CN201268945Y - Casing tube reserved pre-burying system - Google Patents
Casing tube reserved pre-burying system Download PDFInfo
- Publication number
- CN201268945Y CN201268945Y CNU2008201322604U CN200820132260U CN201268945Y CN 201268945 Y CN201268945 Y CN 201268945Y CN U2008201322604 U CNU2008201322604 U CN U2008201322604U CN 200820132260 U CN200820132260 U CN 200820132260U CN 201268945 Y CN201268945 Y CN 201268945Y
- Authority
- CN
- China
- Prior art keywords
- sleeve
- sleeve pipe
- handle
- angle steel
- utility
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Abstract
The utility model discloses a sleeve preserving and pre-burying system belonging to the technical field of architectural construction. The sleeve preserving and pre-burying system comprises a sleeve, a handle, a closure plate, flat irons and angle steels. The handle is located at one end of the sleeve; the closure plate is located between the sleeve and the handle; and the flat irons and the angle steels are fixed on the template. The utility model has the advantages that the positioning accuracy rate is high, the fixing is firm, the position is not easy to move, the hole-maintenance and hole-opening frequency is decreased, and the rework cost is reduced; the construction is convenient and the mounting rate is high; the occupied area and the influence on the civil construction steel bars are small; the closure effect is good so that the concretes can not enter the sleeve; the material source is rich; the short steel bars are waste civil construction materials, and the angle steels and the flat irons are leftover materials in the project; when in dismantling, only the sleeve is pulled out and the cross fixing rack is dismantled, so the dismantling is convenient.
Description
Technical field
The utility model belongs to technical field of building construction, is specifically related to a kind of sleeve pipe set aside pre-embedded system.
Background technology
In the structure construction stage, all kinds of piping erection does not mostly possess execution conditions, therefore just must carry out the set aside pre-embedded work of hole, sleeve pipe, and most of project casing construction methods are that iron wire is fixed colligation all around.Find that in construction this kind method has some constructional difficulties:
1), reserved location is inaccurate: iron wire to around fixedly the time, the center is looked for inaccurate, sleeve pipe put do not stay just easily flat;
2), the finished product protection difficulty: during fluid concrete, even bump easily askew, bump tiltedly and bump.
The utility model content
The utility model is in order to solve in the structure construction stage, and all kinds of piping erection does not mostly possess execution conditions, finds some constructional difficulties in construction:
1), reserved location is inaccurate: iron wire to around fixedly the time, the center is looked for inaccurate, sleeve pipe put do not stay just easily flat;
2), the finished product protection difficulty: during fluid concrete, even bump easily askew, bump tiltedly and bump;
In order to overcome the above problems, the utility model has adopted a kind of sleeve pipe set aside pre-embedded system.
The utility model comprises sleeve pipe, handle, closure plate, band iron and angle steel, and described handle is positioned at an end of sleeve pipe, and described closure plate is between described sleeve pipe and handle, and described band iron and angle steel are fixed on the template.
Bolt hole is left in the centre position of described closure plate.
Described band iron and angle steel are fixed into cross, and described casing pipe sleeve is on described cross, and angle steel and band iron are fixed into round steel of the vertical welding of planar central of cross.
On the described round steel screw thread is arranged.
The nail hole is left at the two ends of described band iron and angle steel respectively.
The utlity model has following beneficial effect: there is following advantage in the sleeve pipe set aside pre-embedded system that the utility model provides:
1), the locating accuracy height, fixation is not easy the shift position, can reduce the frequency of repairing the hole, punching, and reduces rework cost;
2), easy construction, the installation effectiveness height;
3), floor space is little, and is little to the influence of civil engineering reinforcing bar;
4), plugging effect is good, do not worry that concrete enters in the sleeve pipe;
5), the material therefor source is abundant: used bar dowel can be used the civil engineering waste material, and angle steel and band iron use leftover pieces remaining in the engineering;
6), remove conveniently, only need to pull out sleeve pipe during dismounting and tear the cross fixed mount open.
Description of drawings
Fig. 1 cuts off the pipe schematic diagram in the utility model;
Fig. 2 makes center fixation cross schematic diagram for the utility model;
Fig. 3 is the stereogram of the utility model Fig. 2;
Fig. 4 is the utility model installation schematic diagram.
Fig. 5 removes schematic diagram for the utility model.
The specific embodiment
The utility model will be further described below in conjunction with accompanying drawing.Concrete job practices is as follows:
1), make sleeve pipe: welded steel pipe or seamless steel pipe are cut into the length that we need, the handle of burn-oning in the upper end, and carry out shutoff with iron sheet or iron plate, the bolt hole of φ about 10 is stayed at the center, as shown in Figure 1, Fig. 1 cuts off in the utility model to manage schematic diagram.
2), make the center fixation cross: one section band iron and angle steel are pressed the blanking of casing inner diameter length, be vertically welded in together, at vertical angle steel and round steel that is with screw thread of band iron planar central welding, as shown in Figure 2, Fig. 2 makes center fixation cross schematic diagram for the utility model again.
3), " four nails are determined the course of events ": according to drawing or in-depth figure, the center of sleeve pipe is marked on the template, and the sleeve pipe center of circle with the center alignment tab of cross is fixed on band iron and angle steel on the template respectively with iron nail, as shown in Figure 3, Fig. 3 is the stereogram of the utility model Fig. 2.
4), sleeve pipe installs: with casing pipe sleeve on cross, first-class bolt, as shown in Figure 4, Fig. 4 is the utility model installation schematic diagram.
5), sleeve pipe is removed: when treating that civil engineering has been broken concrete, bolt is laid down, extracted sleeve pipe, pull out cross, prepare next time and use.
Claims (6)
1, a kind of sleeve pipe set aside pre-embedded system, it is characterized in that: described system comprises sleeve pipe (1), handle (2), closure plate (3), band iron (4) and angle steel (5), described handle (2) is positioned at an end of sleeve pipe (1), described closure plate (3) is positioned between described sleeve pipe (1) and the handle (2), and described band iron (4) and angle steel (5) are fixed on the template (6).
2, sleeve pipe set aside pre-embedded according to claim 1 system, it is characterized in that: bolt hole (7) is left in the centre position of described closure plate (3).
3, sleeve pipe set aside pre-embedded according to claim 1 and 2 system, it is characterized in that: described band iron (4) and angle steel (5) are fixed into cross, described sleeve pipe (1) is enclosed within on the described cross, and angle steel (5) and band iron (4) are fixed into a planar central round steel of vertical welding (8) of cross.
4, sleeve pipe set aside pre-embedded according to claim 3 system, it is characterized in that: described round steel has screw thread on (8).
5, sleeve pipe set aside pre-embedded according to claim 1 and 2 system, it is characterized in that: nail hole (9) is left at the two ends of described band iron (4) and angle steel (5) respectively.
6, sleeve pipe set aside pre-embedded according to claim 3 system, it is characterized in that: nail hole (9) is left at the two ends of described band iron (4) and angle steel (5) respectively.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNU2008201322604U CN201268945Y (en) | 2008-08-19 | 2008-08-19 | Casing tube reserved pre-burying system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNU2008201322604U CN201268945Y (en) | 2008-08-19 | 2008-08-19 | Casing tube reserved pre-burying system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201268945Y true CN201268945Y (en) | 2009-07-08 |
Family
ID=40841542
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNU2008201322604U Expired - Fee Related CN201268945Y (en) | 2008-08-19 | 2008-08-19 | Casing tube reserved pre-burying system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201268945Y (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102251658A (en) * | 2011-04-13 | 2011-11-23 | 中建七局第二建筑有限公司 | Device for pre-burying and fixing sleeve |
CN102383601A (en) * | 2011-08-24 | 2012-03-21 | 中国葛洲坝集团股份有限公司 | Method and device for leading pre-embedded pipes in concrete out of side wall joints |
CN108533876A (en) * | 2018-05-08 | 2018-09-14 | 五冶集团上海有限公司 | A kind of method for blocking of pre-buried pipeline casing joint |
-
2008
- 2008-08-19 CN CNU2008201322604U patent/CN201268945Y/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102251658A (en) * | 2011-04-13 | 2011-11-23 | 中建七局第二建筑有限公司 | Device for pre-burying and fixing sleeve |
CN102383601A (en) * | 2011-08-24 | 2012-03-21 | 中国葛洲坝集团股份有限公司 | Method and device for leading pre-embedded pipes in concrete out of side wall joints |
CN102383601B (en) * | 2011-08-24 | 2013-12-04 | 中国葛洲坝集团股份有限公司 | Method and device for leading pre-embedded pipes in concrete out of side wall joints |
CN108533876A (en) * | 2018-05-08 | 2018-09-14 | 五冶集团上海有限公司 | A kind of method for blocking of pre-buried pipeline casing joint |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103061504B (en) | Concrete slab Pipe installing hole to be provided construction mould and construction method | |
CN112796514A (en) | Masonry corner constructional column template shaping and reinforcing device and construction method | |
CN201268945Y (en) | Casing tube reserved pre-burying system | |
CN109208902A (en) | A kind of corner constructional column standardization bracing reinforcement device | |
CN202047597U (en) | Sleeve fixator | |
CN110863644A (en) | Novel turnover tool type beam side connecting wall piece fixing device and method | |
CN108547383B (en) | Hoisting and inclined strut integrated embedded part and using method | |
CN206220499U (en) | The integrated mould of water-heating preformed hole | |
CN102400552B (en) | Boundary beam upper-port anti-expansion mold reinforcing device | |
CN203347233U (en) | Tapered tie bolt for large steel formworks | |
CN202596148U (en) | Reusable cantilever scaffold anchoring compression ring | |
CN205857693U (en) | A kind of canalization template being applied to movement joint both sides shear wall synchronous construction | |
CN207314850U (en) | A kind of split bolt continued access combination unit | |
CN203701564U (en) | Anchoring fixing piece for cantilever scaffold | |
CN206815804U (en) | A kind of new builder's jack girder steel built-in fitting | |
CN210067407U (en) | Scaffold wall connecting piece | |
CN207569004U (en) | A kind of hanger fixing device of a Preembedded | |
CN215760424U (en) | Be used for interior positioner of shear force wall template | |
CN205134546U (en) | But quick detachable I -steel built -in fitting of encorbelmenting of cyclic utilization | |
CN206245709U (en) | A kind of outrigger wall-connecting piece | |
CN201447862U (en) | Instrumental operating platform used for elevator shaft shear wall shuttering erection | |
CN207436500U (en) | A kind of three sections of split bolt continued accesses combination unit | |
CN207619988U (en) | The cast-in-place concrete of bar shaped foundation pit is to supportting the connection structure with prefabricated linking beam | |
CN206769245U (en) | A kind of combination construction component for strengthening Sloping roof construction quality | |
CN206090939U (en) | Brickwork wall drawknot muscle connecting tool |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20090708 Termination date: 20170819 |
|
CF01 | Termination of patent right due to non-payment of annual fee |