CN201778497U - 一种多节柱高空拼装的临时固定装置 - Google Patents

一种多节柱高空拼装的临时固定装置 Download PDF

Info

Publication number
CN201778497U
CN201778497U CN2010202402800U CN201020240280U CN201778497U CN 201778497 U CN201778497 U CN 201778497U CN 2010202402800 U CN2010202402800 U CN 2010202402800U CN 201020240280 U CN201020240280 U CN 201020240280U CN 201778497 U CN201778497 U CN 201778497U
Authority
CN
China
Prior art keywords
column
aloft
section
fixing device
utility
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010202402800U
Other languages
English (en)
Inventor
罗放
王永乐
李杨
赵艳丽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN2010202402800U priority Critical patent/CN201778497U/zh
Application granted granted Critical
Publication of CN201778497U publication Critical patent/CN201778497U/zh
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本实用新型涉及高层、超高层钢结构,尤其涉及一种多节柱高空拼装的辅助装置。一种多节柱高空拼装的临时固定装置,所述临时固定装置设置在每节柱的两端,并包括:焊接在每节柱两端侧面的并设有螺纹孔的耳板;夹持在所述耳板之间的两个夹板,并以螺栓和耳板固定连接。本实用新型不仅保证了超重型吊车梁吊装安全,提高了吊装效率,同时也节约了吊装成本,具有广泛的经济效益及社会效益。

Description

一种多节柱高空拼装的临时固定装置
技术领域
本实用新型涉及高层、超高层钢结构,尤其涉及一种多节柱高空拼装的辅助装置。
背景技术
在工程结构施工过程中,随着工程的发展,高层和超高层结构应用越来越多,许多工业及民用建筑的高度越来越大,由于设计刚度及强度要求,部分钢柱在设计过程中均超长。因运输长度及安装现场起重设备等客观因素的影响,超长构件在运输及现场吊装过程中十分不便,且易发生安全事故,如分节运至安装现场进行拼接,安装的定位及精度很难控制,且易出现偏差过大,影响整个工程的质量,消耗大量人力物力及大型的起重设备。
发明内容
本实用新型旨在解决上述问题,提供一种超重型钢结构吊车梁吊装用吊耳。本实用新型不仅保证了超重型吊车梁吊装安全,提高了吊装效率,同时也节约了吊装成本,具有广泛的经济效益及社会效益。
本实用新型是这样实现的:一种多节柱高空拼装的临时固定装置,其特征在于,所述临时固定装置设置在每节柱的两端,并包括:
焊接在每节柱两端侧面的并设有螺纹孔的耳板;和
夹持在所述耳板之间的两个夹板,并以螺栓和耳板固定连接。
本实用新型是利用几组耳板打双夹板的方式分别将对接的上下节柱的几部分固定,用螺栓加垫板将上下节柱连接,待焊接完成达到设计要求后,将装置切割下来回收利用。考虑安装工程荷载,上下节柱在安装过程中,对耳板及连接板有一定的刚度及强度要求,故其厚度不宜过薄,一般厚度在10mm以上。这样将柱分节运输至安装现场,上下节柱相对应位置上均焊有连接装置,钢柱吊装到位后,用拉揽绳准确调整好位置后,校好垂直度后,在现场进行用螺栓加垫板将上下节柱连接起来,作为临时固定装置,待焊接强度达到设计要求后,将装置切割下来回收利用。这样既确保安装精度,提高效率及整个工程的质量,同时又减少安装吊机的占用时间,大大节省了运输及起重设备等的费用。
附图说明
下面结合附图和实施方式对本实用新型作进一步的详细说明:
图1为本实用新型结构示意图;
图2为图1的A-A剖面图。
具体实施方式
本实用新型使用各种多节柱子,如圆形柱、H型钢柱、方形柱等,本具体实施方式以方形柱来说明,如图1所示:一种多节柱高空拼装的临时固定装置,所述临时固定装置设置在每节柱4的两端,并包括:
焊接在每节柱两端侧面的并设有螺纹孔的耳板1;和
夹持在所述耳板1之间的两个夹板2,并以螺栓3和耳板1固定连接。

Claims (1)

1.一种多节柱高空拼装的临时固定装置,其特征在于,所述临时固定装置设置在每节柱的两端,并包括:
焊接在每节柱两端侧面的并设有螺纹孔的耳板;
夹持在所述耳板之间的两个夹板,并以螺栓和耳板固定连接。
CN2010202402800U 2010-06-25 2010-06-25 一种多节柱高空拼装的临时固定装置 Expired - Fee Related CN201778497U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010202402800U CN201778497U (zh) 2010-06-25 2010-06-25 一种多节柱高空拼装的临时固定装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010202402800U CN201778497U (zh) 2010-06-25 2010-06-25 一种多节柱高空拼装的临时固定装置

Publications (1)

Publication Number Publication Date
CN201778497U true CN201778497U (zh) 2011-03-30

Family

ID=43791711

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010202402800U Expired - Fee Related CN201778497U (zh) 2010-06-25 2010-06-25 一种多节柱高空拼装的临时固定装置

Country Status (1)

Country Link
CN (1) CN201778497U (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101906849A (zh) * 2010-07-14 2010-12-08 中建钢构有限公司 钢柱对接的连接装置及安装方法
CN102966184A (zh) * 2012-12-03 2013-03-13 中建一局钢结构工程有限公司 大跨度钢结构桁架预留合拢带装置及其施工方法
CN104295104A (zh) * 2014-10-29 2015-01-21 防城港中一重工有限公司 箱型吊车梁高强螺栓群现场安装方法
CN108560928A (zh) * 2018-02-13 2018-09-21 广西建工集团第五建筑工程有限责任公司 一种可调式钢结构拼装夹具及其用于钢结构拼装的施工方法
CN114250724A (zh) * 2021-11-25 2022-03-29 上海建工集团股份有限公司 一种钢抱箍支撑式桥梁下部结构拆除装置及其安装方法

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101906849A (zh) * 2010-07-14 2010-12-08 中建钢构有限公司 钢柱对接的连接装置及安装方法
CN102966184A (zh) * 2012-12-03 2013-03-13 中建一局钢结构工程有限公司 大跨度钢结构桁架预留合拢带装置及其施工方法
CN104295104A (zh) * 2014-10-29 2015-01-21 防城港中一重工有限公司 箱型吊车梁高强螺栓群现场安装方法
CN108560928A (zh) * 2018-02-13 2018-09-21 广西建工集团第五建筑工程有限责任公司 一种可调式钢结构拼装夹具及其用于钢结构拼装的施工方法
CN114250724A (zh) * 2021-11-25 2022-03-29 上海建工集团股份有限公司 一种钢抱箍支撑式桥梁下部结构拆除装置及其安装方法
CN114250724B (zh) * 2021-11-25 2023-07-28 上海建工集团股份有限公司 一种钢抱箍支撑式桥梁下部结构拆除装置及其安装方法

Similar Documents

Publication Publication Date Title
CN201778497U (zh) 一种多节柱高空拼装的临时固定装置
CN102535682A (zh) 一种预制混凝土剪力墙结构墙板构件可更换连接节点
CN102530732A (zh) 大型压力机部件液压提升滑移就位方法及设备
CN105442701A (zh) 一种空间网架结构及其施工方法
CN104005569A (zh) 一种托梁拔柱施工方法
CN103835527A (zh) 一种可拆卸的顶撑装置和它的应用
CN203938346U (zh) 自动扶梯桁架连接结构
CN103669218A (zh) 新型的钢混结合段钢箱梁模块及其组拼方法
CN203247868U (zh) 大跨度钢结构施工临时支撑架
CN103343639A (zh) 一种高效调节的滑模系统
CN103225396B (zh) 梁架式建筑模板系统
CN202509667U (zh) 组合式钢筋桁架楼承板
CN202090291U (zh) 张拉支座
CN103485463A (zh) 钢结构楼板
CN204024088U (zh) 厂房钢柱分段吊装对接的快速定位装置
CN204126297U (zh) 一种钢桁架屋顶的临时支撑架
CN102155095A (zh) 大型冶金工业厂房钢骨混凝土钢筋的布置方法
CN203420359U (zh) 钢结构支撑系统中承受超大荷载的梁柱连接的刚接节点
CN203188612U (zh) 梁架式建筑模板系统
CN202049034U (zh) 千吨模块化组合式可调自反力台架装置
CN210395642U (zh) 一种可拆卸装配式钢结构建筑连接节点
CN203247718U (zh) 一种钢柱对接安装装置
CN208965579U (zh) 一种非落地式格构式塔吊基础平台
CN104032975B (zh) 一种集装箱式房屋的加固方法
CN202595911U (zh) 旋转盘式连接器

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110330

Termination date: 20180625