CN102433886A - Construction method for adding water lowering well in water collecting well - Google Patents

Construction method for adding water lowering well in water collecting well Download PDF

Info

Publication number
CN102433886A
CN102433886A CN2011102952532A CN201110295253A CN102433886A CN 102433886 A CN102433886 A CN 102433886A CN 2011102952532 A CN2011102952532 A CN 2011102952532A CN 201110295253 A CN201110295253 A CN 201110295253A CN 102433886 A CN102433886 A CN 102433886A
Authority
CN
China
Prior art keywords
steel pipe
round steel
water
collecting well
well
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011102952532A
Other languages
Chinese (zh)
Inventor
李呈蔚
冯云
王凯
刁晓翔
沈怀宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN HOUSING GROUP CONSTRUCTION ENGINEERING CONTRACTION Co Ltd
Original Assignee
TIANJIN HOUSING GROUP CONSTRUCTION ENGINEERING CONTRACTION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN HOUSING GROUP CONSTRUCTION ENGINEERING CONTRACTION Co Ltd filed Critical TIANJIN HOUSING GROUP CONSTRUCTION ENGINEERING CONTRACTION Co Ltd
Priority to CN2011102952532A priority Critical patent/CN102433886A/en
Publication of CN102433886A publication Critical patent/CN102433886A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The invention discloses a construction method for adding a water lowering well in a water collecting well, which comprises the following steps of: driving a prepared round steel pipe water lowering well structure into a bottom wall of the water collecting well until the scale height required is met; removing the earth in the round steel pipe; refilling gravels on the bottom of the round steel pipe to form a water filtering layer; placing a water pump in the round steel pipe for pumping water according to water level situation; paving in sequence a cushion layer, a waterproof layer and a waterproof protection layer on a side wall and a bottom wall of the water collecting well for construction recovery; binding steel bars on the side wall and the bottom wall of the water collecting well out of the waterproof protection layer, and pouring concretes on the bottom wall and the side wall of the water collecting well; and blocking the top of the round steel pipe. By means of the construction method provided by the invention, the water lowering well has the advantages of simple and convenient construction method, fast construction speed, low cost and high intensity, is capable of effectively solving the problem that the water cannot be timely discharged to the specified depth below a bottom plate on the condition that a water stop curtain is slightly cracked to leak the water to damage the waterproof layer of the water collecting well nearby and satisfying the basement construction requirements, and is simple in structure.

Description

Increase precipitation well construction method in a kind of collecting well
Technical field
The present invention relates to a kind of job practices of precipitation well, relate in particular to the job practices that increases the precipitation well in a kind of collecting well.
Background technology
Along with the development of urban construction, highrise building, civil air defense constructions and installations and subway engineering emerge in multitude.The success or not of pattern foundation pit supporting structure directly influences the benefit and the success or failure of engineering construction.Underground water is as the tax dis environment factor of geotechnical body, and is disadvantageous often to the influence of base pit engineering.For the higher area of groundwater table, need large-area provisional precipitation and sealing in the excavation of foundation pit, if improper, be prone to cause accidents such as foundation ditch caves in, surface settlement to groundwater treatment in the foundation ditch.In the shoveling and basement construction of deep-foundation pit engineering, guarantee the construction under " doing " state.For addressing this problem, the way of taking usually has: sealing, precipitation and draining.Sealing adopts the form of water-stop curtain, and purpose is the infiltration that stops the foundation ditch secondary water.But the seepage that water-stop curtain in reality, often occurs; The internal cause of analyzing water stopping curtain seepage mainly is the defective of itself; External cause mainly is that the hydrogeological conditions in place is bad or because the excavation of foundation pit degree of depth is big, flowing pressure on every side increases relatively, causes water-stop curtain deflection or sidesway.Water-stop curtain is that seepage is caused in slight crack in construction; After making the collecting well that closes on the water-stop curtain place finish bed course, waterproof and fish tail and waterproof layer; Find that water-stop curtain leaks here, cause groundwater table to go up, collecting well fish tail and waterproof layer, waterproof stringcourse are split.To this problem, there is not effective treating method at present.
Summary of the invention
The objective of the invention is to overcome the deficiency of prior art; Provide a kind of simple in structure; Can effectively solve and leak at water-stop curtain; In time water is discharged to the base plate following provisions degree of depth under the ruined situation of the waterproofing course of the collecting well that closes on, has satisfied the interior job practices that increases the precipitation well of collecting well of basement construction requirement.
Increase precipitation well construction method in a kind of collecting well of the present invention, it may further comprise the steps:
(1) on the sidewall of the collecting well that digs and diapire, lays bed course, waterproofing course and fish tail and waterproof layer successively, as groundwater table occurs and go up described bed course, waterproofing course and waterproofing protection stringcourse are split, then remove bed course, waterproofing course and fish tail and waterproof layer;
(2) the round steel pipe precipitation well construction for preparing is squeezed in the diapire of described collecting well until meeting the requirements of absolute altitude; Described round steel pipe precipitation well construction comprises round steel pipe; The compartment of terrain is welded with upper track seal ring and following road seal ring on described round steel pipe outer wall; On the predetermined said round steel pipe of imbedding part in the soil, have a plurality of holes, swathed gauze wire cloth being provided with on the porose round steel pipe outer wall, described road seal ring down is positioned at the diapire position of collecting well;
(3) soil in the described round steel pipe is removed;
(4) at described round steel pipe pipe inner bottom part backfill rubble as the drainage layer;
(5) water pump being put to the round steel pipe the observing water level situation draws water;
(6) on the sidewall of described collecting well and diapire, lay bed course, waterproofing course and fish tail and waterproof layer successively and recover construction;
(7) reinforcing bar of colligation collecting well sidewall and diapire outside described fish tail and waterproof layer is built the concrete of collecting well diapire and sidewall;
(8) the described round steel pipe of shutoff top.
Adopt the beneficial effect of the inventive method to be: job practices is easy, speed of application is fast, cost is low, intensity is high, can effectively solve the slight crack of water-stop curtain causes seepage; Make under the ruined situation of waterproofing course of the collecting well that closes on and in time water is discharged to the base plate following provisions degree of depth, satisfied basement construction requirement and simple in structure.
Description of drawings
Fig. 1 adopts the constructing structure sketch map that increases precipitation well construction method in a kind of collecting well of the present invention;
Fig. 2 is the bottom wall portion structure for amplifying sketch map of constructing structure shown in Figure 1.
The specific embodiment
Describe the present invention below in conjunction with accompanying drawing and specific embodiment.
Shown in accompanying drawing, increase precipitation well construction method in a kind of collecting well of the present invention; It may further comprise the steps: bed course 6, waterproofing course 8 and fish tail and waterproof layer 7 are laid successively in (1) on the sidewall of the collecting well that digs and diapire; As groundwater table occurs and go up described bed course, waterproofing course and waterproofing protection stringcourse are split, then remove bed course, waterproofing course and fish tail and waterproof layer; (2) the round steel pipe precipitation well construction for preparing is squeezed in the diapire of described collecting well until meeting the requirements of absolute altitude; Described round steel pipe precipitation well construction comprises round steel pipe 1; The compartment of terrain is welded with upper track seal ring 2-1 and following road seal ring 2-2 on described round steel pipe outer wall; On the predetermined said round steel pipe of imbedding part in the soil, have a plurality of holes, swathed gauze wire cloth being provided with on the porose round steel pipe outer wall, described road seal ring down is positioned at the diapire position of collecting well; (3) soil in the described round steel pipe is removed; (4) at described round steel pipe pipe inner bottom part backfill rubble as drainage layer 4; (5) water pump being put to the round steel pipe the observing water level situation draws water; (6) on the sidewall of described collecting well and diapire, lay bed course, waterproofing course and fish tail and waterproof layer successively and recover construction; (7) reinforcing bar of colligation collecting well sidewall and diapire outside described fish tail and waterproof layer is built the concrete of collecting well diapire and sidewall; (8) the described round steel pipe of shutoff top.Shutoff can be adopted steel plate 9.
Preferred described drainage layer presses gradation with rubble and level is arranged once construction completion, and thickness is 250mm-350mm.Filtration through the drainage layer is unimpededly taken away the current that infilter by water pump, prevented to take place the stifled phenomenon of becoming silted up.
The bore dia in preferred described a plurality of holes is 16-23mm.Spacing between two adjacent holes is 45-55mm, and current are entered in the round steel pipe precipitation well evenly.
