CN105971012A - Prefabricated pipe gallery - Google Patents
Prefabricated pipe gallery Download PDFInfo
- Publication number
- CN105971012A CN105971012A CN201610522584.8A CN201610522584A CN105971012A CN 105971012 A CN105971012 A CN 105971012A CN 201610522584 A CN201610522584 A CN 201610522584A CN 105971012 A CN105971012 A CN 105971012A
- Authority
- CN
- China
- Prior art keywords
- plate
- fixed station
- fixed
- frame
- piping lane
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
Landscapes
- Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Supports For Pipes And Cables (AREA)
Abstract
The invention discloses a prefabricated pipe gallery which comprises a frame. The left side and the right side of the top end in the frame are each provided with a first fixed table. The left side and the right side of the bottom end in the frame are each provided with a second fixed table. Each first fixed table is connected with the corresponding second fixed table through a supporting column. The left end in the frame is provided with a first fixed plate, and the right end in the frame is provided with a second fixed plate. According to the prefabricated pipe gallery, by means of cooperation of the supporting columns, shield plates and a lifting plate, the first fixed tables and the second fixed tables cooperate through the supporting columns to support and divide the frame; the solidness and the space utilization effect of the frame are improved; lifting is achieved through cooperation, and maintenance workers can repair cables on first cable containing frames and second cable containing frames conveniently; and the shield plates are used for carrying out shield protection on a water feed pipe, a drain pipe and a heat pipe, the water feed pipe, the drain pipe and the heat pipe are prevented from being damaged during walking, and the actual work need of the gallery is greatly met.
Description
Technical field
The present invention relates to piping lane technical field, a kind of prefabricated piping lane.
Background technology
Underground pipe gallery is also known as common trench, and it is enforcement unified planning, designs, constructs and safeguard, is built in city
Underground, city, for laying the public utility of municipal public use pipeline, refers at Urban Underground deposited for concentrating
If the public tunnel of the municipal pipelines such as electric power, communication, radio and television, feedwater, draining, heating power, combustion gas,
As far back as the '20s in last century, Japan's Tokyo, capital municipalities is just in the main line road that nine sections of center, city is regional
Under road, the pipelines such as electric power, phone, water supply and coal gas are concentrated and lays, define Article 1 underground, Tokyo
Pipe gallery, in the prior art, the such as utility model patent of Application No. 201520881472.2,
Including web and wing plate, internal stiffener, be arranged on the connection at web and wing plate two ends seal structure and
Longitudinal stress structure, web height meets piping lane and uses requirement, and wing plate cross side includes that stiffener is reserved
End, connecting sealing structure is connected structure, and longitudinal stress structure is prestressed cable attachment structure, or even
Connect sealing structure and longitudinal stress structure be cast-in-place structural, although this patent by cable wire facilitate transport with
Install, but poor to the space utilization effect within piping lane when actually used, and the support of piping lane is firm
Spend poor, it is impossible to meet the real work demand of piping lane.
Summary of the invention
It is an object of the invention to provide a kind of prefabricated piping lane, with solve in above-mentioned background technology propose ask
Topic.
For achieving the above object, the present invention provides following technical scheme: a kind of prefabricated piping lane, including framework,
The inner tip left and right sides of described framework is equipped with the first fixed station, about the inner bottom of described framework
Both sides are equipped with the second fixed station, and described first fixed station is connected by support column and the second fixed station, institute
The front stating support column is provided with enabling, be respectively arranged at two ends with about the inside of described framework the first fixed plate and
Second fixed plate, the inner side of described first fixed plate is provided with the first cable rack, described second fixed plate
Inner side be respectively arranged at two ends with the second cable rack and supporting plate up and down, the inner side of described second fixed station sets
Having cover plate, the center of described cover plate and the left and right sides to be equipped with maintenance groove, the bottom of described cover plate is from a left side
Be sequentially provided with upper hose, downcomer and thermal pipe to the right side, the left and right sides, bottom of described cover plate be equipped with every
Plate.
Preferably, the outside of described second fixed station is provided with fixed station, and the top of described fixed station is provided with liter
Fall plate, described lifter plate is connected with fixed station by atmospheric pressure pole, and the left end of described lifter plate is provided with adjusting rod,
The top of described lifter plate is provided with turnover panel, and described turnover panel is connected with turnover panel by movable part.
