Drainage device falls in deep basal pit blind ditch sump pit Download PDFInfo
- Publication number
- CN202247922U CN202247922U CN 201120390762 CN201120390762U CN202247922U CN 202247922 U CN202247922 U CN 202247922U CN 201120390762 CN201120390762 CN 201120390762 CN 201120390762 U CN201120390762 U CN 201120390762U CN 202247922 U CN202247922 U CN 202247922U
- Authority
- CN
- China
- Prior art keywords
- basement
- wall
- french drain
- drain pipe
- post
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 17
- 239000004575 stone Substances 0.000 claims description 10
- 238000009434 installation Methods 0.000 claims description 7
- 238000000926 separation method Methods 0.000 claims description 5
- 239000004746 geotextile Substances 0.000 claims description 4
- 230000008595 infiltration Effects 0.000 claims description 4
- 238000001764 infiltration Methods 0.000 claims description 4
- 238000010276 construction Methods 0.000 abstract description 19
- 239000003673 groundwater Substances 0.000 abstract description 2
- 238000001556 precipitation Methods 0.000 abstract 1
- 238000007493 shaping process Methods 0.000 abstract 1
- 238000005266 casting Methods 0.000 description 5
- 238000005516 engineering process Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 239000011449 brick Substances 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 239000004927 clay Substances 0.000 description 1
- 238000004140 cleaning Methods 0.000 description 1
- 239000012141 concentrate Substances 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000000605 extraction Methods 0.000 description 1
- 239000004744 fabric Substances 0.000 description 1
- 238000007667 floating Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000000465 moulding Methods 0.000 description 1
- 239000002245 particle Substances 0.000 description 1
- 239000010865 sewage Substances 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- 239000002002 slurry Substances 0.000 description 1
Images
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
The utility model discloses a deep foundation pit blind ditch sump pit water collecting well drainage device, which comprises a catch basin arranged between the basement outer wall and the foundation pit support, and a blind ditch pipe arranged below the catch basin; comprises an inner bottom arranged outside the underground chamberBlind ditch pipes are arranged below the plates; a blind ditch pipe is arranged below the intercepting ditch and communicated with a blind ditch pipe below a bottom plate on the inner side of the basement outer wall, and a temporary water collecting well is arranged at the overlapped part of the blind ditch pipe on the inner side of the basement outer wall and the basement post-pouring zone; more than one drainage hole is arranged on the basement post-pouring belt. The utility model discloses the construction is simple, and the shaping is quick. When effectively reducing ground water level, still solved the unable actual conditions of precipitation construction in basement periphery, solved the work of the unnecessary water drainage of later stage, the basement outer wall post-cast strip construction of being convenient for has solved the unable problem of handling of traditional handicraft post-cast strip construction ponding.
Description
Technical field
the utility model relates to a kind of draining side device, particularly relates to a kind of deep foundation ditch french drain collecting well and falls dewatering installation, belongs to the construction drainage technical field.
Background technology
along with domestic each metropolis building density is increasing, each new building periphery all round all kinds ofly build, structure.New building construction period can supply to utilize site area also more and more littler, then large quantities of building foundation pit supporting all by there being the angle supporting to change vertical supporting into, foundation ditch retaining wall and outer wall of basement vertical distance are more and more littler.All below the groundwater table of place, during outer wall of basement and basement bottom board and the bearing platform construction, deep foundation ditch french drain collecting well falls most of basement bottom board absolute altitudes, drainage has become an important engineering measure during the deep foundation pit construction.
Summary of the invention
The purpose of
the utility model is; Provide a kind of do not need the later stage remove, fall draining economy, convenience and practical, also can effectively reduce the ater-casting cleaning and base plate early stage anti-floating pressure deep foundation ditch french drain collecting well dewatering installation falls, thereby overcome the deficiency of prior art.
The technical scheme of
the utility model: dewatering installation falls in a kind of deep foundation ditch french drain collecting well of the utility model, comprises being located between outer wall of basement and the pattern foundation pit supporting structure catchwater is set, and is provided with the french drain pipe below the catchwater; Comprise being located at and the french drain pipe is set below the inboard base plate of outer wall of basement; Be provided with the french drain pipe of french drain pipe below the inboard base plate of outer wall of basement below the catchwater and be communicated with, the french drain pipe inboard at outer wall of basement is provided with interim collecting well with the position that overlaps of basement post-pouring zone; On basement post-pouring zone, be provided with more than one spilled water hole.
In
aforementioned means, said french drain pipe comprises the gutter that is located in the trench, and gutter is provided with the infiltration hole; The gutter bottom is provided with rubble packed layer, fine-stone concrete bed course and back fill course from top to bottom successively; The gutter top is provided with rubble packed layer, geotextiles separation layer and fine-stone concrete bed course from the bottom to top successively.
compared with prior art, the utility model construction is simple, moulding is quick.In effective dewatering; The actual conditions that the basement periphery can't dewatering construction have also been solved; And solved the work that draining falls in later stage unnecessary water body to a great extent; Be convenient to the construction of outer wall of basement ater-casting, solved the problem that traditional handicraft ater-casting construction ponding can't be handled.Realize base plate cushion construction in advance, avoided the various matching program work holdup phenomenons that cause the multiple operation intersection to bring because of simultaneous construction.The difficulty of construction of basement bottom board reduces; The engineering time of base plate is shortened dramatically, saved construction and construction cost, what is more important; Guaranteed the safety of foundation ditch retaining wall; The shortening in basement construction cycle when guaranteeing whole foundation ditch safety, has also guaranteed neighboring buildings and safety of environment.
Description of drawings
Fig. 1 is the structural representation of the utility model;
Fig. 2 is the structural representation of french drain pipe;
Fig. 3 is the structural representation of catchwater.
Being labeled as in
accompanying drawing: 1-outer wall of basement, 2-pattern foundation pit supporting structure, 3-catchwater, 4-geotextiles separation layer; The 5-spilled water hole, 6-french drain pipe, 7-interim collecting well, 8-basement post-pouring zone; 9-trench, 10-gutter, the 11-hole of seeping water; The 12-back fill course, 13-fine-stone concrete bed course, 14-rubble packed layer.
The specific embodiment
are done further to specify to the utility model below in conjunction with accompanying drawing and embodiment, but not as any restriction to the utility model.
embodiment.
water discharge method that falls that the utility model adopted is between outer wall of basement 1 and pattern foundation pit supporting structure 2, catchwater 3 to be set, and french drain pipe 6 is set below catchwater 3; Below the base plate of outer wall of basement 1 inboard, french drain pipe 6 is set; French drain pipe 6 intercommunications of the french drain pipe 6 of outer wall of basement 1 inboard below catchwater 3; With the position that overlaps of basement post-pouring zone 8 interim collecting well 7 is set at outer wall of basement 1 inboard french drain pipe 6; Along basement post-pouring zone 8 spilled water hole 5 is set at interval; The outer ponding of basement is introduced interim collecting well 7 through catchwater 3 and french drain pipe 6; The outer ponding of basement is introduced interim collecting well 7 through spilled water hole 5, will concentrate on interim collecting well 7 ponding through water pump and efflux.
said french drain pipe 6 is as shown in Figure 2, and french drain pipe 6 is the gutters 10 that are embedded in 9 li of trenches, and gutter 10 is provided with infiltration hole 11; The bottom of trench 9 is a back fill course 12; It above the back fill course 12 fine-stone concrete bed course 13; Be rubble packed layer 14 above the fine-stone concrete bed course 13, gutter 10 is placed on above the rubble packed layer 14, and then with rubble packed layer 14 gutter 10 is covered; The worker's cloth separation layer 4 that spreads a layer of clay above the rubble packed layer 14 is a fine-stone concrete bed course 13 topmost.Said interim collecting well 7 adopts brick building, and water silt particle slurry is plastered in the outside.
Structural representation such as Fig. 1 of dewatering installation~shown in Figure 3 fall in the deep foundation ditch french drain collecting well of the utility model that
make up according to the method described above; This device comprises being located between outer wall of basement 1 and the pattern foundation pit supporting structure 2 catchwater 3 is set, and is provided with french drain pipe 6 below the catchwater 3; Comprise being located at and french drain pipe 6 is set below the outer wall of basement 1 inboard base plate; Be provided with the french drain pipe 6 of french drain pipe 6 below outer wall of basement 1 inboard base plate below the catchwater 3 and be communicated with, be provided with interim collecting well 7 with the position that overlaps of basement post-pouring zone 8 at outer wall of basement 1 inboard french drain pipe 6; On basement post-pouring zone 8, be provided with more than one spilled water hole 5.Said french drain pipe 6 is as shown in Figure 2, and french drain pipe 6 comprises the gutter 10 that is located in the trench 9, and gutter 10 is provided with infiltration hole 11; Gutter 10 bottoms are provided with rubble packed layer 14, fine-stone concrete bed course 13 and back fill course 12 from top to bottom successively; Gutter 10 tops are provided with rubble packed layer 14, geotextiles separation layer 4 and fine-stone concrete bed course 13 from the bottom to top successively.
are when specifically constructing; Can before constructing basement bottom board, carry out the construction of the utility model earlier; A circle french drain pipe 6 is constructed in the inboard and the outside at the outer wall of basement 1 of drawing requirement respectively, and the french drain pipe 6 in the outside in the basement is communicated with.Expectation is provided with the position of ater-casting and constructs interim collecting well 7, and then constructs basement bottom board and exterior wall.The principle of the utility model is: the ponding in the outer wall of basement outside is concentrated the french drain pipe 6 that flows into the basement bottom board bottom through catchwater 3; Ponding in the basement is concentrated through spilled water hole 5 and is flowed into base plate bottom french drain pipe 6; Ignorant of the economics sewer pipe 6 causes the interim collecting well 7 at basement post-pouring zone 8 positions then; Use water pump to extract ponding out and efflux, after main body construction finishes, take to build the interim collecting well of shutoff with the technology of constructing in the ater-casting.The collecting well material adopts by on-site actual situations.The water body of collecting well can adopt submersible sewage pump extraction foundation ditch and efflux.
Claims (2)
1. dewatering installation falls in a deep foundation ditch french drain collecting well, it is characterized in that: comprise being located between outer wall of basement (1) and the pattern foundation pit supporting structure (2) catchwater (3) is set, be provided with french drain pipe (6) below the catchwater (3); Comprise being located at and french drain pipe (6) is set below the inboard base plate of outer wall of basement (1); Be provided with the french drain pipe (6) of french drain pipe (6) below the inboard base plate of outer wall of basement (1) below the catchwater (3) and be communicated with, the french drain pipe (6) inboard at outer wall of basement (1) is provided with interim collecting well (7) with the position that overlaps of basement post-pouring zone (8); On basement post-pouring zone (8), be provided with more than one spilled water hole (5).
2. dewatering installation falls in deep foundation ditch french drain collecting well according to claim 1, it is characterized in that: said french drain pipe (6) comprises the gutter (10) that is located in the trench (9), and gutter (10) is provided with infiltration hole (11); Gutter (10) bottom is provided with rubble packed layer (14), fine-stone concrete bed course (13) and back fill course (12) from top to bottom successively; Gutter (10) top is provided with rubble packed layer (14), geotextiles separation layer (4) and fine-stone concrete bed course (13) from the bottom to top successively.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201120390762 CN202247922U (en) | 2011-01-07 | 2011-10-14 | Drainage device falls in deep basal pit blind ditch sump pit |
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201120003849 | 2011-01-07 | ||
CN201120003849.6 | 2011-01-07 | ||
CN 201120390762 CN202247922U (en) | 2011-01-07 | 2011-10-14 | Drainage device falls in deep basal pit blind ditch sump pit |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202247922U true CN202247922U (en) | 2012-05-30 |
Family
ID=46109184
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201120390762 Expired - Fee Related CN202247922U (en) | 2011-01-07 | 2011-10-14 | Drainage device falls in deep basal pit blind ditch sump pit |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202247922U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103669418A (en) * | 2013-12-25 | 2014-03-26 | 中建六局土木工程有限公司 | Novel maintenance and construction method for drainage settlement post-pouring belt |
CN103726504A (en) * | 2014-01-23 | 2014-04-16 | 北京锄禾环保技术有限公司 | Foundation structure for reducing surface water of impermeable layer base plane |
CN104314090A (en) * | 2014-08-29 | 2015-01-28 | 中铁八局集团建筑工程有限公司 | Deep foundation pit bedrock drainage culvert and drainage system and drainage construction method thereof |
-
2011
- 2011-10-14 CN CN 201120390762 patent/CN202247922U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103669418A (en) * | 2013-12-25 | 2014-03-26 | 中建六局土木工程有限公司 | Novel maintenance and construction method for drainage settlement post-pouring belt |
CN103669418B (en) * | 2013-12-25 | 2016-05-18 | 中建六局土木工程有限公司 | A kind of hydrophobic place pouring after settlement maintenance construction method |
CN103726504A (en) * | 2014-01-23 | 2014-04-16 | 北京锄禾环保技术有限公司 | Foundation structure for reducing surface water of impermeable layer base plane |
CN104314090A (en) * | 2014-08-29 | 2015-01-28 | 中铁八局集团建筑工程有限公司 | Deep foundation pit bedrock drainage culvert and drainage system and drainage construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102116033B (en) | Method and device for dewatering and draining water collecting well of blind drain of deep foundation pit | |
CN203947484U (en) | Foundation pit drainage and circulating water utilization system | |
CN103046565B (en) | Draining method for ultra-deep batholith deep foundation pit | |
CN102418347B (en) | Drainage construction method for blind drain and sump wells in deep foundation pit | |
CN103510528A (en) | Blind trench water discharging structure used for underground structure up-floating prevention | |
CN102433886A (en) | Construction method for adding water lowering well in water collecting well | |
CN206298900U (en) | A kind of diaphram wall built-in type steel encloses purlin plug system | |
CN103741715A (en) | Novel waterproof hydrophobic construction method for basement | |
CN110847327A (en) | Waterproof and drainage construction method for large-area basement roof | |
CN105155562A (en) | Construction method for bottom sealing treatment of spring openings of deep foundation pit | |
CN202247922U (en) | Drainage device falls in deep basal pit blind ditch sump pit | |
CN104234089B (en) | The construction method that a kind of basement guarded drainage combines | |
CN109723071B (en) | Construction method of double-layer steel drum drainage system built in basement floor post-cast strip | |
CN202202335U (en) | Flow guiding and water draining structure in deep foundation pit | |
CN113445525A (en) | Method and structure for controlling water pressure of bottom plate in construction of bottom plate of foundation pit of deep foundation pit | |
CN105569063A (en) | Collecting and utilizing method for underground water on periphery of basement retaining wall and water collecting structure | |
CN110093965A (en) | A kind of water discharge method of construction site | |
CN210712963U (en) | Drainage structure of basement bottom plate post-cast strip | |
CN201679008U (en) | Rigid water drainage device for foundation pit | |
CN204447424U (en) | A kind of architectural engineering groundwater treatment and reclamation set | |
CN110258660A (en) | The manufacture craft and shut-in well technique of the decompression drainage sump of basement anti-floating | |
CN205421500U (en) | Basement french drain is dredged and is fallen drainage device | |
CN214656351U (en) | Foundation pit construction water level reduces structure | |
CN101967834A (en) | Pulp concentration pool underground base structure with anti-floating function | |
CN211898587U (en) | Rear-mounted thin-wall steel pipe water draining device for large bottom plate anti-floating |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20120530 Termination date: 20151014 |
|
EXPY | Termination of patent right or utility model |