CN202672139U CN 201220260960 CN201220260960U CN202672139U CN 202672139 U CN202672139 U CN 202672139U CN 201220260960 CN201220260960 CN 201220260960 CN 201220260960 U CN201220260960 U CN 201220260960U CN 202672139 U CN202672139 U CN 202672139U
Authority
CN
China
Prior art keywords
pile
joint stake
reinforced concrete
grouting pipe
prefabricated reinforced
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220260960
Other languages
Chinese (zh)
Inventor
赵卫政
张习上
钱邦栋
徐春荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU XINGXIA BUILDING INSTALLATION CO Ltd
Original Assignee
JIANGSU XINGXIA BUILDING INSTALLATION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU XINGXIA BUILDING INSTALLATION CO Ltd filed Critical JIANGSU XINGXIA BUILDING INSTALLATION CO Ltd
Priority to CN 201220260960 priority Critical patent/CN202672139U/en
Application granted granted Critical
Publication of CN202672139U publication Critical patent/CN202672139U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a prefabricated reinforced concrete square pile which comprises an upper segment pile and a lower segment pile and further comprises a first injection pipe and a second injection pipe. The first injection pipe is placed on the center of the upper segment pile, the second injection pipe is placed on the center of the lower segment pile, the first injection pipe communicate the upper segment pile, and the second injection pipe communicate the lower segment pile. The upper end of the lower segment pile is connected with the lower end of the upper segment pile, the lower end of the lower segment pile is provided with a pile point which is provided with an injection hole, and the second injection pipe is communicated with the injection hole. Compared with the background art, the prefabricated reinforced concrete square pile not only can improve the bearing capacity of a single pile and save costs, but also can overcome the shortages of large construction noise, low efficiency and serious environmental pollution and the like when a pile is poured by a drill hole.

Description

Prefabricated Reinforced Concrete Square Pile
Technical field
The utility model relates to a kind of Prefabricated Reinforced Concrete Square Pile.
Background technology
Continuous propelling along with China's urban development construction process, gradually reducing of the idle land area in urban district, cause building longitudinally short transverse significantly improve, plane figure is significantly compressed, in the urban district between adjacent building the distance constantly reduce, Design of Foundation and the construction of building are had higher requirement.
East China-Shanghai, Jiangsu, zhejiang and other places Pile Foundations Design adopt more pile foundation type that bored pile, prestressed concrete pipe pile and Prefabricated Reinforced Concrete Square Pile are arranged at present.It is high that bored pile has a bearing capacity of single pile, on the less characteristics of surrounding enviroment impact, the shortcomings such as but it is various to have simultaneously the construction technology link, and efficiency of construction is low, long in time limit, the mechanical execution noise is large, the problems such as mud drilling construction and discharging are also very serious to the pollution of environment.Prestressed concrete pipe pile and Prefabricated Reinforced Concrete Square Pile, technological characteristics of construction are that mechanical execution efficient is higher, and the job site civilized construction is effective, adopt the static pressure construction pollution from environmental noise less.But it is that bearing capacity of single pile is low that these two kinds of techniques have common shortcoming, and the soil extrusion in construction effect is larger, must take into full account the protection to peripheral path pipeline and Nearby Structure during construction.These two kinds of stake types are compared, and prestressed concrete pipe pile Under Lateral Loading ability is very low, the shearing resistance weak effect, and precast square pile also can bear the part horizontal loading simultaneously except bearing vertical load, the soil compaction effect pile tube is more a shade better again than square pile.Several techniques respectively have quality.
Therefore, need a kind of new pile body to address the above problem.
The utility model content
The purpose of this utility model is for problems of the prior art, and a kind of raising bearing capacity of single pile is provided, and saves the Prefabricated Reinforced Concrete Square Pile of cost to address the above problem.
For realizing above-mentioned utility model purpose, Prefabricated Reinforced Concrete Square Pile of the present utility model can adopt following technical scheme:
A kind of Prefabricated Reinforced Concrete Square Pile, comprise joint stake and the stake of lower joint, also comprise the first Grouting Pipe and the second Grouting Pipe, described the first Grouting Pipe is positioned at the center of described upper joint stake, described the second Grouting Pipe is positioned at the center of described lower joint stake, described the first Grouting Pipe connects described upper joint stake, and described the second Grouting Pipe connects described lower joint stake; The upper end of described lower joint stake is connected with the lower end of described upper joint stake, and the lower end of described lower joint stake has pile top, and described pile top is provided with injected hole, and described the second Grouting Pipe is communicated with described injected hole.
Beneficial effect: compare with background technology, Prefabricated Reinforced Concrete Square Pile of the present utility model can either improve bearing capacity of single pile, saves cost, can remedy the deficiencies such as the bored pile construction noise is large, efficient is low, environment pollution is serious again.
Description of drawings
Fig. 1 is the structural representation of upper joint stake;
Fig. 2 is the sectional drawing at upper joint stake pile body A-A place;
Fig. 3 is the structural representation of lower joint stake;
Fig. 4 is the sectional drawing at lower joint stake pile body B-B place;
Fig. 5 is the generalized section of upper joint stake;
Fig. 6 is upper joint stake and the lower connection diagram that saves stake;
Fig. 7 is the connection diagram of the first Grouting Pipe and the second Grouting Pipe;
Fig. 8 is the front view of the pile top of lower joint stake;
Fig. 9 is the generalized section of the pile top of lower joint stake.
The specific embodiment
Below in conjunction with the drawings and specific embodiments, further illustrate the utility model, should understand these embodiment only is used for explanation the utility model and is not used in restriction scope of the present utility model, after having read the utility model, those skilled in the art all fall within the application's claims limited range to the modification of the various equivalent form of values of the present utility model.
See also Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5, Fig. 6, shown in Figure 7, Prefabricated Reinforced Concrete Square Pile of the present utility model, comprise joint stake 1 and lower joint stake 2, comprise that also the first Grouting Pipe 11 and the second Grouting Pipe 21, the first Grouting Pipe 11 are positioned at the center of joint stake 1 and connect upper joint stake 1.The second Grouting Pipe 21 is positioned at the center of lower joint stake 2 and connects lower joint stake 2.The upper end of lower joint stake 2 is connected with the lower end of upper joint stake 1, and the lower end of lower joint stake 2 has pile top 23, and pile top 23 is provided with injected hole 24, the second Grouting Pipe 21 and is communicated with injected hole 24.Wherein, the lower end of upper joint stake 1 is provided with the first pile cover 12, and the upper end of lower joint stake 2 is provided with the second pile cover 22.Wherein the first pile cover 12 and the second pile cover 22 are driving cap.The center, upper surface of lower joint stake 2 is preset with groove 23.Upper joint stake 1, lower joint stake 2 pipeline general arrangements: bury one of Grouting Pipe at the center of stake underground, the first Grouting Pipe 11 of upper joint stake 1 connects whole upper joint stake 1, the second Grouting Pipe 21 of lower joint stake 2 is buried underground to pile top 23 positions from lower joint stake 2 pile body tops, is connected with slurry casting machine cavity 26.
See also Fig. 6, shown in Figure 7, because pile follower needs, after 1 top bit the first Grouting Pipe 11 usefulness blocking device 13 of upper joint stake clog, be cast in the stake top of joint stake 1, behind excavation of foundation pit, the stake top is cut the fraction concrete, cut the degree of depth and be not more than 50mm, pull out blocking device 13 after cleaning out, carry out slip casting after the connection Grouting Pipe.Wherein blocking device 13 can be rubber stopper.
See also Fig. 6, shown in Figure 7, when carrying out pile extension with lower joint stake 2, upper joint stake 1 should notice that upper joint stake 1 and the Grouting Pipe of lower joint stake 2 align, after silicone sealant is smeared at the first Grouting Pipe 11 tube head positions of joint stake 1, link to each other with lower the second Grouting Pipe 21 tops compression that saves stake 2, with connecting angle the operation of electric welding pile extension is carried out in upper joint stake 1 and lower four jiaos of saving stake 2 afterwards.
See also Fig. 8, shown in Figure 9, pile top 23 places of lower joint stake 2 are provided with slurry casting machine cavity 26, the second Grouting Pipe 21 and are communicated with slurry casting machine cavity 26, and slurry casting machine cavity 26 is communicated with injected hole 24.The key position of whole filling system is a top slurry casting machine, require the second Grouting Pipe and being connected of slurry casting machine cavity to seal reliable, weld seam required closely when slurry casting machine cavity 26 was made, the crack phenomenon must not be arranged, each injected hole 24 below must arrange damping ring 25 and enter in the slurry casting machine cavity 26 with suitable obstruct earth, and injected hole 24 must be taked necessary seal approach before pressing pile construction.
Prefabricated Reinforced Concrete Square Pile of the present utility model can either improve bearing capacity of single pile, saves cost, can remedy the deficiencies such as the bored pile construction noise is large, efficient is low, environment pollution is serious again.

Claims (7)

1. Prefabricated Reinforced Concrete Square Pile, comprise joint stake (1) and lower joint stake (2), it is characterized in that, also comprise the first Grouting Pipe (11) and the second Grouting Pipe (21), described the first Grouting Pipe (11) is positioned at the center of described upper joint stake (1), described the second Grouting Pipe (21) is positioned at the center of described lower joint stake (2), and described the first Grouting Pipe (11) connects described upper joint stake (1), and described the second Grouting Pipe (21) connects described lower joint stake (2); The upper end of described lower joint stake (2) is connected with the lower end of described upper joint stake (1), the lower end of described lower joint stake (2) has pile top (23), described pile top (23) is provided with injected hole (24), and described the second Grouting Pipe (21) is communicated with described injected hole (24).
2. Prefabricated Reinforced Concrete Square Pile as claimed in claim 1 is characterized in that, the mouth of pipe of first Grouting Pipe (11) of described upper joint stake (1) upper surface is provided with blocking device (13).
3. Prefabricated Reinforced Concrete Square Pile as claimed in claim 1 is characterized in that, the below of described injected hole (24) is provided with damping ring (25).
4. Prefabricated Reinforced Concrete Square Pile as claimed in claim 1 is characterized in that, the lower end of described upper joint stake (1) is provided with the first pile cover (12), and the upper end of described lower joint stake (2) is provided with the second pile cover (22).
5. Prefabricated Reinforced Concrete Square Pile as claimed in claim 4 is characterized in that, described the first pile cover (12) and the second pile cover (22) are driving cap.
6. Prefabricated Reinforced Concrete Square Pile as claimed in claim 1 is characterized in that, the center, upper surface of described lower joint stake (2) is provided with groove (23).
7. Prefabricated Reinforced Concrete Square Pile as claimed in claim 1, it is characterized in that, the pile top (23) of described lower joint stake (2) locates to be provided with slurry casting machine cavity (26), described the second Grouting Pipe (21) is communicated with described slurry casting machine cavity (26), and described slurry casting machine cavity (26) is communicated with described injected hole (24).
CN 201220260960 2012-06-05 2012-06-05 Prefabricated reinforced concrete square pile Expired - Fee Related CN202672139U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220260960 CN202672139U (en) 2012-06-05 2012-06-05 Prefabricated reinforced concrete square pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220260960 CN202672139U (en) 2012-06-05 2012-06-05 Prefabricated reinforced concrete square pile

Publications (1)

Publication Number Publication Date
CN202672139U true CN202672139U (en) 2013-01-16

Family

ID=47493049

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220260960 Expired - Fee Related CN202672139U (en) 2012-06-05 2012-06-05 Prefabricated reinforced concrete square pile

Country Status (1)

Country Link
CN (1) CN202672139U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102888836A (en) * 2012-06-05 2013-01-23 江苏兴厦建筑安装有限公司 Prefabricated reinforced concrete square pile
CN103498467A (en) * 2013-10-14 2014-01-08 成军 High-bearing-capacity foundation pile and processing method for high-bearing-capacity foundation pile and foundation

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102888836A (en) * 2012-06-05 2013-01-23 江苏兴厦建筑安装有限公司 Prefabricated reinforced concrete square pile
CN102888836B (en) * 2012-06-05 2013-11-06 江苏兴厦建筑安装有限公司 Prefabricated reinforced concrete square pile
CN103498467A (en) * 2013-10-14 2014-01-08 成军 High-bearing-capacity foundation pile and processing method for high-bearing-capacity foundation pile and foundation
CN103498467B (en) * 2013-10-14 2015-07-22 江苏溧阳城建集团有限公司 High-bearing-capacity foundation pile and processing method for high-bearing-capacity foundation pile and foundation

Similar Documents

Publication Publication Date Title
CN202124865U (en) Quick plugging device for dewatering wellhead of sand-free cement pipe deep well
CN102383431B (en) Middle pick prestressed centrifugally pile tube pile-sinking device and pile sinking method thereof
CN204199335U (en) A kind of pressure release well reducing PHC tube pile construction soil compaction effect
CN201883435U (en) Preburied pipe pile grouting device
CN102852141A (en) Rock-socketed pipe pile foundation with pile core by concrete pouring and pile side by static pressure grouting and construction method for rock-socketed pipe pile foundation
CN102373705A (en) Pile sinking device and method for outer digging pre-stressed centrifugal pipe pile and square pile
CN102359112A (en) Method for bracing foundation pit by using steel box piles
CN203213101U (en) Embedding grouting combined pile
CN201704688U (en) Double sleeve for cast-in-situ bored pile capable of isolating pile-earth contact
CN103572770B (en) A kind of stake case hydraulic structures and construction method thereof
CN205857173U (en) A kind of Novel steel casing sheath applying bored concrete pile on the water
CN202672139U (en) Prefabricated reinforced concrete square pile
CN204941551U (en) A kind of subway station of Curve Pipe Jacking supporting and protection structure enlarging shield-tunneling construction
CN2828146Y (en) Flushing gas-lift pile sinking construction equipment
CN202124863U (en) Screw anchor excavated composite foundation
CN208472716U (en) Crack geology mortar leakage prevention drill-pouring pilework
CN201873992U (en) Steel pipe pile with different external diameters
CN206495205U (en) A kind of prefabricated PHC pile tubes
CN102758434B (en) Middle pick prestressed centrifugally pile tube pile-sinking device and pile sinking method thereof
CN102888836B (en) Prefabricated reinforced concrete square pile
CN206800379U (en) Grouting behind shaft or drift lining pre-stress hollow square pile
CN201474602U (en) Prestressed pipe pile perforated pile-driving machine
CN104895066B (en) The construction method of overlength churning strength core built pile
CN202099803U (en) Post grouting device of enlarged head of prestressed concrete tube pile
CN113718752A (en) Ground diaphragm wall composite grouting method and grouting structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130116