CN201013397Y - 一种急倾斜综采液压支架 - Google Patents
一种急倾斜综采液压支架 Download PDFInfo
- Publication number
- CN201013397Y CN201013397Y CNU2006200344077U CN200620034407U CN201013397Y CN 201013397 Y CN201013397 Y CN 201013397Y CN U2006200344077 U CNU2006200344077 U CN U2006200344077U CN 200620034407 U CN200620034407 U CN 200620034407U CN 201013397 Y CN201013397 Y CN 201013397Y
- Authority
- CN
- China
- Prior art keywords
- jack
- hydraulic support
- push rod
- dipping
- accent
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Harvesting Machines For Root Crops (AREA)
Abstract
一种急倾斜综采液压支架,涉及煤矿支护设备。本实用新型主要包括工作面的刮板运输机和液压支架的顶梁、立柱、掩护梁、前连杆、后连杆、推移千斤顶、推杆、十字连接头、底座、调推千斤顶等。由于本实用新型能有效控制液压支架的下滑和下滑后的复位,并能有效控制刮板运输机的下滑,确保综采液压支架在急倾斜煤层,特别是倾角大于55°煤层的正常开采和安全作业,故本实用新型可广泛应用于急倾斜煤层开采中,特别适用于煤层倾角大于55°的开采中。
Description
技术领域
本实用新型属于煤矿机械技术领域,特别涉及煤矿支护设备。
背景技术
国内外按照煤层倾角的大小分类,将煤层倾角分为缓倾斜煤层、倾斜煤层、急倾斜煤层。煤层倾角25°以下为缓倾斜煤层,大于45°为急倾斜煤层。目前,急倾斜煤层综采技术比缓倾斜和倾斜煤层综采技术发展缓慢,且差距较大,主要原因是急倾斜煤层倾角大,设备自重产生的向下分力增大,造成工作面设备容易产生向下滑动,煤层倾角越大,该方面问题就越严重。因此,对急倾斜综采工作面的采煤机、运输机、液压支架等主要设备在不断地移动过程中的防倒、防滑要求极高,依靠现有技术解决安全保障的难度大。因此,解决好急倾斜煤层综采液压支架防倒、防滑(向下滑动)和工作面刮板运输机下滑,是确保急倾斜煤层综采成功和安全生产的重要保障措施。
国内外现有煤矿开采中,综采由于产量和效率高,安全可靠性好,生产成本低。因此综采是煤矿首选的采煤工艺技术。但由于现有综采液压支架的结构和性能不适应于急倾斜煤层开采,特别是煤层倾角大于55°后,现有综采液压支架防倒、防滑性能将基本失去作用,造成急倾斜煤层采用综采技术开发十分困难。
发明内容
本实用新型的目的是针对现有综采液压支架的不足之处,提供一种急倾斜综采液压支架,具有能有效控制液压支架的下滑和下滑后的复位,并能有效控制刮板运输机的下滑等特点。
本实用新型的目的是这样实现的:一种急倾斜综采液压支架,主要包括工作面的刮板运输机和液压支架的顶梁、立柱、掩护梁、前连杆、后连杆、推移千斤顶、推杆、底座、十字连接头、调推千斤顶等,其特征是连接推移千斤顶的推杆和刮板运输机的十字连接头的头部为方头或长方形头。使十字连接头无法产生转动,从而使液压支架中的推移千斤顶的推杆不产生向下偏移,有效地控制了液压支架的下滑,同时也有效地控制了刮板运输机的下滑。在液压支架的底座上并对应于十字连接头连接处或上、下两侧,装设1个或2个调推千斤顶,与推移千斤顶推杆垂直布置。在采煤过程中,当推移千斤顶的推杆向下产生偏移时,在调推千斤顶的作用下,使推杆与刮板运输机始终保持垂直状态,不发生向下偏移,达到工作面的刮板运输机和液压支架不产生相对位移和整体位移的目的,从而控制了刮板运输机和液压支架的下滑。当液压支架有少量下滑时,通过调推千斤顶的作用,推动推杆向上移动,使下滑的液压支架恢复到正常位置。
调推千斤顶的缸径为80-120mm、活塞柱直径为50-90mm、行程为60-120mm。
本实用新型的采煤过程:当采煤机每割完一刀煤,液压支架的推移千斤顶顶出,推动推杆伸出,通过十字连接头推动刮板运输机前移一刀煤的距离,然后推移千斤顶缩回,并带动推杆缩回。在推杆缩回的过程中,拉动整台液压支架前移一刀煤的距离,完成一个循环采煤作业。
本实用新型提供的急倾斜综采液压支架,通过在液压支架底座上增加一个调推千斤顶和将液压支架中连接推移千斤顶推杆和刮板运输机的十字头连接头,由圆头连接改为方头或长方形头连接,能有效控制液压支架的下滑和下滑后的复位,同时也使运输机的下滑得到有效控制,确保了综采液压支架在急倾斜煤层,特别是倾角大于55°煤层的正常开采和安全作业,为煤矿急倾斜煤层综采的发展,提供了重要的保障作用。本实用新型可广泛应用于急倾斜煤层开采中,特别适用于煤层倾角大于55°的开采中。
附图说明
图1为急倾斜综采工作面设备布置主视图;
图2为急倾斜综采工作面设备布置俯视图;
图3为本实用新型的急倾斜综采支架与工作面刮板运输机和滚筒采煤机组合安装图;
图4为实施例的综采支架俯视图;
图5为图4中A-A剖面图;
图6为本实用新型的调推千斤顶结构图;
图7为本实用新型的推杆结构主视图;
图8为图7的俯视图;
图9为本实用新型的十字连接头结构主视图;
图10为图9的俯视图;
下面结合附图对本实用新型作进一步说明。
图中:1刮板运输机,2液压支架,3滚筒采煤机,4端头支架,5桥式转载机,6皮带运输机,7工作面下出口排头支架防倒防滑装置,8综采液压支架防倒防滑装置,9工作面上出口排尾支架防倒防滑装置,10运输机防滑装置,11工作面运输巷,12工作面回风巷,13顶梁,14立柱,15掩护梁,16前连杆,17后连杆,18推移千斤顶,19、21、23连接件,20推杆,24底座,25调推千斤顶,26插接件,27十字连接头,28连接耳。
具体实施例
下面结合具体实施方式,进一步说明本实用新型。
如图3~10所示,一种急倾斜综采液压支架,主要包括工作面的刮板运输机1和液压支架2的顶梁13、立柱14、掩护梁15、前连杆16、后连杆17、推移千斤顶18、推杆20、底座24、十字连接头27、调推千斤顶25等。其特征是连接推移千斤顶18的推杆20和刮板运输机1的十字连接头27的头部为方头,并在液压支架2的底座24上并对应于十字连接头27方头的上、下两侧,装设2个调推千斤顶25,与推移千斤顶18推杆20垂直布置。调推千斤顶25的缸径为100mm、活塞柱直径为70mm、最大行程为90mm、工作压力为31.5Mpa。
Claims (3)
1.一种急倾斜综采液压支架,主要包括工作面的刮板运输机(1)和液压支架(2)的顶梁(13)、立柱(14)、掩护梁(15)、前连杆(16)、后连杆(17)、推移千斤顶(18)、推杆(20)、底座(24)、十字连接头(27),其特征在于还有调推千斤顶(25),推移千斤顶(18)的推杆(20)和刮板运输机(1)的十字连接头(27)的头部为方头或长方形头,并在液压支架(2)的底座(24)上并对应于十字连接头(27)连接处或上、下两侧,装设1个或2个调推千斤顶(25),与推移千斤顶(18)推杆(20)垂直布置。
2.按照权利要求1所述的一种急倾斜综采液压支架,其特征在于所述的调推千斤顶(25)的缸径为80mm-120mm、活塞柱直径为50mm-90mm、行程为60mm-120mm。
3.按照权利要求1所述的一种急倾斜综采液压支架,其特征在于一种急倾斜综采液压支架,主要包括工作面的刮板运输机(1)和液压支架(2)的顶梁(13)、立柱(14)、掩护梁(15)、前连杆(16)、后连杆(17)、推移千斤顶(18)、推杆(20)、底座(24)、调推千斤顶(25)、连接推移千斤顶(18)的推杆(20)和刮板运输机(1)的十字连接头(27)的头部为方头,并在液压支架(2)的底座(24)上并对应于十字连接头(27)方头的上、下两侧,装设2个调推千斤顶(25),与推移千斤顶(18)推杆(20)垂直布置,调推千斤顶(25)的缸径为100mm、活塞柱直径为70mm、行程为90mm、工作压力为31.5Mpa。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNU2006200344077U CN201013397Y (zh) | 2006-05-31 | 2006-05-31 | 一种急倾斜综采液压支架 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNU2006200344077U CN201013397Y (zh) | 2006-05-31 | 2006-05-31 | 一种急倾斜综采液压支架 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201013397Y true CN201013397Y (zh) | 2008-01-30 |
Family
ID=39025184
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNU2006200344077U Expired - Fee Related CN201013397Y (zh) | 2006-05-31 | 2006-05-31 | 一种急倾斜综采液压支架 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201013397Y (zh) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102116163A (zh) * | 2010-12-10 | 2011-07-06 | 李泽宇 | 一种立层液压支架 |
CN102373937A (zh) * | 2011-09-30 | 2012-03-14 | 天地科技股份有限公司 | 急倾斜煤层俯伪斜开采工作面菱形液压支架 |
CN104389599A (zh) * | 2014-09-16 | 2015-03-04 | 四川华蓥山广能集团嘉华机械有限责任公司 | 伪俯斜刮板输送机推进方法 |
CN104727839A (zh) * | 2015-03-16 | 2015-06-24 | 中煤北京煤矿机械有限责任公司 | 大倾角工作面端头支架的辅助拉移装置 |
CN106996306A (zh) * | 2017-05-02 | 2017-08-01 | 中煤北京煤矿机械有限责任公司 | 综采工作刮板输送机机头的辅助拉移装置 |
CN110173290A (zh) * | 2019-07-02 | 2019-08-27 | 重庆市能源投资集团科技有限责任公司 | 一种用于急倾斜回采工作面的液压支架 |
-
2006
- 2006-05-31 CN CNU2006200344077U patent/CN201013397Y/zh not_active Expired - Fee Related
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102116163A (zh) * | 2010-12-10 | 2011-07-06 | 李泽宇 | 一种立层液压支架 |
CN102116163B (zh) * | 2010-12-10 | 2013-02-20 | 李泽宇 | 一种立层液压支架 |
CN102373937A (zh) * | 2011-09-30 | 2012-03-14 | 天地科技股份有限公司 | 急倾斜煤层俯伪斜开采工作面菱形液压支架 |
CN102373937B (zh) * | 2011-09-30 | 2016-06-29 | 天地科技股份有限公司 | 急倾斜煤层俯伪斜开采工作面菱形液压支架 |
CN104389599A (zh) * | 2014-09-16 | 2015-03-04 | 四川华蓥山广能集团嘉华机械有限责任公司 | 伪俯斜刮板输送机推进方法 |
CN104727839A (zh) * | 2015-03-16 | 2015-06-24 | 中煤北京煤矿机械有限责任公司 | 大倾角工作面端头支架的辅助拉移装置 |
CN106996306A (zh) * | 2017-05-02 | 2017-08-01 | 中煤北京煤矿机械有限责任公司 | 综采工作刮板输送机机头的辅助拉移装置 |
CN110173290A (zh) * | 2019-07-02 | 2019-08-27 | 重庆市能源投资集团科技有限责任公司 | 一种用于急倾斜回采工作面的液压支架 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201013397Y (zh) | 一种急倾斜综采液压支架 | |
CN104234711B (zh) | 适用于7~10m厚煤层的三滚筒采煤机以及开采方法 | |
CN100582435C (zh) | 综放工作面运顺端头液压支架 | |
CN102587913A (zh) | 一种急倾斜煤层俯伪斜走向长壁综合机械化采煤方法 | |
CN202467843U (zh) | 一种急倾斜煤层俯伪斜走向长壁综采工作面综合配套方式 | |
CN203066995U (zh) | 急倾斜煤层工作面两巷超前支护液压支架侧护装置 | |
CN102251774B (zh) | 急倾斜长壁钻式采煤机结合液压掩护式支架的综采采煤法 | |
CN101915102A (zh) | 急倾斜走向长壁综合机械化采煤方法 | |
CN102562113A (zh) | 一种用于急倾斜煤层综采工作面三机配套设备的防滑结构 | |
CN202108528U (zh) | 液压支架操纵阀操纵手柄防护闭锁装置 | |
CN201554481U (zh) | 充填支护液压支架 | |
CN201391324Y (zh) | 轻型薄煤层完整顶板综采液压支架 | |
CN203412606U (zh) | 采煤与充填平行作业的支套式液压支架 | |
CN201090231Y (zh) | 采煤工作面支护联合液压支架 | |
CN102373937B (zh) | 急倾斜煤层俯伪斜开采工作面菱形液压支架 | |
CN103147757A (zh) | 一种间歇式采煤方法 | |
CN201982127U (zh) | 多级插接连杆式充填液压支架 | |
CN103557023A (zh) | 极软煤层液压支架 | |
CN202467879U (zh) | 用于急倾斜煤层综采工作面三机配套设备的防滑结构 | |
CN101526004B (zh) | 一种大倾角低位放顶煤液压支架 | |
CN103696793A (zh) | 伪俯斜综采液压支架 | |
CN113653523B (zh) | 液压支架快速回撤的三角区宽型临时支护装置及支护方法 | |
CN103195458A (zh) | 煤矿井下大通道端头悬移液压支架 | |
CN200982199Y (zh) | 一种倾斜和急倾斜综采液压支架架前挡矸装置 | |
CN203130131U (zh) | 煤矿井下大通道端头悬移液压支架 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20080130 Termination date: 20150531 |
|
EXPY | Termination of patent right or utility model |