CN102619152A - Split mounting type prefabricated reinforced concrete construction temporary road - Google Patents
Split mounting type prefabricated reinforced concrete construction temporary road Download PDFInfo
- Publication number
- CN102619152A CN102619152A CN2012100588917A CN201210058891A CN102619152A CN 102619152 A CN102619152 A CN 102619152A CN 2012100588917 A CN2012100588917 A CN 2012100588917A CN 201210058891 A CN201210058891 A CN 201210058891A CN 102619152 A CN102619152 A CN 102619152A
- Authority
- CN
- China
- Prior art keywords
- temporary road
- reinforced concrete
- prefabricated reinforced
- construction
- box
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Road Paving Structures (AREA)
Abstract
The invention discloses a split mounting type prefabricated reinforced concrete construction temporary road, which comprises a box type member, wherein a reinforced concrete box type member is arranged in the box type member; reinforcement of the reinforced concrete box type member is welded and fixed to the box type member; four angular points of the reinforced concrete box type member are provided with omega-shaped lifting rings respectively; and water discharge holes are also formed at the omega-shaped lifting rings. The split mounting type prefabricated reinforced concrete construction temporary road has the beneficial effects that: through development of the split mounting type prefabricated reinforced concrete construction temporary road, a reinforcement welding net, angle steel and concrete are formed into a whole, so that the performances of the steel and the concrete are fully utilized, particularly, the periphery of the construction temporary road is protected by using the angle steel, and the unavailability due to corner stripping caused by collision or other reasons during use of the construction temporary road is avoided; and a temporary road module is manufactured by using a shaped steel mould, and meanwhile, a special formwork and a strengthening system are matched, so that the construction quality of the corner part and the entire temporary road is effectively guaranteed.
Description
Technical field
The present invention relates to a kind of temporary road, more specifically say, it relates to a kind of pin-connected panel prefabricated reinforced concrete construction temporary road.
Background technology
The interim builder's road of construction site does not also form the system of regularization, tool; The industrial chain of pin-connected panel prefabricated reinforced concrete construction temporary road does not also form; Along with the continuous development of China's building construction technology, to carry out energetically under the background of green construction, the form of construction work of existing building construction temporary road does not meet the requirement of green construction; And serious waste of resources; For promoting the construction benefit of object of construction production, improve the managerial skills of construction site, make the construction of building temporary road form intrinsic pin-connected panel prefabricated reinforced concrete temporary road structure and have enough to meet the need use; Reduce the construction site wet trade, promote construction site green construction process.
As the construction site temporary road construction usually at present by the project management personnel of construction enterprises; Through the project construction arrangement whole place is planned; The correct position planning construction temporary road in the place, through excavation and filling to the roadbed of temporary road carry out smooth, measure the construction that operations such as unwrapping wire, a template and concreting are accomplished temporary roads.Because general temporary road construction is unworthy of reinforcing bar; And temporary road traffick weight is big, causes a large amount of concrete to be damaged by pressure, does not also wait construction to accomplish; Temporary road is dressed in rags; Form a large amount of building wastes, propose new requirement for the management of site safety civilized construction, be unfavorable for the implementation of green construction.
Summary of the invention
The objective of the invention is to overcome deficiency of the prior art; Providing a kind of makes the construction of building temporary road form intrinsic pin-connected panel prefabricated reinforced concrete temporary road structure and have enough to meet the need use; Reduce the construction site wet trade, promote the pin-connected panel prefabricated reinforced concrete construction temporary road of construction site green construction process.
This pin-connected panel prefabricated reinforced concrete construction temporary road; Comprise box-type member; Be provided with steel concrete box member in the said box-type member; The reinforcing bar of said steel concrete box member is fixing with the box-type member welding, and four angle points of said steel concrete box member are respectively equipped with Ω type suspension ring, and the place also is provided with drain hole at said Ω type suspension ring.
As preferably: said box-type member is made up of rectangular elements lower end four welded corner joint member supporting legs.
As preferably: said rectangular elements is that angle steel is welded.
As preferably: said member supporting leg is that angle steel is welded.
As preferably: said box-type member is peripheral to be provided with template with the bottom, and four jiaos of employings of said template girth member is reinforced.
As preferably: the round steel that said Ω type suspension ring are 20mm and the reinforcing bar of steel concrete box member are welded.
The invention has the beneficial effects as follows: can realize the safe, clean and tidy, civilized, orderly of the interim builder's road of construction site; Avoid interim builder's road to be damaged easily; Reduce the generation of building waste; Improve construction site civilized construction level, help building enterprise and carry out green construction.Simultaneously; Through this pin-connected panel prefabricated reinforced concrete construction temporary road exploitation; Adopt welded steel fabric, angle steel and concrete to form integral body; Given full play to steel and concrete performance, especially adopted angle steel that construction temporary road periphery is protected, avoided unavailable owing to the corner of colliding in the use of construction temporary road or other reasons causes comes off; The making of this temporary road module adopts the punching block of typing to make, and is furnished with dedicated templates and reinforcement system simultaneously, has effectively guaranteed the construction quality of position, corner and whole temporary road.This invention achievement is applicable to the application of building site temporary road, can effectively temporary road road surface on the building site be reused, and reaches the effect of economical with materials; For guaranteeing the economic benefit of this temporary road, general temporary road is produced in building and a plurality of engineering of exploitation by stages and continues the turnover use; This construction temporary road can organically combine with other temporary roads commonly used simultaneously, adopts present technique in local highway section, and conventional temporary road is adopted in the part highway section.In a word, this pin-connected panel prefabricated reinforced concrete construction temporary road is solid and reliable, economic and practical, flexible, can in the temporary road construction of a plurality of engineerings, turnover use, and is convenient to enterprise in charge of construction and applies widely.
Description of drawings
Fig. 1 is a box-type member master TV structure sketch map;
Fig. 2 is a box-type member side cross-sectional structural representation;
Fig. 3 is that box-type member is looked up the cross section structure sketch map;
Fig. 4 is a steel concrete box member master TV structure sketch map;
Fig. 5 is that steel concrete box member side is looked the cross section structure sketch map;
Fig. 6 is that steel concrete box member is looked up the cross section structure sketch map;
Fig. 7 is that steel concrete box component template is installed the ruggedized construction sketch map;
Fig. 8 is a steel concrete box member concreting structural representation;
Fig. 9 is a pin-connected panel prefabricated reinforced concrete construction temporary road master TV structure sketch map;
Figure 10 is a pin-connected panel prefabricated reinforced concrete construction temporary road side-looking structural representation;
Figure 11 is that pin-connected panel prefabricated reinforced concrete construction temporary road is looked up structural representation;
Reference numeral: rectangular elements 1, member supporting leg 2, box-type member 3, steel concrete box member 4, reinforcing bar 5, Ω type suspension ring 6, drain hole 7, template 8, girth member 9, concrete 10.
The specific embodiment
Below in conjunction with accompanying drawing and embodiment the present invention is done and to further describe.Though the present invention will combine preferred embodiment to describe, and should know, not represent to limit the invention among the said embodiment.On the contrary, the present invention will be contained alternative, modified and the equivalent in the scope of the present invention that can be included in attached claims qualification.
Extremely shown in Figure 3 like Fig. 1; Size according to the construction site temporary road; Adopt angle steel to be welded into rectangular elements 1, four jiaos of employings are welded rectangular elements supporting leg 2 with rectangular elements 1 identical angle steel in rectangular elements 1 lower end, form pin-connected panel prefabricated reinforced concrete construction temporary road box-type member 3.
Extremely shown in Figure 6 like Fig. 4; With reinforcing bar 5 firm welding in box-type member 3 and the steel concrete box member 4; Simultaneously being connected employing between the reinforcing bar 5 in steel concrete box member 4 and the reinforcing bar 5 welds; Adopting diameter in 4 four corner location of steel concrete box member is reinforcing bar 5 welding of round steel and the steel concrete box member 4 of 20mm; Form the Ω type suspension ring 6 of 4 pin-connected panel prefabricated reinforced concrete construction temporary roads,, reserve the drain hole 7 of 4 temporary roads simultaneously in the position of Ω type suspension ring 6 as the suspension centre that pin-connected panel prefabricated reinforced concrete construction temporary road is installed.After treating that preparation is carried out; Around box-type member 3, the pin-connected panel prefabricated reinforced concrete temporary road template 8 of constructing is installed with the bottom; As shown in Figure 7, adopt 9 pairs of templates 8 of formwork reinforcement spare to reinforce, after template 8 installations scene is cleared up and inspected for acceptance.
As shown in Figure 8, acceptance(check) after-pouring concrete 10 also carries out maintenance.
To shown in Figure 11, after the intensity that reaches designing requirement, stripping girth member 9 and template 8 form pin-connected panel prefabricated reinforced concrete construction temporary road like Fig. 9.
When the job site is tamped smooth to the ground of temporary road and is reached requirement; Pin-connected panel prefabricated reinforced concrete construction temporary road is transported to the scene; Adopt hoisting machine tool that pin-connected panel prefabricated reinforced concrete construction temporary road is lifted, accomplish the construction of pin-connected panel prefabricated reinforced concrete construction temporary road.
Claims (6)
1. pin-connected panel prefabricated reinforced concrete construction temporary road; It is characterized in that: comprise box-type member (3); Be provided with steel concrete box member (4) in the said box-type member (3); The same box-type member of reinforcing bar (5) (3) welding of said steel concrete box member (4) is fixing, and four angle points of said steel concrete box member (4) are respectively equipped with Ω type suspension ring (6), locate also to be provided with drain hole (7) at said Ω type suspension ring (6).
2. pin-connected panel prefabricated reinforced concrete construction temporary road according to claim 1, it is characterized in that: said box-type member (3) is made up of rectangular elements (1) lower end four welded corner joint rectangular elements supporting legs (2).
3. pin-connected panel prefabricated reinforced concrete construction temporary road according to claim 2, it is characterized in that: said rectangular elements (1) is welded for equal leg angle.
4. pin-connected panel prefabricated reinforced concrete construction temporary road according to claim 2, it is characterized in that: said member supporting leg (2) is welded for angle steel.
5. pin-connected panel prefabricated reinforced concrete construction temporary road according to claim 1, it is characterized in that: said box-type member (3) periphery and bottom are provided with template (8), and said template adopts girth member (9) to reinforce for (8) four jiaos.
6. pin-connected panel prefabricated reinforced concrete construction temporary road according to claim 1, it is characterized in that: said Ω type suspension ring (6) are welded for the reinforcing bar (5) of the round steel of 20mm and steel concrete box member (4).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012100588917A CN102619152A (en) | 2012-03-08 | 2012-03-08 | Split mounting type prefabricated reinforced concrete construction temporary road |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012100588917A CN102619152A (en) | 2012-03-08 | 2012-03-08 | Split mounting type prefabricated reinforced concrete construction temporary road |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102619152A true CN102619152A (en) | 2012-08-01 |
Family
ID=46559336
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012100588917A Pending CN102619152A (en) | 2012-03-08 | 2012-03-08 | Split mounting type prefabricated reinforced concrete construction temporary road |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102619152A (en) |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103194947A (en) * | 2013-04-25 | 2013-07-10 | 中建四局第六建筑工程有限公司 | Recyclable temporary road subgrade block |
CN103866670A (en) * | 2014-02-28 | 2014-06-18 | 中国建筑股份有限公司 | Novel fabricated vehicle bearing pavement and construction method thereof |
CN104088213A (en) * | 2014-07-18 | 2014-10-08 | 中建三局集团有限公司 | Temporary road high-strength walkway plate and special trolley |
CN105563640A (en) * | 2015-12-30 | 2016-05-11 | 江海燕 | Manufacturing process for environment-friendly construction modularization tool type temporary road plate block |
CN106884366A (en) * | 2017-04-24 | 2017-06-23 | 中建二局第二建筑工程有限公司华东分公司 | A kind of assembled road and its construction method |
CN107841911A (en) * | 2017-10-13 | 2018-03-27 | 北京天恒建设工程有限公司 | A kind of partition design method for closed construction site precast splice type temporary road |
CN108277716A (en) * | 2018-03-23 | 2018-07-13 | 中交雄安投资有限公司 | A kind of recyclable assembly concrete Prefabricated road and its construction technology |
CN108394013A (en) * | 2018-03-23 | 2018-08-14 | 中交航局第工程有限公司 | A kind of harbour wearing course and the prefabricated mounting process of the big plate of road and storage yard |
CN108708241A (en) * | 2018-07-10 | 2018-10-26 | 江苏金贸科技发展有限公司 | A kind of prefabricated ground of the repeatable temporary building utilized |
CN109183550A (en) * | 2018-10-09 | 2019-01-11 | 中建四局第六建筑工程有限公司 | One kind can fast have enough to meet the need interim road laying method |
CN109252711A (en) * | 2018-11-12 | 2019-01-22 | 上海宝冶集团有限公司 | Precast splice type steel bar meter field and its manufacturing method |
CN110593049A (en) * | 2019-09-16 | 2019-12-20 | 中冶天工集团有限公司 | Rapid threading pipeline and threading method for temporary road |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008156934A (en) * | 2006-12-25 | 2008-07-10 | Nippon Steel Corp | Lining plate |
CN201908244U (en) * | 2010-12-28 | 2011-07-27 | 北京城乡建设集团有限责任公司 | Massive road precast slab |
CN202073005U (en) * | 2011-04-15 | 2011-12-14 | 中天建设集团有限公司 | Shaped road module |
CN202466352U (en) * | 2012-03-08 | 2012-10-03 | 中天建设集团有限公司 | Spliced prefabricated reinforced concrete construction temporary road |
-
2012
- 2012-03-08 CN CN2012100588917A patent/CN102619152A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008156934A (en) * | 2006-12-25 | 2008-07-10 | Nippon Steel Corp | Lining plate |
CN201908244U (en) * | 2010-12-28 | 2011-07-27 | 北京城乡建设集团有限责任公司 | Massive road precast slab |
CN202073005U (en) * | 2011-04-15 | 2011-12-14 | 中天建设集团有限公司 | Shaped road module |
CN202466352U (en) * | 2012-03-08 | 2012-10-03 | 中天建设集团有限公司 | Spliced prefabricated reinforced concrete construction temporary road |
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103194947A (en) * | 2013-04-25 | 2013-07-10 | 中建四局第六建筑工程有限公司 | Recyclable temporary road subgrade block |
CN103194947B (en) * | 2013-04-25 | 2015-08-19 | 中建四局第六建筑工程有限公司 | A kind of temporary road ballast lump having enough to meet the need use |
CN103866670A (en) * | 2014-02-28 | 2014-06-18 | 中国建筑股份有限公司 | Novel fabricated vehicle bearing pavement and construction method thereof |
CN104088213A (en) * | 2014-07-18 | 2014-10-08 | 中建三局集团有限公司 | Temporary road high-strength walkway plate and special trolley |
CN105563640A (en) * | 2015-12-30 | 2016-05-11 | 江海燕 | Manufacturing process for environment-friendly construction modularization tool type temporary road plate block |
CN106884366A (en) * | 2017-04-24 | 2017-06-23 | 中建二局第二建筑工程有限公司华东分公司 | A kind of assembled road and its construction method |
CN107841911A (en) * | 2017-10-13 | 2018-03-27 | 北京天恒建设工程有限公司 | A kind of partition design method for closed construction site precast splice type temporary road |
CN107841911B (en) * | 2017-10-13 | 2019-11-12 | 北京天恒建设工程有限公司 | A kind of partition design method for closed construction site temporary road |
CN108277716A (en) * | 2018-03-23 | 2018-07-13 | 中交雄安投资有限公司 | A kind of recyclable assembly concrete Prefabricated road and its construction technology |
CN108394013A (en) * | 2018-03-23 | 2018-08-14 | 中交航局第工程有限公司 | A kind of harbour wearing course and the prefabricated mounting process of the big plate of road and storage yard |
CN108708241A (en) * | 2018-07-10 | 2018-10-26 | 江苏金贸科技发展有限公司 | A kind of prefabricated ground of the repeatable temporary building utilized |
CN109183550A (en) * | 2018-10-09 | 2019-01-11 | 中建四局第六建筑工程有限公司 | One kind can fast have enough to meet the need interim road laying method |
CN109252711A (en) * | 2018-11-12 | 2019-01-22 | 上海宝冶集团有限公司 | Precast splice type steel bar meter field and its manufacturing method |
CN110593049A (en) * | 2019-09-16 | 2019-12-20 | 中冶天工集团有限公司 | Rapid threading pipeline and threading method for temporary road |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102619152A (en) | Split mounting type prefabricated reinforced concrete construction temporary road | |
CN104746422B (en) | A kind of hollow pier stud delay-pour joint structure of bridge prefabrication and construction method | |
CN113481931B (en) | Modular assembly type high-pile wharf structure and construction method thereof | |
CN105563640A (en) | Manufacturing process for environment-friendly construction modularization tool type temporary road plate block | |
CN105603843A (en) | Assembled reinforced concrete prefabricated pavement slab and construction method thereof | |
CN102704948A (en) | Formworking jumbo construction process for long and large box culvert | |
CN104047422B (en) | A kind of cylinder mold fabrication and installation method | |
WO2021097863A1 (en) | Swirl pool construction method employing semi-reverse construction | |
CN103711056A (en) | Steel tool type temporary construction road and construction method thereof | |
CN204097864U (en) | A kind of bridge prefabrication hollow pier stud delay-pour joint structure | |
CN103452350A (en) | Fabricated electronic workshop and construction method thereof | |
CN205443834U (en) | Novel reinforced concrete prefabricated section | |
CN102425190A (en) | Superposed tower crane foundation | |
CN202466352U (en) | Spliced prefabricated reinforced concrete construction temporary road | |
CN104032767A (en) | Tower crane foundation in deep foundation pit and construction method of tower crane foundation | |
CN112431208A (en) | Construction method for deep foundation pit supporting by adopting component type force transmission belt | |
CN210288002U (en) | But reuse is construction way temporarily | |
CN103882883A (en) | Method for constructing foundation shared by tower crane and garage frame column | |
CN207003465U (en) | A kind of detachable prefabricated steel body tower crane | |
CN104963344B (en) | The deep basal pit underground construction method that concrete supporting removal and structure construction are synchronously carried out | |
CN205502058U (en) | Pin -connected panel tower crane foundation | |
CN213296364U (en) | Connecting piece and supporting beam steel bar assembly for cast-in-place reinforced concrete foundation pit inner support sectional construction | |
CN210163936U (en) | Pile culvert integrally-assembled steel bone concrete comprehensive pipe gallery | |
CN103088829B (en) | The construction method that in a kind of foundation ditch, concrete supports | |
CN204151662U (en) | A kind of one across the temporary trestle bridge crossing over river valley |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20120801 |