CN201635308U - Multi-channel exhausting-prevention waterproof structure of prefabricated external wallboards - Google Patents

Multi-channel exhausting-prevention waterproof structure of prefabricated external wallboards Download PDF

Info

Publication number
CN201635308U
CN201635308U CN2009203183615U CN200920318361U CN201635308U CN 201635308 U CN201635308 U CN 201635308U CN 2009203183615 U CN2009203183615 U CN 2009203183615U CN 200920318361 U CN200920318361 U CN 200920318361U CN 201635308 U CN201635308 U CN 201635308U
Authority
CN
China
Prior art keywords
side fascia
wall panel
row
decompression cavity
multiple tracks
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009203183615U
Other languages
Chinese (zh)
Inventor
栗新
李矱宓
居晓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction Group Design Institute Co., Ltd.
Shanghai Jianhao Engineering Consultancy Co., Ltd.
Original Assignee
Shanghai Construction Group Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction Group Design Institute Co Ltd filed Critical Shanghai Construction Group Design Institute Co Ltd
Priority to CN2009203183615U priority Critical patent/CN201635308U/en
Application granted granted Critical
Publication of CN201635308U publication Critical patent/CN201635308U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Building Environments (AREA)

Abstract

The utility model relates to a multi-channel exhausting-prevention waterproof structure of prefabricated external wallboards, belonging to the technical field of building engineering and comprising external wallboards, water stopping bars, PVC plastic sheets, seam filling layers, sealing layers and drainage tubes, wherein the inner parts of the external wallboards are provided with horizontal or vertical decompression cavities; the water stopping bars are positioned in the external wallboards and are communicated with the decompression cavities of a plurality of adjacent external wallboards; the PVC plastic sheets, the seam filling layers and the sealing layers are arranged at the other end of the decompression cavities in sequence from the external to the internal; the drainage tubes are positioned at the outer sides of the external wallboards and are connected with the sealing layers. The multi-channel exhausting-prevention waterproof structure of prefabricated external wallboards improves the waterproof reliability of the seams of the prefabricated external wallboards, utilizes novel materials, and reduces the construction complexity.

Description

The anti-row of precast wall panel multiple tracks waterproof construction
Technical field
The utility model relates to a kind of device of construction engineering technical field, specifically is the anti-row of a kind of precast wall panel multiple tracks waterproof construction.
Background technology
At present, along with the rise of architectural industrialization, the range of application of prefabricated assembled exterior wall enlarges gradually, handles for the water proof structure of piece between wallboard, and two kinds of material waterproofing, constructional waterproofings are arranged, and pluses and minuses are as follows separately for it:
1. cavity configuration waterproofing process (physics waterproof)
Essential structure: the lineament of suitable shape is set at side fascia lateral edges seam crossing, as drip, dash platform, Pi Shui, anti-waft plate, afflux groove, guiding gutter (pipe) etc., form the pressure balance cavity, utilize horizontal or vertical decompression cavity effect with atmosphere UNICOM, block the capillary passage of side fascia face edge joint position environment aqueous vapor, and discharge by the condensate water that guiding gutter (pipe) will infiltrate in the body of wall to indoor infiltration.
Shortcoming: because textural inadequate natural endowment causes very easily in the work progress that structure lost efficacy; Edges of boards need be processed into the tongue and groove of special shape, make comparatively complicated; Be subjected to the influence of natural temperature differential bigger; The dry-shrinkage deformed shingle nail interface cracking destruction that causes of material; Poor seismic behavior.
2. material seal method
Shortcoming: the conventional mechanical type mode of connection that adopts, between the wallboard, all exist between wallboard and the agent structure and is connected seam, when in order to the construction sealant damage of waterproof, very easily cause the infiltration phenomenon; Only set up defences together, the reliability of waterproof depends on the processing mode of the weak part of encapsulant.
The utility model content
The utility model is at the prior art above shortcomings, the anti-row of a kind of precast wall panel multiple tracks is provided waterproof construction, comprehensively solves the problem that exists in the background technology, improve the waterproof reliability of precast wall panel piece, utilize new material, reduce the construction complexity.
The utility model is achieved through the following technical solutions, the utility model comprises: side fascia, sealing rod, PVC plastic sheet, joint filling layer, sealant and mozzle, wherein: the inside of side fascia is provided with the decompression cavity, sealing rod is positioned at side fascia and is connected with the decompression cavity of some blocks of adjacent side fascias, PVC plastic sheet, joint filling layer and sealant are set in turn in the other end of decompression cavity from outside to inside, and mozzle is positioned at the outside of side fascia and is connected with sealant.
Described decompression cavity is the zigzag structure, and its inside is provided with an end height of sealing rod greater than an end height that is provided with the PVC plastic sheet.
Described side fascia is prefabricated reinforced concrete solid wall plate or steel concrete compound heat preservation body of wall, and the inside of side fascia is provided with insulation layer.
The utility model technology is set up defences in line with the principle of " block up, hinder, dredge, lead, arrange ", make full use of the material property of novel synthetic high polymer sealing compound, water conservancy diversion and Drainage Design in the cavity of uniqueness are combined with tradition decompression cavity principle, be aided with novel hollow rubber tube sealing rod and form reliable three road waterproof.By construction measure each story height is vertically prevented the row unit as one, each potential breakthrough is isolated mutually; In each vertically anti-row unit, the rhone that is provided with in rhone and the vertical decompression cavity is set in level decompression cavity interpenetrates, establish mozzle at lowest part of each vertical decompression cavity rhone and enter moisture in the decompression cavity with timely eliminating.
The utility model technology has following characteristics: 1) multi-way prevention, strengthen the water resistance of exterior wall panel plate seam splicing place, and in case avoid single track water proof structure water proof structure to destroy the shortcoming that seepage promptly occurs, improve node waterproof service life.2) vertical division block, wall face vertically is being anti-row unit with each story height, and each anti-row unit isolates mutually, avoids the influence of anti-row unit, top breakthrough to anti-row unit, bottom, when improving waterproof effect, be convenient in time find breakthrough, be convenient to safeguard.3) rhone is set in cavity, the water that leaks into cavity can be concentrated and enter the vertical drainage groove, water is introduced gutter, discharge by the rhone that is arranged in the vertical cavity.4) utilize hollow rubber pipe place of cement to sit slurry, be convenient to batch production, programming operations, simultaneously compacted effect between reinforcement plate.5) the joint structure key position all uses elastomeric material, and the vibration of building, distortion are had bigger compliance.
Description of drawings
Fig. 1 is the utility model splicing schematic diagram.
Fig. 2 is an II part partial cut away side views among Fig. 1.
Fig. 3 is an I part part section vertical view among Fig. 1.
Fig. 4 is embodiment 2 schematic diagrames.
The specific embodiment
Below embodiment of the present utility model is elaborated; present embodiment is being to implement under the prerequisite with technical solutions of the utility model; provided detailed embodiment and concrete operating process, but protection domain of the present utility model is not limited to following embodiment.
Embodiment 1
As shown in Figure 1, Shanghai real estate dwelling house project, 14 layers on the ground of experimental projects, underground 1 layer, building height is 42.50m, adopts the plug-in prefabricated reinforced concrete side fascia 1 of cast-in-situ concrete frame-shear wall structure, wallboard nominal thickness 160mm, the integrated facing tile of plate face, conventional exterior wall internal insulation way is adopted in insulation.Project is built up follow-up investigation and is found no breakthrough.
As depicted in figs. 1 and 2, present embodiment comprises: side fascia 1, sealing rod 2, PVC plastic sheet 3, joint filling layer 4, sealant 5 and mozzle 6, wherein: the inside of side fascia 1 is provided with the decompression cavity 7 of level, sealing rod 2 is positioned at side fascia 1 and is connected with the decompression cavity 7 of some blocks of adjacent side fascias 1, PVC plastic sheet 3, joint filling layer 4 and sealant 5 are set in turn in the other end of decompression cavity 7 from outside to inside, and mozzle 6 is positioned at the outside of side fascia 1 and is connected with sealant 5.
Described decompression cavity 7 is the zigzag structure, and its inside is provided with an end height of sealing rod 2 greater than an end height that is provided with PVC plastic sheet 3.
Be provided with rhone 8 in the described decompression cavity 7, this rhone 8 is a trapezium structure, specifically is positioned at the bottom of decompression cavity 7;
The node waterproof tectonic position thickness of slab of described side fascia 1 is more than or equal to 120mm, and this side fascia 1 is prefabricated reinforced concrete solid wall plate or steel concrete compound heat preservation body of wall, and the inside of side fascia 1 is provided with insulation layer 9.
Described sealing rod 2 is a hollow rubber pipe sealing rod 2, its diameter 27mm.
The thickness of described PVC plastic sheet 3 equals 2mm.
Embodiment 2:
Another real estate dwelling house project of Shanghai, 14 layers on the ground of experimental projects, building height is 40m, the plug-in steel concrete composite self-insulation of reinforced concrete shear wall structure precast wall panel 1, wallboard nominal thickness 270mm, with primary structure member binding site thickness 90mm, node waterproof tectonic position ribs position thickness 90mm.
As Fig. 1, Fig. 3 and shown in Figure 4, decompression cavity 7 among the embodiment 2 is the vertical direction setting, under nominal situation, and the passage that drainage duct is communicated with atmosphere as decompression cavity 7, stable to keep the cavity inner and outer air pressure, avoid cavity " suction " phenomenon under negative pressure, to occur.Precast wall panel 1 side links to each other with the vertical cavity of following piece plate at the decompression cavity 7 that the bottom of drainage duct forms, and enters and will discharge by lower floor's drainage duct if any steam.
The foregoing description specifically can carry out execute-in-place in the following manner: different according to precast wall panel 1 with the agent structure ways of connecting, and be divided into and be rigidly connected and flexibly connect two kinds of connected modes:
Be rigidly connected: colligation stress members reinforcing cage is also reserved the connector position, during precast wall panel 1 lifting splicing, level to and the i.e. bearing certain pressure and jam-packed enters normal operating conditions of vertical hollow rubber sealing rod 2; Finishing side fascia 1 reserves the drawknot device and with after the piece sealing, carries out the main structure construction operation of This floor with the stress members binding site.After main structure construction finishes, each level and vertical decompression cavity 7 are cleared up, finish the structure of node waterproof shown in the present embodiment by the operation that PVC hard plastic sheet pointing polymer mortar synthetic high polymer sealing compound filleting is installed.
Flexibly connect: during main structure construction, by design relevant position built-in connection, treat that agent structure is finished after, carry out the lifting and the splicing of precast facade, this moment level to and the i.e. bearing certain pressure and jam-packed enters normal operating conditions of vertical hollow rubber sealing rod 2; By connector precast wall panel 1 is connected with agent structure.Other operation be rigidly connected identical.
For avoiding the pollution of operating process to finished product, the top by building during plate face filleting begins, and finishes to ground floor.

Claims (6)

1. a precast wall panel multiple tracks is prevented row's waterproof construction, it is characterized in that, comprise: side fascia, sealing rod, PVC plastic sheet, joint filling layer, sealant and mozzle, wherein: the inside of side fascia is provided with level or vertical decompression cavity, sealing rod is positioned at side fascia and is connected with the decompression cavity of some blocks of adjacent side fascias, PVC plastic sheet, joint filling layer and sealant are set in turn in the other end of decompression cavity from outside to inside, and mozzle is positioned at the outside of side fascia and is connected with sealant.
2. the anti-row of precast wall panel multiple tracks according to claim 1 waterproof construction is characterized in that described decompression cavity is the zigzag structure, and its inside is provided with an end height of sealing rod greater than an end height that is provided with the PVC plastic sheet.
3. the anti-row of precast wall panel multiple tracks according to claim 1 waterproof construction is characterized in that be provided with rhone in the described decompression cavity, this rhone is a trapezium structure, specifically is positioned at the bottom of decompression cavity.
4. the anti-row of precast wall panel multiple tracks according to claim 1 waterproof construction is characterized in that the node waterproof tectonic position thickness of slab of described side fascia is more than or equal to 120mm.
5. according to claim 1 or the anti-row of 4 described precast wall panel multiple tracks waterproof construction, it is characterized in that described side fascia is prefabricated reinforced concrete solid wall plate or steel concrete compound heat preservation body of wall, the inside of side fascia is provided with insulation layer.
6. the anti-row of precast wall panel multiple tracks according to claim 1 waterproof construction is characterized in that described sealing rod is a hollow rubber pipe sealing rod.
CN2009203183615U 2009-12-24 2009-12-24 Multi-channel exhausting-prevention waterproof structure of prefabricated external wallboards Expired - Fee Related CN201635308U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009203183615U CN201635308U (en) 2009-12-24 2009-12-24 Multi-channel exhausting-prevention waterproof structure of prefabricated external wallboards

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009203183615U CN201635308U (en) 2009-12-24 2009-12-24 Multi-channel exhausting-prevention waterproof structure of prefabricated external wallboards

Publications (1)

Publication Number Publication Date
CN201635308U true CN201635308U (en) 2010-11-17

Family

ID=43079793

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009203183615U Expired - Fee Related CN201635308U (en) 2009-12-24 2009-12-24 Multi-channel exhausting-prevention waterproof structure of prefabricated external wallboards

Country Status (1)

Country Link
CN (1) CN201635308U (en)

Cited By (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103669742A (en) * 2013-04-12 2014-03-26 龙宏元 Diversion waterproof thermal-insulation system
CN104452961A (en) * 2014-12-08 2015-03-25 上海应用技术学院 Rural low-rise assembled damping building structure system
CN104895200A (en) * 2015-05-06 2015-09-09 苏州建鑫建设集团有限公司 Slab joint structure of waterproof external wallboard
CN105525555A (en) * 2016-01-17 2016-04-27 重庆交通大学 Waterproof structure of embedding hollow elastic pipe in cement concrete pavement joint
CN105821979A (en) * 2016-05-16 2016-08-03 北京友城建筑科技有限公司 Waterproof assembly for joint of PC externally-hung wall and cast-in-situ layer and construction method thereof
CN105863087A (en) * 2015-01-19 2016-08-17 任丘市永基建筑安装工程有限公司 Waterproof technology of prefabricated external wall panel
CN105863124A (en) * 2016-05-31 2016-08-17 中民筑友科技投资有限公司 Outer wallboard waterproof node
CN105863129A (en) * 2016-05-31 2016-08-17 中民筑友科技投资有限公司 Waterproof node of exterior wallboard
CN105863086A (en) * 2016-05-31 2016-08-17 中民筑友科技投资有限公司 Waterproof joint for external wall panel
CN105863128A (en) * 2016-05-31 2016-08-17 中民筑友科技投资有限公司 Outer wall plate waterproof node
CN105888055A (en) * 2016-05-31 2016-08-24 中民筑友科技投资有限公司 External wall panel installation node
CN106013474A (en) * 2016-06-23 2016-10-12 中天建设集团有限公司 Drainage structure for prefabricated building external wall panel
CN106320574A (en) * 2016-10-17 2017-01-11 澄筑投资控股(上海)有限公司 Light-gauge steel joist composite concrete wallboard
EP3115526A1 (en) * 2015-07-09 2017-01-11 Winterface GmbH Sealing of joints between insulating elements for building insulation
CN106703225A (en) * 2015-11-18 2017-05-24 上海宝冶集团有限公司 Fabricated building prefabricated outer wall joint waterproof method
CN107060143A (en) * 2017-03-23 2017-08-18 北京城建建设工程有限公司 A kind of prefabricated outer wall joint construction and fair-faced concrete outer wall construction method
CN108018954A (en) * 2017-12-15 2018-05-11 龙信建设集团有限公司 Prefabricated assembled exterior wall splices joint waterproofing node
CN108517994A (en) * 2016-01-27 2018-09-11 南京奥捷墙体材料有限公司 Curtain-wall water-proof structure and the GRC curtain wall panels with waterproof construction and curtain wall
CN109296088A (en) * 2018-09-29 2019-02-01 宁波普利凯建筑科技有限公司 A kind of precast light self-heat conserving out-hung panel and preparation method thereof
CN110528730A (en) * 2019-09-18 2019-12-03 上海建科建筑设计院有限公司 A kind of waterproof construction of prefabricated plug-in sandwich type wall panel
CN111119495A (en) * 2020-01-20 2020-05-08 中铁十二局集团建筑安装工程有限公司 PCF plate construction method for fabricated building
CN111997290A (en) * 2020-08-06 2020-11-27 浙江可久建筑工程有限公司 Waterproof connected node structure of prefabricated side fascia of assembly type structure
CN112726871A (en) * 2020-12-30 2021-04-30 上海建工五建集团有限公司 Waterproof structure of prefabricated external wall panel
CN113846815A (en) * 2021-09-26 2021-12-28 浙江绿筑集成科技有限公司 External wallboard waterproof structure with drainage plate seam water seepage function and construction method

Cited By (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103669742B (en) * 2013-04-12 2016-03-30 龙宏元 Diversion waterproof thermal-insulation system
CN103669742A (en) * 2013-04-12 2014-03-26 龙宏元 Diversion waterproof thermal-insulation system
CN104452961A (en) * 2014-12-08 2015-03-25 上海应用技术学院 Rural low-rise assembled damping building structure system
CN105863087A (en) * 2015-01-19 2016-08-17 任丘市永基建筑安装工程有限公司 Waterproof technology of prefabricated external wall panel
CN104895200A (en) * 2015-05-06 2015-09-09 苏州建鑫建设集团有限公司 Slab joint structure of waterproof external wallboard
EP3115526A1 (en) * 2015-07-09 2017-01-11 Winterface GmbH Sealing of joints between insulating elements for building insulation
CN106703225A (en) * 2015-11-18 2017-05-24 上海宝冶集团有限公司 Fabricated building prefabricated outer wall joint waterproof method
CN105525555A (en) * 2016-01-17 2016-04-27 重庆交通大学 Waterproof structure of embedding hollow elastic pipe in cement concrete pavement joint
CN108517994A (en) * 2016-01-27 2018-09-11 南京奥捷墙体材料有限公司 Curtain-wall water-proof structure and the GRC curtain wall panels with waterproof construction and curtain wall
CN105821979B (en) * 2016-05-16 2019-07-02 北京友城建筑科技有限公司 A kind of water repellent component and its construction method of the plug-in wall of PC and in-situ layer seam
CN105821979A (en) * 2016-05-16 2016-08-03 北京友城建筑科技有限公司 Waterproof assembly for joint of PC externally-hung wall and cast-in-situ layer and construction method thereof
CN105863124A (en) * 2016-05-31 2016-08-17 中民筑友科技投资有限公司 Outer wallboard waterproof node
CN105888055A (en) * 2016-05-31 2016-08-24 中民筑友科技投资有限公司 External wall panel installation node
CN105863128A (en) * 2016-05-31 2016-08-17 中民筑友科技投资有限公司 Outer wall plate waterproof node
CN105863086A (en) * 2016-05-31 2016-08-17 中民筑友科技投资有限公司 Waterproof joint for external wall panel
CN105863129A (en) * 2016-05-31 2016-08-17 中民筑友科技投资有限公司 Waterproof node of exterior wallboard
CN106013474A (en) * 2016-06-23 2016-10-12 中天建设集团有限公司 Drainage structure for prefabricated building external wall panel
CN106320574A (en) * 2016-10-17 2017-01-11 澄筑投资控股(上海)有限公司 Light-gauge steel joist composite concrete wallboard
CN107060143A (en) * 2017-03-23 2017-08-18 北京城建建设工程有限公司 A kind of prefabricated outer wall joint construction and fair-faced concrete outer wall construction method
CN107060143B (en) * 2017-03-23 2019-06-07 北京城建建设工程有限公司 A kind of construction method of prefabricated exterior wall clear-water concrete seam construction
CN108018954A (en) * 2017-12-15 2018-05-11 龙信建设集团有限公司 Prefabricated assembled exterior wall splices joint waterproofing node
CN109296088A (en) * 2018-09-29 2019-02-01 宁波普利凯建筑科技有限公司 A kind of precast light self-heat conserving out-hung panel and preparation method thereof
CN110528730A (en) * 2019-09-18 2019-12-03 上海建科建筑设计院有限公司 A kind of waterproof construction of prefabricated plug-in sandwich type wall panel
CN111119495A (en) * 2020-01-20 2020-05-08 中铁十二局集团建筑安装工程有限公司 PCF plate construction method for fabricated building
CN111997290A (en) * 2020-08-06 2020-11-27 浙江可久建筑工程有限公司 Waterproof connected node structure of prefabricated side fascia of assembly type structure
CN112726871A (en) * 2020-12-30 2021-04-30 上海建工五建集团有限公司 Waterproof structure of prefabricated external wall panel
CN113846815A (en) * 2021-09-26 2021-12-28 浙江绿筑集成科技有限公司 External wallboard waterproof structure with drainage plate seam water seepage function and construction method
CN113846815B (en) * 2021-09-26 2023-01-03 浙江绿筑集成科技有限公司 External wallboard waterproof structure with drainage plate seam water seepage function and construction method

Similar Documents

Publication Publication Date Title
CN201635308U (en) Multi-channel exhausting-prevention waterproof structure of prefabricated external wallboards
CN102758509B (en) Horizontal seam waterproof plate of prefabricated exterior wall cladding
US7913469B2 (en) Concrete load-bearing wall with compound heat-insulating layer
CN203411994U (en) Support pile basement outer wall structure
CN103993679B (en) Low layer assembling combined wall house bolt connection node structure
CN103924710B (en) Low layer assembled combined wall house Plate Welding node structure
CN105003020A (en) Ceramsite concrete metal net rack light wallboard and splicing structure thereof
CN1888344B (en) Composite thermal insulation concrete load-bearing wall
CN108729692A (en) A kind of method of construction of assembled Low-rise Lightweight system of steel residential structure
CN201713979U (en) Novel light wall body brick with male and female sleeve
CN211257093U (en) Underground cast-in-place structure outer wall post-cast strip template pre-supporting device
CN210459831U (en) Waterproof material of metal mesh interlayer
CN107152034A (en) A kind of pipe gallery and its construction method
CN108035453B (en) Sliding shock insulation device with ring beam masonry structure and construction method thereof
CN204252367U (en) Air-conditioning duct wears the lightweight precast concrete component of building block exterior wall
CN1932242B (en) Well wall with steel plate aquifuge and construction method thereof
CN202689421U (en) Waterproof board for horizontal joint of precast exterior wall hanging board
CN206607675U (en) A kind of basement composite external wall anti-cracking and seepage control structure construction
CN205134980U (en) Whole anti -seismic performance's of reinforcing adobe wall bearing local -style dwelling houses device
CN211312560U (en) Simple and easy core section of thick bamboo stepping water conservancy diversion drainage structures
CN108005405B (en) Sliding shock insulation device of girderless masonry structure and construction method thereof
CN201952911U (en) Plate end water stop for composite wall plate
CN108729563B (en) Anti-decay construction system for wood columns in archaize building wall body
CN111962632A (en) Rainwater sewer and construction method thereof
CN201614679U (en) Assembled building reinforced concrete precast plate

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: SHANGHAI JIANHAO ENGINEERING CONSULTANCY CO., LTD.

Effective date: 20130617

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20130617

Address after: 200050 No. 150, Shanghai, Wuyi Road

Patentee after: Shanghai Construction Group Design Institute Co., Ltd.

Patentee after: Shanghai Jianhao Engineering Consultancy Co., Ltd.

Address before: 200050 No. 150, Shanghai, Wuyi Road

Patentee before: Shanghai Construction Group Design Institute Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20101117

Termination date: 20161224

CF01 Termination of patent right due to non-payment of annual fee