CN107152034A - A kind of pipe gallery and its construction method - Google Patents

A kind of pipe gallery and its construction method Download PDF

Info

Publication number
CN107152034A
CN107152034A CN201710408411.8A CN201710408411A CN107152034A CN 107152034 A CN107152034 A CN 107152034A CN 201710408411 A CN201710408411 A CN 201710408411A CN 107152034 A CN107152034 A CN 107152034A
Authority
CN
China
Prior art keywords
pipe gallery
soil
corrugated plating
section
piping lane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710408411.8A
Other languages
Chinese (zh)
Other versions
CN107152034B (en
Inventor
岑文杰
周红星
王永平
王胜年
胡利文
熊建波
范志宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Fourth Harbor Engineering Institute Co Ltd
Guangzhou Harbor Engineering Quality Inspection Co Ltd
Original Assignee
CCCC Fourth Harbor Engineering Institute Co Ltd
Guangzhou Harbor Engineering Quality Inspection Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Fourth Harbor Engineering Institute Co Ltd, Guangzhou Harbor Engineering Quality Inspection Co Ltd filed Critical CCCC Fourth Harbor Engineering Institute Co Ltd
Priority to CN201710408411.8A priority Critical patent/CN107152034B/en
Publication of CN107152034A publication Critical patent/CN107152034A/en
Application granted granted Critical
Publication of CN107152034B publication Critical patent/CN107152034B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells

Abstract

The invention discloses a kind of pipe gallery, it is formed by the longitudinal continued access in some piping lane sections, there is a cross section formed by the assembly of steel corrugated plating to be close-shaped casing for piping lane section, casing is encapsulated in the Foam lightweight soil soil body, it is to be backfilling and compacted soil on the outside of the Foam lightweight soil soil body, box house lays terrace, terrace lower section Foam lightweight soil or Concrete Filled flooring base.The pipe gallery of the present invention can give full play to the respective advantage of material with Foam lightweight soil and the combination of steel corrugated plating:Foam lightweight soil lightweight, good integrity, anti-permeability performance are good, energy-saving;Steel corrugated plating ring stiffness height, good endurance, construction are convenient, and steel are saved after combination, and water proof anti-seepage, endurance quality is notable.

Description

A kind of pipe gallery and its construction method
Technical field
The present invention relates to pipe gallery technical field of construction, belong to municipal works Urban Underground facility technology field.
The content of the invention
Pipe gallery engineering refers to that municipal administration is built below urban road shares tunnel, by electric power, communication, water supply, A variety of municipal pipelines such as combustion gas are concentrated in together, and " unified planning, unified construction, unified management " are carried out, to accomplish the underground space Comprehensive utilization and resource-sharing.Pipe gallery takes full advantage of the underground space of road, reduces to periphery business activity Influence, solves " slide fastener road " that maintenance, the dilatation of all kinds of pipelines during urban development cause and " cobweb " is asked in the air Topic, to lifting city pan-image, creates the harmonious ecological environment in city and serves the effect actively promoted.Pipe gallery turns into 21 One of the focus of century city modernization construction and mark of measurement urban construction modernization level.
The armored concrete and masonry marshalling structure design of routine, construction are cumbersome, and from excavation of foundation pit to needed for being open to traffic Duration is longer, using the city integrated piping lane of the steel corrugated plating of new material and structure there is material to be easily worked, quick construction etc. Feature starts to be generalized.But steel corrosion easily occur in ground corrosion environment, the position such as steel plate seam crossing, bolt hole holds Easily there is underground water Seepage.The pipe gallery of buried underground is by very big soil pressure and Driving Loading in addition Enable steel plate to be subjected to larger soil pressure, there are enough safety stocks, generally require to use thicker steel plate.
Foam lightweight soil, is that foaming agent is mechanically fully foamed by the foamed system of air bubble machine, and by foam Uniformly mixed with cement mortar, then carry out cast-in-place construction, the one kind formed through natural curing by the pumping system of foaming machine Novel light insulation material containing a large amount of sealed porositys.It belongs to air bubble-shaped material, and outstanding feature is in inside concrete shape Into the foam hole of closing, make concrete light, its dry volume density is generally 300-1600kg/m3, equivalent to ordinary cement 1/5~1/8 or so of concrete, can mitigate building Integral Loading, and compression strength is about 0.6-25.0MPa.
The content of the invention
It is an object of the invention to make up problem of the prior art, there is provided a kind of new conjunction pipe gallery and its construction party Method, the advantages of possessing that lightweight, water resistance is good, larger car load can be born.
To achieve these goals, present invention employs following technical scheme:A kind of pipe gallery, the pipe gallery by The longitudinal continued accesses in some piping lane sections and formed, there is a cross section formed by the assembly of steel corrugated plating to be close-shaped for piping lane section Casing, casing is encapsulated in the Foam lightweight soil soil body, to be backfilling and compacted soil, box house laying on the outside of the Foam lightweight soil soil body Terrace, terrace lower section Foam lightweight soil or Concrete Filled flooring base.
The pipe gallery also includes buttress, and buttress is supported in bottom half and is embedded in the native soil body of foam makings, branch Pier is autoclave aerated concrete building block buttress.
Construction subgrade road surface above the Foam lightweight soil soil body.
The cabinets cavity of pipe gallery is provided with line holder and is disposed with municipal pipeline, and the municipal pipeline includes supplying water Pipeline, intermediate water pipeline, gutter, power pipeline, communication line and burning line.
The cross section of the casing is circular or ellipse or pyriform or quadrangle or vault quadrilateral shape.
The casing of the piping lane section is single chamber or is separated into two chambers or is separated into many chambers.
The steel corrugated plating is circular arc corrugated plating or trapezoidal corrugated plating, rectangle corrugated plating.
The construction method of a kind of as above any described pipe gallery, it comprises the following steps:With the fast Speed Pinyin of steel corrugated plating It is close-shaped casing as piping lane section to be connected into mode cross section, and then the longitudinal continued access in piping lane section is got up, piping lane section Cast-in-place foamed light soil is encapsulated to casing formation outside casing, and the box house in piping lane section is laid to enter below terrace, terrace The filling of row basis.
The pipe gallery that the present invention is combined using a kind of Foam lightweight soil and steel corrugated plating casing, steel corrugated plating bending resistance Pressure energy power is strong, easy to assembly, efficiency of construction is high, various close-shaped piping lane sections can be quickly spliced into steel corrugated plating, so It is afterwards that piping lane section is longitudinally connected into steel corrugated plating pipe gallery, then steel corrugated plating is encapsulated using cast-in-place foamed light soil Filled with below terrace.Foam lightweight soil is corrosion-resistant, impermeability is good, whole compressive strength is good, deadweight is small, can reduce steel ripple The soil pressure of plate all directions, and provide durability protection and the impervious effect of underground water for steel corrugated plating.Due to Foam lightweight soil Unit weight (value 1000kg/m3) it is only that (wet density is about 2100kg/m to common backfill element soil3) or dirt (1900kg/m3) 50% or so, and there is more preferable globality and compression strength than the common soil that is backfilling and compacted, after being combined with steel corrugated plating, due to The significantly reduction of soil pressure and uniform force, therefore, for the pipe gallery of identical scale, steel plate thickness can reduce 10% to 30%, so as to accordingly reduce rolled steel dosage.
It is of the invention compared with traditional reinforced concrete structure, with construction technology is simple, efficiency of construction is high, deadweight Small, settlement after construction is small, basement process requires low;Compared with simple steel corrugated board structures, with excellent in te pins of durability, impervious energy Power is strong, rolled steel dosage is small, road surface large carrying capacity the advantages of.Due to can significantly reduce basement process expense and rolled steel dosage and Efficiency of construction is high, and cost of the invention is far below traditional reinforced concrete structure;Relative to simple steel corrugated board structures more Saving steel, service life is obviously prolonged, with significant economic benefit.
Brief description of the drawings
Fig. 1 is the structural representation of the present invention;
Fig. 2 a are the circular arc corrugated steel exemplary plots of the present invention.
Fig. 2 b are the trapezoidal corrugated steel exemplary plots of the present invention.
Fig. 2 c are the rectangle corrugated steel exemplary plots of the present invention.
Fig. 3 a are the pyriform chamber topology example figures of the present invention;
Fig. 3 b are the circular tank cell structure exemplary plots of the present invention;
Fig. 3 c are the vault quadrangle chamber topology example figures of the present invention;
Fig. 3 d are the chamber chamber topology example figures of rectangle three of the present invention;
Fig. 3 e are the chamber topology example figures of isomery rectangle two of the present invention;
Wherein:Foam lightweight soil 1, casing 2, flooring base 3, terrace 4, line holder 5, pipeline 6, steam-pressing aero-concrete Building block buttress 7, be backfilling and compacted soil 8, subgrade and pavement 9.
Pyriform chamber 2.1, circular chamber 2.2, vault quadrangle chamber 2.3, the chamber 2.4 of rectangle three, the case of isomery rectangle two Room 2.5, circular arc corrugated plating 2.6, trapezoidal corrugated plating 2.7, rectangle corrugated plating 2.8
Embodiment
A kind of construction method step of Foam lightweight soil steel corrugated plating combination pipe gallery of the present invention is as follows:
(1) it is close-shaped casing as piping lane section that mode cross section is quickly spliced into steel corrugated plating, casing it is transversal Face shape can be as shown in Fig. 3 a~Fig. 3 e are any, can be cross section for circular or ellipse or pyriform or quadrangle, Or vault quadrilateral shape;The casing of the piping lane section can for as shown in Fig. 3 a, Fig. 3 b, Fig. 3 c single chamber, can also be Two chambers or many chambers are divided into as shown in Fig. 3 d or Fig. 3 e.The steel corrugated plating is can be using circle as shown in Figure 2 a Arc corrugated plating, or the trapezoidal corrugated plating shown in Fig. 2 b, or the rectangle corrugated plating shown in Fig. 2 c.
(2) the longitudinal continued access in piping lane section is got up, bottom half uses autoclave aerated concrete building block buttress as support, Backfilled on the outside of the cast-in-place foamed light soil formation encapsulating of the casing outside of piping lane section and buttress, Foam lightweight soil encapsulated member Compacting soil, the common subgrade and pavement of top construction.Box house in piping lane section lays terrace, terrace lower section Foam lightweight soil Or normal concrete filling flooring base.Line holder 5 can be arranged as required in piping lane of the present invention and lay water supply line, in The various municipal pipelines such as waterpipe, gutter, power pipeline, communication line and burning line.
When there is underground water, and level of ground water it is higher when, Foam lightweight soil steel corrugated plating combination pipe gallery should be carried out Antifloating computation is not less than 1000kg/m using unit weight3

Claims (8)

1. a kind of pipe gallery, it is characterised in that:The pipe gallery is formed, piping lane section by the longitudinal continued access in some piping lane sections There is section a cross section formed by the assembly of steel corrugated plating to be close-shaped casing, and casing is encapsulated in the Foam lightweight soil soil body Interior, to be backfilling and compacted soil on the outside of the Foam lightweight soil soil body, box house lays terrace, terrace lower section Foam lightweight soil or coagulation Soil filling flooring base.
2. pipe gallery according to claim 1, it is characterised in that:The pipe gallery also includes buttress, buttress support In bottom half and it is embedded in the native soil body of foam makings, buttress is autoclave aerated concrete building block buttress.
3. pipe gallery according to claim 1, it is characterised in that:Construction subgrade road surface above the Foam lightweight soil soil body.
4. pipe gallery according to claim 1, it is characterised in that:The cabinets cavity of pipe gallery is provided with line holder And be disposed with municipal pipeline, the municipal pipeline include water supply line, intermediate water pipeline, gutter, power pipeline, communication line and Burning line.
5. pipe gallery according to claim 1, it is characterised in that:The cross section of the casing is circular or ellipse, Or pyriform or quadrangle or vault quadrilateral shape.
6. pipe gallery according to claim 1, it is characterised in that:The casing of the piping lane section is single chamber or divided It is divided into two chambers or is separated into many chambers.
7. pipe gallery according to claim 1, it is characterised in that:The steel corrugated plating is circular arc corrugated plating or trapezoidal Corrugated plating, rectangle corrugated plating.
8. the construction method of any described pipe gallery of a kind of claim 1~7, it is characterised in that comprise the following steps:With It is close-shaped casing as piping lane section that steel corrugated plating, which is quickly spliced into mode cross section, and then the longitudinal continued access in piping lane section is risen Come, cast-in-place foamed light soil is encapsulated to casing formation outside the casing of piping lane section, the box house in piping lane section lays ground Basic filling is carried out below level ground, terrace.
CN201710408411.8A 2017-06-02 2017-06-02 Comprehensive pipe rack and construction method thereof Active CN107152034B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710408411.8A CN107152034B (en) 2017-06-02 2017-06-02 Comprehensive pipe rack and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710408411.8A CN107152034B (en) 2017-06-02 2017-06-02 Comprehensive pipe rack and construction method thereof

Publications (2)

Publication Number Publication Date
CN107152034A true CN107152034A (en) 2017-09-12
CN107152034B CN107152034B (en) 2023-10-10

Family

ID=59796315

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710408411.8A Active CN107152034B (en) 2017-06-02 2017-06-02 Comprehensive pipe rack and construction method thereof

Country Status (1)

