Summary of the invention
In order to overcome the deficiencies in the prior art, the utility model provides a kind of buried natural gas line earth's surface excessive drainage hood, while solving buried natural gas line generation leakage, how by see through the inflammable gass such as the excessive methane in earth's surface of buried soil layer as early as possible drainage walk the problem so that digging in-situ, repair personnel are marched into the arena etc. fast.
The excessive drainage hood in a kind of buried natural gas line earth's surface, middle bleed jigsaw is made up of mainboard, rotating shaft cover, prepackage hinging shaft and auxiliary handgrip in V-type funnel cover, Sledge type; V-type funnel cover band hollow funnel chamber, V-type funnel cover top socket cloth wind air entraining pipe, in V-type funnel cover bottom and Sledge type, mainboard is welded; In Sledge type, there is the arc warpage twisting at mainboard two ends, and in Sledge type, mainboard middle part hole and V-type funnel cover lower end match; Rotating shaft cover is combined into six covers with prepackage hinging shaft and is evenly arranged in middle bleed jigsaw both sides; Middle part, bleed jigsaw two ends in the middle of auxiliary handgrip is welded in; Left and right expansion jigsaw is made up of left and right wing plate and rotating shaft cover; Left and right wing plate profile is band major axis semiellipse and long rectangle combination; Rotating shaft cover is corresponding with the rotating shaft cover dislocation on middle bleed jigsaw, is fixedly welded on the long straight flange of left and right wing plate; Under cloth wind air entraining pipe, be terminated at the osculum end of V-type funnel cover; Cloth wind air entraining pipe communicates with leaking analog channel, leaks analog channel and communicates with buried natural gas line.
A using method for the excessive drainage hood in buried natural gas line earth's surface, contains following steps;
First cloth wind air entraining pipe is raised to high-altitude by assistance for lifting lever arrangement, makes air entraining pipe produce atm difference up and down and there is nature suction; Pull lid and be pressed onto excessive gas top being hinged to overall bleed jigsaw and left and right expansion jigsaw again, under the excessive pressure of excessive gas itself and the draught head acting in conjunction of the different generations of the upper and lower rarefaction of air degree of air entraining pipe, realize the excessive inflammable gas of the carrying-off earth's surface overwhelming majority; Simultaneously by manually earthing compacting suitably being done in jigsaw top.
Excessive like this gas, by the excessive pressure of itself and the suction of air entraining pipe, has just been directed into high-altitude, has reduced near the combustable gas concentration in earth's surface, has realized drainage target, for condition has been created in follow-up processing.
The beneficial effects of the utility model are: when buried natural gas line occurs to leak, by timely drainage hood device being covered in to excessive place, earth's surface, solve the harm that excessive gas that pipeline stopping transportation step-down in time produces is marched into the arena to surrounding environment, the personnel equipment of speedily carrying out rescue work and excavated operation etc.The application of the excessive drainage hood in earth's surface, the response efficiency by riser tubing operation maintenance business scope to accident, is the important supplementary equipment of pipe first-aid accident treatment, therefore, the excessive drainage hood in buried rock gas earth's surface will have good application prospect.
Brief description of the drawings
When considered in conjunction with the accompanying drawings, by the detailed description with reference to below, can more completely understand better the utility model and easily learn wherein many advantages of following, but accompanying drawing described herein is used to provide further understanding of the present utility model, form a part of the present utility model, schematic description and description of the present utility model is used for explaining the utility model, do not form improper restriction of the present utility model, as schemed wherein:
Fig. 1 is mounting structure schematic diagram of the present utility model.
Fig. 2 is structural representation of the present utility model.
Fig. 3 is middle bleed jigsaw structural representation of the present utility model.
Fig. 4 is left and right expansion jigsaw structural representation of the present utility model.
Below in conjunction with drawings and Examples, the utility model is further illustrated.
Embodiment
Obviously the many modifications and variations that, those skilled in the art do based on aim of the present utility model belong to protection domain of the present utility model.
Embodiment 1: as shown in Figure 1, Figure 2, Figure 3 and Figure 4, and the excessive drainage hood in a kind of buried natural gas line earth's surface, middle bleed jigsaw 1, left and right expansion jigsaw 2, cloth wind air entraining pipe 3.
Middle bleed jigsaw 1 is made up of mainboard 5, rotating shaft cover 6, prepackage hinging shaft 7 and auxiliary handgrip 8 in V-type funnel cover 4, Sledge type.V-type funnel cover 4 aluminium sheet materials, band hollow funnel chamber, V-type funnel cover 4 top socket cloth wind air entraining pipes 3, in V-type funnel cover 4 bottoms and Sledge type, mainboard 5 is welded; In Sledge type, there is the arc warpage twisting at mainboard 5 two ends, and facilitate earth's surface to slide, and in Sledge type, mainboard 5 middle part holes and V-type funnel cover 4 lower ends match; Rotating shaft cover 6 is combined into six covers with prepackage hinging shaft 7 and is evenly arranged in middle bleed jigsaw 1 both sides, waits until pairing; Assist handgrip 8 to be welded in middle bleed jigsaw 1 middle part, two ends, be beneficial to personnel's lift to move, can be used for again rope far-end and pull the slip of drive drainage hood entirety.
Expansion jigsaw 2 in left and right is made up of left and right wing plate 9 and rotating shaft cover 10.Left and right wing plate 9 is aluminium sheet material, and profile is band major axis semiellipse and long rectangle combination; Rotating shaft cover 10 is corresponding with rotating shaft cover 6 dislocation on middle bleed jigsaw 1, is fixedly welded on the long straight flange of left and right wing plate.
In the time not applying, folding two wing plates dwindle space, are convenient to transport, launch to be jointly combined into nearly square cover plate with middle bleed jigsaw 1 when on-the-spot application, are covered to the excessive earth's surface of gas place, and top can be aided with hack compacting.
Cloth wind air entraining pipe 3 adopts commercially available finished product flame-retardant fiber wind-distributing pipe, in the time of application, be aided with lifting bar its one end is risen to high vacancy, cloth wind air entraining pipe is terminated at the osculum end of V-type funnel cover 4 for 3 times, under the excessive pressure of excessive gas itself and the draught head acting in conjunction of the different generations of the upper and lower rarefaction of air degree of air entraining pipe, realize the excessive inflammable gas of the carrying-off earth's surface overwhelming majority.
Cloth wind air entraining pipe 3 communicates with revealing analog channel 11, reveals analog channel 11 and communicates with buried natural gas line 12.
The design invention of the excessive drainage hood in buried natural gas line earth's surface, its outstanding innovation is to comprise following several respects:
1). middle bleed jigsaw be convenient to pull sliding motion structure form: have in the Sledge type of the arc warpage that twists mainboard taking two ends as sliding body,, personnel excessive at excessive inflammable gas cannot be closely near time, be aided with rope bolt and drag auxiliary handgrip and can overcome easily that earth's surface is unequal stumbles, drainage hood is pulled and be placed on excessive leakage point at a distance;
2). the folding both wings structure choice of left and right expansion jigsaw: profile is more aobvious round and smooth with long rectangle combination with band major axis semiellipse, reduces placement space when folding, is convenient to lifting, transport, increases area coverage, expands bleed scope when expansion;
3). the material of parts is selected to arrange: middle bleed jigsaw and the left and right main material of expansion jigsaw, taking lightweight aluminium sheet as main, have reduced the overall weight of equipment, are convenient to transport and manual operation; Cloth wind air entraining pipe is selected commercially available finished product flame-retardant fiber wind-distributing pipe, and lightweight, inexpensive, has avoided redesign.
Middle bleed jigsaw be convenient to pull sliding motion structure form: have in the Sledge type of the arc warpage that twists mainboard taking two ends as sliding body, be convenient to be aided with rope bolt and drag auxiliary handgrip and pull, overcome earth's surface injustice, stumble etc.
The special part of folding both wings structural form selection of left and right expansion jigsaw is: profile is more aobvious round and smooth with long rectangle combination with band major axis semiellipse, reduces placement space when folding, is convenient to lifting, transport, increases area coverage, expands bleed scope when expansion.
The material of parts is selected that special part is set and is: middle bleed jigsaw and the left and right main material of expansion jigsaw, taking lightweight aluminium sheet as main, have reduced the overall weight of equipment, are convenient to transport and manual operation; Cloth wind air entraining pipe is selected commercially available finished product flame-retardant fiber wind-distributing pipe, and lightweight, inexpensive, has avoided redesign.
As mentioned above, embodiment of the present utility model is explained, but as long as not departing from fact inventive point of the present utility model and effect can have a lot of distortion, this will be readily apparent to persons skilled in the art.Therefore, within such variation is also all included in protection domain of the present utility model.