Preferably, the inside of described lifter plate is provided with placing trough, and the inside of described placing trough is provided with and pulls and pushes plate.
Preferably, the upper surface of described turnover panel and lifter plate is equipped with anti-skidding rib.
Preferably, the inwall top of described maintenance groove is provided with dismounting net.
Compared with prior art, the invention has the beneficial effects as follows: this prefabricated piping lane, by support column, cover
Plate and the cooperation of lifter plate, framework is carried out by the first fixed station by the cooperation of support column and the second fixed station
Support and separate, improving solidness and the space utilization effect of framework, coordinate and raise, convenient maintenance
Cable on first cable rack and the second cable rack is keeped in repair by workman, cover plate to upper hose,
Downcomer and thermal pipe carry out hiding protection, it is to avoid cause upper hose, downcomer and thermal pipe when walking
Damaging, maintenance groove is convenient to be overhauled upper hose, downcomer and thermal pipe, significantly meets the reality of corridor
Border work requirements.
Accompanying drawing explanation
Fig. 1 is present configuration schematic diagram;
Fig. 2 is the atmospheric pressure pole structural representation of the present invention;
Fig. 3 be the present invention pull and push plate structure schematic diagram;
Fig. 4 is the reverse turning bed structure schematic diagram of the present invention;
Fig. 5 is the maintenance groove structural representation of the present invention.
In figure: 1, the first fixed station, 2, open the door, 3, support column, the 4, first fixed plate, 5, first
Cable rack, 6, framework, the 7, second cable rack, the 8, second fixed plate, 9, fixed station,
10, the second fixed station, 11, upper hose, 12, downcomer, 13, thermal pipe, 14, cover plate, 15,
Supporting plate, 16, movable part, 17, adjusting rod, 18, turnover panel, 19, lifter plate, 20, atmospheric pressure pole, 21,
Pull and push plate, 22, placing trough, 23, anti-skidding rib, 24, maintenance groove, 25, dismounting net, 26, dividing plate.
Detailed description of the invention
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out
Clearly and completely describe, it is clear that described embodiment is only a part of embodiment of the present invention, and
It is not all, of embodiment.Based on the embodiment in the present invention, those of ordinary skill in the art are not doing
Go out the every other embodiment obtained under creative work premise, broadly fall into the scope of protection of the invention.
Referring to Fig. 1-5, the present invention provides a kind of technical scheme: a kind of prefabricated piping lane, including framework 6,
The inner tip left and right sides of described framework 6 is equipped with the first fixed station 1, the inner bottom of described framework 6
The left and right sides is equipped with the second fixed station 10, and described first fixed station 1 is fixed by support column 3 and second
Platform 10 is connected, and the front of described support column 3 is provided with enabling 2, the first fixed station 1 by support column 3 with
Framework 6 is supported and separates by the cooperation of the second fixed station 10, improves solidness and the space of framework 6
Utilizing status, the outside of described second fixed station 10 is provided with fixed station 9, and the top of described fixed station 9 sets
Having lifter plate 19, described lifter plate 19 to be connected with fixed station 9 by atmospheric pressure pole 20, lifter plate 19 passes through
Raise with coordinating of atmospheric pressure pole 20, facilitate maintenance worker to the first cable rack 5 and the second cable
Cable on rack 7 keeps in repair, and the left end of described lifter plate 19 is provided with adjusting rod 17, described lifting
The inside of plate 19 is provided with placing trough 22, and the inside of described placing trough 22 is provided with and pulls and pushes plate 21, by arranging
Pulling and pushing plate 21 to be supported turnover panel 18, the top of described lifter plate 19 is provided with turnover panel 18, by arranging
Turnover panel 18 improves the usable floor area of lifter plate 19, facilitates maintenance person to keep in repair, described turnover panel 18 and lifter plate
The upper surface of 19 is equipped with anti-skidding rib 23, and described turnover panel 18 is connected with turnover panel 18 by movable part 16,
The first fixed plate 4 and the second fixed plate 8 it is respectively arranged at two ends with about the inside of described framework 6, described first
The inner side of fixed plate 4 is provided with the first cable rack 5, and the upper and lower two ends, inner side of described second fixed plate 8 are divided
Not being provided with the second cable rack 7 and supporting plate 15, the inner side of described second fixed station 10 is provided with cover plate 14,
The center of described cover plate 14 and the left and right sides are equipped with maintenance groove 24, the inwall top of described maintenance groove 24
End is provided with dismounting net 25, and the bottom of described cover plate 14 is from left to right sequentially provided with upper hose 11, downcomer
12 and thermal pipe 13, the left and right sides, bottom of described cover plate 14 is equipped with dividing plate 26, and cover plate 14 is to upper water
Pipe 11, downcomer 12 and thermal pipe 13 carry out hide protection, it is to avoid cause when walking upper hose 11,
Downcomer 12 and thermal pipe 13 damage, and upper hose 11, downcomer 12 and thermal pipe 13 are entered by dividing plate 26
Row is shown in a differentiation, and maintenance groove 24 is convenient to be overhauled upper hose 11, downcomer 12 and thermal pipe 13.
Although an embodiment of the present invention has been shown and described, for those of ordinary skill in the art
Speech, it is possible to understand that these embodiments can be carried out without departing from the principles and spirit of the present invention
Multiple change, revising, replace and modification, the scope of the present invention is limited by claims and equivalent thereof
Fixed.
Claims (5)
1. a prefabricated piping lane, including framework, it is characterised in that: about the inner tip of described framework two
Side is equipped with the first fixed station, and the inner bottom left and right sides of described framework is equipped with the second fixed station, institute
Stating the first fixed station to be connected by support column and the second fixed station, the front of described support column is provided with enabling,
Being respectively arranged at two ends with the first fixed plate and the second fixed plate about the inside of described framework, described first fixes
The inner side of plate is provided with the first cable rack, and the inner side of described second fixed plate is respectively arranged at two ends with up and down
Two cable rack and supporting plates, the inner side of described second fixed station is provided with cover plate, the center of described cover plate
Being equipped with maintenance groove with the left and right sides, the bottom of described cover plate is from left to right sequentially provided with upper hose, Xia Shui
Pipe and thermal pipe, the left and right sides, bottom of described cover plate is equipped with dividing plate.
The prefabricated piping lane of one the most according to claim 1, it is characterised in that: described second fixed station
Outside be provided with fixed station, the top of described fixed station is provided with lifter plate, and described lifter plate passes through atmospheric pressure pole
Being connected with fixed station, the left end of described lifter plate is provided with adjusting rod, and the top of described lifter plate is provided with turnover panel,
Described turnover panel is connected with turnover panel by movable part.
The prefabricated piping lane of one the most according to claim 2, it is characterised in that: described lifter plate interior
Portion is provided with placing trough, and the inside of described placing trough is provided with and pulls and pushes plate.
The prefabricated piping lane of one the most according to claim 2, it is characterised in that: described turnover panel and lifting
The upper surface of plate is equipped with anti-skidding rib.
The prefabricated piping lane of one the most according to claim 1, it is characterised in that: described maintenance groove interior
Wall top is provided with dismounting net.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610522584.8A CN105971012B (en) | 2016-07-05 | 2016-07-05 | A kind of prefabricated piping lane |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610522584.8A CN105971012B (en) | 2016-07-05 | 2016-07-05 | A kind of prefabricated piping lane |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105971012A true CN105971012A (en) | 2016-09-28 |
CN105971012B CN105971012B (en) | 2018-04-03 |
Family
ID=56954991
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610522584.8A Expired - Fee Related CN105971012B (en) | 2016-07-05 | 2016-07-05 | A kind of prefabricated piping lane |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105971012B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106638681A (en) * | 2016-12-19 | 2017-05-10 | 北京建筑大学 | Integrated pipe gallery |
CN108842830A (en) * | 2018-07-10 | 2018-11-20 | 赵雅琴 | Underground pipe gallery antidetonation support column |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20010057097A (en) * | 1999-12-18 | 2001-07-04 | 이계철 | The precast concrete segment block for cable tunnel |
CN203924111U (en) * | 2014-06-10 | 2014-11-05 | 郑州市交通规划勘察设计研究院 | Underground municipal Pipe rack |
CN204151824U (en) * | 2014-10-14 | 2015-02-11 | 四川全丰新材料科技有限公司 | A kind of glass reinforced plastic underground comprehensive pipe network common trench |
CN105484291A (en) * | 2016-01-12 | 2016-04-13 | 上海市城市建设设计研究总院 | Unilaterally-expanded comprehensive pipe gallery joint structure |
CN205171549U (en) * | 2015-11-06 | 2016-04-20 | 深圳华瀚管廊物业服务有限公司 | Piping lane prefab and prefabricated formula utility tunnel |
CN205742270U (en) * | 2016-07-05 | 2016-11-30 | 宏大国源(芜湖)资源环境治理有限公司 | A kind of prefabricated piping lane |
-
2016
- 2016-07-05 CN CN201610522584.8A patent/CN105971012B/en not_active Expired - Fee Related
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20010057097A (en) * | 1999-12-18 | 2001-07-04 | 이계철 | The precast concrete segment block for cable tunnel |
CN203924111U (en) * | 2014-06-10 | 2014-11-05 | 郑州市交通规划勘察设计研究院 | Underground municipal Pipe rack |
CN204151824U (en) * | 2014-10-14 | 2015-02-11 | 四川全丰新材料科技有限公司 | A kind of glass reinforced plastic underground comprehensive pipe network common trench |
CN205171549U (en) * | 2015-11-06 | 2016-04-20 | 深圳华瀚管廊物业服务有限公司 | Piping lane prefab and prefabricated formula utility tunnel |
CN105484291A (en) * | 2016-01-12 | 2016-04-13 | 上海市城市建设设计研究总院 | Unilaterally-expanded comprehensive pipe gallery joint structure |
CN205742270U (en) * | 2016-07-05 | 2016-11-30 | 宏大国源(芜湖)资源环境治理有限公司 | A kind of prefabricated piping lane |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106638681A (en) * | 2016-12-19 | 2017-05-10 | 北京建筑大学 | Integrated pipe gallery |
CN108842830A (en) * | 2018-07-10 | 2018-11-20 | 赵雅琴 | Underground pipe gallery antidetonation support column |
Also Published As
Publication number | Publication date |
---|---|
CN105971012B (en) | 2018-04-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205875537U (en) | Metal containment system roofing expansion joint resistance to deformation waterproof construction | |
CN204356595U (en) | Medium-and low-speed maglev railway is low puts circuit continuous arch support rail girder construction | |
CN105971012A (en) | Prefabricated pipe gallery | |
CN205742270U (en) | A kind of prefabricated piping lane | |
CN104295147B (en) | A kind of framework being applicable to transformer station's outlet | |
CN104818867B (en) | A kind of mobile assembling public lavatory | |
CN203775798U (en) | Assembled-type agricultural greenhouse | |
CN202755695U (en) | Coke-oven big canopy with coke-oven oven column used for installation | |
CN211257514U (en) | Steel construction furred ceiling with leak protection water function | |
CN204113295U (en) | A kind of municipal shield tunnel | |
CN103276838B (en) | High-altitude vertical stereo greening system | |
CN104265363A (en) | Underground roadway gushing point dewatering device | |
CN203891514U (en) | Main transformer framework for omitting end support in substation | |
CN208633236U (en) | A kind of drainpipe being easily installed | |
CN204401651U (en) | Abnormity resistance to compression longitudinal prestressing pin-connected panel underground pipe gallery | |
CN106013230A (en) | Novel pipe rack structure | |
CN206376226U (en) | A kind of accessible all standing dust falling system of contrary sequence method platform | |
CN201901019U (en) | Arrangement mode of AT branch area and AT position | |
CN207376821U (en) | A kind of electronic rain shade suitable on Metro station excavation | |
CN205935796U (en) | Sled formula components of a whole that can function independently pump house | |
CN207194258U (en) | The crossbeam monoblock type broken line unit curtain wall system of multi-span flexible combination | |
CN209353764U (en) | A kind of post-cast strip covered protection device | |
CN205878880U (en) | Drying rack of non -metallic mineral shaping filter cake | |
CN211973567U (en) | Pipe gallery trolley | |
CN206034470U (en) | Novel photovoltaic support basis mounting structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180403 Termination date: 20190705 |
|