Country Link
CN (1) CN107152034B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107859062A (en) * 2017-10-27 2018-03-30 中交二航局第三工程有限公司 The earth-filling method of underground pipe gallery
CN113914145A (en) * 2021-10-15 2022-01-11 中铁第四勘察设计院集团有限公司 Tramcar embedded roadbed light structure for protecting municipal pipeline and construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103952986A (en) * 2014-05-19 2014-07-30 中国地质大学(武汉) Load-shedding type rigid culvert structure
KR20160070865A (en) * 2014-12-10 2016-06-21 한국해양과학기술원 Backfiling method for heat pipe
CN105804118A (en) * 2016-03-15 2016-07-27 广东盛瑞科技股份有限公司 Underground structure construction method based on cast-in-place foam lightweight materials
CN105971018A (en) * 2016-07-19 2016-09-28 中冶京诚工程技术有限公司 Tubular-cross-section urban underground comprehensive pipe gallery formed by steel corrugated plates
CN106242421A (en) * 2016-07-15 2016-12-21 中冶集团武汉勘察研究院有限公司 Stalk fibre air bubble mix light-textured soil and the structures and methods with its construction underground pipe gallery top vibration damping
CN206859259U (en) * 2017-06-02 2018-01-09 中交四航工程研究院有限公司 A kind of pipe gallery

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103952986A (en) * 2014-05-19 2014-07-30 中国地质大学(武汉) Load-shedding type rigid culvert structure
KR20160070865A (en) * 2014-12-10 2016-06-21 한국해양과학기술원 Backfiling method for heat pipe
CN105804118A (en) * 2016-03-15 2016-07-27 广东盛瑞科技股份有限公司 Underground structure construction method based on cast-in-place foam lightweight materials
CN106242421A (en) * 2016-07-15 2016-12-21 中冶集团武汉勘察研究院有限公司 Stalk fibre air bubble mix light-textured soil and the structures and methods with its construction underground pipe gallery top vibration damping
CN105971018A (en) * 2016-07-19 2016-09-28 中冶京诚工程技术有限公司 Tubular-cross-section urban underground comprehensive pipe gallery formed by steel corrugated plates
CN206859259U (en) * 2017-06-02 2018-01-09 中交四航工程研究院有限公司 A kind of pipe gallery

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
中国公路学会道路工程分会主编: "《2004年道路工程学术交流会论文集》", 31 October 2004, 北京:人民交通出版社 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107859062A (en) * 2017-10-27 2018-03-30 中交二航局第三工程有限公司 The earth-filling method of underground pipe gallery
CN113914145A (en) * 2021-10-15 2022-01-11 中铁第四勘察设计院集团有限公司 Tramcar embedded roadbed light structure for protecting municipal pipeline and construction method

Also Published As

Publication number Publication date
CN107152034B (en) 2023-10-10

Similar Documents

Publication Publication Date Title
CN101914925B (en) Basement by using optimized composite prefabricated arch wall as external wall
CN101298782B (en) Method and system for basement engineering water proof and water drain
CN104805866A (en) Prefabricated comprehensive pipe gallery and construction method
CN108252329B (en) Assembly type comprehensive pipe gallery for bearing force of enclosure structure and construction method thereof
CN107859065A (en) A kind of ultra-high performance concrete precast assembly pipe gallery and construction method
CN106555408A (en) The structure and construction method of underground pipe gallery
US11566390B2 (en) Construction method of reclaiming land from the sea based on basement utilization
CN204753627U (en) Prefabricated comprehensive piping lane
CN110004991B (en) Underground structure anti-floating system based on convex wing foot plate and construction method
CN206859259U (en) A kind of pipe gallery
CN101418569A (en) Optimization complex arch wall combining prefabricated arch leaf, support and major structure
CN107152034A (en) A kind of pipe gallery and its construction method
CN107268675A (en) The laying method and structure of a kind of many storehouse underground pipe galleries of combined type
CN206376277U (en) The structure of underground pipe gallery
CN202247719U (en) Corresponding corrugated pre-stressed anti-sedimentation culvert pipe for bridge
CN206035045U (en) Prefabricated assembled underground granary of endocyst plastics
CN207392241U (en) A kind of ultra-high performance concrete precast assembly pipe gallery
CN201400679Y (en) Prestressed steel cylinder concrete marsh gas generation tank
CN203701145U (en) Underground pipe network inspection well concrete assembly
CN216897881U (en) Photovoltaic-pumped storage-geothermal combined development and utilization system for abandoned coal mine
CN201883453U (en) Combined pipe jacking working well
CN106013911B (en) A kind of interior steel plated assembled circle underground granary with premoulded filler strip
CN210341986U (en) Piping lane composite waterproof structure
CN202483590U (en) Buried high-pressure water channel or tunnel seepage-proofing lining structure
CN206545284U (en) A kind of subsided rest room

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant