CN202081633U - Detachable scaffold locking plate - Google Patents
Detachable scaffold locking plate Download PDFInfo
- Publication number
- CN202081633U CN202081633U CN2011201688805U CN201120168880U CN202081633U CN 202081633 U CN202081633 U CN 202081633U CN 2011201688805 U CN2011201688805 U CN 2011201688805U CN 201120168880 U CN201120168880 U CN 201120168880U CN 202081633 U CN202081633 U CN 202081633U
- Authority
- CN
- China
- Prior art keywords
- sleeve
- lock collar
- locking plate
- vertical rod
- detachable scaffold
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Abstract
The utility model discloses a detachable scaffold locking plate, which consists of a sleeve (1) and latches (2). The detachable scaffold locking plate is characterized in that latches (2) are symmetrically arranged on the sleeve (1); the sleeve (1) is fixedly connected with the latches (2) into a whole to form a locking plate; and a screw hole (3) is arranged at the side face of the sleeve (1). The latches (2) are in a shape of diamond or square. The detachable scaffold locking plate has the advantages of being simply structured and being convenient to store and being stably structured, being convenient to mount and dismount, saving resources, being beneficial to maintaining a vertical rod and increasing work efficiency.
Description
Technical field
The utility model relates to a kind of link of scaffold, relates to a kind of detachable scaffold lock collar specifically, the support that is widely used in high lowrise construction, overpass bridge, power station, sports palace building complex assembly unit scaffold be connected.
Background technology
In recent years, along with China's rapid economy development, real estate building, bridge construction were also constantly accelerated development thereupon.At present, the bracing frame of room finish, building operations or bridge construction adopts the lumps of wood as stressed support system usually, perhaps be connected and fixed built as bracing frame by steel pipe, brace, lock collar, the connection of its bracing frame generally is that lock collar directly is weldingly fixed in the vertical rod, and cross bar reinstalls in the lock collar jack and connects to form bracing frame then.So, the deficiency of its existence is: 1. the component lock collar is directly to be weldingly fixed on vertical rod, is unfavorable for the replacing and the maintenance of lock collar; 2. the component lock collar is directly to be weldingly fixed in the vertical rod, and when the vertical rod damage needed to change, the lock collar in the vertical rod can't be dismantled also to be needed to change, and causes the wasting of resources.
Summary of the invention
In order to overcome the deficiency that now above technology exists, the purpose of this utility model be to provide a kind of simple in structure, structure firmly, easy accessibility, cheap, safe and reliable detachable scaffold lock collar.
The technical scheme that the utility model technical solution problem is adopted is: a kind of detachable scaffold lock collar, it is made up of sleeve, snap close, it is characterized in that: described sleeve is provided with the snap close of symmetry, described sleeve and the snap close composition lock collar that is connected to one, described cartridges sides is provided with screw.Described snap close is shaped as rhombus or square.
The beneficial effects of the utility model: not only simple in structure, store convenient, and Stability Analysis of Structures, easy accessibility, economize on resources, help vertical rod maintenance, increase work efficiency.
Description of drawings
Below in conjunction with drawings and Examples the utility model is further specified.
Fig. 1 is the structural representation of lock collar embodiment one;
Fig. 2 is the plan structure schematic diagram of Fig. 1;
Fig. 3 is another example structure schematic diagram of lock collar;
Fig. 4 is the plan structure schematic diagram of Fig. 3;
Fig. 5 is the user mode structural representation of lock collar;
Among the figure: 1. sleeve, 2. snap close, 3. screw, 4a. rhombus jack, the square jack of 4b., 5. vertical rod, 6. cross bar, 7. bolt, 8. latch.
The specific embodiment
Embodiment one
Shown in Fig. 1,2,5, a kind of detachable scaffold lock collar, it is made up of sleeve 1, snap close 2.Described snap close 2 inboards are provided with sleeve 1, and described sleeve 1 and snap close 2 are fixedly connected by welding and form lock collar into one, and described sleeve 1 side is provided with screw 3, and described snap close 2 is shaped as rhombus.
During installation, on smooth ground, at first lock collar of the present utility model is inserted in vertical rod 5, pass screw 3 by the 3 usefulness bolts 7 of the screw on sleeve 1 side lock collar is connected fixing with vertical rod 5, then the latch 8 of cross bar 6 is aimed in the rhombus jack 4a that inserts snap closes 2 fixing, four rhombus jack 4a cross bar 6 of all packing into.By above mounting method, lock collar of the present utility model is fixedlyed connected by bolt 7 with another vertical rod 5, and then connects by cross bar 6, forms bracing frame by cross bar 6 between promptly per two lock collars, install repeatedly with the method, form a bracing frame that needs by real work.Damage that needs are safeguarded or when changing vertical rod 5, bolt 7 turned on the back take out lock collar when occurring vertical rod 5 in the use, keep in repair or the vertical rod 5 that more renews after reinstall again, thereby effectively avoid the waste of lock collar, economize on resources, increase work efficiency.
Embodiment two
Shown in Fig. 3,4,5, a kind of detachable scaffold lock collar, it is made up of sleeve 1, snap close 2.Described snap close 2 inboards are provided with sleeve 1, and described sleeve 1 and snap close 2 are fixedly connected by welding and form lock collar into one, and described sleeve 1 side is provided with screw 3, and described snap close 2 is shaped as square.
During installation, on smooth ground, at first lock collar of the present utility model is inserted in vertical rod 5, pass screw 3 by the 3 usefulness bolts 7 of the screw on sleeve 1 side lock collar is connected fixing with vertical rod 5, then the latch 8 of cross bar 6 is aimed in the square jack 4b that inserts snap closes 2 fixing, four square jack 4b cross bar 6 of all packing into.By above mounting method, lock collar of the present utility model is fixedlyed connected by bolt 7 with another vertical rod 5, and then connects by cross bar 6, forms bracing frame by cross bar 6 between promptly per two lock collars, install repeatedly with the method, form a bracing frame that needs by real work.Damage that needs are safeguarded or when changing vertical rod 5, bolt 7 turned on the back take out lock collar when occurring vertical rod 5 in the use, keep in repair or the vertical rod 5 that more renews after reinstall again, thereby effectively avoid the waste of lock collar, economize on resources, increase work efficiency.
Above disclosed only is preferred embodiment of the present utility model, can not limit the interest field of the utility model certainly with this, and therefore the equivalent variations of being done according to the utility model claim still belongs to the scope that the utility model is contained.
Claims (2)
1. detachable scaffold lock collar, it is made up of sleeve (1), snap close (2), it is characterized in that: described sleeve (1) is provided with the snap close (2) of symmetry, described sleeve (1) and snap close (2) the composition lock collar that is connected to one, and described sleeve (1) side is provided with screw (3).
2. detachable scaffold lock collar according to claim 1 is characterized in that: described snap close (2) is shaped as rhombus or square.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011201688805U CN202081633U (en) | 2011-05-25 | 2011-05-25 | Detachable scaffold locking plate |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011201688805U CN202081633U (en) | 2011-05-25 | 2011-05-25 | Detachable scaffold locking plate |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202081633U true CN202081633U (en) | 2011-12-21 |
Family
ID=45342269
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011201688805U Expired - Fee Related CN202081633U (en) | 2011-05-25 | 2011-05-25 | Detachable scaffold locking plate |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202081633U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102704670A (en) * | 2012-06-24 | 2012-10-03 | 郑德春 | Lower bowl-type coupler for bowl-type coupler scaffolding, and mounting method thereof |
CN103452305A (en) * | 2012-05-30 | 2013-12-18 | 王新宏 | Movable scaffold allowing quick assembly and disassembly |
CN103628667A (en) * | 2013-12-02 | 2014-03-12 | 魏志光 | Slippage-preventing cross-shaped connecting pallet |
-
2011
- 2011-05-25 CN CN2011201688805U patent/CN202081633U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103452305A (en) * | 2012-05-30 | 2013-12-18 | 王新宏 | Movable scaffold allowing quick assembly and disassembly |
CN102704670A (en) * | 2012-06-24 | 2012-10-03 | 郑德春 | Lower bowl-type coupler for bowl-type coupler scaffolding, and mounting method thereof |
CN102704670B (en) * | 2012-06-24 | 2014-05-07 | 郑德春 | Lower bowl-type coupler for bowl-type coupler scaffolding, and mounting method thereof |
CN103628667A (en) * | 2013-12-02 | 2014-03-12 | 魏志光 | Slippage-preventing cross-shaped connecting pallet |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204435843U (en) | A kind of steel tube scaffold linkage | |
CN203808484U (en) | Integrated cantilevered and attached external scaffolding | |
CN206487126U (en) | A kind of scaffold for the architectural engineering being easily installed | |
CN202081633U (en) | Detachable scaffold locking plate | |
CN201176703Y (en) | Tripod for construction of hyperbola cooling tower cylinder | |
CN103362298A (en) | Mobile tower scaffold with circular disc connecting device | |
CN202081634U (en) | Detachable bolt for locking disc of scaffold | |
CN204199667U (en) | Detachable builder's jack corner tripod | |
CN201428238Y (en) | Expansion sleeve type scaffold connecting part | |
CN202990407U (en) | Quick-release scaffold | |
CN201943331U (en) | Direct insertion type scaffold | |
CN202544399U (en) | Supporting frame for overhang floor slab with steel structure | |
CN202850515U (en) | Regulating-type temporary supporting rod for inclined steel column installation | |
CN203034788U (en) | Flexible scaffold capable of being rapidly assembled and detached | |
CN202055509U (en) | Upright rod installation structure of directly-inserted scaffold | |
CN205591507U (en) | Scaffold frame of easily dismantling | |
CN201588414U (en) | Supporting structure for framework scaffolds | |
CN103866865B (en) | The pre-buried fixing means of a diameter of 48mm foundation bolt | |
CN202990417U (en) | Building modularized floor support | |
CN204590563U (en) | A kind of Novel dismountable scaffold | |
CN203729567U (en) | Scaffold connecting rod | |
CN218970608U (en) | Scaffold connecting piece for construction engineering construction | |
CN205224557U (en) | Lift scaffold pole setting connection structure | |
CN203257115U (en) | Tool-type welding steel pipe border protection frame fixing piece | |
CN204552038U (en) | A kind of mortise and tenon type scaffold diagonal brace system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |