CN202969370U - Novel steel pipe pile - Google Patents

Novel steel pipe pile Download PDF

Info

Publication number
CN202969370U
CN202969370U CN 201220601136 CN201220601136U CN202969370U CN 202969370 U CN202969370 U CN 202969370U CN 201220601136 CN201220601136 CN 201220601136 CN 201220601136 U CN201220601136 U CN 201220601136U CN 202969370 U CN202969370 U CN 202969370U
Authority
CN
China
Prior art keywords
steel
pile
steel pipe
pipe
tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220601136
Other languages
Chinese (zh)
Inventor
周继忠
罗才松
蔡雪峰
蔡建平
陈小成
许小燕
叶婉玲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Nan'an No1 Construction Co Ltd
Fujian University of Technology
Original Assignee
Fujian Nan'an No1 Construction Co Ltd
Fujian University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Nan'an No1 Construction Co Ltd, Fujian University of Technology filed Critical Fujian Nan'an No1 Construction Co Ltd
Priority to CN 201220601136 priority Critical patent/CN202969370U/en
Application granted granted Critical
Publication of CN202969370U publication Critical patent/CN202969370U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model provides a novel steel pipe pile, which comprises a steel pipe, a pile tip and a pressure grouting pipe, wherein the pile tip is vertically arranged on the end part of the steel pipe; the pressure grouting pipe is arranged in the steel pipe; a plurality of holes are formed in the peripheral side of the pipe wall within a length range of 50-100 cm at the lower end of the pressure grouting pipe; the diameter of the holes is 0.3-0.6 cm; cement grout can flow out of the grouting pipe from the holes during grouting; filler is filled between the outer wall of the pressure grouting pipe and the inner wall of the steel pipe and is a mixture of the cement grout and gravels; the diameter of the gravels is 1-4 cm; and the cement grout is injected into inner bottom of the steel pipe through the pressure grouting pipe to seep along gaps of the gravels so as to fill and compact the gaps of the gravels in the steel pipe. The steel pipe pile has the characteristics of convenience in construction and high bearing capacity, and the bearing capacity can be improved by 10-20 percent compared with the bearing capacity of the normal steel pipe pile.

Description

A kind of Novel steel pile tube
[technical field]
The utility model relates to a kind of building pile foundation, specifically refers to a kind of Novel steel pile tube.
[background technology]
A kind of deep foundation that pile foundation is comprised of stake and the pile cap (abbreviation cushion cap) that is connected stake top, have that bearing capacity is high, settling amount is little and more uniform characteristics, almost can be applied to various engineering geological conditionss and various types of engineering, especially be applicable to build the heavy building on soft foundation.Therefore, in coastal and soft clay area, pile foundation is more extensive.The pile foundation type is more, as precast reinforced concrete piles, pile tube, various castinplace piles etc., the reason extensive uses such as pile tube is high because of its intensity, easy construction, but pile tube mostly diameter is less, bearing capacity is relatively low, in view of this, a kind of Novel steel pile tube of the utility model exploitation has higher stiffness and bearing capacity.
[summary of the invention]
The technical problems to be solved in the utility model is to provide a kind of Novel steel pile tube, has higher stiffness and bearing capacity, avoids present steel pipe pile rigidity and the relatively low problem of bearing capacity.
The utility model is achieved in that a kind of Novel steel pile tube, comprises steel pipe, pile top and slip casing by pressure pipe; Described pile top is vertically installed in described steel tube end part, and described slip casing by pressure pipe is located in steel pipe, and the tube wall week of described slip casing by pressure pipe lower end is offered a plurality of holes on side, is filled with filler between the outer wall of described slip casing by pressure pipe and the inwall of steel pipe.
Further, the tube wall week side of the long scope of the 50cm of described slip casing by pressure pipe lower end~100cm is opened described hole, and the diameter of this hole is at 0.3~0.6cm.
Further, described diameter of steel tube is 300~600mm, and steel pipe length is 10~30m.
Further, described pile top is steel pile tip, and this steel pile tip and described steel-pipe welding are fixed together.
Further, described pile top is the steel concrete pile top.
Further, described outer wall of steel pipe is provided with a rust protection agent layer.
The utility model has the advantage of: the utility model is first put into rubble in steel pipe, recycling slip casing by pressure machinery is injected into the end in steel pipe with cement paste, cement paste fills up the described rubble of steel duct gap closely knit along the gap of rubble, form filler, the Rigidity and strength of steel pipe pile is improved, improve the vertical bearing capacity of steel pipe pile.Therefore, this steel pipe pile has easy construction, rigidity is large, bearing capacity is high characteristic, can improve bearing capacity 10%-20% than ordinary steel pile tube.
[description of drawings]
Fig. 1 is the structural representation that the utility model adopts the steel pipe pile after the steel concrete pile top is implemented.
Fig. 2 is the structural representation that the utility model adopts the steel pipe pile after steel pile tip is implemented.
[specific embodiment]
See also shown in Figure 1ly, a kind of Novel steel pile tube of the utility model the first embodiment comprises steel pipe 1, pile top 2 and slip casing by pressure pipe 3; Described pile top 2 is vertically installed in described steel pipe 1 end, described slip casing by pressure pipe 3 is located in steel pipe 1, offer a plurality of holes (not shown) on all sides of the tube wall of the long scope of described slip casing by pressure pipe 3 lower end 50cm~100cm, described hole diameter is 0.3~0.6cm, when being used for slip casting, cement paste can flow out Grouting Pipe from described hole, is filled with filler 4 between the inwall of the outer wall of described slip casing by pressure pipe 3 and steel pipe 1.Described filler 4 is the mixture of cement paste 41 and rubble 42, and these rubble 42 diameters are 1~4cm.And then fill the space of 42 of rubbles by slip casing by pressure pipe 3 injected water mud 41, make the described filler 4 in described steel pipe 1 reach full closely knit.
Wherein, described steel pipe 1 diameter is 300~600mm, and steel pipe 1 length is 10~30m.Described outer wall of steel pipe is provided with a rust protection agent layer (not shown).
In the present embodiment, described pile top 2 is the steel concrete pile top.
The Specific construction mode of this first embodiment is: at first measure setting-out and make a position, bury at place, stake position that this steel concrete pile top of steel concrete pile top 2(sets in advance underground), adopt immersed tube machinery (not shown) that described steel pipe 1 vertically is located on steel concrete pile top 2 and sinks in the stratum, then pipeline sinking pile machinery is removed; Slip casing by pressure pipe 3 is put into steel pipe 1 inner bottom part, insert rubble 42 in steel pipe 1, with slip casing by pressure pipe 3 and slip casing by pressure mechanical connection (not shown), to the interior slip casting of steel pipe 1, until cement paste is filled with; Cement paste 41 is filled the space of 42 of rubbles, makes the described filler 4 in described steel pipe 1 reach full closely knit.
Seeing also shown in Figure 2ly, is that the utility model adopts the structural representation after steel pile tip is implemented.The Novel steel pile tube of this second embodiment and the first embodiment difference are: described pile top 2 is steel pile tip, and this steel pile tip 2 is welded and fixed together with described steel pipe 1.
The Specific construction mode of this second embodiment is: at first measure setting-out and make a position, adopt immersed tube machinery (not shown) to sink in the stratum at place, stake position with the described steel pipe 1 of described steel pile tip, then pipeline sinking pile machinery is removed; Slip casing by pressure pipe 3 is put into steel pipe 1 inner bottom part, insert rubble 42 in steel pipe 1, with slip casing by pressure pipe 3 and slip casting mechanical connection (not shown), to the interior slip casting of steel pipe 1, until cement paste is filled with; Cement paste 41 is filled the space of 42 of rubbles, makes the described filler 4 in described steel pipe 1 reach full closely knit.
After implementing, the utility model has following remarkable benefit:
Take full advantage of slurry filling machine cement paste is injected in steel pipe, cement paste is along the hole seepage flow of rubble, the gap of the described rubble of steel duct filled up closely knit, and the Rigidity and strength of steel pipe pile is improved.Therefore, this pile tube has the high characteristic of easy construction, rigidity and bearing capacity, can improve bearing capacity 10%-20% than ordinary steel pile tube.
The above is only preferred embodiment of the present utility model, and all equalizations of doing according to the utility model claim change and modify, and all should belong to covering scope of the present utility model.

Claims (6)

1. a Novel steel pile tube, is characterized in that: comprise steel pipe, pile top and slip casing by pressure pipe; Described pile top is vertically installed in described steel tube end part, and described slip casing by pressure pipe is located in steel pipe, and the tube wall week of described slip casing by pressure pipe lower end is offered a plurality of holes on side, is filled with filler between the outer wall of described slip casing by pressure pipe and the inwall of steel pipe.
2. a kind of Novel steel pile tube according to claim 1 is characterized in that: the tube wall week side of the 50cm of described slip casing by pressure pipe lower end~long scope of 100cm is opened described hole, and the diameter of this hole is at 0.3~0.6cm.
3. a kind of Novel steel pile tube according to claim 1, it is characterized in that: described diameter of steel tube is 300~600mm, steel pipe length is 10~30m.
4. a kind of Novel steel pile tube according to claim 1, it is characterized in that: described pile top is steel pile tip, this steel pile tip and described steel-pipe welding are fixed together.
5. a kind of Novel steel pile tube according to claim 1, it is characterized in that: described pile top is the steel concrete pile top.
6. a kind of Novel steel pile tube according to claim 1, it is characterized in that: described outer wall of steel pipe is provided with a rust protection agent layer.
CN 201220601136 2012-11-14 2012-11-14 Novel steel pipe pile Expired - Fee Related CN202969370U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220601136 CN202969370U (en) 2012-11-14 2012-11-14 Novel steel pipe pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220601136 CN202969370U (en) 2012-11-14 2012-11-14 Novel steel pipe pile

Publications (1)

Publication Number Publication Date
CN202969370U true CN202969370U (en) 2013-06-05

Family

ID=48510464

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220601136 Expired - Fee Related CN202969370U (en) 2012-11-14 2012-11-14 Novel steel pipe pile

Country Status (1)

Country Link
CN (1) CN202969370U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105421446A (en) * 2015-12-29 2016-03-23 武汉中力岩土工程有限公司 Mixed soil extruded and cured precast pile for soft foundation treatment as well as construction method
CN106522257A (en) * 2016-11-04 2017-03-22 成都启立辰智科技有限公司 Gravel-filled support foundation pile
CN106545008A (en) * 2015-09-17 2017-03-29 江苏远卓地下工程技术有限公司 A kind of cast-in-situ bored pile pile making method
CN111636417A (en) * 2020-05-14 2020-09-08 湖北中南岩土工程有限公司 Grouting type steel pipe pile and construction method thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106545008A (en) * 2015-09-17 2017-03-29 江苏远卓地下工程技术有限公司 A kind of cast-in-situ bored pile pile making method
CN105421446A (en) * 2015-12-29 2016-03-23 武汉中力岩土工程有限公司 Mixed soil extruded and cured precast pile for soft foundation treatment as well as construction method
CN106522257A (en) * 2016-11-04 2017-03-22 成都启立辰智科技有限公司 Gravel-filled support foundation pile
CN111636417A (en) * 2020-05-14 2020-09-08 湖北中南岩土工程有限公司 Grouting type steel pipe pile and construction method thereof

Similar Documents

Publication Publication Date Title
CN103215960B (en) Grouting method for high polymer vertical support system
CN102953372A (en) Steel pipe pile and construction method thereof
CN103184734B (en) A kind of construction method implanting slip casting compound pile
CN105544512A (en) Reinforced sack grouting stone-breaking pile with heat transferring tube buried therein and construction method
CN105298516A (en) Combined supporting structure of steel pipe pile steel-bar-embedded tunnel composite lining used for soft foundation
CN203213124U (en) Steel sheet pile and cement-mixed pile combined support
CN103422510B (en) Steel pipe frame type cofferdam structure and construction method
CN102051879B (en) Process for constructing soil anchor
CN103437348A (en) Construction device and method of pile peripheral cemented soil cast-in-place stiffness core pile
CN202969370U (en) Novel steel pipe pile
CN202787334U (en) Sealing structure of deep well casing used during tunnel construction
CN102168419B (en) Method for compounding anchor rod by geotextile reinforcing
CN205225280U (en) A combined supporting structure that is used for steel -pipe pile bar planting tunnel composite lining of soft base
CN202039771U (en) Long-spiral grouting and guncreting multifunctional drilling tool
CN201933510U (en) Outlet shaft structure of underground factories in hydroelectric engineering
CN203462463U (en) Construction device of pile-peripheral cemented-soil cast-in-situ stiffening core pile
CN105464105A (en) Pile forming structure and method of zero-friction pile
CN104988914A (en) Cast-in-situ bored pile breakage processing method under water area environment
CN204959787U (en) Novel tower crane combination formula basis
CN105672329B (en) The large size prefabricated building enclosure of deep basal pit and construction method
CN101545255B (en) Method for manufacturing a PHC tubular pile in soft soil region through chambering and grouting
CN101793027A (en) Core-grouted static pressure anchor rod pile
CN106869153A (en) A kind of method of the quick soft soil foundation treatment of well-points dewatering
CN204662246U (en) steep slope bridge pier structure
CN103993609B (en) The multi-functional fast hard concrement manual repair foundation pit waterproof curtain of silicon ash sand guide drainage

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130605

Termination date: 20161114