CN112030750A - Construction process for tie beam in water - Google Patents

Construction process for tie beam in water Download PDF

Info

Publication number
CN112030750A
CN112030750A CN202010689968.5A CN202010689968A CN112030750A CN 112030750 A CN112030750 A CN 112030750A CN 202010689968 A CN202010689968 A CN 202010689968A CN 112030750 A CN112030750 A CN 112030750A
Authority
CN
China
Prior art keywords
tie beam
steel
construction
concrete
template
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202010689968.5A
Other languages
Chinese (zh)
Inventor
周敏
易文龙
蒋妙强
彭红心
王强
朱继根
刘兴勃
孙磊
曹庆国
陈系阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cccc Guanglian Expressway Investment Development Co ltd
CCCC First Highway Engineering Co Ltd
Bridge and Tunnel Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Original Assignee
Cccc Guanglian Expressway Investment Development Co ltd
CCCC First Highway Engineering Co Ltd
Bridge and Tunnel Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cccc Guanglian Expressway Investment Development Co ltd, CCCC First Highway Engineering Co Ltd, Bridge and Tunnel Engineering Co Ltd of CCCC First Highway Engineering Co Ltd filed Critical Cccc Guanglian Expressway Investment Development Co ltd
Priority to CN202010689968.5A priority Critical patent/CN112030750A/en
Publication of CN112030750A publication Critical patent/CN112030750A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention provides a construction process of a tie beam in water, and relates to the technical field of tie beam construction. The underwater tie beam construction process specifically comprises the following steps: s1, construction preparation: firstly, cutting off a steel trestle platform, then cutting off a steel casing, and then chiseling and cleaning a pile head after cutting off the casing; s2, erecting a hoop support operation platform: after preparation work such as chiseling a construction platform and pile heads is finished, arranging measuring personnel to discharge the axis of the tie beam, and installing a hoop by the constructor according to the axis of the tie beam and the elevation of the tie beam; s3, mounting a bottom die; s4, processing and installing the steel bars; s6, pouring concrete; and S7, maintaining and removing the mold. According to the underwater beam tying construction process, the hoop support operation platform is directly established on the bridge pier stud during construction, workers can conveniently construct on the hoop support operation platform through the platform, and do not need to work on a ship body all the time, so that the construction cost and the construction time are greatly reduced.

Description

Construction process for tie beam in water
Technical Field
The invention relates to the technical field of tie beam construction, in particular to a construction process of a tie beam in water.
Background
The TJ04 standard section starts from the tail of a Li xi Zhen Wushi bridge in Engde, and finally reaches the 3 rd span of a big bridge in the North river, the origin-destination mileage is K56+ 208.2-K62 +243.726, the total length is 6036m, wherein 3 seats/1035.5 m of a main bridge and 5 seats/642.4 m of a ramp bridge, and the standard section has 8 bridges, namely a west-mouth big bridge, a Li xi Bei intercommunicated main line bridge, a Ping gang ridge big bridge, a Li xi Bei intercommunicated No. A ramp No. 1 bridge, a Li xi Bei intercommunicated No. 2 bridge, a Li xi Bei intercommunicated No. 4 bridge, a Li xi C ramp bridge and a Li xi Bei intercommunicated D ramp.
West-mouth bridge aquatic tie beam 10, set up the landing stage and construct, the construction scale is great, and west-mouth bridge is the environmental protection district of controlling closely, there is fishery to breed in the periphery, construction concrete placement, the vibration is to around, the environment produces great influence, so need improve the aquatic tie beam and construct to the surface of water, reduce the construction degree of difficulty, present surface of water construction mostly goes on the hull, construction cost is higher like this, and inconvenient operation, waste construction time relatively, need design an aquatic tie beam construction technology for this reason.
Disclosure of Invention
Technical problem to be solved
Aiming at the defects of the prior art, the invention provides an underwater tie beam construction process, which solves the problem that the existing tie beam construction process cannot meet the project construction.
(II) technical scheme
In order to achieve the purpose, the invention is realized by the following technical scheme: an underwater tie beam construction process specifically comprises the following steps:
s1, construction preparation: firstly, cutting off a steel trestle platform, then cutting off a steel casing, and then chiseling and cleaning a pile head after cutting off the casing;
s2, erecting a hoop support operation platform: after preparation work such as construction platform and pile head chisel out is accomplished, arrange the measurement personnel and emit the tie beam axis, constructor installs the staple bolt according to tie beam axis and tie beam elevation, its main step is as follows:
s2-1, firstly wrapping the pre-installation part of the underwater pile foundation by using geotextile, then hooping the anchor ear with the same diameter as the pile foundation at the pre-installation part of the pile foundation, and fastening by using bolts;
s2-2, installing two I56a I-shaped steel bars on hoops on two sides of a pile foundation respectively by using a truck crane, and welding the ends of the two I-shaped steel bars by using reinforcing steel bars to form a whole;
s2-3, after the I-shaped steel is installed, installing I18I-shaped steel serving as a distribution beam on the top surface of the I-shaped steel, wherein the distance is 0.5m, and the channel steel is placed vertically;
s2-4, after the construction platform is installed, arranging a vertical ladder from the trestle platform to the construction platform;
s3, installation of a bottom die: the bottom die is a shaped combined steel die, is uniformly processed and transported to a construction site by a manufacturer, then is assembled, then the template is assembled in sections by using a steam crane, the upper camber of 5-8 mm is reserved in the midspan when the bottom die is installed, the bottom die is arranged according to a parabolic line so as to eliminate lower deflection caused by the load bearing effect of a load bearing I-beam, rubber strips or adhesive tapes with the thickness of about 3mm are padded between the template joints to prevent concrete pitted surface caused by slurry leakage of the joints, and a release agent is uniformly coated after the template is installed;
s4, processing and installing the steel bars: the tie beam steel bars are manufactured in a concentrated mode in a steel bar yard, then the tie beam steel bars are transported to pier columns, and then the steel bars are adjusted to construction points through a steam crane to be installed;
s5, mounting of a side die: the installation of the side mold uses back cover mortar as a support, and uses the ink line which is well bounced on a mortar cushion layer to accurately position and install the tie beam template, after the installation of the side mold is finished, reinforcing steel bars with the diameter of 22mm are used as counter-pull rods to oppositely pull square channel steel at the top opening and the bottom of the template, so that the template is prevented from deforming, bolts with the diameter of 18mm are connected between the templates, and the bolts are connected and fastened according to requirements;
s6, pouring concrete: the concrete is intensively mixed in a mixing station and is transported to a construction site through a concrete tank truck, the concrete is transported into a tie beam template by adopting a chute during pouring, the chute is processed by adopting a bamboo plywood, and the lower part of the chute is supported by a steel pipe; the tie beam is formed by one-step pouring, concrete is poured in layers, the thickness of each layer is controlled to be 30cm, the next layer can be poured after one layer is vibrated, the vibration is carried out by adopting an inserted vibrator, the moving distance of the inserted vibrator is not more than 1.5 times of the action radius of the vibrator, the distance between the inserted vibrator and a side mold is kept to be 5-10 cm, the vibration time is 20-30 s, the degree is that the concrete stops sinking, no bubbles appear, the surface of the concrete presents laitance, the top surface is polished after the pouring is finished, and the surface flatness is ensured to meet the requirement;
s7, maintaining and removing the mold
S7-1, curing, namely, after concrete pouring is finished, covering and watering curing are carried out as soon as possible after final setting, the surface of the concrete cannot be damaged or polluted when covering, and when a template is covered on the surface of the concrete, the template is kept wet frequently during curing;
s7-2, dismantling the side mould, namely dismantling the side mould after the concrete strength reaches 2.5Mpa, and symmetrically, uniformly and sequentially propelling the side mould from the middle to two ends by using a crane;
s7-3, detaching the bottom die: and (3) when the strength of the concrete reaches 75% of the design strength, removing the bottom die, respectively threading two steel wire ropes with the diameter of 20 on each anchor ear, after the steel wire ropes are fixed, hoisting the four steel wire ropes by using a crane, after the crane is stable and in a stressed state, loosening the anchor ears on two sides simultaneously, slowly and upwards lifting the tie beam bottom die by using the crane at a constant speed until the tie beam bottom die falls onto the trestle platform, and then detaching the tie beam bottom die.
Preferably, the hoop in the step S2-1 is formed by connecting two semicircular arc-shaped plates through bolts, the arc-shaped plates are 16mm in thickness and 600mm in height, the radius of the arc-shaped plates is the same as the outer diameter of the pile foundation, and the bolts are high-strength bolts with the diameter of 30 mm.
Preferably, a sand cylinder is arranged between the hoop and the I-steel in the step S2-2, the height of the sand cylinder is 15cm, and the sand cylinder is provided with steel plates with the thickness of 1cm at the upper part and the lower part.
Preferably, in the step S2-3, each I18I-steel has a total length of 4 meters, and the two sides of each I-steel are respectively picked out to form a tie beam side of about 1.25 m.
Preferably, in the step S3, the bottom die is a steel die plate, the surface die is 5mm thick, the transverse rib channel steel is 8mm thick, and the vertical rib channel steel is 12mm thick.
(III) advantageous effects
The invention provides a construction process of a tie beam in water. The method has the following beneficial effects:
according to the underwater beam-tying construction process, the hoop support operation platform is directly established on the bridge pier stud during construction, workers can conveniently construct on the hoop support operation platform only by transporting materials through the transport ship, the workers only need to operate on the ship body when establishing the operation platform in the previous period, and do not need to always work on the ship body by the constructors, so that the construction cost and the construction time are greatly reduced.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Example (b):
the embodiment of the invention provides a construction process of a tie beam in water, which specifically comprises the following steps:
s1, construction preparation: firstly, cutting off a steel trestle platform, then cutting off a steel casing, wherein the steel casing is cut off, the elevation of the steel casing is controlled by a measuring team, the bottom of a hoop can be just clamped at the top of the cut-off steel casing, the steel casing is cut off by adopting ferry as a construction platform for construction, pile heads are chiseled and cleaned immediately after the casing is cut off, and when the pile heads are chiseled off, concrete on the top of the pile heads is chiseled off to be 15cm above the elevation of the bottom surface of a tie beam by adopting a circular cutting method. Crushing concrete by adopting an air compressor and an air pick, manually cleaning the pile top when the concrete is broken to 15cm above the elevation of the bottom surface of the tie beam, and washing the pile top by using clear water to ensure the combination quality of the pile foundation and the new and old concrete of the tie beam;
s2, erecting a hoop support operation platform: after preparation work such as construction platform and pile head chisel out is accomplished, arrange the measurement personnel and emit the tie beam axis, constructor installs the staple bolt according to tie beam axis and tie beam elevation, its main step is as follows:
s2-1, firstly wrapping the pre-installation part of the underwater pile foundation by using geotextile, then hooping an anchor ear with the same diameter as the pile foundation on the pre-installation part of the pile foundation, and fastening by using a bolt, wherein the measure can improve the friction force between the pile foundation and the anchor ear, the anchor ear is adjusted to a specified position by a crane during construction, constructors take an ferry to the specified pile foundation, fix the ferry, and install and fasten the anchor ear bolt by using the ferry as a construction platform;
s2-2, installing two I56a I-shaped steel bars on anchor ears on two sides of a pile foundation respectively by using a truck crane, welding the end parts of the two I-shaped steel bars into a whole by using steel bars, arranging a sand cylinder between the anchor ears and the I-shaped steel bars for facilitating adjustment and installation of a later template, wherein the height of the sand cylinder is 15cm, and the upper part and the lower part of the sand cylinder are provided with 1cm thick steel plates;
s2-3, after I-beams are installed, I18I-beams are installed on the top surfaces of the I-beams and are used as distribution beams, the distance is 0.5m, channel steel is placed vertically, the total length of each I18I-beam is 4m, the beam tying edges on two sides are respectively selected to be about 1.25m, 100 battens are laid on the walkway part, the distance is 300mm, a splint is laid on the walkway part and is used as a construction worker operating platform and a passageway, the outer side of the I18I-beam is vertically and transversely welded into a guardrail handrail by phi 60 steel pipes, the periphery of the guardrail is protected by a green net, one steel pipe is arranged every 2m and is 1.5m high, construction safety is guaranteed, the I18I-beams and the double-spliced I56a I-beam are connected in a spot welding mode, and the situation that the distribution beams are overturned due to;
s2-4, after the construction platform is installed, a vertical ladder stand is arranged from the trestle platform to the construction platform, so that the construction personnel can get on and off conveniently;
s3, installation of a bottom die: the bottom die is a shaped combined steel die and is uniformly processed and transported to a construction site by a manufacturer, then the bottom die is assembled, the bottom die is a steel template, the thickness of a face die is 5mm, the thickness of transverse rib channel steel is 8mm, the thickness of vertical rib channel steel is 12mm, then the templates are assembled in sections by using a steam crane, the upper camber of 5-8 mm is reserved in a span during installation of the bottom die, the bottom die is arranged according to a parabola so as to eliminate lower bending caused by the load bearing effect of a bearing I-beam, rubber strips or adhesive tapes with the thickness of about 3mm are padded between template joints, concrete pitted surfaces caused by slurry leakage of the joints are prevented, and a release agent is uniformly coated after the templates are installed;
s4, processing and installing the steel bars: the tie beam steel bars are manufactured in a concentrated mode in a steel bar yard, then the tie beam steel bars are transported to pier columns, and then the steel bars are adjusted to construction points through a steam crane to be installed;
s5, mounting of a side die: the installation of the side mold uses back cover mortar as a support, and uses the ink line which is well bounced on a mortar cushion layer to accurately position and install the tie beam template, after the installation of the side mold is finished, reinforcing steel bars with the diameter of 22mm are used as counter-pull rods to oppositely pull square channel steel at the top opening and the bottom of the template, so that the template is prevented from deforming, bolts with the diameter of 18mm are connected between the templates, and the bolts are connected and fastened according to requirements;
s6, pouring concrete: the concrete is intensively mixed in a mixing station and is transported to a construction site through a concrete tank truck, the concrete is transported into a tie beam template by adopting a chute during pouring, the chute is processed by adopting a bamboo plywood, and the lower part of the chute is supported by a steel pipe; the tie beam is formed by one-step pouring, concrete is poured in layers, the thickness of each layer is controlled to be 30cm, the next layer can be poured after one layer is vibrated, the vibration is carried out by adopting an inserted vibrator, the moving distance of the inserted vibrator is not more than 1.5 times of the action radius of the vibrator, the distance between the inserted vibrator and a side mold is kept to be 5-10 cm, the vibration time is 20-30 s, the degree is that the concrete stops sinking, no bubbles appear, the surface of the concrete presents laitance, the top surface is polished after the pouring is finished, and the surface flatness is ensured to meet the requirement;
s7, maintaining and removing the mold
S7-1, curing, namely, after concrete pouring, covering and watering curing as soon as possible after final setting, wherein the surface of the concrete is not damaged or polluted when the covering is carried out, the template is required to be kept wet frequently during curing when the concrete surface is covered by the template, the covering and heat preservation are carried out when the temperature is lower than 5 ℃, the water for curing the concrete is required to be covered and not sprayed to the concrete surface, the condition of the water for curing the concrete is the same as that of mixing water, the watering curing time of the concrete is generally 7 days, and the concrete can be prolonged or shortened as required according to the humidity and the temperature of air, the variety of the cement, the mixed additive and the like. Spraying water every day for a time of keeping the surface of the concrete in a wet state frequently, removing the side template after the strength of the concrete reaches 2.5MPa, and then modifying the surface, covering with steam for curing when the temperature is too low, wherein the concrete cannot bear external load until the strength of the concrete reaches 2.5 MPa;
s7-2, dismantling the side mould, namely dismantling the side mould after the concrete strength reaches 2.5Mpa, pushing the side mould symmetrically, uniformly and sequentially from the middle to two ends by a crane, immediately wrapping the whole tie beam by a plastic film after the template is dismantled, and sealing the joint between the plastic films by an adhesive tape to ensure that the plastic film is airtight;
s7-3, detaching the bottom die: and (3) when the concrete strength reaches 75% of the design strength, the bottom die is removed, two steel wire ropes with the diameter of 20 are respectively threaded on each anchor ear, after the steel wire ropes are fixed, the four steel wire ropes are hung by a crane, after the crane is stable and in a stressed state, the anchor ears are simultaneously loosened on two sides, the crane keeps a constant speed to slowly lift the bottom die of the tie beam upwards until the bottom die of the tie beam falls onto the trestle platform, then the bottom die of the tie beam is detached, the removed formwork must be timely cleaned and repaired, a release agent is coated, and the next tie beam is transferred to construction.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (5)

1. An underwater tie beam construction process is characterized in that: the method specifically comprises the following steps:
s1, construction preparation: firstly, cutting off a steel trestle platform, then cutting off a steel casing, and then chiseling and cleaning a pile head after cutting off the casing;
s2, erecting a hoop support operation platform: after preparation work such as construction platform and pile head chisel out is accomplished, arrange the measurement personnel and emit the tie beam axis, constructor installs the staple bolt according to tie beam axis and tie beam elevation, its main step is as follows:
s2-1, firstly wrapping the pre-installation part of the underwater pile foundation by using geotextile, then hooping the anchor ear with the same diameter as the pile foundation at the pre-installation part of the pile foundation, and fastening by using bolts;
s2-2, installing two I56a I-shaped steel bars on hoops on two sides of a pile foundation respectively by using a truck crane, and welding the ends of the two I-shaped steel bars by using reinforcing steel bars to form a whole;
s2-3, after the I-shaped steel is installed, installing I18I-shaped steel serving as a distribution beam on the top surface of the I-shaped steel, wherein the distance is 0.5m, and the channel steel is placed vertically;
s2-4, after the construction platform is installed, arranging a vertical ladder from the trestle platform to the construction platform;
s3, installation of a bottom die: the bottom die is a shaped combined steel die, is uniformly processed and transported to a construction site by a manufacturer, then is assembled, then the template is assembled in sections by using a steam crane, the upper camber of 5-8 mm is reserved in the midspan when the bottom die is installed, the bottom die is arranged according to a parabolic line so as to eliminate lower deflection caused by the load bearing effect of a load bearing I-beam, rubber strips or adhesive tapes with the thickness of about 3mm are padded between the template joints to prevent concrete pitted surface caused by slurry leakage of the joints, and a release agent is uniformly coated after the template is installed;
s4, processing and installing the steel bars: the tie beam steel bars are manufactured in a concentrated mode in a steel bar yard, then the tie beam steel bars are transported to pier columns, and then the steel bars are adjusted to construction points through a steam crane to be installed;
s5, mounting of a side die: the installation of the side mold uses back cover mortar as a support, and uses the ink line which is well bounced on a mortar cushion layer to accurately position and install the tie beam template, after the installation of the side mold is finished, reinforcing steel bars with the diameter of 22mm are used as counter-pull rods to oppositely pull square channel steel at the top opening and the bottom of the template, so that the template is prevented from deforming, bolts with the diameter of 18mm are connected between the templates, and the bolts are connected and fastened according to requirements;
s6, pouring concrete: the concrete is intensively mixed in a mixing station and is transported to a construction site through a concrete tank truck, the concrete is transported into a tie beam template by adopting a chute during pouring, the chute is processed by adopting a bamboo plywood, and the lower part of the chute is supported by a steel pipe; the tie beam is formed by one-step pouring, concrete is poured in layers, the thickness of each layer is controlled to be 30cm, the next layer can be poured after one layer is vibrated, the vibration is carried out by adopting an inserted vibrator, the moving distance of the inserted vibrator is not more than 1.5 times of the action radius of the vibrator, the distance between the inserted vibrator and a side mold is kept to be 5-10 cm, the vibration time is 20-30 s, the degree is that the concrete stops sinking, no bubbles appear, the surface of the concrete presents laitance, the top surface is polished after the pouring is finished, and the surface flatness is ensured to meet the requirement;
s7, maintaining and removing the mold
S7-1, curing, namely, after concrete pouring is finished, covering and watering curing are carried out as soon as possible after final setting, the surface of the concrete cannot be damaged or polluted when covering, and when a template is covered on the surface of the concrete, the template is kept wet frequently during curing;
s7-2, dismantling the side mould, namely dismantling the side mould after the concrete strength reaches 2.5Mpa, and symmetrically, uniformly and sequentially propelling the side mould from the middle to two ends by using a crane;
s7-3, detaching the bottom die: and (3) when the strength of the concrete reaches 75% of the design strength, removing the bottom die, respectively threading two steel wire ropes with the diameter of 20 on each anchor ear, after the steel wire ropes are fixed, hoisting the four steel wire ropes by using a crane, after the crane is stable and in a stressed state, loosening the anchor ears on two sides simultaneously, slowly and upwards lifting the tie beam bottom die by using the crane at a constant speed until the tie beam bottom die falls onto the trestle platform, and then detaching the tie beam bottom die.
2. The underwater tie beam construction process of claim 1, wherein: the hoop in the step S2-1 is formed by connecting two semicircular arc-shaped plates through bolts, the thickness of each arc-shaped plate is 16mm, the height of each arc-shaped plate is 600mm, the radius of each arc-shaped plate is the same as the outer diameter of the pile foundation, and each bolt is a high-strength bolt with the diameter of 30 mm.
3. The underwater tie beam construction process of claim 1, wherein: and in the step S2-2, a sand cylinder is arranged between the hoop and the I-steel, the height of the sand cylinder is 15cm, and the sand cylinder is vertically provided with 1cm thick steel plates.
4. The underwater tie beam construction process of claim 1, wherein: in the step S2-3, the total length of each I-steel I18 is 4 meters, and the tie beam edges are picked out from two sides to be about 1.25 meters.
5. The underwater tie beam construction process of claim 1, wherein: and in the step S3, the bottom die is a steel template, the thickness of the face die is 5mm, the thickness of the transverse rib channel steel is 8mm, and the thickness of the vertical rib channel steel is 12 mm.
CN202010689968.5A 2020-07-17 2020-07-17 Construction process for tie beam in water Withdrawn CN112030750A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010689968.5A CN112030750A (en) 2020-07-17 2020-07-17 Construction process for tie beam in water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010689968.5A CN112030750A (en) 2020-07-17 2020-07-17 Construction process for tie beam in water

Publications (1)

Publication Number Publication Date
CN112030750A true CN112030750A (en) 2020-12-04

Family

ID=73579558

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010689968.5A Withdrawn CN112030750A (en) 2020-07-17 2020-07-17 Construction process for tie beam in water

Country Status (1)

Country Link
CN (1) CN112030750A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114000525A (en) * 2021-11-23 2022-02-01 中国二十二冶集团有限公司 Construction method of tie beam in water

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003321806A (en) * 2002-05-01 2003-11-14 Kawada Construction Co Ltd Timbering beam
CN201762666U (en) * 2010-09-16 2011-03-16 中铁十九局集团第二工程有限公司 Capping construction support
CN204039921U (en) * 2014-05-19 2014-12-24 赵燕 A kind of Construction Support without support bent cap
CN104612120A (en) * 2014-12-15 2015-05-13 中铁上海工程局集团有限公司 Integrated construction method related to in-water steel pipe pile establishing platform
CN204589824U (en) * 2015-05-04 2015-08-26 中交一公局第六工程有限公司 A kind of " embracing ear Implant Method " template system for pier stud construction in water
CN105421245A (en) * 2015-12-18 2016-03-23 江苏兆通工程技术有限公司 Cap beam no-support steel hoop construction technology
CN106930194A (en) * 2017-05-10 2017-07-07 山西路桥第二工程有限公司 Inter-tie and pier stud global formation construction method and template used support
CN206667070U (en) * 2017-04-18 2017-11-24 中交一公局第六工程有限公司 A kind of suspension holdfast for being used for constructing tie beam in water
CN110306443A (en) * 2019-07-24 2019-10-08 中铁四局集团有限公司 Binder bracket system and corresponding construction in a kind of new type water
CN210066493U (en) * 2019-01-19 2020-02-14 广西建工集团第四建筑工程有限责任公司 Hoop mold for trestle hanging mold construction

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003321806A (en) * 2002-05-01 2003-11-14 Kawada Construction Co Ltd Timbering beam
CN201762666U (en) * 2010-09-16 2011-03-16 中铁十九局集团第二工程有限公司 Capping construction support
CN204039921U (en) * 2014-05-19 2014-12-24 赵燕 A kind of Construction Support without support bent cap
CN104612120A (en) * 2014-12-15 2015-05-13 中铁上海工程局集团有限公司 Integrated construction method related to in-water steel pipe pile establishing platform
CN204589824U (en) * 2015-05-04 2015-08-26 中交一公局第六工程有限公司 A kind of " embracing ear Implant Method " template system for pier stud construction in water
CN105421245A (en) * 2015-12-18 2016-03-23 江苏兆通工程技术有限公司 Cap beam no-support steel hoop construction technology
CN206667070U (en) * 2017-04-18 2017-11-24 中交一公局第六工程有限公司 A kind of suspension holdfast for being used for constructing tie beam in water
CN106930194A (en) * 2017-05-10 2017-07-07 山西路桥第二工程有限公司 Inter-tie and pier stud global formation construction method and template used support
CN210066493U (en) * 2019-01-19 2020-02-14 广西建工集团第四建筑工程有限责任公司 Hoop mold for trestle hanging mold construction
CN110306443A (en) * 2019-07-24 2019-10-08 中铁四局集团有限公司 Binder bracket system and corresponding construction in a kind of new type water

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
李瑞俊主编: "《铁路桥涵工程施工技术 中》", 30 June 2014, 中国铁道出版社 *
谈海斌等: "下立柱中系梁整体装模浇注方法的利用", 《湖南交通科技》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114000525A (en) * 2021-11-23 2022-02-01 中国二十二冶集团有限公司 Construction method of tie beam in water
CN114000525B (en) * 2021-11-23 2023-08-22 中国二十二冶集团有限公司 Construction method of underwater tie beam

Similar Documents

Publication Publication Date Title
CN111455855B (en) Construction process of main bridge of double-tower single-cable-plane short-tower cable-stayed bridge
CN110509417A (en) A kind of floorings are prefabricated and its installation method
CN108005387B (en) Synchronous construction method for cast-in-place main body of assembled wallboard and short-limb shear wall
CN110952456A (en) Pile type bridge construction process
CN111996906B (en) Efficient construction method of assembled pier
CN113752379B (en) Concrete T beam prefabrication construction method adopting secondary tensioning process and movable pedestal
CN113605771B (en) Prestress assembly type frame structure system
CN114164764A (en) Construction method for high-fill bridge bearing platform structure
CN111997066A (en) Manufacturing and construction method of assembled prestressed anchor cable frame beam for slope reinforcement
CN104631332A (en) Prestressed concrete T-shaped beam on-site prefabricating erection construction method
CN113202222A (en) Construction method for assembled type superposed beam slab
CN110747762A (en) Cement member crossing highway and its installation method
CN112030750A (en) Construction process for tie beam in water
CN117449216A (en) Bridge lower beam construction method
CN111648256A (en) Pier body reinforcing construction method
AU2021105980A4 (en) Construction method for impervious concrete for mbbr water treatment process structure
CN115890877A (en) Adjustable diaphragm plate template and construction method thereof
CN105804448A (en) Vertical prefabricating construction method of cooling tower herringbone column
CN107586068B (en) Upright column concrete and construction method of concrete upright column
CN114851374A (en) T-beam prefabricating and mounting construction method in bridge tunnel
CN210712595U (en) Cement member crossing road
CN114164763A (en) Construction method of bridge pier column system
CN114457846A (en) Road station main body structure construction method
CN114277672A (en) Large-span prestressed concrete bent cap structure and construction method thereof
CN111827239A (en) Construction method of assembled berthing pier

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20201204

WW01 Invention patent application withdrawn after publication