CN102277836B - Construction method of tilting concrete tower base - Google Patents

Construction method of tilting concrete tower base Download PDF

Info

Publication number
CN102277836B
CN102277836B CN 201110158179 CN201110158179A CN102277836B CN 102277836 B CN102277836 B CN 102277836B CN 201110158179 CN201110158179 CN 201110158179 CN 201110158179 A CN201110158179 A CN 201110158179A CN 102277836 B CN102277836 B CN 102277836B
Authority
CN
China
Prior art keywords
tower
steel
construction
concrete
base
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN 201110158179
Other languages
Chinese (zh)
Other versions
CN102277836A (en
Inventor
王学明
苟祖宽
朱长城
杨俊�
余贵钱
徐亮
石磊
周浩
高晓忠
颜旭旺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Construction Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Original Assignee
Construction Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Construction Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd filed Critical Construction Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Priority to CN 201110158179 priority Critical patent/CN102277836B/en
Publication of CN102277836A publication Critical patent/CN102277836A/en
Application granted granted Critical
Publication of CN102277836B publication Critical patent/CN102277836B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了在斜拉桥施工中采用的一种倾斜式混凝土塔座施工方法。该方法分为三层进行施工。在塔座内部设置钢管支架(2)和劲性骨架(6)支撑钢筋束(3)、预应力钢绞线束(4)和钢拱塔预埋段(7),在塔座外部高端两侧预埋顺塔向型钢(5)作为模板的悬挂支架结构,设置垫块(8)减短型钢(5)的悬臂受力长度。本发明成功解决了当倾斜式混凝土塔座(1)自身高度较小、悬臂较长、倾斜角度较大、离基础地面较高,且钢拱塔预埋段(7)自重较大时,原有支架法或爬模施工方法费用过高、钢拱塔预埋段(7)安装精度和施工安全风险不易控制的问题。本发明适用于采用倾斜式钢混结合塔座的斜拉桥塔座施工,也适用于其他倾斜式钢混结合部的施工。

The invention discloses a construction method for an inclined concrete tower used in the construction of a cable-stayed bridge. The method is divided into three layers for construction. Steel pipe brackets (2) and stiff skeletons (6) are installed inside the tower base to support steel tendons (3), prestressed steel strand bundles (4) and steel arch tower embedded sections (7), on both sides of the high-end outside the tower base Pre-embed the section steel (5) in the direction of the tower as the suspension support structure of the formwork, and set the spacer (8) to shorten the cantilever force length of the section steel (5). The invention successfully solves the problem when the inclined concrete tower base (1) has a small height, a long cantilever, a large inclination angle, and a high distance from the foundation ground, and the pre-buried section of the steel arch tower (7) has a large self-weight. There are problems that the support method or climbing formwork construction method is too expensive, the installation accuracy of the embedded section of the steel arch tower (7) and the construction safety risk are not easy to control. The invention is applicable to the construction of the pylons of cable-stayed bridges adopting inclined steel-concrete combined pylons, and is also applicable to the construction of other inclined steel-concrete combined parts.

Description

倾斜式混凝土塔座的施工方法The Construction Method of Inclined Concrete Tower Base

技术领域 technical field

本发明涉及一种倾斜式悬臂钢混结合塔座的施工方法。  The invention relates to a construction method of an inclined cantilever steel-concrete combined tower seat. the

背景技术 Background technique

在传统的混凝土塔座施工中,一般采用落地式支架或采用爬模施工。当倾斜式悬臂混凝土塔座自身高度较小、悬臂较长、倾斜角度较大、离基础地面较高,且钢拱塔预埋段自重较大时,采用传统的施工方法,模板支架和劲性骨架费用过高,且钢拱塔预埋段安装精度和施工安全风险不易控制。  In the construction of traditional concrete towers, floor supports or climbing formwork are generally used. When the height of the inclined cantilever concrete tower is small, the cantilever is long, the angle of inclination is large, the distance from the foundation ground is high, and the self-weight of the pre-buried section of the steel arch tower is large, the traditional construction method, formwork support and stiffness The cost of the skeleton is too high, and the installation accuracy and construction safety risks of the embedded section of the steel arch tower are not easy to control. the

发明内容 Contents of the invention

本发明要解决的技术问题是:提供一种倾斜式混凝土塔座的施工方法,解决了倾斜式混凝土塔座施工中各种构件的悬臂受力问题,该方法安全、经济,以克服现有技术存在的模板支架和劲性骨架费用过高,且钢拱塔预埋段安装精度和施工安全风险不易控制等不足。 The technical problem to be solved by the present invention is to provide a construction method for an inclined concrete tower, which solves the cantilever stress problem of various components in the construction of an inclined concrete tower. The cost of existing formwork supports and stiff skeletons is too high, and the installation accuracy and construction safety risks of the embedded sections of steel arch towers are not easy to control.

本发明的技术方案如下:倾斜式混凝土塔座分为三层施工,以减小悬臂立模高度、减短受力钢筋悬臂安装长度。在塔座内部设置劲性骨架支撑钢筋束、钢绞线束和钢拱塔预埋段,在塔座外部高端预埋顺塔向型钢作为模板的悬挂支架结构。该三层施工,包括以下过程:第一层施工,在塔座内部设置钢管支架支撑第一层悬臂钢筋束和预应力钢绞线束,在塔座外部高端顺塔向设置型钢,立模浇筑混凝土;第二层施工,采用预埋的型钢通过拉杆和背肋作为模板的悬挂支架结构,采用劲性骨架作为第二层悬臂钢筋束和预应力钢绞线束的支撑架,将劲性骨架的上平联临时固定在钢拱塔预埋段的底部高程上,立模浇筑混凝土至上平联以下0.1m处;第三层施工,精确调整上平联并固定作为钢拱塔预埋段的基座和限位装置;并将钢拱塔预埋段安装在劲性骨架的上平联上,利用钢拱塔预埋段作为第三层模板、钢筋束和钢绞线束的支撑结构,立模浇筑混凝土。 The technical scheme of the present invention is as follows: the inclined concrete tower base is divided into three layers of construction, so as to reduce the height of the cantilever vertical formwork and shorten the cantilever installation length of the stressed steel bar. Inside the tower base, a rigid skeleton support tendons, steel strand bundles and steel arch tower pre-embedded sections are set, and high-end pre-embedded tower-direction section steel is used as the suspension support structure of the formwork outside the tower base. The three-story construction includes the following processes: first-story construction, steel pipe brackets are installed inside the tower base to support the first layer of cantilever steel tendons and prestressed steel strand bundles, profiled steel is installed along the tower direction at the high end outside the tower base, and concrete is poured in vertical form. ; For the second layer of construction, the pre-embedded section steel is used as the suspension support structure of the formwork through the tie rods and back ribs, and the stiff skeleton is used as the support frame for the cantilever steel tendons and prestressed steel strand bundles of the second layer. The flat joint is temporarily fixed at the bottom elevation of the embedded section of the steel arch tower, and the concrete is cast to a position 0.1m below the upper flat joint; the third floor is constructed, and the upper flat joint is precisely adjusted and fixed as the base of the embedded section of the steel arch tower and limit device; install the pre-embedded section of the steel arch tower on the upper flat connection of the rigid frame, use the pre-embedded section of the steel arch tower as the supporting structure of the third-layer formwork, steel tendons and steel strand bundles, and formwork pouring concrete.

当施工塔座第一层时,在塔座内部设置劲性骨架支撑第一层悬臂的3×?? 28钢筋束和顺塔向4×??15.2预应力钢绞线束。 When constructing the first floor of the tower base, a rigid skeleton is set inside the tower base to support the 3×?? 28 steel tendons of the cantilever on the first layer and the 4×??

在塔座外部两侧高端预埋纵桥向倾斜58°~78°、横桥向倾斜64°~84°的顺塔向型钢。 On both sides of the tower base, the high-end pre-embedded longitudinal bridges are inclined 58°~78°, and the transverse bridges are inclined 64°~84° along the tower.

当施工塔座第二层时,在第一层混凝土顶部与型钢之间设置垫块,以减短型钢的悬臂受力长度。 When constructing the second floor of the tower base, a spacer is provided between the concrete top of the first floor and the section steel to shorten the cantilever stress length of the section steel.

当施工塔座第三层时,精确调整上平联并牢固固定作为钢拱塔预埋段的基座和限位装置后,将钢拱塔预埋段牢固安装在劲性支架的上平联上。 When constructing the third floor of the tower base, after accurately adjusting the upper flat connection and firmly fixing the base and the limit device as the embedded section of the steel arch tower, the embedded section of the steel arch tower is firmly installed on the upper flat connection of the stiff support superior.

钢拱塔预埋段的重量为20吨。 The weight of the embedded section of the steel arch tower is 20 tons.

施工完成塔座第三层待混凝土强度达到100%后拆除倾斜式混凝土塔座的模板系统。 After the construction of the third floor of the tower base is completed, the formwork system of the inclined concrete tower base will be removed after the concrete strength reaches 100%.

倾斜式混凝土塔座分为三层施工,以减小悬臂立模高度、减短受力钢筋悬臂安装长度。 The inclined concrete tower base is divided into three layers of construction to reduce the height of the cantilever vertical formwork and shorten the installation length of the stressed steel cantilever.

本发明解决了倾斜式混凝土塔座施工中各种构件的悬臂受力问题,节约了成本,保证了钢拱塔预埋段的安装精度,使施工安全风险得到有效控制。 The invention solves the cantilever stress problem of various components in the construction of the inclined concrete tower, saves the cost, ensures the installation accuracy of the pre-embedded section of the steel arch tower, and effectively controls the construction safety risk.

附图说明 Description of drawings

图1为本发明的剖视图; Fig. 1 is a sectional view of the present invention;

图2为施工塔座第一层时的剖视图; Fig. 2 is the cross-sectional view when constructing the first floor of the pylon;

图3为施工塔座第二层时的剖视图; Figure 3 is a sectional view of the second floor of the construction tower;

图4为施工塔座第三层时的剖视图; Fig. 4 is the cross-sectional view when constructing the third floor of the pedestal;

图5为图3的A-A截面图 Fig. 5 is the A-A sectional view of Fig. 3

具体实施方式 Detailed ways

倾斜式混凝土塔座1分为三层施工。塔座第一层施工,在塔座内部设置钢管支架2支撑悬臂的3×?? 28钢筋束3、顺塔向4×??15.2预应力钢绞线束4,在塔座外部两侧高端预埋纵桥向倾斜58°~78°、横桥向倾斜64°~84°的顺塔向型钢5。立模浇筑混凝土。 The inclined concrete tower base 1 is divided into three layers of construction. For the construction of the first floor of the tower base, the steel pipe bracket 2 is installed inside the tower base to support the 3×?? 28 steel tendons 3 of the cantilever, and the 4×?? Embed longitudinal section steel 5 with a 58°~78° inclination to the longitudinal bridge and a 64°~84° inclination to the transverse bridge. Formwork pouring concrete.

塔座第二层施工,采用预埋的型钢5通过拉杆和背肋作为模板的悬挂支架结构。采用劲性骨架6作为悬臂钢筋束3和预应力钢绞线束4的支撑架,将劲性骨架6的上平联临时固定在钢拱塔预埋段7的底部高程上,在第一层混凝土顶部与型钢5之间设置垫块8,以减短型钢的悬臂受力长度。立模浇筑混凝土至上平联以下0.1m处。 For the construction of the second floor of the tower base, the pre-embedded section steel 5 is used as the suspension bracket structure of the formwork through the tie rods and back ribs. The stiff skeleton 6 is used as the supporting frame of the cantilever steel tendon 3 and the prestressed steel strand bundle 4, and the upper parallel connection of the stiff skeleton 6 is temporarily fixed on the bottom elevation of the embedded section 7 of the steel arch tower. Pad block 8 is arranged between the top and section steel 5, to shorten the cantilever stress length of section steel. Formwork pouring concrete to 0.1m below the upper parallel joint.

