CN201334669Y - Anchoring structure of tailings reservoir preliminary dam top leakproof geomembrane - Google Patents

Anchoring structure of tailings reservoir preliminary dam top leakproof geomembrane Download PDF

Info

Publication number
CN201334669Y
CN201334669Y CNU2008203033401U CN200820303340U CN201334669Y CN 201334669 Y CN201334669 Y CN 201334669Y CN U2008203033401 U CNU2008203033401 U CN U2008203033401U CN 200820303340 U CN200820303340 U CN 200820303340U CN 201334669 Y CN201334669 Y CN 201334669Y
Authority
CN
China
Prior art keywords
dam
geomembrane
leakproof
groove
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2008203033401U
Other languages
Chinese (zh)
Inventor
宋竞宁
吴长华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Original Assignee
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guiyang Aluminum Magnesium Design and Research Institute Co Ltd filed Critical Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority to CNU2008203033401U priority Critical patent/CN201334669Y/en
Application granted granted Critical
Publication of CN201334669Y publication Critical patent/CN201334669Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model discloses an anchoring structure of a tailings reservoir preliminary dam top leakproof geomembrane. A groove (2) is dug at one side of the inner slope of a dam body which needs the leakage prevention; the leakproof geomembrane (3) is paved along the inner wall of the groove (2); a landfill concrete layer (4) is cast on the leakproof geomembrane (3); and the landfill concrete layer (4) is filled in the whole groove (2). Compared with the prior art, by forming kinks in the groove which is dug at the dam top of the preliminary dam of the tailings reservoir, after the groove is filled with the landfill concrete layer, the leakproof geomembrane can realize rigid connection between the leakproof geomembrane and the preliminary dam top, greatly improves reliability, and further guarantees the rigidity and the reliability of the connection between the leakproof geomembran and the preliminary dam top since the landfill concrete layer and a road around the dam are simultaneously integrally cast with the same grade concrete.

Description

The anchor structure of a kind of mine tailing storehouse initial stage dam crest anti-seepage geomembrane
Technical field
The utility model relates to the anchor structure of a kind of mine tailing storehouse initial stage dam crest anti-seepage geomembrane, belongs to initial stage dam crest seepage control technique field, mine tailing storehouse.
Background technology
In alumina mine tailing storehouse; for the seepage that prevents wastewater from red mud pollutes environment; need in the stockyard, reach mine tailing storehouse initial dam inner slope anti-seepage geomembrane is set; and the anti-seepage geomembrane anchoring of dam crest in the early stage is a critical boundaries condition of place antiseepage, and the reliability of its anchoring is significant to the antiseepage and the environmental protection that realize the place.Present existing anchoring is that anti-seepage geomembrane is directly anchored into initial stage dam crest certain depth; this kind method has realized being articulated and connected of anti-seepage geomembrane and initial stage dam crest; but reliability is low; geomembrane is pulled out possibility under external force, is the extremely unfavorable factor of the whole antiseepage and the environmental protection of place.
The utility model content
Technical problem to be solved in the utility model is, the anchor structure of a kind of mine tailing storehouse initial stage dam crest anti-seepage geomembrane is provided, to solve the anchoring problem of mine tailing storehouse initial stage dam crest anti-seepage geomembrane and initial stage dam crest, realize both being rigidly connected, improve the connection reliability.
The technical solution of the utility model: need the dam body inner slope one side excavation of antiseepage fluted in the early stage on the dam, be equipped with anti-seepage geomembrane along the inwall of groove, be cast with the landfill layer of concrete on anti-seepage geomembrane, the landfill layer of concrete fills up whole groove.
The dam crest on dam is provided with dam crest ring field road in the early stage, and dam crest ring field road and landfill layer of concrete are to use that the concrete of same numeral is integrated poured to be obtained.
Compared with prior art, the utility model anti-seepage geomembrane forms bending in the groove of the dam crest excavation of mine tailing storehouse initial dam, after tamping with the landfill layer of concrete, can realize being rigidly connected of anti-seepage geomembrane and initial stage dam crest, significantly improved the connection reliability, it is integrated poured that the concrete of landfill layer of concrete and dam crest ring field road employing same numeral carries out the while, then further guaranteed rigidity and reliability that anti-seepage geomembrane is connected with the initial stage dam crest.
Description of drawings
Accompanying drawing 1 is a structural representation of the present utility model.
The specific embodiment
Embodiment of the present utility model: the anchor structure of this mine tailing storehouse initial stage dam crest anti-seepage geomembrane, as shown in Figure 1, comprise initial dam 1, need dam body inner slope one side of antiseepage to excavate fluted 2 in the early stage on the dam 1, inwall along groove 2 is equipped with anti-seepage geomembrane 3, be cast with landfill layer of concrete 4 on anti-seepage geomembrane 3, landfill layer of concrete 4 fills up whole groove 2, and its dam crest ring field road 5 and landfill layer of concrete 4 are to use that the concrete of same numeral is integrated poured to be obtained.
Implementation step of the present utility model is as follows:
The first step
When initial dam 1 is built a dam to the dam crest position, need the inner slope one side excavation groove 2 of antiseepage at dam body, the geometry of groove 2 is seen shown in Figure 1, concrete size should be according to calculating such as the relevant mechanical property of anti-seepage geomembrane 3 such as tensile strength;
Second step
After groove 2 excavations finish, carry out the laying of anti-seepage geomembrane 3, and anti-seepage geomembrane 3 is involved in the groove 2 by shown in Figure 1;
The 3rd step
With concrete groove is tamped and to obtain landfill layer of concrete 4; Generally speaking, dam crest is provided with a ring road 5, landfill layer of concrete 4 should with dam crest ring field road 5 integral cast-in-situs and the concrete grade identical with its use.

Claims (2)

1. the anchor structure of a mine tailing storehouse initial stage dam crest anti-seepage geomembrane, it is characterized in that: the dam body inner slope one side excavation fluted (2) that needs antiseepage in the early stage on dam (1), inwall along groove (2) is equipped with anti-seepage geomembrane (3), be cast with landfill layer of concrete (4) on anti-seepage geomembrane (3), landfill layer of concrete (4) fills up whole groove (2).
2. the anchor structure of mine tailing according to claim 1 storehouse initial stage dam crest anti-seepage geomembrane, it is characterized in that: the dam crest of dam (1) is provided with dam crest ring field road (5) in the early stage, and dam crest ring field road (5) and landfill layer of concrete (4) are to use that the concrete of same numeral is integrated poured to be obtained.
CNU2008203033401U 2008-12-11 2008-12-11 Anchoring structure of tailings reservoir preliminary dam top leakproof geomembrane Expired - Fee Related CN201334669Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2008203033401U CN201334669Y (en) 2008-12-11 2008-12-11 Anchoring structure of tailings reservoir preliminary dam top leakproof geomembrane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2008203033401U CN201334669Y (en) 2008-12-11 2008-12-11 Anchoring structure of tailings reservoir preliminary dam top leakproof geomembrane

Publications (1)

Publication Number Publication Date
CN201334669Y true CN201334669Y (en) 2009-10-28

Family

ID=41286319

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2008203033401U Expired - Fee Related CN201334669Y (en) 2008-12-11 2008-12-11 Anchoring structure of tailings reservoir preliminary dam top leakproof geomembrane

Country Status (1)

Country Link
CN (1) CN201334669Y (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101914918A (en) * 2010-07-12 2010-12-15 无锡市政设计研究院有限公司 High-steep side slope and intensely weathered bed rock solid waste landfill site seepage prevention structure and treatment method thereof
CN102367672A (en) * 2011-09-13 2012-03-07 北京高能时代环境技术股份有限公司 Method for installing vertical soft barrier system based on soil-stone foundation
CN103266633A (en) * 2013-06-04 2013-08-28 贵州遵义汇兴铁合金有限责任公司 Seepage-proof sewage discharging and floodwater draining method for tailing reservoir in wet metallurgy
CN103669419A (en) * 2012-09-21 2014-03-26 贵阳铝镁设计研究院有限公司 Connecting structure of red mud storage yard anti-seepage film and concrete column and construction method
CN105672443A (en) * 2016-01-20 2016-06-15 中国电建集团贵阳勘测设计研究院有限公司 Structure integrating anchoring of anti-seepage film, flood interception and passing
CN106140772A (en) * 2015-03-25 2016-11-23 深圳市利赛实业发展有限公司 Overlay film gas gathering system
CN111893957A (en) * 2020-07-27 2020-11-06 中国恩菲工程技术有限公司 Initial dam of tailing pond
CN113089584A (en) * 2021-03-18 2021-07-09 中国水利水电第九工程局有限公司 Construction method of soil dam heightening anti-seepage PVC geomembrane
CN113802523A (en) * 2020-06-16 2021-12-17 中国水利水电第九工程局有限公司 Anti-seepage earth dam heightening construction process
CN114837176A (en) * 2022-06-14 2022-08-02 中国一冶集团有限公司 Method for fixing anti-seepage geotextile in separation belt

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101914918A (en) * 2010-07-12 2010-12-15 无锡市政设计研究院有限公司 High-steep side slope and intensely weathered bed rock solid waste landfill site seepage prevention structure and treatment method thereof
CN102367672A (en) * 2011-09-13 2012-03-07 北京高能时代环境技术股份有限公司 Method for installing vertical soft barrier system based on soil-stone foundation
CN103669419A (en) * 2012-09-21 2014-03-26 贵阳铝镁设计研究院有限公司 Connecting structure of red mud storage yard anti-seepage film and concrete column and construction method
CN103669419B (en) * 2012-09-21 2015-12-09 贵阳铝镁设计研究院有限公司 The syndeton of red mud dump antiseepage film and concrete column and construction method
CN103266633A (en) * 2013-06-04 2013-08-28 贵州遵义汇兴铁合金有限责任公司 Seepage-proof sewage discharging and floodwater draining method for tailing reservoir in wet metallurgy
CN103266633B (en) * 2013-06-04 2015-09-09 贵州遵义汇兴铁合金有限责任公司 A kind of hydrometallurgy tailings storehouse antiseep sewer drains off floodwaters method
CN106140772A (en) * 2015-03-25 2016-11-23 深圳市利赛实业发展有限公司 Overlay film gas gathering system
CN105672443A (en) * 2016-01-20 2016-06-15 中国电建集团贵阳勘测设计研究院有限公司 Structure integrating anchoring of anti-seepage film, flood interception and passing
CN113802523A (en) * 2020-06-16 2021-12-17 中国水利水电第九工程局有限公司 Anti-seepage earth dam heightening construction process
CN111893957A (en) * 2020-07-27 2020-11-06 中国恩菲工程技术有限公司 Initial dam of tailing pond
CN113089584A (en) * 2021-03-18 2021-07-09 中国水利水电第九工程局有限公司 Construction method of soil dam heightening anti-seepage PVC geomembrane
CN114837176A (en) * 2022-06-14 2022-08-02 中国一冶集团有限公司 Method for fixing anti-seepage geotextile in separation belt

Similar Documents

Publication Publication Date Title
CN201334669Y (en) Anchoring structure of tailings reservoir preliminary dam top leakproof geomembrane
CN102587358B (en) Construction technology of high polymer material post-grouting squeezed cast-in-place pile
CN104612134A (en) Cast-in place pile post-grouting construction method for pouring construction
CN103866762A (en) Pile body longitudinal multipoint grouting device
CN102108869A (en) Grout stop pad construction method for kilometer vertical shaft grouting for water control
CN102817621B (en) Comprehensive construction method applicable to controlling arch basement sedimentation for tunnel in unfavorable geological conditions
CN204185844U (en) Draining slip casting structure
CN101532386B (en) Method and device for underpinning antifriction separator for shallow underground space construction
CN207700221U (en) A kind of prefabricated pipe gallery steel plate cast-in-place concrete sealing connection structure
CN101793027A (en) Core-grouted static pressure anchor rod pile
CN202969370U (en) Novel steel pipe pile
CN103343534A (en) Closed precipitation method for foundation pit construction
CN204083520U (en) Pipeline runs through concrete floor waterproof construction
CN101545255B (en) Method for manufacturing a PHC tubular pile in soft soil region through chambering and grouting
CN104180077A (en) Waterproof structure with pipeline penetrating through concrete floor
CN204662246U (en) steep slope bridge pier structure
CN201095741Y (en) Conjoined tubular filling bag
CN2718073Y (en) Ejection rubber water plugging band
CN105332716A (en) Adaptive lining structure capable of bearing simultaneous actions of high internal and external water
CN214423394U (en) Dewatering well reinforced by annular capsule
CN205100992U (en) Self -adaptation lining cutting structure for can bear high interior extra income does simultaneously
CN203879548U (en) Sealing wall for water plugging of mine roadway
CN204570705U (en) Three-dimensional post jacking structure is held in a kind of artificial grouting layer method stake
CN203878568U (en) Longitudinal multi-point pile body grouting device
CN203096696U (en) High and low composite backwater weir

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: GUIYANG ALUMINUM AND MAGNESIUM DESIGN INSTITUTE CO

Free format text: FORMER NAME: GUIYANG ALUMINIUM AND MAGNESIUM DESIGN INST.

CP03 Change of name, title or address

Address after: 550081 Guiyang Province, Jinyang New District, Zhu Zhu Road, No. 2

Patentee after: Guiyang Aluminum & Magnesium Design Institute Co., Ltd.

Address before: 550004 No. 208, Beijing Road, Guiyang, Guizhou

Patentee before: Guiyang Aluminium and Magnesium Design Inst.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20091028

Termination date: 20141211

EXPY Termination of patent right or utility model