Prior art keywords
roof boarding
alc
mounting structure
eave tile
shaped steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201521008817.XU
Other languages
Chinese (zh)
Inventor
刘煜
朱蕾宏
吴锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
XUZHOU ZM-BESTA HEAVY STEEL STRUCTURE CO.,LTD.
Original Assignee
Xuzhou Chinacoal Hantai Building Industrialization Co Ltd
Huzhou Zm-Besta Heavy Steel Structure Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xuzhou Chinacoal Hantai Building Industrialization Co Ltd, Huzhou Zm-Besta Heavy Steel Structure Co Ltd filed Critical Xuzhou Chinacoal Hantai Building Industrialization Co Ltd
Priority to CN201521008817.XU priority Critical patent/CN205296607U/en
Application granted granted Critical
Publication of CN205296607U publication Critical patent/CN205296607U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Roof Covering Using Slabs Or Stiff Sheets (AREA)

Abstract

The utility model provides an embedded steel construction assembly house roof boarding mounting structure, it mainly comprises characterized by ALC roof boarding (1) and H shaped steel roof beam (2), take the dress on H shaped steel roof beam (2) after adjacent two ALC roof boarding (1) concatenation, all be equipped with the mounting hole of dress eave tile bolt (3) on every layer ALC roof boarding (1), the eave tile part of eave tile bolt (3) is colluded on H shaped steel roof beam (2), the the threaded portion of eave tile bolt (3) passes the mounting hole and is equipped with nut (4) soon. The utility model discloses utilizing the eave tile bolt to realize the quick location and the installation of ALC roof boarding, utilizing H shaped steel roof beam upper surface as bearing surface, the roughness is good.

Description

Built-in steel Standard house roof board mounting structure
Technical field
This utility model relates to a kind of Building technology, especially a kind of prefabricated shape can factorial praluction, field-installed building element, specifically a kind of built-in steel Standard house roof board mounting structure.
Background technology
At present, the steel house technology on market mainly has three kinds: one is Low-rise Lightweight Steel Os Draconis residence technology, the second is steel support structure+blockwork on the middle and senior level, the third is steel support structure on the middle and senior level+Light trabs technology, the first technology is relatively ripe, but owing to main structure adopts light gauge cold-formed steel shape bearing capacity limited to doing multilamellar, skyscraper, it is difficult to large-scale promotion. the second builds work by laying bricks or stones owing to there is a large amount of scene, greatly differs from each other with the theory of architectural industrialization, does not meet the developing direction in future. the third technology is still also ripe far away in development, there is also some technical problems, its maximum problem is all to adopt grouting Light trabs owing to inner-outer wall adopts, it is in that main structure junction easily produces the crack caused by displacement structure, this phenomenon is especially susceptible to occur in some high residential buildings, at more built experimental county, this problem ratio is more prominent. except stating three kinds of structures except one, also has a kind of built-in steel Standard building system, it is a kind of green novel fabricated steel structure technique, it is build principal character and with built-in steel structure based on " double modulus " coordination and " block combiner " technology of modularization, the big plate of PC etc. is the industrialized building technique system of feature, this technology through building (house) design, processing, install, equipment is installed, decorations, the overall processes such as Smart Home, achieve the industrialization of house building overall process, intensive and socialization, thus improving construction engineering quality and benefit, realize energy-saving and emission-reduction and resources conservation.
The building system that is mainly characterized in that: of this embedded assembling house adopts double modulus to coordinate to form module machine, and the architectural plane of all kinds of houses from 80��160 and elevation of building be can be combined.As long as the on-gauge plate that basic module is formed being added part sketch plate can meet plane and the facade size of all kinds of living require-ments, thus forming standardized designs, and lay the foundation for factorial praluction. Building adopts steel construction bearing system and the big plate series of PC, overlapping flooring (roofing) plate, and EC wallboard, ALC wallboard form complete agent structure, improve life-span and the anti-seismic performance of building. The big plate of PC adopts the inside holding structure adding heat-insulation layer in the middle of the concrete of both sides, meets incubation and thermal insulation function, improves energy-saving effect, meanwhile, meets the requirements such as fire prevention, sound insulation. The project such as substantially eliminate scaffold, template, plaster, eliminate that beam, post be cast-in-place and the operation such as the colligation of reinforcing bar, decrease situ wet operation, and the finishing of integration, its specimen surface is smooth, smooth, eliminate the operations such as tradition mortar levelling, Puttying can be made directly, spray the operations such as white, save material. Therefore, the construction period of this assembled industrialized building shortens 2/3 than routine, and labour cost reduces by 2/3, it is ensured that safety in production and construction quality. The advantages such as steel house usable floor area can increase by 3%��5% simultaneously, energy-conserving and environment-protective highlight. Through to agent structure Cost Comparison and Analysis, steel construction assembled-type house remains basically stable with the cost of tradition concrete main structure body, but its construction period is traditional 1/3, shorten the investment payback time, and from current steel market upward price trend, Traditional Man expense constantly increases, and price of steel product drops, and the cost of steel house will be expected to further reduction. The roofing mounting technique of one of the key technology as built-in steel Standard building system seems particularly significant.
Utility model content
The purpose of this utility model is a kind of built-in steel Standard house roof board mounting structure of needs design according to built-in steel Standard building system, to improve the installation rate of building roof.
The technical solution of the utility model is:
A kind of built-in steel Standard house roof board mounting structure, it is characterized in that it is mainly made up of ALC roof boarding 1 and H profile steel beam 2, taking after two pieces of adjacent ALC roof boarding 1 splicings is contained on H profile steel beam 2, every layer of ALC roof boarding 1 is equipped with the installing hole installing HOOK BOLTS 3, the eave tile part of HOOK BOLTS 3 hooks on H profile steel beam 2, and the threaded portion of HOOK BOLTS 3 is through installing hole and is installed with nut 4.
Described nut 4 is arranged in the counter sink 5 on ALC roof boarding 1.
The beneficial effects of the utility model:
This utility model utilizes HOOK BOLTS achieve the quickly location of ALC roof boarding and install, and utilizes H profile steel beam upper surface as weight-bearing surface, and flatness is good.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
In figure, 6 is foaming agent or rock wool, and 7 is U-shaped galvanized iron sheet or aluminum skin.
Detailed description of the invention
Below in conjunction with drawings and Examples, this utility model is further described.
As shown in Figure 1.
A kind of built-in steel Standard house roof board mounting structure, it is mainly made up of ALC roof boarding 1 and H profile steel beam 2, taking after two pieces of adjacent ALC roof boarding 1 splicings is contained on H profile steel beam 2, every layer of ALC roof boarding 1 is equipped with the installing hole installing HOOK BOLTS 3, the eave tile part of HOOK BOLTS 3 hooks on H profile steel beam 2, the threaded portion of HOOK BOLTS 3 is through installing hole and is installed with nut 4, and in order to attractive in appearance, nut 4 can be located in the counter sink 5 on ALC roof boarding 1.
This utility model is not directed to part and all same as the prior art prior art maybe can be adopted to be realized.

Claims (2)

1. a built-in steel Standard house roof board mounting structure, it is characterized in that it is mainly made up of ALC roof boarding (1) and H profile steel beam (2), taking after two pieces of adjacent ALC roof boarding (1) splicings is contained on H profile steel beam (2), every layer of ALC roof boarding (1) is equipped with the installing hole installing HOOK BOLTS (3), the eave tile part of HOOK BOLTS (3) hooks on H profile steel beam (2), and the threaded portion of HOOK BOLTS (3) is through installing hole and is installed with nut (4).
2. built-in steel Standard house roof board mounting structure according to claim 1, is characterized in that described nut (4) is arranged in the counter sink (5) on ALC roof boarding (1).
CN201521008817.XU 2015-12-08 2015-12-08 Embedded steel construction assembly house roof boarding mounting structure Active CN205296607U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201521008817.XU CN205296607U (en) 2015-12-08 2015-12-08 Embedded steel construction assembly house roof boarding mounting structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201521008817.XU CN205296607U (en) 2015-12-08 2015-12-08 Embedded steel construction assembly house roof boarding mounting structure

Publications (1)

Publication Number Publication Date
CN205296607U true CN205296607U (en) 2016-06-08

Family

ID=56436776

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201521008817.XU Active CN205296607U (en) 2015-12-08 2015-12-08 Embedded steel construction assembly house roof boarding mounting structure

Country Status (1)

Country Link
CN (1) CN205296607U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106702831A (en) * 2017-01-24 2017-05-24 北京交通大学 Straddling type monorail traffic full-steel structural system based on assembly type technology
CN106703276A (en) * 2017-01-16 2017-05-24 中民筑友科技投资有限公司 Roof assembly method
CN109024992A (en) * 2018-08-27 2018-12-18 山西尚风科技股份有限公司 A kind of soundproof plate and its connection method with fashioned iron

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106703276A (en) * 2017-01-16 2017-05-24 中民筑友科技投资有限公司 Roof assembly method
CN106702831A (en) * 2017-01-24 2017-05-24 北京交通大学 Straddling type monorail traffic full-steel structural system based on assembly type technology
CN109024992A (en) * 2018-08-27 2018-12-18 山西尚风科技股份有限公司 A kind of soundproof plate and its connection method with fashioned iron

Similar Documents

Publication Publication Date Title
CN105421818B (en) Built-in steel Standard house
CN203247737U (en) Light steel keel composite board partition wall
CN204983131U (en) DGC modularization prefabricated buildings system
WO2017036185A1 (en) Aluminum alloy house
WO2017041517A1 (en) Movable aluminum alloy house
CN105863110A (en) Modular assembling type cold-bent thin-wall type steel wall board structural system
WO2017028575A1 (en) Installation and connection structure of outer wall and crossbeam in aluminium alloy house
CN104179250A (en) Light-board house system and construction method thereof
CN203821627U (en) Wall structure system with light steel keels, and wall
CN204282709U (en) Diatom veneer rock wool composite wall
CN205296607U (en) Embedded steel construction assembly house roof boarding mounting structure
CN202324323U (en) Outer wall plate
CN204491984U (en) Stone facing precast wall panel and external wall system
CN105421656B (en) External wall board installation structure of embedded type steel structure assembled house
CN205296893U (en) Embedded steel construction assembly house
CN205296407U (en) Embedded steel construction assembly house post roof beam connection structure
CN205296452U (en) Embedded steel construction assembly house stand fire resistive construction
CN107217758B (en) Fully-prefabricated load-bearing light steel assembly type composite wallboard and manufacturing method thereof
CN208950069U (en) A kind of light-duty prefabricated buildings
CN203821925U (en) Earthquake-proofing house of light steel structure
CN110593397A (en) Multilayer assembled plate type building
CN206090827U (en) Have embedded steel construction of bathroom precast floor plank assembly house
CN206110463U (en) Energy -conserving big board of decorating is gone along with sb. to guard him outward to steel construction assembled
CN104047457A (en) Light steel structure anti-seismic house
CN205296572U (en) Embedded steel construction assembly house side fascia

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20220402

Address after: 221116 in the third industrial park in the north of Huanghe Road and the west of beizongyi Road, Tongshan new area, Tongshan District, Xuzhou City, Jiangsu Province

Patentee after: XUZHOU ZM-BESTA HEAVY STEEL STRUCTURE CO.,LTD.

Address before: 221116 in the third industrial park in the north of Huanghe Road and the west of beizongyi Road, Tongshan new area, Tongshan District, Xuzhou City, Jiangsu Province

Patentee before: XUZHOU ZM-BESTA HEAVY STEEL STRUCTURE CO.,LTD.

Patentee before: Xuzhou China Coal Hantai construction industrialization Co., Ltd

TR01 Transfer of patent right