塔座第三层施工,精确调整上平联并牢固固定作为钢拱塔预埋段7的基座和限位装置。将20吨重的钢拱塔预埋段7牢固安装在劲性骨架6的上平联上,利用钢拱塔预埋段7作为模板、钢筋束3和钢绞线束4的支撑结构。立模浇筑混凝土。 For the construction of the third floor of the tower base, the upper parallel connection is precisely adjusted and firmly fixed as the base and limit device of the embedded section 7 of the steel arch tower. The 20-ton steel arch tower embedded section 7 is firmly installed on the upper parallel connection of the rigid frame 6, and the steel arch tower embedded section 7 is used as the supporting structure of the formwork, steel tendons 3 and steel strands 4. Formwork pouring concrete.

施工完成塔座第三层待混凝土强度达到100%后方能拆除倾斜式混凝土塔座1的模板系统,以保证各层的施工安全和质量。  After the construction of the third floor of the tower base is completed, the formwork system of the inclined concrete tower base 1 can be removed only after the concrete strength reaches 100%, so as to ensure the construction safety and quality of each floor. the

Claims (6)

1.一种倾斜式混凝土塔座施工方法,其特征在于:倾斜式混凝土塔座(1)分为三层施工,包括以下过程:第一层施工,在塔座内部设置钢管支架(2)支撑第一层悬臂钢筋束(3)和预应力钢绞线束(4),在塔座外部高端顺塔向设置型钢(5),浇筑第一层混凝土;第二层施工,采用预埋的型钢(5)通过拉杆和背肋作为模板的悬挂支架结构,设置劲性骨架(6)作为第二层悬臂钢筋束(3)和预应力钢绞线束(4)的支撑架,将劲性骨架(6)的上平联临时固定在钢拱塔预埋段(7)的底部高程上,浇筑混凝土至上平联以下0.1m处;第三层施工,精确调整上平联并固定作为钢拱塔预埋段(7)的基座和限位装置;并将钢拱塔预埋段(7)安装在劲性骨架(6)的上平联上,利用钢拱塔预埋段(7)作为第三层模板、钢筋束和钢绞线束的支撑结构,浇筑第三层混凝土。 1. A construction method for an inclined concrete tower, characterized in that: the inclined concrete tower (1) is divided into three layers of construction, including the following process: the first layer of construction, the steel pipe support (2) is set inside the tower for support For the first layer of cantilever reinforcement bundles (3) and prestressed steel strand bundles (4), profile steel (5) is installed along the direction of the tower at the high end outside the tower base, and the first layer of concrete is poured; the second layer of construction uses pre-embedded profile steel ( 5) Use the tie rods and back ribs as the suspension bracket structure of the formwork, set the stiff skeleton (6) as the support frame for the second layer of cantilever steel tendons (3) and prestressed steel strand bundles (4), and place the stiff skeleton (6 ) is temporarily fixed at the bottom elevation of the pre-embedded section (7) of the steel arch tower, and concrete is poured to a point 0.1m below the upper connection; for the third layer of construction, the upper connection is precisely adjusted and fixed as a pre-embedded steel arch tower The base and limit device of the section (7); and the embedded section of the steel arch tower (7) is installed on the upper parallel connection of the rigid frame (6), and the embedded section of the steel arch tower (7) is used as the third Formwork, tendons and strands for the supporting structure, pouring the third layer of concrete. 2.根据权利要求1所述的倾斜式混凝土塔座的施工方法,其特征在于:当施工塔座第一层时,在塔座内部设置钢管支架(2)支撑第一层悬臂的3×? 28钢筋束和顺塔向4×?15.2预应力钢绞线束,在塔座外部两侧高端预埋顺塔向型钢(5),型钢(5)的倾斜角度与塔座倾斜角度相差±10°。 2. The construction method of the inclined concrete tower base according to claim 1, characterized in that: when constructing the first floor of the tower base, a steel pipe support (2) is set inside the tower base to support the 3×? 28 steel tendons and 4×?15.2 prestressed steel strands in the direction of the tower, pre-embedded high-end profile steel (5) in the direction of the tower on both sides of the tower base, and the inclination angle of the profile steel (5) is ±10° from the inclination angle of the tower base. 3.根据权利要求2所述的倾斜式混凝土塔座的施工方法,其特征在于:在塔座外部两侧高端预埋纵桥向倾斜58°~78°、横桥向倾斜64°~84°的顺塔向型钢(5)。 3. The construction method of the inclined concrete tower according to claim 2, characterized in that: the high-end pre-embedded longitudinal bridges on both sides of the outer sides of the tower are inclined at 58°~78°, and the transverse bridges are inclined at 64°~84° along the tower to the steel (5). 4.根据权利要求1所述的倾斜式混凝土塔座的施工方法,其特征在于:当施工塔座第二层时,在第一层混凝土顶部与型钢(5)之间设置垫块(8),以减短型钢(5)的悬臂受力长度。 4. The construction method of the inclined concrete tower according to claim 1, characterized in that: when constructing the second layer of the tower, a spacer (8) is set between the top of the first layer of concrete and the section steel (5) , to shorten the cantilever stress length of the section steel (5). 5.根据权利要求1所述的倾斜式混凝土塔座的施工方法,其特征在于:当施工塔座第三层时,精确调整上平联并牢固固定作为钢拱塔预埋段(7)的基座和限位装置后,将钢拱塔预埋段(7)牢固安装在劲性支架的上平联上。 5. The construction method of the inclined concrete tower base according to claim 1, characterized in that: when constructing the third floor of the tower base, the upper parallel connection is precisely adjusted and firmly fixed as the embedded section (7) of the steel arch tower After the base and the limit device, install the embedded section (7) of the steel arch tower firmly on the upper parallel connection of the rigid support. 6.根据权利要求1所述的倾斜式混凝土塔座的施工方法,其特征在于:施工完成塔座第三层待混凝土强度达到100%后拆除倾斜式混凝土塔座(1)的模板系统。 6. The construction method of the inclined concrete tower according to claim 1, characterized in that: the formwork system of the inclined concrete tower (1) is removed after the construction of the third floor of the tower is completed and the concrete strength reaches 100%.
CN 201110158179 2011-06-14 2011-06-14 Construction method of tilting concrete tower base Active CN102277836B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110158179 CN102277836B (en) 2011-06-14 2011-06-14 Construction method of tilting concrete tower base

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110158179 CN102277836B (en) 2011-06-14 2011-06-14 Construction method of tilting concrete tower base

Publications (2)

Publication Number Publication Date
CN102277836A CN102277836A (en) 2011-12-14
CN102277836B true CN102277836B (en) 2013-07-10

Family

ID=45103539

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110158179 Active CN102277836B (en) 2011-06-14 2011-06-14 Construction method of tilting concrete tower base

Country Status (1)

Country Link
CN (1) CN102277836B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103790115B (en) * 2014-02-20 2015-12-09 中铁十局集团第三建设有限公司 Auxiliary equipment for installation of steel tower joint section of cable-stayed bridge
CN105332342B (en) * 2015-10-30 2017-01-11 中交第二航务工程局有限公司 Bridge tower cantilever gradient concrete synchronous construction method
CN105821770B (en) * 2016-04-01 2017-05-24 上海城建市政工程(集团)有限公司 Connecting and locating method for multiple tower roots and large-size concrete bearing platform foundation of steel structure main tower
CN110387824B (en) * 2019-07-12 2021-07-06 中交第二航务工程局有限公司 Cable tower creeping formwork aerial rail transfer construction method
CN113216003A (en) * 2021-05-31 2021-08-06 中交路桥建设有限公司 Construction method for reinforced concrete joint section of cable-stayed bridge of consolidation system
CN113373971B (en) * 2021-07-13 2026-05-29 青岛华斯壮能源科技有限公司 Positioning tool and inclined foundation structure system of prestress framework type steel pipe wind power tower
CN113737661B (en) * 2021-10-11 2023-01-31 中铁二局集团有限公司 A construction method for steel-concrete joint section of cable-stayed bridge pylon

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100503977C (en) * 2007-03-21 2009-06-24 浙江省舟山连岛工程建设指挥部 Tower column of stayed-cable bridge and its construction method
CN101122114A (en) * 2007-09-14 2008-02-13 中铁大桥局集团第五工程有限公司 Back-cable-free cable-stayed bridge steel tower vertical turn construction method
JP2010048060A (en) * 2008-08-25 2010-03-04 Shimizu Corp Construction method of structure
CN101476293B (en) * 2009-01-16 2010-10-27 广东省长大公路工程有限公司 Construction Method of Large Bridge Arch Rib Without Support
KR101127923B1 (en) * 2009-07-01 2012-03-21 주식회사 포스코건설 Pylon of cable-stayed bridge having composite combination structure and construction method thereof
CN101649604B (en) * 2009-08-28 2011-04-13 中铁八局集团第一工程有限公司 Construction bracket of 1# block of inclined pull bridge and constructing method thereof
KR100962575B1 (en) * 2009-10-05 2010-06-11 (주)대우건설 Pendulum type vibration damping device for cable-stayed bridge of main tower
CN101781879B (en) * 2010-01-21 2011-09-07 中铁二十局集团有限公司 Construction method of single-pylon cable-stayed bridge without dorsal cables
CN201770940U (en) * 2010-07-30 2011-03-23 中铁四局集团第六工程有限公司 Mounting structure for lower load bearing plate of steel box tower with spatial variable cross section

Also Published As

Publication number Publication date
CN102277836A (en) 2011-12-14

Similar Documents

Publication Publication Date Title
CN213267529U (en) A prefabricated bridge splicing cover beam installation support structure
KR101171039B1 (en) Partially and fully earth-anchored cable-stayed bridge using main span prestressing appratus and construction method for the same
CN101922143B (en) Cover beam construction method
CN107100076A (en) Cast-in-place bent cap construction method
CN105113388B (en) Formwork and bracket combining structure of vase pier of viaduct and application method
EP3181755A1 (en) Prefabricated pier column member with steel-concrete composite structure
CN101597960B (en) Large-tonnage jack tension construction technology for non-bonded prestressed silo
CN102277836A (en) Construction method of tilting concrete tower base
CN201395769Y (en) Tie bar arch type bracket used for building bridge pylon concrete upper cross beam
CN103290784A (en) Arched beam combination bridge lifting construction method
CN109457814B (en) Construction method for top cover of high-rise and large-diameter building based on Bailey truss structure
CN103255717A (en) Method for constructing hit-preventing wall
CN105178200A (en) Construction method of cable-stayed combined support for construction of first segment of suspended-pouring arch bridge
CN110318342B (en) Construction equipment is assembled to prefabricated bent cap cantilever of festival section
CN105803947A (en) Integral traversing system and method for portal-type full space support of cast-in-situ box girder
CN104314013B (en) Two Cantilever Construction Methods of a kind of pole asymmetrical array beam
CN107761542A (en) One kind arch oblique pull combined system bridge and its construction method
CN115387234A (en) Template system of lower beam of ultrahigh rhombic tower pier and construction method
CN103132702A (en) Longspan pipe truss pulling bar lifting and overhead rotating emplacing construction method
CN104562944B (en) Long span steel-concrete composite beam cable-stayed bridge limit steel case anchoring temporarily system
KR100981982B1 (en) Precast coping lifting system
CN103835238B (en) A kind of high pier cable stayed bridge No. 0 block non-stand construction method and the structure in constructing
CN101793012B (en) Novel non-bracket bridge constructing method
CN110184915A (en) The cast-in-place king-post of cable-stayed bridge and its construction method
CN106758855B (en) Arc-shaped pier cap construction arch support component and arc-shaped pier cap construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant