CN202108296U - Assembled segmental water tank tower - Google Patents

Assembled segmental water tank tower Download PDF

Info

Publication number
CN202108296U
CN202108296U CN201120154194.2U CN201120154194U CN202108296U CN 202108296 U CN202108296 U CN 202108296U CN 201120154194 U CN201120154194 U CN 201120154194U CN 202108296 U CN202108296 U CN 202108296U
Authority
CN
China
Prior art keywords
tower
water tank
assembled
section
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201120154194.2U
Other languages
Chinese (zh)
Inventor
梁超
聂江华
刘玉波
宁明阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Engineering Co Ltd of CTCE Group
Original Assignee
First Engineering Co Ltd of CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Engineering Co Ltd of CTCE Group filed Critical First Engineering Co Ltd of CTCE Group
Priority to CN201120154194.2U priority Critical patent/CN202108296U/en
Application granted granted Critical
Publication of CN202108296U publication Critical patent/CN202108296U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A20/00Water conservation; Efficient water supply; Efficient water use

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本实用新型公开了一种拼装节式水箱塔架,其特征是在底部混凝土基础中预埋钢板组合件构成塔架基础,设置在塔架基础上的塔架本体是由各塔架标准节在沿塔架的高度上拼装而成,塔架顶部设置一水箱底座,水箱放置在所述水箱底座上;各塔架标准节是由立柱和片桁架通过交接销拼装构成的空间钢桁架,片桁架是由横梁和斜撑焊接成剪刀支架的组件。本实用新型的拼装结构使施工快捷方便、工期短、结构稳定性强,钢结构的可重复利用性能有效避免了原材料的浪费。

Figure 201120154194

The utility model discloses an assembled section-type water tank tower, which is characterized in that steel plate assemblies are pre-embedded in the concrete foundation at the bottom to form the tower foundation, and the tower body arranged on the tower foundation is composed of standard joints of each tower. Assembled along the height of the tower, a water tank base is set on the top of the tower, and the water tank is placed on the base of the water tank; each tower standard section is a space steel truss assembled by columns and piece trusses through transfer pins, piece trusses It is an assembly of scissors brackets welded by beams and diagonal braces. The assembled structure of the utility model makes the construction fast and convenient, the construction period is short, and the structure is stable, and the reusable performance of the steel structure effectively avoids the waste of raw materials.

Figure 201120154194

Description

A kind of assembly unit joint formula tank tower
Technical field
The utility model relates to tank tower, a kind of tank tower that is particularly suited for being applied in the job site, to guarantee that construction water is pressed of more specifically saying so.
Background technology
Overwhelming majority engineering construction is to construct in the open air; One big difference of field construction and municipal construction is to adopt city tap-water to supply water when being municipal construction; And field construction need be dug place's well at the scene; From well, draw water to the water supply water tower, need keep the certain hydraulic pressure of water in the water tower simultaneously.
In the prior art, be applied in the water tower in the engineering construction, its tank tower normally adopts concrete foundation and full masonry walls body, and there is following problem in this form of structure in practice of construction:
1, the work progress of full masonry walls body comprises: basic formwork erection, base concrete construction and pre-buried wall body connecting reinforcement, concrete curing, form removal, segmentation masonry wall body, water tank base are set up etc.; Manufacturing process takes a lot of work, time-consuming; Cycle is long, and masonry walls body verticality is difficult to control;
2, full masonry walls dismantle big, cost of dismantling and freight height in man-hour when the later stage reclaims in the place;
3, masonry walls body construction quality is difficult to control, and wall body building construction causes structural stability poor after too high, has great potential safety hazard.
The utility model content
The utility model is for avoiding above-mentioned existing in prior technology weak point, a kind of tank tower of segmented assembly unit being provided, to simplify work progress, useless, the increase structural stability of the raw-material consumption of minimizing.
The utility model technical solution problem adopts following technical scheme:
The design feature of the utility model assembly unit joint formula tank tower is: the pre-embedded steel slab composite member constitutes tower foundation in the concrete foundation of bottom; Be arranged on pylon body on the tower foundation and be by each pylon standard knot along assembled on the height of pylon; Tower top is provided with a water tank base, and water tank is placed on the said water tank base; Said each pylon standard knot is the Steel Space Truss that is made up of through the assembly unit of handing-over pin column and sheet truss, and said truss is the assembly that is welded into Holder for scissors by crossbeam and diagonal brace.
The design feature of the utility model assembly unit joint formula tank tower also is:
Said pylon standard knot comprises bottom standard knot, intermediate layer standard knot and top layer standard knot, and said bottom standard knot is to be connected with pre-embedded steel slab composite member flange in its Steel Space Truss central post and the bottom concrete foundation; Be to adopt flange to connect between the column in the Steel Space Truss on relative position between the pylon standard knot of adjacent one deck; Said top layer standard knot is to be connected with flange between its space truss central post and the water tank base.
Said water tank base is a truss structural.
Compared with present technology, the utility model beneficial effect is embodied in:
1, the utility model adopts steel truss structure, has significantly reduced the use amount of brick, and the form of structure of its assembly unit has been simplified production process, convenient, effective reduction of erection time of quick construction greatly; Its tank tower, standard knot and water tank base can be reused, and have avoided waste;
2, the utility model through adjustment tank tower assembly unit quantity reach adjustment water tower height purpose, simple and convenient, Practical Performance is high;
3, the steel truss structure of the utility model has good rigidity and stability;
4, the utility model can adopt batch production processing, its sheet trussed construction convenient transportation.
Description of drawings
Fig. 1 is the utility model structural representation;
Fig. 2 is the utility model pylon standard knot sketch map;
Fig. 3 is the utility model water tank base sketch map;
Label among the figure: 1 concrete foundation; 2 pre-embedded steel slab composite membeies; 3 pylon standard knots; 31 bottom standard knots; 32 intermediate layer standard knots; 33 top layer standard knots; 4 water tank bases; 5 water tanks; The 3a column; The 3b crossbeam; The 3c diagonal brace.
The specific embodiment
Referring to Fig. 1, Fig. 2 and Fig. 3; Present embodiment is that pre-embedded steel slab composite member 2 constitutes tower foundation in bottom concrete foundation 1; Be arranged on pylon body on the tower foundation and be by each pylon standard knot 3 along assembled on the height of pylon; Tower top is provided with a water tank base 4, and water tank 5 is placed on the water tank base 4;
Shown in Figure 2, each pylon standard knot 3 is the Steel Space Truss that are made up of through the assembly unit of handing-over pin column 3a and sheet truss, and the sheet truss is the assembly that is welded into Holder for scissors by crossbeam 3b and diagonal brace 3c; Shown in Figure 3, water tank base 4 is a truss structural;
In the practical implementation, as shown in Figure 1, each pylon standard knot 3 comprises bottom standard knot 31, intermediate layer standard knot 32 and top layer standard knot 33, and bottom standard knot 31 is to be connected with pre-embedded steel slab composite member 2 flanges in its Steel Space Truss central post and the bottom concrete foundation 1; Be to adopt flange to connect between the column in the Steel Space Truss on relative position between the pylon standard knot of adjacent one deck; Top layer standard knot 33 is to be connected with flange between its space truss central post and the water tank base 4, and the form that flange connects makes disassembly process more convenient.
Work progress:
1, at first presses the construction that usual manner is accomplished water tower concrete foundation 1; And in water tower basis 1, pre-embedded steel slab composite member 2 is set; When construction, wrapped up the bolt silk mouth of pre-embedded steel slab composite member 2; And the planeness of the steel plate on the requirement assurance pre-embedded steel slab composite member 2, four jiaos of discrepancy in elevation must not be greater than 2mm;
2, adopt the bolt double nut of M20 to fix between pre-embedded steel slab composite member 2 and the bottom standard knot 31, and by joint intermediate layer standard knot 32 and top layer standard knot 33 are installed from lower to upper, water tank base 4 is installed at top layer standard knot 33;
3, on lifting water tank 5 to the water tank base 4, water tank is installed firmly and is promptly accomplished.

Claims (3)

1.一种拼装节式水箱塔架,其特征是在底部混凝土基础(1)中预埋钢板组合件(2)构成塔架基础,设置在塔架基础上的塔架本体是由各塔架标准节(3)在沿塔架的高度上拼装而成,塔架顶部设置一水箱底座(4),水箱(5)放置在所述水箱底座(4)上;所述各塔架标准节(3)是由立柱(3a)和片桁架通过交接销拼装构成的空间钢桁架,所述片桁架是由横梁(3b)和斜撑(3c)焊接成剪刀支架的组件。1. An assembled section type water tank tower is characterized in that the steel plate assembly (2) is pre-embedded in the bottom concrete foundation (1) to form the tower foundation, and the tower body arranged on the tower foundation is formed by each tower The standard sections (3) are assembled along the height of the tower, and a water tank base (4) is arranged on the top of the tower, and the water tank (5) is placed on the water tank base (4); each of the tower standard sections ( 3) It is a space steel truss formed by assembling columns (3a) and sheet trusses through transfer pins, and the sheet truss is an assembly of scissors brackets welded by beams (3b) and diagonal braces (3c). 2.根据权利要求1所述的拼装节式水箱塔架,其特征是所述塔架标准节(3)包括底层标准节(31)、中间层标准节(32)和顶层标准节(33),所述底层标准节(31)是以其空间钢桁架中立柱与底部混凝土基础(1)中预埋钢板组合件(2)法兰连接;相邻一层的塔架标准节之间是在相对位置上的空间钢桁架中的立柱之间采用法兰连接;所述顶层标准节(33)是以其空间桁架中立柱与水箱底座(4)之间法兰连接。2. The assembled section water tank tower according to claim 1, characterized in that said tower standard section (3) comprises a bottom floor standard section (31), an intermediate floor standard section (32) and a top floor standard section (33) , the bottom standard section (31) is flange-connected with the pre-embedded steel plate assembly (2) in the bottom concrete foundation (1) by the column in the space steel truss; between the tower standard sections of the adjacent floor The columns in the space steel trusses at relative positions are connected by flanges; the top floor standard section (33) is connected by flanges between the columns in the space trusses and the water tank base (4). 3.根据权利要求2所述的拼装节式水箱塔架,其特征是所述水箱底座(4)为平面桁架结构。3. The assembled section water tank tower according to claim 2, characterized in that the water tank base (4) is a planar truss structure.
CN201120154194.2U 2011-05-16 2011-05-16 Assembled segmental water tank tower Expired - Fee Related CN202108296U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201120154194.2U CN202108296U (en) 2011-05-16 2011-05-16 Assembled segmental water tank tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201120154194.2U CN202108296U (en) 2011-05-16 2011-05-16 Assembled segmental water tank tower

Publications (1)

Publication Number Publication Date
CN202108296U true CN202108296U (en) 2012-01-11

Family

ID=45433732

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201120154194.2U Expired - Fee Related CN202108296U (en) 2011-05-16 2011-05-16 Assembled segmental water tank tower

Country Status (1)

Country Link
CN (1) CN202108296U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103303814A (en) * 2013-07-01 2013-09-18 张家港市天运建筑机械有限公司 Tower footing assembly
CN103437588A (en) * 2013-09-11 2013-12-11 程富文 Adjustable assembled-type water tower base
CN107503558A (en) * 2017-08-30 2017-12-22 重庆标王机械设备有限公司 A kind of steel construction tower body standard knot of combined tower

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103303814A (en) * 2013-07-01 2013-09-18 张家港市天运建筑机械有限公司 Tower footing assembly
CN103437588A (en) * 2013-09-11 2013-12-11 程富文 Adjustable assembled-type water tower base
CN103437588B (en) * 2013-09-11 2016-03-02 程富文 Adjustable assembled-type water tower base
CN107503558A (en) * 2017-08-30 2017-12-22 重庆标王机械设备有限公司 A kind of steel construction tower body standard knot of combined tower

Similar Documents

Publication Publication Date Title
CN100482892C (en) Lower chord opening beam type corrugated steel web combination beam
CN102425306B (en) Construction method of steel bar truss floor bearing plate and steel bar truss floor bearing plate
CN101694110B (en) Beam-column joint connection structure and its construction method
CN103422667B (en) Double-plate prefabricated superposed wall supporting system
CN201738250U (en) Arch culvert and arch ring steel die trolley
CN102182303A (en) Oblique annular closed structural template supporting method
CN111188457A (en) Edge sealing beam structure of super high-rise steel structure building and construction method
CN204282530U (en) Adopt the industrial premises frame construction of prefabricated concrete column structure
CN204097864U (en) A kind of bridge prefabrication hollow pier stud delay-pour joint structure
CN103206088B (en) Parts of shear wall structure wall, slab integral pouring construction method
CN103321153B (en) A kind of construction method of Mid and minor spans channel girder
CN102767282B (en) Prefabricated high formwork construction method for cantilever beam of oversized special-shaped conversion layer
CN202108296U (en) Assembled segmental water tank tower
CN103485574A (en) Method for constructing reinforced concrete structure of tower top of prilling tower
CN112227218A (en) Stainless steel-wood combined template applied to bare concrete and manufacturing method thereof
CN111733972A (en) New fabricated reinforced concrete structure beam-column joint
CN102418417B (en) Long-slab-span cast-in-situ beam ribbed floor early-dismantling template formwork system
CN202108299U (en) Segmented assembled water tank tower with adjustable height
CN103243910B (en) Hydraulic pressure controlled reinforced concrete structure bed die vertical supporting system and construction method thereof
CN214245382U (en) Stainless steel-wood combined template applied to bare concrete
CN202117390U (en) Segmentally spliced water tank tower
CN102454298B (en) Large-sized reinforced concrete construction of frame beam method
CN116290581A (en) A temporary support tool for column skeleton reinforcement and its application method
CN104963344B (en) The deep basal pit underground construction method that concrete supporting removal and structure construction are synchronously carried out
CN100422483C (en) Formwork Supporting Technology of Concrete Structure Without Demolition Composite Formwork

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120111

Termination date: 20180516