CN201272657Y - Special apparatus for anode framework assembly and swinging of revolving furnace flue gas cleaning equipment - Google Patents
Special apparatus for anode framework assembly and swinging of revolving furnace flue gas cleaning equipment Download PDFInfo
- Publication number
- CN201272657Y CN201272657Y CNU2008201534877U CN200820153487U CN201272657Y CN 201272657 Y CN201272657 Y CN 201272657Y CN U2008201534877 U CNU2008201534877 U CN U2008201534877U CN 200820153487 U CN200820153487 U CN 200820153487U CN 201272657 Y CN201272657 Y CN 201272657Y
- Authority
- CN
- China
- Prior art keywords
- platform
- assembling
- assembly platform
- anode
- anode superstructure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Electrostatic Separation (AREA)
Abstract
The utility model discloses a special device for assembling and hoisting anode frames in converter fume purification equipment, which comprises a fixing platform and an assembling platform. The plane size of the assembling platform matches with that of a transverse anode frame, the planes of both the fixing platform and the assembling platform are of a hollow structure, the assembling platform is disposed on the fixing platform, two ends of the adjacent sides of the joint faces of the fixing platform and the assembling platform are respectively provided with lugs and screw holes, holes of the lugs are provided with bolts screwed into the screw holes, one side of the fixing platform is movably connected with one side of the assembling platform through the lugs and the bolts, the movable side of the assembling platform is provided with a notch opening up, and two sides of the notch are respectively provided with lifting lugs. The anode plate and the anode frame can be conveniently assembled and hoisted by using the special device without erecting scaffolds, thereby increasing the construction efficiency, and preventing people and equipment from hidden dangers.
Description
Technical field
The utility model relates to a kind of isolated plant of converter gas purification equipment anode superstructure assembling handling.
Background technology
Converter gas purification equipment is divided into two kinds substantially, i.e. wet cleaning and dry cleaning.The most crucial equipment of dry cleaning is electrostatic precipitator, and it mainly comprises cathode line and anode plate, and anode plate is assembled on the anode superstructure; Electrostatic precipitator is owing to be in the down operation of abominable working environment of high temperature and corrosive fume for a long time, and flexural deformation in various degree can appear in anode plate, and this situation is on the rise, and finally will influence dedusting environment friendly and coal-gas recovering effect.Therefore need electrostatic precipitator is regularly overhauled.The main contents of its maintenance are the assembling and the replacing of anode superstructure, the adjustment of the assembling of cathode frame and replacing and die opening etc.
It is an important component part of electrostatic precipitator maintenance that anode plate is assembled on the anode superstructure, and the maintenance progress and the quality of whole converter gas purification equipment had very big influence.As shown in Figure 1, anode superstructure is made up of 1,32 arcs of a top cross-bar 2, a middle part rapping anvil 3 and a bottom platen 4, and 16 anode plates 5 are assembled in respectively between the arc 2 and bottom platen 4 of anode superstructure.
Because the anode superstructure volume is bigger, very inconvenience of its storage and transportation, therefore when the assembling of carrying out anode superstructure and replacing operation, usually in the close openr place assembled on site of converter gas purification equipment, after finishing, assembling installs at once, to improve the degree of utilization in place, the scaffold of two rows multilayer arranged side by side is set up in ground on the scene, be provided with the installation passage in the middle of the scaffold, earlier the top cross-bar of anode superstructure is placed on the top of scaffold during construction, again piece of anode plate is moved into the installation passage of scaffold, anode plate is connected with crossbeam with arc, rapping anvil in middle part is installed then, bottom platen is installed at last.
Because anode plate is one positive one anti-installation on anode superstructure, therefore framework the right and left all must be arranged the workmen, and when assembling the workmen need on scaffold swashes, climb down, moreover the employing of the anode plate of big C type structure is the steel plate of 1.5mm, whole anode superstructure seems top-heavy, and the anode plate area is big, waves with the wind when running into strong wind, therefore operating efficiency is low, and exists the potential safety hazard of the bigger person and equipment.
Summary of the invention
Technical problem to be solved in the utility model provides a kind of isolated plant of converter gas purification equipment anode superstructure assembling handling, utilize this device need not set up scaffold, make things convenient for the assembling and the handling of anode plate and anode superstructure, improve operating efficiency, stopped the potential safety hazard of the person and equipment.
For solving the problems of the technologies described above, the isolated plant of the utility model converter gas purification equipment anode superstructure assembling handling comprises fixed platform and assembly platform, size coupling when the plane sizes of described assembly platform and anode superstructure are horizontal, the plane of described fixed platform and assembly platform is an engraved structure, described assembly platform places on the described fixed platform, the two ends of described fixed platform and assembly platform joint face sides adjacent are respectively equipped with otic placode and screw, be provided with bolt in the earhole of described otic placode, described bolt is screwed in the described screw, one side of described fixed platform and assembly platform flexibly connects by otic placode and bolt, described assembly platform active side is provided with groove, described slot opening makes progress, and described groove two ends are respectively equipped with hanger.
For preventing anode superstructure landing on assembly platform, the identical both sides that described assembly platform is provided with otic placode are respectively equipped with some plate washers.
Because the isolated plant of the utility model converter gas purification equipment anode superstructure assembling handling has adopted technique scheme, promptly utilize fixed platform and the horizontal anode superstructure of assembly platform that places on the fixed platform, the plane of fixed platform and assembly platform is an engraved structure, fixed platform and assembly platform one side flexibly connect by otic placode and bolt, opposite side is provided with groove, and the groove two ends are provided with hanger; When anode superstructure is constructed, the top cross-bar of anode superstructure is placed in the groove so that the stack-mounted anode superstructure is in stabilized conditions and maintenance level, the workmen is positioned at the hollow space ease of assembly anode superstructure and the anode plate on fixed platform and assembly platform plane, after assembling finishes, lifting appliance is at first by the hanger of the assembly platform assembly platform of slinging, make assembly platform rotate an angle, then the sling anode superstructure that finishes of assembling and being installed on the converter gas purification equipment of lifting appliance by otic placode and bolt; Utilize this device need not set up scaffold, make things convenient for the assembling and the handling of anode plate and anode superstructure, improved operating efficiency, stopped the potential safety hazard of the person and equipment.
Description of drawings
The utility model is described in further detail below in conjunction with drawings and embodiments:
Fig. 1 is the structural representation of this device anode superstructure,
Fig. 2 is the front elevation of this apparatus structure,
Fig. 3 is the birds-eye view of this apparatus structure,
Scheme drawing when Fig. 4 slings for this device assembly platform.
The specific embodiment
As shown in Figures 2 and 3, the isolated plant of the utility model converter gas purification equipment anode superstructure assembling handling comprises fixed platform 1 and assembly platform 2, size coupling when the plane sizes of described assembly platform 2 and anode superstructure are horizontal, the plane of described fixed platform 1 and assembly platform 2 is engraved structures, described assembly platform 2 places on the described fixed platform 1, the two ends of described fixed platform 1 and assembly platform 2 joint face sides adjacent are respectively equipped with otic placode 5 and screw, be provided with bolt 6 in the earhole of described otic placode 5, described bolt 6 is screwed in the described screw, one side of described fixed platform 1 and assembly platform 2 flexibly connects by otic placode 5 and bolt 6, described assembly platform 2 is provided with groove 3 with the same side that is provided with otic placode 5, described groove 3 openings make progress, and described groove 3 two ends are respectively equipped with hanger 4.
For preventing anode superstructure landing on assembly platform 2, the identical both sides that described assembly platform 2 is provided with otic placode 5 are respectively equipped with some plate washers 7.
The isolated plant of the utility model converter gas purification equipment anode superstructure assembling handling utilizes fixed platform and the horizontal anode superstructure of assembly platform that places on the fixed platform, the plane of fixed platform and assembly platform is an engraved structure, fixed platform and assembly platform one side flexibly connect by otic placode and bolt, opposite side is provided with groove, and the groove two ends are provided with hanger; When anode superstructure is constructed, the top cross-bar of anode superstructure is placed in the groove so that the stack-mounted anode superstructure is in stabilized conditions and maintenance level, and when anode superstructure lifts by crane not because of the deadweight landing, the assembly platform plate washer of both sides setting in addition is used to prevent that anode superstructure from breakking away, and the workmen can be located in the interior ease of assembly anode superstructure of hollow space and the anode plate on fixed platform and assembly platform plane.
As shown in Figure 4, after assembling finishes, lifting appliance is at first by the hanger 4 of assembly platform 2 assembly platform 2 of slinging, make assembly platform 2 by otic placode 5 and bolt 6 rotations one angle, the sling anode superstructure 8 that finishes of assembling and being installed on the converter gas purification equipment of lifting appliance then, because the anode superstructure that installs is top-heavy, so this is mainly the possibility that prevents from directly to lift by crane anode superstructure and anode superstructure is fractureed; Utilize this device need not set up scaffold, make things convenient for the assembling and the handling of anode plate and anode superstructure, improved operating efficiency, stopped the potential safety hazard of the person and equipment.
Claims (2)
1, a kind of isolated plant of converter gas purification equipment anode superstructure assembling handling, it is characterized in that: this device comprises fixed platform and assembly platform, size coupling when the plane sizes of described assembly platform and anode superstructure are horizontal, the plane of described fixed platform and assembly platform is an engraved structure, described assembly platform places on the described fixed platform, the two ends of described fixed platform and assembly platform joint face sides adjacent are respectively equipped with otic placode and screw, be provided with bolt in the earhole of described otic placode, described bolt is screwed in the described screw, one side of described fixed platform and assembly platform flexibly connects by otic placode and bolt, the active side of described assembly platform is provided with groove, described slot opening makes progress, and described groove two ends are respectively equipped with hanger.
2, the isolated plant of converter gas purification equipment anode superstructure assembling handling according to claim 1, it is characterized in that: the identical both sides that described assembly platform is provided with otic placode are respectively equipped with some plate washers.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNU2008201534877U CN201272657Y (en) | 2008-09-25 | 2008-09-25 | Special apparatus for anode framework assembly and swinging of revolving furnace flue gas cleaning equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNU2008201534877U CN201272657Y (en) | 2008-09-25 | 2008-09-25 | Special apparatus for anode framework assembly and swinging of revolving furnace flue gas cleaning equipment |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201272657Y true CN201272657Y (en) | 2009-07-15 |
Family
ID=40883005
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNU2008201534877U Expired - Fee Related CN201272657Y (en) | 2008-09-25 | 2008-09-25 | Special apparatus for anode framework assembly and swinging of revolving furnace flue gas cleaning equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201272657Y (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105883048A (en) * | 2016-06-08 | 2016-08-24 | 艾尼科环保技术(安徽)有限公司 | Packaging device for anode rows of electrostatic dust collector |
CN108622784A (en) * | 2017-03-24 | 2018-10-09 | 中国二十冶集团有限公司 | RS or BS discharge lines deduster electric field combined hanging methods |
CN109623742A (en) * | 2017-10-09 | 2019-04-16 | 上海宝冶集团有限公司 | Quick assembly or fitting table for electrostatic precipitator anode plate |
CN110142595A (en) * | 2019-05-16 | 2019-08-20 | 中国能源建设集团山西电力建设第三有限公司 | The combination of electric precipitator cathode-anode plate and lifting integrated platform and combination hoisting method |
-
2008
- 2008-09-25 CN CNU2008201534877U patent/CN201272657Y/en not_active Expired - Fee Related
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105883048A (en) * | 2016-06-08 | 2016-08-24 | 艾尼科环保技术(安徽)有限公司 | Packaging device for anode rows of electrostatic dust collector |
CN105883048B (en) * | 2016-06-08 | 2018-03-30 | 艾尼科环保技术(安徽)有限公司 | A kind of electrostatic precipitator anode arranges packing device |
CN108622784A (en) * | 2017-03-24 | 2018-10-09 | 中国二十冶集团有限公司 | RS or BS discharge lines deduster electric field combined hanging methods |
CN109623742A (en) * | 2017-10-09 | 2019-04-16 | 上海宝冶集团有限公司 | Quick assembly or fitting table for electrostatic precipitator anode plate |
CN110142595A (en) * | 2019-05-16 | 2019-08-20 | 中国能源建设集团山西电力建设第三有限公司 | The combination of electric precipitator cathode-anode plate and lifting integrated platform and combination hoisting method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201272657Y (en) | Special apparatus for anode framework assembly and swinging of revolving furnace flue gas cleaning equipment | |
CN203499229U (en) | Operating platform for construction of elevator shaft | |
CN204299175U (en) | Hydraulic climbing die block system | |
CN103352559B (en) | Storage tank keeps in repair special hanging movable job platform | |
CN205773024U (en) | Convenient pipeline promotes auxiliary device | |
CN109911106B (en) | Operation device and method for installing positioning pin of container ship | |
CN209760033U (en) | Auxiliary adjusting device for beam falling of steel truss arch bridge | |
CN216613870U (en) | Rail mounted lift platform is used in curtain engineering construction | |
CN201695661U (en) | Component for arranging external suspending bracket of window | |
CN213979839U (en) | Assembled I-shaped girder steel operation device that encorbelments that can have enough to meet need not wear wall | |
CN211159160U (en) | Filtering mechanism of hydrogen fluoride tail gas treatment device | |
CN110388042A (en) | A kind of construction of lift well operating platform | |
CN201099690Y (en) | Steel-smelting converter repairing equipment | |
CN211257761U (en) | Lifting type elevator shaft operating platform | |
CN209147117U (en) | A kind of dry bottom hopper inspection platform | |
CN112696083A (en) | Chimney installation method in limited area | |
CN202785248U (en) | Basket device special for truck crane | |
CN207276043U (en) | A kind of large component lifts positioning auxiliary device | |
CN205894641U (en) | Elevartor shaft lifting platform | |
CN112481437A (en) | Blast furnace Y-shaped downcomer dismounting and replacing method | |
CN217420153U (en) | Detachable switching structure of unit curtain wall | |
CN205421886U (en) | Novel instrument formula elevator shaft operating platform | |
CN220506189U (en) | Generator set chassis with telescopic lifting lugs | |
CN218438172U (en) | Safety auxiliary device for preventing hanging basket from falling down during construction | |
CN109296213A (en) | A kind of Mobile crane using skyscraper brush window machine track curtain wall construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |