CN104963344B - The deep basal pit underground construction method that concrete supporting removal and structure construction are synchronously carried out - Google Patents

The deep basal pit underground construction method that concrete supporting removal and structure construction are synchronously carried out Download PDF

Info

Publication number
CN104963344B
CN104963344B CN201510418572.6A CN201510418572A CN104963344B CN 104963344 B CN104963344 B CN 104963344B CN 201510418572 A CN201510418572 A CN 201510418572A CN 104963344 B CN104963344 B CN 104963344B
Authority
CN
China
Prior art keywords
purlin
concrete
trestle
bearing type
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510418572.6A
Other languages
Chinese (zh)
Other versions
CN104963344A (en
Inventor
朱雪峰
张宗建
强化
王小培
王政
姜伟
王超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU JIANGDU CONSTRUCTION GROUP CO Ltd
Original Assignee
JIANGSU JIANGDU CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU JIANGDU CONSTRUCTION GROUP CO Ltd filed Critical JIANGSU JIANGDU CONSTRUCTION GROUP CO Ltd
Priority to CN201510418572.6A priority Critical patent/CN104963344B/en
Publication of CN104963344A publication Critical patent/CN104963344A/en
Application granted granted Critical
Publication of CN104963344B publication Critical patent/CN104963344B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The deep basal pit underground construction method that concrete supporting removal and structure synchronization are carried out, it is related to architectural engineering construction technique field, while subterranean excavation bottom is applied, concrete structure is built between subsurface structure periphery and subterranean excavation inwall to stand to enclosing purlin, bearing type concrete trestle is built in the same aspect in purlin of enclosing, the end of bearing type concrete trestle respectively with enclose purlin and be fixedly connected, and the main support of concrete structure is built in subterranean excavation inwall and between enclosing purlin, main support it is inner with enclose purlin and be fixedly connected;Bearing type concrete trestle lower section is divided into two layers of B1 and underground, and carries out the reinforcing bar colligation of two layers of underground and structure construction;After two layers of the top plate concrete in underground reaches upper people's condition, the colligation of B1 reinforcing bar and structural segmented construction are carried out.Speed of application of the present invention is high, removes short time limit, environmental protection.

Description

The deep basal pit underground construction method that concrete supporting removal and structure construction are synchronously carried out
Technical field
The present invention relates to architectural engineering construction technique field, particularly there is the construction work of the deep basal pit underground structure of inner support Method.
Background technology
Commonly used with skyscraper, requirement to subterranean excavation also more and more higher, according to construction process requirement, has The deep basal pit Underground Construction of inner support, reaches after design strength meets support replacement condition in every layer of underground structure, can remove Top concrete inner support, and wait the formation of structure concrete strength and to the support remove at least 20 day time of occupancy that needs, 20 It is well imagined for the influence of construction period.
Therefore, existing deep basal pit underground construction method is long in time limit, and the influence power caused to surrounding enviroment is big, is also unfavorable for Protection to environment.
The content of the invention
It is an object of the invention to propose that a kind of concrete supporting removal and structure synchronization are carried out, can effectively shorten the deep base of duration Hole underground construction method.
The present invention is comprised the following steps:
1)Excavate subterranean excavation;
2)While subterranean excavation bottom is applied, built between the peripheral and described subterranean excavation inwall of subsurface structure of design Make concrete structure to stand to purlin is enclosed, bearing type concrete trestle, the bearing type concrete structure are built in the same aspect enclosed in purlin The end of trestle is fixedly connected with the purlin that encloses respectively, and subterranean excavation inwall and it is described enclose purlin between build the main branch of concrete structure Support, main support it is inner with enclose purlin and be fixedly connected;
3)Bearing type concrete trestle lower section is divided into two layers of B1 and underground, and carries out two layers of underground reinforcing bar Colligation and structure construction;
4)After two layers of the top plate concrete in underground reaches upper people's condition, carry out the colligation of B1 reinforcing bar and structural segmented apply Work, while purlin, bearing type concrete trestle and main support are enclosed in dismounting;
5)After purlin and the dismounting of bearing type concrete trestle is enclosed, adjacent B1 construction segment structure is attached, Then subsurface structure waterproof is made again.
The present invention does not influence Underground Construction, save take needed for the maintenance of support replacement floor and first supporting removal when Between, can synchronously carry out, speed of application is greatly enhanced, and removes the duration very short;Job site airborne dust is few, reduction is largely made an uproar Sound, environmental protection, material-saving with it is artificial, and construct it is convenient.
In the subterranean excavation of large span, also built in concrete trestle in bearing type and connect support link.By support Connecting rod improves the intensity that bearing type builds concrete trestle, prevents load-bearing from deforming.
Before purlin and bearing type concrete trestle are enclosed in dismounting, the wall column reinforcing bar of the vertical structure of first colligation B1, Then the full hall structure scaffold of B1 is built in the region on the outside of trestle bottom and trestle;Treat the full hall structural feet of B1 When the intensity of hand cradle meets wall column insertion construction requirement, concrete structurally lower two layers of wall column is built in the inner side for enclosing purlin, and adjacent Two layers of underground wall column between casting beams concrete.
First the inside and outside both sides for enclosing purlin are built with full hall structure scaffold, then to enclosing purlin, bearing type concrete trestle and main branch Support is removed.
Specific embodiment
First, Engineering Notice:Somewhere downtown area center, project overall floorage is about 158235 square metres, foundation ditch area about 3.2 Ten thousand square metres.
2nd, engineering difficult point:
1st, the duration is tight:It is required that underground structure is uninterruptedly constructed, support the time of abolishing very nervous, traditional support mechanical removal Mode cannot meet.
2nd, foundation pit deformation requirement is high:Remove around region close to town road, it is high to periphery pipeline and environmental protection requirement, The influence to it, particularly 3# car ramps position is controlled to melt true foundation ditch across a causeway with adjacent in demolishing process.
3rd, supporting removal quantities is big:Especially first support and trestle region are big, and cleaning work amount is big;Surrounding construction field Ground is smaller, turnover inconvenience, and removing waste material must transport in time, can otherwise influence the overall progress of engineering.
4th, civilized construction requirement is high:Remove region and be located at business district, to civilized construction, sanitary clean, management of safe operation It is required that higher.
3rd, work progress:
1st, subterranean excavation is excavated by design requirement.
2nd, while subterranean excavation bottom is applied, concrete is built between the subsurface structure periphery of design and subterranean excavation inwall Structure is stood to purlin is enclosed, and grid type bearing type concrete trestle is built in the same aspect in purlin of enclosing, bearing type concrete trestle Outer end respectively with enclose purlin and be fixedly connected by reinforced concrete structure.Concrete structure master is built in subterranean excavation inwall and between enclosing purlin Support, the inner of main support is connected by reinforced concrete structure with purlin is enclosed.In the grid of each bearing type concrete trestle Many support links of connection.
3rd, bearing type concrete trestle lower section is divided into two layers of B1 and underground, by bearing type concrete trestle Lower section connects ladder, operating personnel is gone downwards to two layers of underground through trestle, ladder from ground, and carry out the reinforcing bar colligation of two layers of underground And structure construction.
4th, after the top plate concrete of two layers of underground reaches upper people's condition, carry out the colligation of B1 reinforcing bar and structural segmented apply Work, while purlin, bearing type concrete trestle and main support are enclosed in dismounting.
Before purlin and bearing type concrete trestle are enclosed in dismounting, the wall column reinforcing bar of the vertical structure of first colligation B1, Then the full hall structure scaffold of B1 is built in the region on the outside of trestle bottom and trestle.
When the intensity of the full hall structure scaffold of B1 meets wall column insertion construction requirement, built in the inner side for enclosing purlin Concrete structurally lower two layers of wall column, and the casting beams concrete between adjacent two layers of underground wall column.
Before purlin is enclosed in dismounting, full hall structure scaffold first is built to the inside and outside both sides for enclosing purlin, then it is cable-styled using SK-SD Cutting machine segmentation is split to enclosing purlin, bearing type concrete trestle and main support, is crushed, being removed, then using truck crane or The direct handling of tower crane.
Transport outward away carries out demolition reduction in beta site.
5th, enclose in purlin and bearing type concrete trestle region having removed original, adjacent B1 construction segment structure is adopted It is attached with armored concrete, subsurface structure waterproof is then made again.
Conclusion:The construction of this method for dismounting does not influence Underground Construction, can synchronously carry out, and speed of application is very fast, tears open Except the duration is very short;Job site airborne dust is little, reduce much noise, environmental protection;Mechanically actuated is simple, material-saving and people Work, and it is convenient to construct.
Supporting removal scheme takes into full account high requirement, foundation ditch surrounding environment, the supporting removal quantities to job site Greatly, construction site is smaller, the duration tight around when first support and trestle region are removed and the factor, selection such as engineering design requirements Rational construction method for dismounting, achieves good construction effect.

Claims (3)

1. the deep basal pit underground construction method that concrete supporting removal and structure construction are synchronously carried out, comprises the following steps:
1)Excavate subterranean excavation;
2)While subterranean excavation bottom is constructed, built between the peripheral and described subterranean excavation inwall of subsurface structure of design Concrete structure is stood to purlin is enclosed, and bearing type concrete trestle, the bearing type concrete structure stack are built in the same aspect enclosed in purlin The end of bridge is fixedly connected with the purlin that encloses respectively, and subterranean excavation inwall and it is described enclose purlin between build the main branch of concrete structure Support, main support it is inner with enclose purlin and be fixedly connected;
3)Bearing type concrete trestle lower section is divided into two layers of B1 and underground, and carries out the reinforcing bar colligation of two layers of underground And structure construction;
4)After two layers of the top plate concrete in underground reaches upper people's condition, the colligation of B1 reinforcing bar and structural segmented construction are carried out, together When remove enclose purlin, bearing type concrete trestle and main support;
5)After purlin and the dismounting of bearing type concrete trestle is enclosed, adjacent B1 construction segment structure is attached, then Subsurface structure waterproof is made again;
It is characterized in that before purlin and bearing type concrete trestle are enclosed in dismounting, the wall column of the vertical structure of first colligation B1 Reinforcing bar, then B1 is built in the region on the outside of trestle bottom and trestle expires hall structure scaffold;Treat the full hall of B1 When the intensity of structure scaffold meets wall column insertion construction requirement, concrete structurally lower two layers of wall column is built in the inner side for enclosing purlin, and The casting beams concrete between adjacent two layers of underground wall column.
2. method according to claim 1, it is characterised in that in the step 2)In, connected in bearing type concrete trestle Support link.
3. method according to claim 1, it is characterised in that full hall structure scaffold first is built to the inside and outside both sides for enclosing purlin, Removed to enclosing purlin, bearing type concrete trestle and main support again.
CN201510418572.6A 2015-07-17 2015-07-17 The deep basal pit underground construction method that concrete supporting removal and structure construction are synchronously carried out Active CN104963344B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510418572.6A CN104963344B (en) 2015-07-17 2015-07-17 The deep basal pit underground construction method that concrete supporting removal and structure construction are synchronously carried out

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510418572.6A CN104963344B (en) 2015-07-17 2015-07-17 The deep basal pit underground construction method that concrete supporting removal and structure construction are synchronously carried out

Publications (2)

Publication Number Publication Date
CN104963344A CN104963344A (en) 2015-10-07
CN104963344B true CN104963344B (en) 2017-05-31

Family

ID=54217416

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510418572.6A Active CN104963344B (en) 2015-07-17 2015-07-17 The deep basal pit underground construction method that concrete supporting removal and structure construction are synchronously carried out

Country Status (1)

Country Link
CN (1) CN104963344B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110777800A (en) * 2019-11-04 2020-02-11 中铁十二局集团有限公司 Construction method for dismantling foundation pit concrete purlin
CN111005388A (en) * 2019-12-12 2020-04-14 中冶天工集团有限公司 Deep foundation pit integral supporting device and supporting method thereof

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2489550C1 (en) * 2011-12-26 2013-08-10 Сергей Олегович Зеге Method for underground structure erection
CN102995659B (en) * 2012-12-03 2015-04-08 杭州南联地基基础工程有限公司 Method for constructing from central area to periphery of ultra-large type underground engineering
CN203066082U (en) * 2013-03-06 2013-07-17 熊楚炎 Temporary trestle on edge of anchor rod support type foundation pit
CN203768788U (en) * 2014-03-13 2014-08-13 上海强劲地基工程股份有限公司 Tool type foundation pit soil conveying trestle bridge

Also Published As

Publication number Publication date
CN104963344A (en) 2015-10-07

Similar Documents

Publication Publication Date Title
CN105926669B (en) A kind of Construction Method of Metro Station
CN102505696B (en) Support system of rear support removing type section steel-concrete double-enclosing-purlin foundation pit and construction method
CN104032744B (en) Support replacement construction method in the engineering of group hole
CN101196116A (en) Three-connected-arch tunnel double-side cavity construction method for soft geological
CN205000974U (en) A tire formula automatic rising equipment rack for tunnel excavation construction
CN102619152A (en) Split mounting type prefabricated reinforced concrete construction temporary road
CN102747735A (en) Treatment method for abnormal deformation of deep foundation pit concrete support piling
CN203961238U (en) Bolt anchor slab adjustable tool formula builder's jack
CN110847915A (en) Construction process for jumping-cutting demolishing and subsection back-jacking of double-side-wall temporary support of shallow-buried fine sand layer
CN104060617A (en) Prefabricated internal support system and construction method for foundation pit support system
CN208072415U (en) Deep foundation pit reinforced concrete support part changes structure
CN107326928A (en) A kind of part is related to the construction method in the deeper subsurface garage of basement
CN106351180A (en) Full hydraulic opening self-propelled template system for aqueduct
CN103452350B (en) Assembling electronic workshop and construction method thereof
CN204715366U (en) A kind of large-area deep foundation pit subregion is along the support system under inverse operating mode
CN104234447B (en) Deep foundation ditch tool-type hangs stair
CN104963344B (en) The deep basal pit underground construction method that concrete supporting removal and structure construction are synchronously carried out
CN106368714A (en) Tire type automatic lifting assembly rack for tunnel excavation construction
CN104032767A (en) Tower crane foundation in deep foundation pit and construction method of tower crane foundation
CN105862897A (en) Original-groove casting construction method for shallow foundation of sandy mudstone foundation
CN205296197U (en) Prefabricated cushion cap of anticorrosive industry factory building concrete rim of a cup formula
CN109837910B (en) Foundation pit construction method combining reverse construction method and steel support
CN103882883A (en) Method for constructing foundation shared by tower crane and garage frame column
CN112030995A (en) Construction method for quickly taking out of ground for supporting and disassembling in advance for main building of super high-rise building
CN207760803U (en) A kind of prefabricated amphistyly armour steel form

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant