6) and is formed the second external corner of cylinder; The turning of first corner board (7) is as the first inner corner trim of cylinder; The turning of second corner board (7) is as the second inner corner trim of cylinder.
8. claim 1 or 2 or 3 described form insulation integrated wallboard and integrated poured buildings is characterized in that: also comprise basement.
9. form insulation integrated wallboard claimed in claim 4 and integrated poured building is characterized in that: also comprise basement.
10. form insulation integrated wallboard claimed in claim 5 and integrated poured building is characterized in that: also comprise basement.
CN201310299899.7A 2013-07-17 2013-07-17 Integrally-poured building house with wallboards integrating thermal insulating and templates Active CN103362235B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310299899.7A CN103362235B (en) 2013-07-17 2013-07-17 Integrally-poured building house with wallboards integrating thermal insulating and templates

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310299899.7A CN103362235B (en) 2013-07-17 2013-07-17 Integrally-poured building house with wallboards integrating thermal insulating and templates

Publications (2)

Publication Number Publication Date
CN103362235A true CN103362235A (en) 2013-10-23
CN103362235B CN103362235B (en) 2015-06-17

Family

ID=49364429

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310299899.7A Active CN103362235B (en) 2013-07-17 2013-07-17 Integrally-poured building house with wallboards integrating thermal insulating and templates

Country Status (1)

Country Link
CN (1) CN103362235B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107587628A (en) * 2017-09-23 2018-01-16 天津市盛泰建筑工程有限公司 A kind of shear wall structure and its pouring procedure
CN107859403A (en) * 2017-10-31 2018-03-30 惠州市宏硕达绿色建筑科技有限公司 A kind of assembled arthitecutral structure
CN108342937A (en) * 2018-03-14 2018-07-31 安徽省交通控股集团有限公司 A kind of prefabricated pier, the floated tubular Crossing brace connection structure of plate
CN110792207A (en) * 2019-12-06 2020-02-14 安微省建筑设计研究总院股份有限公司 Prefabricated partition wall top node of self-heat-preservation beam-free formwork and construction method of prefabricated partition wall top node

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007016471A (en) * 2005-07-07 2007-01-25 Yoshiyuki Hayakawa Heat-insulating concrete wall and construction method therefor
CN101215855A (en) * 2008-01-16 2008-07-09 吴方伯 Combination beam
CN101424104A (en) * 2008-12-05 2009-05-06 北京工业大学 Thickness changeable shear wall with oblique reinforcing bar transition layer and construction method thereof
CN201883677U (en) * 2010-11-26 2011-06-29 清华大学建筑设计研究院 Frame-shear wall structure building free of dismantling prefabricated reinforced concrete templates
CN102182265A (en) * 2011-03-22 2011-09-14 上海理想家园工程营造有限公司 Multifunctional fast building formwork wallboard structure system
CN102660995A (en) * 2012-05-30 2012-09-12 张晶廷 Prefabricated composite plate formwork wall post-pouring concrete frame shear structure house and construction method
CN203320739U (en) * 2013-07-17 2013-12-04 烟台金田科技有限公司 Formwork thermal insulation integrated wallboard and integrally-poured construction building

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007016471A (en) * 2005-07-07 2007-01-25 Yoshiyuki Hayakawa Heat-insulating concrete wall and construction method therefor
CN101215855A (en) * 2008-01-16 2008-07-09 吴方伯 Combination beam
CN101424104A (en) * 2008-12-05 2009-05-06 北京工业大学 Thickness changeable shear wall with oblique reinforcing bar transition layer and construction method thereof
CN201883677U (en) * 2010-11-26 2011-06-29 清华大学建筑设计研究院 Frame-shear wall structure building free of dismantling prefabricated reinforced concrete templates
CN102182265A (en) * 2011-03-22 2011-09-14 上海理想家园工程营造有限公司 Multifunctional fast building formwork wallboard structure system
CN102660995A (en) * 2012-05-30 2012-09-12 张晶廷 Prefabricated composite plate formwork wall post-pouring concrete frame shear structure house and construction method
CN203320739U (en) * 2013-07-17 2013-12-04 烟台金田科技有限公司 Formwork thermal insulation integrated wallboard and integrally-poured construction building

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107587628A (en) * 2017-09-23 2018-01-16 天津市盛泰建筑工程有限公司 A kind of shear wall structure and its pouring procedure
CN107587628B (en) * 2017-09-23 2019-07-05 天津市盛泰建筑工程有限公司 A kind of shear wall structure and its pouring procedure
CN107859403A (en) * 2017-10-31 2018-03-30 惠州市宏硕达绿色建筑科技有限公司 A kind of assembled arthitecutral structure
CN107859403B (en) * 2017-10-31 2024-01-19 惠州市宏硕达绿色建筑科技有限公司 Assembled building structure
CN108342937A (en) * 2018-03-14 2018-07-31 安徽省交通控股集团有限公司 A kind of prefabricated pier, the floated tubular Crossing brace connection structure of plate
CN108342937B (en) * 2018-03-14 2024-03-01 安徽省交通控股集团有限公司 Prefabricated pier and plate suspension type cylindrical shear support connection structure
CN110792207A (en) * 2019-12-06 2020-02-14 安微省建筑设计研究总院股份有限公司 Prefabricated partition wall top node of self-heat-preservation beam-free formwork and construction method of prefabricated partition wall top node

Also Published As

Publication number Publication date
CN103362235B (en) 2015-06-17

Similar Documents

Publication Publication Date Title
CN104947788B (en) A kind of modular assembly formula building systems and its method of construction
CN103821276B (en) A kind of assembled, modular architectural system
CN104005502B (en) A kind of precast light building cover board and industrialized building house floor slab structure
CN101368428B (en) Prefabricated component house and its construction method
CN103352569A (en) Construction method of integrally-poured architecture building
CN106436893A (en) Fully-prefabricated structure and construction method thereof
CN104947792A (en) Simply-built green light steel fabricated building and installation method
CN103821229B (en) Rapid assembly type integrated house and installation method
CN106013811A (en) Mounting method of prefabricated building
CN204983131U (en) DGC modularization prefabricated buildings system
CN105089178B (en) A kind of pre-splicing Standard formula building of prefabricated steel reinforced concrete shear walls
CN102561513A (en) Unit cabin type building system
CN211286074U (en) Self-heat-insulation system for prefabricated light high-strength foam concrete filled wallboard outer wall
CN103266662B (en) The assembled house of light steel composite board
CN105672664A (en) Integral heat insulation wallboard building system
CN204753811U (en) Green light steel prefabricated buildings are built in letter
CN110439291B (en) Assembly type production construction method suitable for low-rise building
CN103362307B (en) Construction method for modularizing insulation wall boards and pouring integrated house building
CN103362235B (en) Integrally-poured building house with wallboards integrating thermal insulating and templates
CN106351358A (en) Method for manufacturing and mounting fabricated steel structure house sandwich thermal insulation concrete external wall panel
CN2846567Y (en) Steel net structure concrete composite building
CN203412312U (en) Thermal-insulating integrated template wallboard construction building
CN100451257C (en) Concrete complex building of steel meshwork framework, and construction procedure
CN203412143U (en) Wall body structure of integrally poured building house
CN203320739U (en) Formwork thermal insulation integrated wallboard and integrally-poured construction building

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant