CN202483590U - Buried high-pressure water channel or tunnel seepage-proofing lining structure - Google Patents

Buried high-pressure water channel or tunnel seepage-proofing lining structure Download PDF

Info

Publication number
CN202483590U
CN202483590U CN2012201108397U CN201220110839U CN202483590U CN 202483590 U CN202483590 U CN 202483590U CN 2012201108397 U CN2012201108397 U CN 2012201108397U CN 201220110839 U CN201220110839 U CN 201220110839U CN 202483590 U CN202483590 U CN 202483590U
Authority
CN
China
Prior art keywords
seepage
pressure
proofing
steel tube
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2012201108397U
Other languages
Chinese (zh)
Inventor
蒋中明
熊小虎
冯树荣
秦卫星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changsha University of Science and Technology
Original Assignee
Changsha University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changsha University of Science and Technology filed Critical Changsha University of Science and Technology
Priority to CN2012201108397U priority Critical patent/CN202483590U/en
Application granted granted Critical
Publication of CN202483590U publication Critical patent/CN202483590U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model discloses a buried high-pressure water channel or tunnel seepage-proofing lining structure, wherein a seepage-proofing steel tube (1) is arranged in a high-pressure pipeline section or a high-pressure branch pipeline section; leveling or backfill concrete (3) is arranged between an outer wall of the seepage-proofing steel tube (1) and the high-pressure pipeline section or the high-pressure branch pipeline section; and reinforced concrete liner (2) is arranged on an inner wall of the seepage-proofing steel tube (1). The excellent seepage-proofing performance of the steel tube is utilized to solve the seepage problem of the high-pressure water pipeline, and the excellent compressive property of the reinforced concrete is utilized to prevent the steel tube from bending and being damaged. The lining structure provides another technical support for further promoting development of the high water head pumped storage power station construction technology.

Description

Embedded high pressure water channel or tunnel sealing liner structure
Technical field
The utility model relates to a kind of liner structure; Particularly relate to a kind of antiseepage and supporting and protection structure that is used for Hydraulic and Hydro-Power Engineering, the embedded high pressure water channel in traffic engineering field or traffic tunnel, especially be directed against the antiseepage and the supporting of pumped storage power plant high pressure diversion tunnel pressure piping section and high pressure bifurcated pipe section.
Background technology
Under the prior art condition, the power station of underground power house and the high pressure water channel liner structure of pumped storage power plant are set adopt form of structure such as steel lining, reinforced concrete lining layer or concrete lining.Under high water head and the high external water pressure condition, steel lining form of structure advantage is that barrier performance is good, and convenient maintenance and replacement, its shortcoming are that buckling failure takes place easily in the steel pipe lining cutting under high external water pressure effect; Be control steel pipe lining cutting generation buckling failure; Need to adopt high-strength steel and select for use the big steel plate of thickness to carry out the making of steel pipe lining cutting; Its consequence is that the manufacture craft difficulty is big, drainage system need be set outside the steel pipe lining cutting simultaneously reduce external water pressure, thereby involve great expense.The advantage of reinforced concrete lining layer and concrete lining structure is not have buckling problem, and construction technology is simple, and is cheap.The shortcoming of reinforced concrete lining layer and concrete lining structure is under high hydraulic action, can form the crack; Barrier performance is relatively poor; The water under high pressure disasters such as causing a large amount of permeable or infiltration unstabilitys easily of exosmosing, even if adopting under the infiltrative situation of grouting treatment country rock, its antiseepage durability is not good yet.
The utility model content
The utility model technical problem to be solved is the weak point that exists to existing high pressure water conservancy project water channel liner structure form, and a kind of high pressure barrier properties, durability and structural stability good embedded high pressure water channel or tunnel sealing liner structure taken into account is provided.
In order to solve the problems of the technologies described above; Embedded high pressure water channel or tunnel sealing liner structure that the utility model provides; In pressure piping section or high pressure bifurcated pipe section, be provided with the antiseepage steel pipe; Between the outer wall of described antiseepage steel pipe and described pressure piping section or high pressure bifurcated pipe section, be provided with levelling or fill concrete, be provided with reinforced concrete lining layer at the inwall of described antiseepage steel pipe.
Adopt the embedded high pressure water channel or the tunnel sealing liner structure of technique scheme; Through being set, certain thickness reinforced concrete lining layer shares the internal water pressure that acts on the outer field antiseepage steel pipe of steel concrete in the antiseepage steel pipe; To reduce the thickness of antiseepage steel pipe; Utilize the good compressive property of steel concrete simultaneously; Opposing is thoroughly avoided the generation of the buckling failure phenomenon of antiseepage steel pipe through the external water pressure that the outside steel pipe transmission comes, and cancellation simultaneously only is provided with the drainage system in the high pressure water channel under the steel lining situation.Through satisfying stressed in the reinforced concrete lining layer arranged outside and certain thickness antiseepage steel pipe durability, realize the compound lining structure block antiseepage function after the crack appears in reinforced concrete lining layer.Unite opposing external water pressure and internal water pressure owing to adopt reinforced concrete lining layer and antiseepage steel pipe; The performance and the thickness requirement of the steel pipe steel of pressure piping section or high pressure bifurcated pipe section have been reduced; Can adopt the steel plate of domestic production to carry out processing and fabricating; Avoided the high-strength steel plate that thickens of use import, can reduce construction costs significantly, promotion prospect is wide.This form of structure is reasonable in design, and is simple in structure, easy to operate.
The advantage of the utility model is: utilize the good barrier performance of steel pipe to solve the leakage problems of high pressure water channel, and utilize the steel concrete good pressure resistance can prevent steel pipe generation buckling failure.This liner structure form provides another technical support for the progress that further promotes the High Head Pumped Storage Power Station construction technique.
Description of drawings
Fig. 1 is the section of structure of the utility model.
The specific embodiment
Below in conjunction with accompanying drawing the utility model is described further.
Referring to Fig. 1, in pressure piping section or high pressure bifurcated pipe section 4, be provided with antiseepage steel pipe 1, between the outer wall of antiseepage steel pipe 1 and pressure piping section or high pressure bifurcated pipe section 4, be provided with levelling or fill concrete 3, be provided with reinforced concrete lining layer 2 at the inwall of antiseepage steel pipe 1.
Referring to Fig. 1; Through being set, certain thickness reinforced concrete lining layer 2 shares the internal water pressure that acts on the outer field antiseepage steel pipe 1 of steel concrete in antiseepage steel pipe 1; To reduce the thickness of antiseepage steel pipe 1, utilize the good compressive property of reinforced concrete lining layer 2 simultaneously, the external water pressure that opposing comes through the outside steel pipe transmission; Thoroughly avoid the generation of the buckling failure phenomenon of antiseepage steel pipe 1, cancellation simultaneously only is provided with the drainage system in the high pressure water channel under the steel lining situation.Through satisfying stressed in reinforced concrete lining layer 2 arranged outside and certain thickness antiseepage steel pipe 1 durability, realize the compound lining structure block antiseepage function after the crack appears in reinforced concrete lining layer 2.Unite opposing external water pressure and internal water pressure owing to adopt reinforced concrete lining layer 2 and antiseepage steel pipe 1; The performance and the thickness requirement of the steel pipe steel of pressure piping section or high pressure bifurcated pipe section 4 have been reduced; Can adopt the steel plate of domestic production to carry out processing and fabricating; Avoided the high-strength steel plate that thickens of use import, can reduce construction costs significantly, promotion prospect is wide.This form of structure is reasonable in design, and is simple in structure, easy to operate.

Claims (1)

1. embedded high pressure water channel or tunnel sealing liner structure; It is characterized in that: in pressure piping section or high pressure bifurcated pipe section, be provided with antiseepage steel pipe (1); Between the outer wall of described antiseepage steel pipe (1) and described pressure piping section or high pressure bifurcated pipe section, be provided with levelling or fill concrete (3), be provided with reinforced concrete lining layer (2) at the inwall of described antiseepage steel pipe (1).
CN2012201108397U 2012-03-22 2012-03-22 Buried high-pressure water channel or tunnel seepage-proofing lining structure Expired - Fee Related CN202483590U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012201108397U CN202483590U (en) 2012-03-22 2012-03-22 Buried high-pressure water channel or tunnel seepage-proofing lining structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012201108397U CN202483590U (en) 2012-03-22 2012-03-22 Buried high-pressure water channel or tunnel seepage-proofing lining structure

Publications (1)

Publication Number Publication Date
CN202483590U true CN202483590U (en) 2012-10-10

Family

ID=46958017

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012201108397U Expired - Fee Related CN202483590U (en) 2012-03-22 2012-03-22 Buried high-pressure water channel or tunnel seepage-proofing lining structure

Country Status (1)

Country Link
CN (1) CN202483590U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102536268A (en) * 2012-03-22 2012-07-04 长沙理工大学 Buried type high-pressure water channel or tunnel seepage-resistant lining structure
CN106320296A (en) * 2016-11-02 2017-01-11 广西大学 Basalt fiber grid reinforced lining structure for high ground temperature high-pressure hydraulic tunnel

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102536268A (en) * 2012-03-22 2012-07-04 长沙理工大学 Buried type high-pressure water channel or tunnel seepage-resistant lining structure
CN106320296A (en) * 2016-11-02 2017-01-11 广西大学 Basalt fiber grid reinforced lining structure for high ground temperature high-pressure hydraulic tunnel

Similar Documents

Publication Publication Date Title
CN203742623U (en) Water-pressure-resistant composite structure for tunnel
CN105064400A (en) Urban comprehensive pipe rack of steel corrugated plate structure
CN204715426U (en) A kind of water burst drainage system for closed deep foundation ditch exploratory hole
CN202483590U (en) Buried high-pressure water channel or tunnel seepage-proofing lining structure
CN102536268A (en) Buried type high-pressure water channel or tunnel seepage-resistant lining structure
CN203904857U (en) Precast-concrete three-arch culvert pipe
CN107355234B (en) Seepage-proofing corrosion-proofing durable confluence regulation type deep tunnel
CN204456124U (en) One is slip casing by pressure pipe repeatedly
CN204345087U (en) Buried thrust wall bushing waterproof seal
CN206859259U (en) A kind of pipe gallery
CN204941551U (en) A kind of subway station of Curve Pipe Jacking supporting and protection structure enlarging shield-tunneling construction
CN204343286U (en) A kind of steel pipe pile support
CN105332716A (en) Adaptive lining structure capable of bearing simultaneous actions of high internal and external water
CN203475580U (en) Multi-functional combined rainwater plastic inspection well
CN107152034A (en) A kind of pipe gallery and its construction method
CN202228090U (en) Multiplex anti-seepage bearing structure of pressure tunnel
CN204983098U (en) Positive pressure box culvert
CN204717161U (en) With the PCCP culvert pipe of pre-buried weldment
CN203307785U (en) Buried pressure pipe exterior drainage structure of hydropower station
CN203641701U (en) Lightweight concrete protective wall combined water charging and discharging pipeline
CN204098062U (en) Novel underground PCCP culvert pipe
CN205000287U (en) Prevention of seepage panel structure of long -term fluctuation zone of groundwater
CN205000311U (en) Water supply tunnel or low pressure hydraulic tunnel's seepage prevention structure
CN211547811U (en) Prefabricated assembled comprehensive pipe gallery
CN204898536U (en) Recess formula box culvert

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121010

Termination date: 20130322