Embodiment 1
(1) on the sidewall of the collecting well that digs and diapire, lays bed course 6, waterproofing course 8 and fish tail and waterproof layer 7 successively, as groundwater table occurs and go up described bed course, waterproofing course and waterproofing protection stringcourse are split, then remove bed course, waterproofing course and fish tail and waterproof layer; (2) the round steel pipe precipitation well construction for preparing is squeezed in the diapire of described collecting well until meeting the requirements of absolute altitude; Described round steel pipe precipitation well construction comprises round steel pipe 1; The compartment of terrain is welded with upper track seal ring 2-1 and following road seal ring 2-2 on described round steel pipe outer wall; On the predetermined said round steel pipe of imbedding part in the soil, have a plurality of holes, swathed gauze wire cloth being provided with on the porose round steel pipe outer wall, described road seal ring down is positioned at the diapire position of collecting well; The diameter in described hole is 20mm, and the spacing between two adjacent holes is 50mm; (3) soil in the described round steel pipe is removed; (4) at the thick rubble of described round steel pipe pipe inner bottom part backfill 250mm as drainage layer 4; (5) water pump being put to the round steel pipe the observing water level situation draws water; (6) on the sidewall of described collecting well and diapire, lay bed course, waterproofing course and fish tail and waterproof layer successively and recover construction; (7) reinforcing bar of colligation collecting well sidewall and diapire outside described fish tail and waterproof layer is built the concrete of collecting well diapire and sidewall; (8) the described round steel pipe of shutoff top.
The effect of implementing: job practices is easy, speed of application is fast, cost is low, drainage system is solid and reliable, safety factor is high. and can effectively solve the slight crack of water-stop curtain and cause seepage; Make under the ruined situation of waterproofing course of the collecting well that closes on and in time water is discharged to the base plate following provisions degree of depth, satisfied basement construction requirement and simple in structure.And the filtration through the drainage layer that is provided with makes and at the uniform velocity infilters the current that come and unimpededly taken away by water pump in drainage procedure, has prevented to take place the stifled phenomenon of becoming silted up.
Embodiment 2
(1) on the sidewall of the collecting well that digs and diapire, lays bed course 6, waterproofing course 8 and fish tail and waterproof layer 7 successively, as groundwater table occurs and go up described bed course, waterproofing course and waterproofing protection stringcourse are split, then remove bed course, waterproofing course and fish tail and waterproof layer; (2) the round steel pipe precipitation well construction for preparing is squeezed in the diapire of described collecting well until meeting the requirements of absolute altitude; Described round steel pipe precipitation well construction comprises round steel pipe 1; The compartment of terrain is welded with upper track seal ring 2-1 and following road seal ring 2-2 on described round steel pipe outer wall; On the predetermined said round steel pipe of imbedding part in the soil, have a plurality of holes, swathed gauze wire cloth being provided with on the porose round steel pipe outer wall, described road seal ring down is positioned at the diapire position of collecting well; The diameter in described hole is 16mm, and the spacing between two adjacent holes is 55mm; (3) soil in the described round steel pipe is removed; (4) at the thick rubble of described round steel pipe pipe inner bottom part backfill 350mm as drainage layer 4; (5) water pump being put to the round steel pipe the observing water level situation draws water; (6) on the sidewall of described collecting well and diapire, lay bed course, waterproofing course and fish tail and waterproof layer successively and recover construction; (7) reinforcing bar of colligation collecting well sidewall and diapire outside described fish tail and waterproof layer is built the concrete of collecting well diapire and sidewall; (8) the described round steel pipe of shutoff top.
The effect of implementing: job practices is easy, speed of application is fast, cost is low, drainage system is solid and reliable, safety factor is high. and can effectively solve the slight crack of water-stop curtain and cause seepage; Make under the ruined situation of waterproofing course of the collecting well that closes on and in time water is discharged to the base plate following provisions degree of depth, satisfied basement construction requirement and simple in structure.And the filtration through the drainage layer that is provided with makes and at the uniform velocity infilters the current that come and unimpededly taken away by water pump in drainage procedure, has prevented to take place the stifled phenomenon of becoming silted up.
Embodiment 3
(1) on the sidewall of the collecting well that digs and diapire, lays bed course 6, waterproofing course 8 and fish tail and waterproof layer 7 successively, as groundwater table occurs and go up described bed course, waterproofing course and waterproofing protection stringcourse are split, then remove bed course, waterproofing course and fish tail and waterproof layer; (2) the round steel pipe precipitation well construction for preparing is squeezed in the diapire of described collecting well until meeting the requirements of absolute altitude; Described round steel pipe precipitation well construction comprises round steel pipe 1; The compartment of terrain is welded with upper track seal ring 2-1 and following road seal ring 2-2 on described round steel pipe outer wall; On the predetermined said round steel pipe of imbedding part in the soil, have a plurality of holes, swathed gauze wire cloth being provided with on the porose round steel pipe outer wall, described road seal ring down is positioned at the diapire position of collecting well; The diameter in described hole is 23mm, and the spacing between two adjacent holes is 45mm; (3) soil in the described round steel pipe is removed; (4) at the thick rubble of described round steel pipe pipe inner bottom part backfill 300mm as drainage layer 4; (5) water pump being put to the round steel pipe the observing water level situation draws water; (6) on the sidewall of described collecting well and diapire, lay bed course, waterproofing course and fish tail and waterproof layer successively and recover construction; (7) reinforcing bar of colligation collecting well sidewall and diapire outside described fish tail and waterproof layer is built the concrete of collecting well diapire and sidewall; (8) the described round steel pipe of shutoff top.
The effect of implementing: job practices is easy, speed of application is fast, cost is low, drainage system is solid and reliable, safety factor is high. and can effectively solve the slight crack of water-stop curtain and cause seepage; Make under the ruined situation of waterproofing course of the collecting well that closes on and in time water is discharged to the base plate following provisions degree of depth, satisfied basement construction requirement and simple in structure.And the filtration through the drainage layer that is provided with makes and at the uniform velocity infilters the current that come and unimpededly taken away by water pump in drainage procedure, has prevented to take place the stifled phenomenon of becoming silted up.

Claims (4)

1. increase precipitation well construction method in a collecting well, it is characterized in that it may further comprise the steps:
(1) on the sidewall of the collecting well that digs and diapire, lays bed course, waterproofing course and fish tail and waterproof layer successively, as groundwater table occurs and go up described bed course, waterproofing course and waterproofing protection stringcourse are split, then remove bed course, waterproofing course and fish tail and waterproof layer;
(2) the round steel pipe precipitation well construction for preparing is squeezed in the diapire of described collecting well until meeting the requirements of absolute altitude; Described round steel pipe precipitation well construction comprises round steel pipe; The compartment of terrain is welded with upper track seal ring and following road seal ring on described round steel pipe outer wall; On the predetermined said round steel pipe of imbedding part in the soil, have a plurality of holes, swathed gauze wire cloth being provided with on the porose round steel pipe outer wall, described road seal ring down is positioned at the diapire position of collecting well;
(3) soil in the described round steel pipe is removed;
(4) at described round steel pipe pipe inner bottom part backfill rubble as the drainage layer;
(5) water pump being put to the round steel pipe the observing water level situation draws water;
(6) on the sidewall of described collecting well and diapire, lay bed course, waterproofing course and fish tail and waterproof layer successively and recover construction;
(7) reinforcing bar of colligation collecting well sidewall and diapire outside described fish tail and waterproof layer is built the concrete of collecting well diapire and sidewall;
(8) the described round steel pipe of shutoff top.
2. increase precipitation well construction method in the collecting well according to claim 1, it is characterized in that: the thickness of described drainage layer is 250mm-350mm.
3. increase precipitation well construction method in the collecting well according to claim 1 and 2, it is characterized in that: the bore dia in described a plurality of holes is 16-23mm.
4. increase precipitation well construction method in the collecting well according to claim 3, it is characterized in that: the spacing between two adjacent holes is 45-55mm.
CN2011102952532A 2011-09-27 2011-09-27 Construction method for adding water lowering well in water collecting well Pending CN102433886A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011102952532A CN102433886A (en) 2011-09-27 2011-09-27 Construction method for adding water lowering well in water collecting well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011102952532A CN102433886A (en) 2011-09-27 2011-09-27 Construction method for adding water lowering well in water collecting well

Publications (1)

Publication Number Publication Date
CN102433886A true CN102433886A (en) 2012-05-02

Family

ID=45982216

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011102952532A Pending CN102433886A (en) 2011-09-27 2011-09-27 Construction method for adding water lowering well in water collecting well

Country Status (1)

Country Link
CN (1) CN102433886A (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102877420A (en) * 2012-11-06 2013-01-16 中铁二十二局哈尔滨铁路建设集团有限责任公司 Construction method of large tube well fixed point precipitation, sealing bottom free concrete and steel sheet pile cofferdam deepwater bearing platform
CN103061350A (en) * 2013-01-31 2013-04-24 中国三冶集团有限公司建筑安装工程公司 Deep foundation pit rigid water drainage platform device and using method
CN103061351A (en) * 2012-12-24 2013-04-24 广西华蓝设计(集团)有限公司 Device for preventing basement bottom floor from heaving and water permeating
CN104452786A (en) * 2014-11-14 2015-03-25 武汉一冶建筑安装工程有限责任公司 Deep foundation pit elevator shaft sump dewatering construction method
CN104631477A (en) * 2014-12-23 2015-05-20 中建四局第六建筑工程有限公司 Device installing and plugging method for lowering water in foundation pit
CN104805855A (en) * 2015-02-25 2015-07-29 成都格瑞思文化传播有限公司 Drainage device
CN104988936A (en) * 2015-07-07 2015-10-21 苏州汇诚智造工业设计有限公司 Automatic drain system for bottom plate construction or reinforcement construction of stilling pool and manufacturing and use method thereof
CN105544574A (en) * 2015-12-04 2016-05-04 中冶集团武汉勘察研究院有限公司 Isolation processing method of polluted groundwater
CN106638641A (en) * 2016-12-16 2017-05-10 中建四局第建筑工程有限公司 Water well structure for foundation pit dewatering and construction method thereof
CN106638642A (en) * 2017-02-21 2017-05-10 潍坊市宏源防水材料有限公司 Underground building pit body waterproof construction precipitation treating method
CN106894431A (en) * 2017-02-21 2017-06-27 潍坊市宏源防水材料有限公司 Hypogee hole body waterproof construction precipitation processing method under a kind of water resource enriched environment
CN109555140A (en) * 2018-12-03 2019-04-02 中国建筑股份有限公司 Foundation pit and Tunnel Base spring pump drainage method for blocking and device
CN110820778A (en) * 2019-10-25 2020-02-21 陕西神州实业有限公司 Local precipitation construction method for foundation pit

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60246914A (en) * 1984-05-18 1985-12-06 Ohbayashigumi Ltd Method of draining water in ground under excavation
CN101250879A (en) * 2008-04-01 2008-08-27 中国第一冶金建设有限责任公司 Method for processing bottom solum trickleing water of deep building pit
CN101634139A (en) * 2009-07-30 2010-01-27 广东省第一建筑工程有限公司 Dynamic compaction method for backfill foundation with drainage layer
CN102051885A (en) * 2009-10-27 2011-05-11 江苏建业建设集团有限公司 Process for absorbing and discharging water under deep foundation concrete

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60246914A (en) * 1984-05-18 1985-12-06 Ohbayashigumi Ltd Method of draining water in ground under excavation
CN101250879A (en) * 2008-04-01 2008-08-27 中国第一冶金建设有限责任公司 Method for processing bottom solum trickleing water of deep building pit
CN101634139A (en) * 2009-07-30 2010-01-27 广东省第一建筑工程有限公司 Dynamic compaction method for backfill foundation with drainage layer
CN102051885A (en) * 2009-10-27 2011-05-11 江苏建业建设集团有限公司 Process for absorbing and discharging water under deep foundation concrete

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘文致: "用砼滤管井点法大面积降低地下水位", 《施工技术》 *
北京土木建筑学会: "《地基与基础工程现场施工处理方法与技巧》", 31 May 2009, 机械工业出版社 *

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102877420A (en) * 2012-11-06 2013-01-16 中铁二十二局哈尔滨铁路建设集团有限责任公司 Construction method of large tube well fixed point precipitation, sealing bottom free concrete and steel sheet pile cofferdam deepwater bearing platform
CN103061351A (en) * 2012-12-24 2013-04-24 广西华蓝设计(集团)有限公司 Device for preventing basement bottom floor from heaving and water permeating
CN103061350A (en) * 2013-01-31 2013-04-24 中国三冶集团有限公司建筑安装工程公司 Deep foundation pit rigid water drainage platform device and using method
CN104452786A (en) * 2014-11-14 2015-03-25 武汉一冶建筑安装工程有限责任公司 Deep foundation pit elevator shaft sump dewatering construction method
CN104631477A (en) * 2014-12-23 2015-05-20 中建四局第六建筑工程有限公司 Device installing and plugging method for lowering water in foundation pit
CN104805855A (en) * 2015-02-25 2015-07-29 成都格瑞思文化传播有限公司 Drainage device
CN104988936A (en) * 2015-07-07 2015-10-21 苏州汇诚智造工业设计有限公司 Automatic drain system for bottom plate construction or reinforcement construction of stilling pool and manufacturing and use method thereof
CN104988936B (en) * 2015-07-07 2017-01-18 郭广军 Automatic drain system for bottom plate construction or reinforcement construction of stilling pool
CN106480894A (en) * 2015-07-07 2017-03-08 苏州汇诚智造工业设计有限公司 Force reduction pool bottom construction or the manufacture method of strengthening construction automatic drain system
CN106480894B (en) * 2015-07-07 2018-11-06 泗洪仁益自来水有限公司 The manufacturing method of force reduction pool bottom construction or strengthening construction automatic drain system
CN105544574B (en) * 2015-12-04 2018-10-02 中冶集团武汉勘察研究院有限公司 A kind of isolation processing method of polluted underground water
CN105544574A (en) * 2015-12-04 2016-05-04 中冶集团武汉勘察研究院有限公司 Isolation processing method of polluted groundwater
CN106638641A (en) * 2016-12-16 2017-05-10 中建四局第建筑工程有限公司 Water well structure for foundation pit dewatering and construction method thereof
CN106638641B (en) * 2016-12-16 2018-11-09 中建四局第一建筑工程有限公司 Base pit dewatering well structure and its construction method
CN106894431A (en) * 2017-02-21 2017-06-27 潍坊市宏源防水材料有限公司 Hypogee hole body waterproof construction precipitation processing method under a kind of water resource enriched environment
CN106638642A (en) * 2017-02-21 2017-05-10 潍坊市宏源防水材料有限公司 Underground building pit body waterproof construction precipitation treating method
CN106638642B (en) * 2017-02-21 2019-08-27 宏源防水科技集团有限公司 A kind of hypogee pit body waterproof construction precipitation processing method
CN106894431B (en) * 2017-02-21 2019-08-27 宏源防水科技集团有限公司 Hypogee pit body waterproof construction precipitation processing method under a kind of water resource enriched environment
CN109555140A (en) * 2018-12-03 2019-04-02 中国建筑股份有限公司 Foundation pit and Tunnel Base spring pump drainage method for blocking and device
CN110820778A (en) * 2019-10-25 2020-02-21 陕西神州实业有限公司 Local precipitation construction method for foundation pit

Similar Documents

Publication Publication Date Title
CN102433886A (en) Construction method for adding water lowering well in water collecting well
CN105201002B (en) A kind of underground structure oozes drainage system and its construction method
CN102418347B (en) Drainage construction method for blind drain and sump wells in deep foundation pit
CN103031837B (en) Well-points dewatering combined stack-load ground preloading deep soft soil foundation method
CN103741714A (en) Construction method for full cover-excavation reverse method of underground engineering
CN206706792U (en) Deep foundation pit precipitation well construction
CN103046565B (en) Draining method for ultra-deep batholith deep foundation pit
CN207512745U (en) A kind of caisson device and its foundation pit structure
CN109797769B (en) Collapsible loess area underground comprehensive pipe gallery foundation structure and construction method thereof
LU500273B1 (en) New comprehensive dewatering and drainage method and drainage device for mudstone subway station
CN108661088A (en) A kind of permanent drainage and step-down anti-floating construction method of basement
CN110029690B (en) Percolate leakage detection and collection structure and construction method thereof
CN112252336A (en) Construction method for backfilling foundation trench of premixed fluidized solidified soil
CN104847010A (en) Urban miniature underground reservoir and construction method
CN110318410A (en) A kind of deep basal pit chance artesian water is prominent to gush decompression drought stress construction method
CN108677982A (en) Complex geological condition foundation pit substrate excavates Tunnel gushing treatment method
CN105544622A (en) Floating resisting device, and seepage insulation device and drainage path checking device thereof for underground building
CN104652495B (en) Internal support of foundation pit column and base plate node waterproof construction technology
CN202247920U (en) Construction structure for water drainage of blind ditch and water collecting wells in deep foundation pit
CN107100206A (en) A kind of prevention and controls of basement leakage
CN107700521B (en) Building foundation reinforcement underpinning pier and construction method thereof
CN109577337A (en) The construction method of deep foundation ditch of flowing line
CN109881691B (en) Method for processing foundation pit inner base exploration hole piping in deep foundation pit excavation process
CN210140850U (en) Leachate collection and drainage guide structure
CN104696011B (en) The improved method of underground mine midplane drainage system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20120502