CN104963344A - Deep foundation pit underground construction method allowing concrete support removal and structure construction to be conducted simultaneously - Google Patents

Deep foundation pit underground construction method allowing concrete support removal and structure construction to be conducted simultaneously Download PDF

Info

Publication number
CN104963344A
CN104963344A CN201510418572.6A CN201510418572A CN104963344A CN 104963344 A CN104963344 A CN 104963344A CN 201510418572 A CN201510418572 A CN 201510418572A CN 104963344 A CN104963344 A CN 104963344A
Authority
CN
China
Prior art keywords
underground
construction
trestle
purlin
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510418572.6A
Other languages
Chinese (zh)
Other versions
CN104963344B (en
Inventor
朱雪峰
张宗建
强化
王小培
王政
姜伟
王超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU JIANGDU CONSTRUCTION GROUP CO Ltd
Original Assignee
JIANGSU JIANGDU CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU JIANGDU CONSTRUCTION GROUP CO Ltd filed Critical JIANGSU JIANGDU CONSTRUCTION GROUP CO Ltd
Priority to CN201510418572.6A priority Critical patent/CN104963344B/en
Publication of CN104963344A publication Critical patent/CN104963344A/en
Application granted granted Critical
Publication of CN104963344B publication Critical patent/CN104963344B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a deep foundation pit underground construction method allowing concrete support removal and structure construction to be conducted simultaneously and relates to the technical field of architectural engineering construction. According to the method, concrete structure vertical circuit purlins are built between the periphery of an underground structure and the inner wall of an underground foundation pit while construction is conducted on the bottom of the underground foundation pit, a bearing type concrete structure trestle is built on the same layer of the circuit purlins, and the ends of the bearing type concrete structure trestle are fixedly connected with the circuit purlins respectively; a concrete structure main support is built between the inner wall of the underground foundation pit and the circuit purlins, and the inner end of the main support is fixedly connected with the circuit purlins; the space under the bearing type concrete structure trestle is divided into a first underground floor and a second underground floor, and reinforced banding and structural construction are conducted on the second underground floor; after roof concrete of the second underground floor reaches the accessible condition, reinforced banding and structural section construction are conducted on the first underground floor. The method has the advantages that construction speed is high, time for dismantlement is short, and environment friendliness is realized.

Description

The deep foundation ditch underground construction method that concrete supporting removal and structure synchronization carry out
Technical field
The present invention relates to architectural engineering construction technique field, particularly have the construction of the deep foundation ditch underground structure of inner support.
Background technology
Along with the generally application of highrise building, also more and more higher to the requirement of subterranean excavation, according to construction process requirement, there is the deep foundation ditch Underground Construction of inner support, reach after design strength meets support replacement condition at every layer of underground structure, can remove top concrete inner support, and wait for the formation of Concrete In Structures intensity and carry out dismounting needs to this support and take at least 20 days time, the impact for the construction period in 20 days is well imagined.
Therefore, existing deep foundation ditch underground construction method is long in time limit, and the influence power caused surrounding enviroment is large, is also unfavorable for the protection to environment.
Summary of the invention
The object of the invention is to propose a kind of concrete supporting removal and structure synchronization carries out, can the deep foundation ditch underground construction method of effective reduction of erection time.
The present invention includes following steps:
1) subterranean excavation is excavated;
2) while executing bottom subterranean excavation, between the subsurface structure periphery and described subterranean excavation inwall of design, build concrete structure stands to enclosing purlin, bearing type concrete trestle is built in described same aspect of enclosing in purlin, the end of described bearing type concrete trestle is fixedly connected with the described purlin that encloses respectively, and build the main support of concrete structure at subterranean excavation inwall and described enclosing between purlin, the inner of main support with enclose purlin and be fixedly connected with;
3) be divided into B1 and two layers, underground by below described bearing type concrete trestle, and carry out two layers, underground reinforcing bar binding and structure construction;
4) after the top plate concrete of two layers, underground reaches upper people's condition, carry out B1 reinforcing bar binding and structural segmented construction, remove simultaneously and enclose purlin, bearing type concrete trestle and main support;
5) after enclosing purlin and the dismounting of bearing type concrete trestle, adjacent B1 construction section structure is connected, and then makes subsurface structure waterproof.
The present invention does not affect Underground Construction, and save the time taken needed for support replacement floor maintenance and first supporting removal, can synchronously carry out, speed of application is greatly enhanced, and the dismounting duration is very short; Job site airborne dust is few, minimizing much noise, environmental protection, save material with artificial, and it is convenient to construct.
In the subterranean excavation of large span, also build in concrete trestle at bearing type and connect support link.Improve by support link the intensity that bearing type builds concrete trestle, prevent load-bearing to be out of shape.
Before purlin and bearing type concrete trestle are enclosed in dismounting, the wall column reinforcing bar of the vertical structure of first colligation B1, the full hall structural feet hand cradle of B1 is built in the region then outside trestle bottom and trestle; Until the intensity of the full hall structural feet hand cradle of B1 meet wall column insert construction requirement time, build concrete lower two layers of wall column structurally in the inner side of enclosing purlin, and between adjacent two layers, underground wall column casting beams concrete.
First full hall structural feet hand cradle is built to the inside and outside both sides of enclosing purlin, then remove enclosing purlin, bearing type concrete trestle and main support.
Detailed description of the invention
One, Engineering Notice: center, downtown area, somewhere, project overall floorage is about 158235 square metres, foundation ditch area about 3.2 ten thousand square metres.
Two, engineering difficult point:
1, the duration is tight: require that underground structure is uninterruptedly constructed, and support the time of abolishing very nervous, traditional support mechanical removal mode cannot meet.
2, foundation pit deformation requires high: remove around region and be close to town road, to periphery pipeline and environmental protection requirement high, the impact on it, particularly 3# car ramp position to be controlled in demolishing process and adjacently melt true foundation ditch across a causeway.
3, supporting removal engineering quantity is large: especially first support and trestle region large, cleaning work amount is large; Around construction plant is less, turnover inconvenience, and removing waste material must transport in time, otherwise can affect the overall progress of engineering.
4, civilized construction requires high: remove region and be positioned at business district, requires higher to civilized construction, sanitary clean, management of safe operation.
Three, work progress:
1, by designing requirement excavation subterranean excavation.
2, while executing bottom subterranean excavation, between the subsurface structure periphery and subterranean excavation inwall of design, build concrete structure stands to enclosing purlin, build grid type bearing type concrete trestle in the same aspect in purlin of enclosing, the outer end of bearing type concrete trestle respectively with enclose purlin and be fixedly connected with by reinforced concrete structure.At subterranean excavation inwall with enclose between purlin and build the main support of concrete structure, the inner of main support by reinforced concrete structure with enclose purlin and be connected.Many support link are connected in the grid of each bearing type concrete trestle.
3, B1 and two layers, underground will be divided into below bearing type concrete trestle, by connecting ladder below bearing type concrete trestle, make operating personnel go downwards to two layers, underground from ground through trestle, ladder, and carry out two layers, underground reinforcing bar binding and structure construction.
4, after the top plate concrete of two layers, underground reaches upper people's condition, carry out B1 reinforcing bar binding and structural segmented construction, remove simultaneously and enclose purlin, bearing type concrete trestle and main support.
Before purlin and bearing type concrete trestle are enclosed in dismounting, the wall column reinforcing bar of the vertical structure of first colligation B1, the full hall structural feet hand cradle of B1 is built in the region then outside trestle bottom and trestle.
Until the intensity of the full hall structural feet hand cradle of B1 meet wall column insert construction requirement time, build concrete lower two layers of wall column structurally in the inner side of enclosing purlin, and between adjacent two layers, underground wall column casting beams concrete.
Before purlin is enclosed in dismounting, first full hall structural feet hand cradle is built to the inside and outside both sides of enclosing purlin, purlin, bearing type concrete trestle and main support are split, broken, dismounting to enclosing to adopt the segmentation of SK-SD cable-styled cutting machine again, then adopt mobile crane or the direct handling of tower crane.
Transport outward away and carry out demolition reduction in beta site.
5, formerly enclose in purlin and bearing type concrete trestle region removing, adopt steel concrete to connect adjacent B1 construction section structure, and then make subsurface structure waterproof.
Conclusion: the construction of this method for dismounting does not affect Underground Construction, can synchronously carry out, quickly, the dismounting duration is very short for speed of application; Job site airborne dust seldom, reduce much noise, environmental protection; Mechanically actuated is simple, save material with artificial, and it is convenient to construct.
Around when supporting removal scheme takes into full account that high requirement to job site, foundation ditch surrounding environment, supporting removal engineering quantity are large, first supports and trestle region is removed, construction plant is less, the duration tight and the factor such as engineering design requirements, have selected method for dismounting of reasonably constructing, achieve good construction effect.

Claims (4)

1. the deep foundation ditch underground construction method that carries out of concrete supporting removal and structure synchronization, feature is levied and is to comprise the following steps:
1) subterranean excavation is excavated;
2) while executing bottom subterranean excavation, between the subsurface structure periphery and described subterranean excavation inwall of design, build concrete structure stands to enclosing purlin, bearing type concrete trestle is built in described same aspect of enclosing in purlin, the end of described bearing type concrete trestle is fixedly connected with the described purlin that encloses respectively, and build the main support of concrete structure at subterranean excavation inwall and described enclosing between purlin, the inner of main support with enclose purlin and be fixedly connected with;
3) be divided into B1 and two layers, underground by below described bearing type concrete trestle, and carry out two layers, underground reinforcing bar binding and structure construction;
4) after the top plate concrete of two layers, underground reaches upper people's condition, carry out B1 reinforcing bar binding and structural segmented construction, remove simultaneously and enclose purlin, bearing type concrete trestle and main support;
5) after enclosing purlin and the dismounting of bearing type concrete trestle, adjacent B1 construction section structure is connected, and then makes subsurface structure waterproof.
2. method according to claim 1, feature is levied and is in described step 2) in, build in concrete trestle at bearing type and connect support link.
3. method according to claim 1, feature is levied and is before purlin and bearing type concrete trestle are enclosed in dismounting, the wall column reinforcing bar of the vertical structure of first colligation B1, the full hall structural feet hand cradle of B1 is built in the region then outside trestle bottom and trestle; Until the intensity of the full hall structural feet hand cradle of B1 meet wall column insert construction requirement time, build concrete lower two layers of wall column structurally in the inner side of enclosing purlin, and between adjacent two layers, underground wall column casting beams concrete.
4. method according to claim 1, feature is levied and is first to build full hall structural feet hand cradle to the inside and outside both sides of enclosing purlin, then removes enclosing purlin, bearing type concrete trestle and main support.
CN201510418572.6A 2015-07-17 2015-07-17 The deep basal pit underground construction method that concrete supporting removal and structure construction are synchronously carried out Active CN104963344B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510418572.6A CN104963344B (en) 2015-07-17 2015-07-17 The deep basal pit underground construction method that concrete supporting removal and structure construction are synchronously carried out

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510418572.6A CN104963344B (en) 2015-07-17 2015-07-17 The deep basal pit underground construction method that concrete supporting removal and structure construction are synchronously carried out

Publications (2)

Publication Number Publication Date
CN104963344A true CN104963344A (en) 2015-10-07
CN104963344B CN104963344B (en) 2017-05-31

Family

ID=54217416

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510418572.6A Active CN104963344B (en) 2015-07-17 2015-07-17 The deep basal pit underground construction method that concrete supporting removal and structure construction are synchronously carried out

Country Status (1)

Country Link
CN (1) CN104963344B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110777800A (en) * 2019-11-04 2020-02-11 中铁十二局集团有限公司 Construction method for dismantling foundation pit concrete purlin
CN111005388A (en) * 2019-12-12 2020-04-14 中冶天工集团有限公司 Deep foundation pit integral supporting device and supporting method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102995659A (en) * 2012-12-03 2013-03-27 杭州南联地基基础工程有限公司 Method for constructing from central area to periphery of ultra-large type underground engineering
CN203066082U (en) * 2013-03-06 2013-07-17 熊楚炎 Temporary trestle on edge of anchor rod support type foundation pit
RU2489550C1 (en) * 2011-12-26 2013-08-10 Сергей Олегович Зеге Method for underground structure erection
CN203768788U (en) * 2014-03-13 2014-08-13 上海强劲地基工程股份有限公司 Tool type foundation pit soil conveying trestle bridge

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2489550C1 (en) * 2011-12-26 2013-08-10 Сергей Олегович Зеге Method for underground structure erection
CN102995659A (en) * 2012-12-03 2013-03-27 杭州南联地基基础工程有限公司 Method for constructing from central area to periphery of ultra-large type underground engineering
CN203066082U (en) * 2013-03-06 2013-07-17 熊楚炎 Temporary trestle on edge of anchor rod support type foundation pit
CN203768788U (en) * 2014-03-13 2014-08-13 上海强劲地基工程股份有限公司 Tool type foundation pit soil conveying trestle bridge

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
孙海忠: "复杂周边环境下的深基坑设计方案比选", 《山西建筑》 *
陈懿: "超深基坑多道钢筋混凝土支撑拆除技术", 《建筑施工》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110777800A (en) * 2019-11-04 2020-02-11 中铁十二局集团有限公司 Construction method for dismantling foundation pit concrete purlin
CN111005388A (en) * 2019-12-12 2020-04-14 中冶天工集团有限公司 Deep foundation pit integral supporting device and supporting method thereof

Also Published As

Publication number Publication date
CN104963344B (en) 2017-05-31

Similar Documents

Publication Publication Date Title
CN105926669B (en) A kind of Construction Method of Metro Station
CN102505696B (en) Support system of rear support removing type section steel-concrete double-enclosing-purlin foundation pit and construction method
CN104032744B (en) Support replacement construction method in the engineering of group hole
CN104594361B (en) A kind of I shape fender post and building enclosure also serve as the construction method of agent structure
CN105155549A (en) Partition support system for large-area deep foundation pit under forward and backward working condition, and construction method thereof
CN102031785A (en) Foundation pit supporting technique for replacing temporary enclosing purlin by using plate belt of permanent structure
CN105113540A (en) Construction method for newly-built large deep foundation pit basements under protection building
CN114016552A (en) Pre-sealing construction method for basement roof settlement post-cast strip
CN111794254A (en) Railway slope prefabricated assembled post-cast framework slope protection structure and construction method thereof
CN104632250A (en) Prefabricated tunnel lining structure of inverted segments for round foundation pit and construction method of prefabricated tunnel lining structure
CN105862897B (en) Sandy Silt ground shallow foundation original groove pouring construction engineering method
CN103452350A (en) Fabricated electronic workshop and construction method thereof
CN110685459A (en) Breaking hammer dismantling construction method for dismantling hoist bent from lower part
CN109339479B (en) Internal replacement structure and method for existing reinforced concrete building
CN111119904A (en) Construction method of soft surrounding rock karst section tunnel
CN104963344A (en) Deep foundation pit underground construction method allowing concrete support removal and structure construction to be conducted simultaneously
CN101550723A (en) Construction method for codes of reserved structural column longitudinal steel bars
CN112030995B (en) Construction method for quickly taking out of ground for supporting and disassembling in advance for main building of super high-rise building
CN104032767A (en) Tower crane foundation in deep foundation pit and construction method of tower crane foundation
KR20060096706A (en) Deck suspension top-down method of sub-structure
CN111778990A (en) Permanent-temporary combined assembly type inner support system and construction method
CN114961335B (en) Demolition construction method for large-span reinforced concrete support beam
CN112610023B (en) Construction method for dismantling building in existing track operation interval
CN212506301U (en) Support system in combination assembled forever
CN103088829B (en) The construction method that in a kind of foundation ditch, concrete supports

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant