CN201762666U - Capping construction support - Google Patents
Capping construction support Download PDFInfo
- Publication number
- CN201762666U CN201762666U CN2010205313086U CN201020531308U CN201762666U CN 201762666 U CN201762666 U CN 201762666U CN 2010205313086 U CN2010205313086 U CN 2010205313086U CN 201020531308 U CN201020531308 U CN 201020531308U CN 201762666 U CN201762666 U CN 201762666U
- Authority
- CN
- China
- Prior art keywords
- ears
- anchor ear
- iron
- construction
- bridge pier
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Abstract
Description
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010205313086U CN201762666U (en) | 2010-09-16 | 2010-09-16 | Capping construction support |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010205313086U CN201762666U (en) | 2010-09-16 | 2010-09-16 | Capping construction support |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201762666U true CN201762666U (en) | 2011-03-16 |
Family
ID=43715277
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010205313086U Expired - Fee Related CN201762666U (en) | 2010-09-16 | 2010-09-16 | Capping construction support |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201762666U (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102234982A (en) * | 2011-05-10 | 2011-11-09 | 吴江市明港道桥工程有限公司 | Circular pier capping beam supporting device |
CN102286925A (en) * | 2011-07-08 | 2011-12-21 | 四川路航建设工程有限责任公司 | Bridge single column pier assembled box bracket system and mounting method thereof |
CN102296542A (en) * | 2011-06-14 | 2011-12-28 | 汇通路桥建设集团有限公司 | Method for constructing high pier capping beams |
CN112030750A (en) * | 2020-07-17 | 2020-12-04 | 中交一公局集团有限公司 | Construction process for tie beam in water |
CN113389144A (en) * | 2021-05-21 | 2021-09-14 | 中冶天工集团有限公司 | Bridge bent cap construction antiskid staple bolt |
CN114045759A (en) * | 2021-11-16 | 2022-02-15 | 广西路桥工程集团有限公司 | Method for erecting cover beam dismantling platform of old bridge in water |
CN114606863A (en) * | 2022-03-11 | 2022-06-10 | 中铁二十四局集团有限公司 | Integrative elevating gear of bent cap template |
CN114875800A (en) * | 2022-06-09 | 2022-08-09 | 福建第一公路工程集团有限公司 | Capping beam construction device and method |
-
2010
- 2010-09-16 CN CN2010205313086U patent/CN201762666U/en not_active Expired - Fee Related
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102234982A (en) * | 2011-05-10 | 2011-11-09 | 吴江市明港道桥工程有限公司 | Circular pier capping beam supporting device |
CN102296542A (en) * | 2011-06-14 | 2011-12-28 | 汇通路桥建设集团有限公司 | Method for constructing high pier capping beams |
CN102296542B (en) * | 2011-06-14 | 2013-06-12 | 汇通路桥建设集团有限公司 | Method for constructing high pier capping beams |
CN102286925A (en) * | 2011-07-08 | 2011-12-21 | 四川路航建设工程有限责任公司 | Bridge single column pier assembled box bracket system and mounting method thereof |
CN112030750A (en) * | 2020-07-17 | 2020-12-04 | 中交一公局集团有限公司 | Construction process for tie beam in water |
CN113389144A (en) * | 2021-05-21 | 2021-09-14 | 中冶天工集团有限公司 | Bridge bent cap construction antiskid staple bolt |
CN114045759A (en) * | 2021-11-16 | 2022-02-15 | 广西路桥工程集团有限公司 | Method for erecting cover beam dismantling platform of old bridge in water |
CN114606863A (en) * | 2022-03-11 | 2022-06-10 | 中铁二十四局集团有限公司 | Integrative elevating gear of bent cap template |
CN114606863B (en) * | 2022-03-11 | 2023-10-03 | 中铁二十四局集团有限公司 | Integrated lifting device for bent cap template |
CN114875800A (en) * | 2022-06-09 | 2022-08-09 | 福建第一公路工程集团有限公司 | Capping beam construction device and method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201762666U (en) | Capping construction support | |
CN202359506U (en) | Double hoop supporting system for pier column capping beam | |
CN105803946B (en) | A kind of bent cap can quick regulation support and its construction method | |
CN205604088U (en) | But bent cap quick adjustment support | |
CN107119574A (en) | A kind of Cantilever Construction Method of arch rib bridge girder | |
CN102296542B (en) | Method for constructing high pier capping beams | |
CN101041974A (en) | Structure conversion layer type steel concrete girder mould suspension construction method | |
CN110331668A (en) | A kind of back-cable-free cable-stayed bridge inclined in two-way V-shaped bridge tower construction method | |
CN204690605U (en) | The self-propelled triangular truss hanging basket of large span beam bridge | |
CN105421245B (en) | Bent cap is without support steel hoop method construction technology | |
CN107905124B (en) | A kind of symmetrical expression rigid frame-continuous girder construction technology | |
CN103306208A (en) | Formwork creeping method for novel 1.6 parabola-shaped four-column type hollow variable section high pier | |
CN105568870B (en) | For the triangle hanging basket method cantilever device and its construction method of cross-line bridge construction | |
CN107905111B (en) | A kind of rigid frame-continuous girder end bay construction technology | |
CN105507168A (en) | Multi-span box girder integral ultrahigh alternate jacking construction system and method | |
CN107905114A (en) | A kind of construction method of large span Successive interference cancellation | |
CN104831639B (en) | A kind of ultra-wide nonprismatic continuous beam 0# block consolidation and releasing construction method | |
CN101781878A (en) | Integral lifting template of main pylon of single-pylon cable-stayed bridge without dorsal cables and lifting construction method thereof | |
CN103195450A (en) | Hydraulic tunnel inverted arch operation trolley and inverted arch construction method | |
CN102251481B (en) | Railway pier layered construction method and construction device | |
CN102797223B (en) | Construction method for cast-in-place of continuous beam at turnout junction for passenger transport line in seawall area by false work method | |
CN103938871B (en) | A kind of construction method adopting the steel core concrete column bonded prestress frame beam structure of reinforced concrete ring beam joint | |
CN102277836B (en) | Construction method of tilting concrete tower base | |
CN209194353U (en) | It is a kind of to ride integral type bracket suitable for the construction of Bridge High-pier 0# block | |
CN102733307A (en) | Method for constructing cast-in-place beam falsework |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
ASS | Succession or assignment of patent right |
Free format text: FORMER OWNER: CHINA RAILWAY 19TH BUREAU GROUP 1ST CO., LTD. CHINA RAILWAY 19 BUREAU GROUP CHINA RAILWAY 19TH BUREAU GROUP 5TH CO., LTD. |
|
C41 | Transfer of patent application or patent right or utility model | ||
TR01 | Transfer of patent right |
Effective date of registration: 20110614 Address after: 111004 No. 17 Heping Road, Baita District, Liaoning, Liaoyang Patentee after: China Railway 19th Bureau Group 2nd Co., Ltd. Address before: 111004 No. 17 Heping Road, Baita District, Liaoning, Liaoyang Co-patentee before: China Railway 19th Bureau Group 1st Engineering Co., Ltd. Patentee before: China Railway 19th Bureau Group 2nd Co., Ltd. Co-patentee before: China Railway 19th Bureau Group Co., Ltd. Co-patentee before: China Railway 19th Bureau Group 5th Co., Ltd. |
|
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20110316 Termination date: 20190916 |
|
CF01 | Termination of patent right due to non-payment of annual fee |