CN1918331A - Method for obtaining a pieced yarn lenght having constant mass in a vortex spinning procedure - Google Patents
Method for obtaining a pieced yarn lenght having constant mass in a vortex spinning procedure Download PDFInfo
- Publication number
- CN1918331A CN1918331A CNA2005800045919A CN200580004591A CN1918331A CN 1918331 A CN1918331 A CN 1918331A CN A2005800045919 A CNA2005800045919 A CN A2005800045919A CN 200580004591 A CN200580004591 A CN 200580004591A CN 1918331 A CN1918331 A CN 1918331A
- Authority
- CN
- China
- Prior art keywords
- drafting system
- roller
- fibrous composite
- rear roller
- jaw line
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- D—TEXTILES; PAPER
- D01—NATURAL OR MAN-MADE THREADS OR FIBRES; SPINNING
- D01H—SPINNING OR TWISTING
- D01H1/00—Spinning or twisting machines in which the product is wound-up continuously
- D01H1/14—Details
- D01H1/20—Driving or stopping arrangements
- D01H1/22—Driving or stopping arrangements for rollers of drafting machines; Roller speed control
-
- D—TEXTILES; PAPER
- D01—NATURAL OR MAN-MADE THREADS OR FIBRES; SPINNING
- D01H—SPINNING OR TWISTING
- D01H15/00—Piecing arrangements ; Automatic end-finding, e.g. by suction and reverse package rotation; Devices for temporarily storing yarn during piecing
- D01H15/002—Piecing arrangements ; Automatic end-finding, e.g. by suction and reverse package rotation; Devices for temporarily storing yarn during piecing for false-twisting spinning machines
-
- D—TEXTILES; PAPER
- D01—NATURAL OR MAN-MADE THREADS OR FIBRES; SPINNING
- D01H—SPINNING OR TWISTING
- D01H4/00—Open-end spinning machines or arrangements for imparting twist to independently moving fibres separated from slivers; Piecing arrangements therefor; Covering endless core threads with fibres by open-end spinning techniques
- D01H4/42—Control of driving or stopping
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Textile Engineering (AREA)
- Spinning Or Twisting Of Yarns (AREA)
- Yarns And Mechanical Finishing Of Yarns Or Ropes (AREA)
Abstract
The invention relates to a method for starting a drawing frame (1) used for drawing a fiber bond (2). Said drawing frame (1) comprises at least one pair of forward rollers (3) and a pair of rear rollers (4) that is provided with a clamping line (5), one end (6) of a fiber bond being provided for starting the drawing frame (1). According to the invention, said end (6) of the fiber band enters the clamping line (5) of the pair of rear rollers (4) during starting of the drawing frame (1) only once the acceleration response process in the rotary speed curve of the pair of forward rollers (3) and in the rotary speed curve of the pair of rear rollers (4) has been completed.
Description
The present invention relates to method according to the operation drafting system of the preceding explanation clause of Patent right requirement 1 independently and 2, relate to according to the controller of the drafting system of the weaving loom of the preceding explanation clause of Patent right requirement 12 and relate to weaving loom with described controller according to Patent right requirement 13.
Prior art
Operate the method for drafting system known dawn in textile technology.Publication EP 121 97 37, EP 807 700 and EP 137 57 09 have described the method for this form.Yet as obviously finding out from the announcement of having mentioned, the present invention is particularly suitable for operating the drafting system that belongs to open-end spinning frame.In open-end spinning frame, fibrous composite is by a kind of spun yarn in the multiple air flow.
Yet the known method of operation drafting system has shortcoming.This is for the drafting system that belongs to open-end spinning frame or particularly like this for the drafting system that the fibrous composite of drawing-off is delivered to according to the spinning unit of open-end spinning process work.The shortcoming of the known method of operation drafting system is: joint quality can not be always satisfactory.Term " joint " is understood to mean " seam " in the yarn, after for example breaking aborning, locates yarn in " seam " and " is connected " once more or " hanging up ".Usually, joint by at existing yarn end place or the fiber that spins other on every side produce.Joint constitutes yarn end and additionally spins actual overlap joint section between thereon the new fiber.Therefore usually form actual undesirable thickness portion (place).Ideally, joint or docking point should be as broad as long with remaining yarn (part), and this is particularly like this for intensity and fiber quality.In the effort that realizes this perfect condition, various possibilities are disclosed in the above-mentioned announcement.For example, the fibrous termination of butt joint nidus is narrowed down and/or delivery ratio still less fiber under the steady state operation subsequently in the overlap joint section.
Yet, in addition, in known devices, also have other the present invention to plan the problem that solves now.
Really say, once find: when drafting system is devoted oneself to work when middle, therefore in relevant roller is devoted oneself to work to quilt or when being accelerated, the velocity of rotation curve is superimposed upon on the corresponding butt joint speed.By roller to producing this stack (cross to be in harmonious proportion and dash down) from pausing to their the corresponding butt joint speed or the quickening of butt joint velocity of rotation, when having reached the butt joint velocity of rotation for the first time, described stack has formed the right non-constant velocity of rotation curve of roller, therefore formed the drafting system roller between non-constant velocity of rotation than (seeing the explanation of Fig. 2 and back).Usually, in drafting system, to during accelerating to operating rate or after just having arrived fixing butt joint speed, just begun mating operation at roller.In other words, roller never is considered in the production of joint up to now to accelerate to the stack during the butt joint speed at it.Like this, up to now, produced under the non-constant velocity of rotation or cause drawing-off drafting system two rollers between non-constant velocity of rotation than under the joint that obtains.Exactly, because right toning and the Xia Chong of roller produced drawing-off coarse or that change in fibrous composite.When this fibrous composite that changes the ground drawing-off combines with yarn end, thereby during the generation joint, then this joint also has quality fluctuation.Consequently: in the overlap joint section of joint, great majority are to have produced unallowed thick position, usually are thereafter unallowed thin positions.On the contrary, be in the overlap joint section, to produce thin position or butt joint falls flat.
Therefore the purpose as basis of the present invention provides the method that operation is used for the drafting system of drawn fiber composite, utilizes described method to avoid the quality fluctuation in the joint or it is reduced to minimum.The purpose that also is considered provides the method for operation drafting system, and in described method, fibrous composite is from the starting just drafted with correct draw ratio.This or these purpose utilizes the feature in the Patent right requirement 1 and 2 independently to reach.
Explain the beneficial effect of the method according to this invention below with reference to Fig. 1 and 2.
Fig. 1 shows drafting system commonly used 1, and the method according to this invention can be applied to wherein.For this purpose, drafting system 1 has: front roller is to 3 and have the rear roller of jaw line 5 to 4.Drafting system 1 can have other roller to 7.Drafting system 1 is used for drawn fiber composite 2.For this purpose, roller rotates with different speed or peripheral speed 3 and 4.Front roller to 3 and rear roller to the 4 so-called main drawing areas 8 that therefore constitute drafting system 1.Drawing-off also occurs in roller to (so-called preliminary draft) between 7 and 3.Usually, at front roller 3 places are had apron 20 such as the illustrated drafting system of Fig. 1, apron 20 is used to guide will drafted fibrous composite 2.Yet the existence of apron 20 is unessential for the present invention or is not absolute demand.During steady operation, fibrous composite 2 operation by roller to 7 (if present), and especially by roller to 3 and 4.In the case, fibrous composite 2 is drafted, and at rear roller drafting system 1 is left in 4 jaw line 5 places or its downstream.The fibrous composite great majority of drawing-off are handled (for example in spinning unit in the same way more afterwards; This respect is seen Fig. 4 subsequently).Then, if owing to any reason, take place to interrupt aborning or usually drafting system 1 must be devoted oneself to work again when middle, fibrous composite 2 must be directed into drafting system 1 again or correctly be located at least.Therefore the effect of particular importance is played in the position of fibrous composite termination 6.In the case no matter drafting system 1 whether have additional roller to 7 or even also have other roller right, all be unessential to the present invention.Normally such: if generation interruption aborning, the roller of drafting system 1 is to stopping in order, and fibrous composite 2 disconnects at jaw line 5 places thus.For this purpose, front roller stopped before rear roller is to 4 to 3.The result is that fibrous composite termination 6 just in time is positioned at the place ahead of jaw line 5.This respect is for example seen above-mentioned EP 137 57 09.
Devoted oneself to work once more when middle when drafting system 1 then, usually, at first, rear roller began to rotate before front roller itself restarts work to 3 to 4.Be preferably in rear roller to 4 work and front roller to the adequate time cycle is arranged between 3 the work, to guarantee: rear roller to 4 velocity of rotation curve in, be superimposed upon front roller to finishing before 3 motions by what acceleration produced.Yet, because fibrous composite termination 6 just in time is positioned at rear roller the place ahead to 4 jaw line 5, at front roller to 3 drawing-offs that fibrous composite 2 taken place after in devoting oneself to work immediately.Because after front roller was devoted oneself to work to 3, it still must accelerate to butt joint speed or operating rate, and the stack to desired butt joint velocity of rotation also takes place herein.The result is that the section that follows the fibrous composite 2 of 6 back, fibrous composite termination closely carries out drawing-off in the mode of fluctuation, therefore has undesirable quality fluctuation.If this of fibrous composite 2 " original sections " is used to produce joint, then this joint also has undesirable quality fluctuation certainly.
Also can most clearly see the generation of these quality fluctuations from Fig. 2.Especially Fig. 2 has shown that rear roller is to 4 velocity of rotation curve U
4(t) and front roller to 3 velocity of rotation curve U
3(t).At time point t=0 place, rear roller is devoted oneself to work to 4.For this purpose, described roller to 4 at time cycle t
H, 4In be accelerated, reach butt joint velocity of rotation U until rear roller to 4
A, 4(for example~5mm/msec).The acceleration of described roller is very high, because otherwise the length of selected yarn end 10 must be unacceptably.Therefore accelerate during several milliseconds, to take place.When reaching desired velocity of rotation, concerning under constant but very high acceleration situation, interrupting suddenly quickening, because physically, be impossible, so at specific time cycle t for roller
EV, 4Produced stack during this time.Same situation also correspondingly be applicable to front roller to 3 (at time cycle t
EV, 3Stack during this time).This stack continuity is depended on the right physical property of driven roller and is depended on their driver, closed loop controller and open-cycle controller how long with toning or dash down and have muchly.By using suitable closed loop controller and driver, but time cycle t
EVBe reduced to minimum.Yet because the right high acceleration of roller, it can not be avoided fully.
Therefore, when drafting system is devoted oneself to work when middle, because the result of the described effect in the original sections of drafted fibrous composite, quality fluctuation does not take place, according to the present invention, only when two rollers when being through with by the corresponding stack that quicken to produce, the fibrous composite termination (that is to say, the most preceding tip of fibrous composite), be fed to the right jaw line of second roller.This time point is used t in Fig. 2
EVEMark; At this time point, two rollers have been to having reached constant butt joint velocity of rotation (releasing as the figure of institute among Fig. 2), perhaps their stacks that is through with at least.Then, according to the present invention, the drawing-off of fibrous composite is as far back as time point t
EVEBeginning, or in other words, the fibrous composite termination should enter the jaw line of next second pair of roller, therefore as far back as time point t
EVEDrafted.If except this coordinated drawing-off, the operation of drafting system also related to the butt joint effect to yarn end, then the time started of butt joint action is put t
KShould not be positioned at time point t
EVEBefore.So time point t
EVEIt is the earliest time point that begins to dock action.When having implemented the butt joint action, it has continued several milliseconds and (has seen time cycle t
AE, for example~8 millisecond), and end at time point t
EAlong with butt joint is moved at time point t
EFinish, drafting system can be operated with stable mode once more.The butt joint velocity of rotation U that the butt joint action is more constant
A, 4Or U
A, 3Following generation, and after docking, two rollers do not have toning ground in other words to can be synchronously and slower ground, accelerate to their work velocity of rotation U separately
B, 3And U
B, 4Yet fully conceivablely be: in fact this butt joint occurs under the work velocity of rotation, so docks velocity of rotation U
A, 3And U
A, 4Operating rate when having represented the drafting system steady operation.The synchronous quickening that reaches the roller that is different from the work velocity of rotation of docking velocity of rotation is represented by dotted lines in Fig. 2.
The useful improvement and the embodiment of many method according to this invention are arranged, and they can find in appended claims.
Explain the present invention and inventive concept or its enforcement below with reference to other each figure.Yet point out especially: the present invention and inventive concept are not limited in accompanying drawing and the example shown
Embodiment.
Fig. 3 is presented at wherein the drafting system of implementing the butt joint action, and the method according to this invention is used to make during it devotes oneself to work in the case.For implementing the butt joint action, opposite with the spinning direction of reality, the spinning unit 12 of yarn end 10 that exist of pull at first by being arranged in the drafting system downstream.Be conducted through rear roller equally 4 jaw line 5 and the yarn end 10 that is chopped to length-specific are arranged to be suitable for work.Devoted oneself to work when middle when drafting system, release as the figure of institute among Fig. 2, at first, rear roller begins to rotate to 4.Only front roller is just devoted oneself to work to 3 after this.Possible is, even two rollers are to side by side devoted oneself to work (this is corresponding to the possible modification of the method according to this invention).Yet, in drafting system is devoted oneself to work before, illustrated as institute, fibrous composite termination 6 is brought to apart from rear roller 4 jaw line 5 specified distance.This distance is so at least: when fibrous composite termination 6 arrived jaw line 5, in the velocity of rotation curve, two rollers had stopped by the stack of quickening generation to 3 and 4.When butt joint took place, as more previously described, the part of yarn end 10 overlapped mutually with the front section part of illustrated fibrous composite 2.This overlap joint section is spun in the spinning unit 12 of back forms actual joint.
Fig. 4 demonstration utilizes the method according to this invention to be dropped into the drafting system of work and the spinning unit 12 of its back.Fig. 4 shows drafting system 1 and the spinning unit 12 that is in steady-working state.Each element is corresponding with previous drawings and correspondingly given identical label.Rear roller is sent to spinning unit 12 to the fibrous composite 11 of drawing-off to 4 roller 16.Spinning unit 12 can spin the fibrous composite 11 of drawing-off according to various spinning methods.This figure figure has released the spinning unit 12 according to open-end spinning process (eddy current type open-end spinning process as is known) work.For this purpose, spinning unit 12 has minor air cell 14 and the spindle 15 that is contained in the minor air cell 14.Exactly, spindle 15 better is nonrotational spinning plate.Air-swirl utilizes nozzle to produce in minor air cell 14, and causes that the fiber of the fibrous composite 11 of drawing-off advances spinning at the mouth of spindle 15.Consequent yarn 13 is correspondingly admitted and is twined (not shown) on coiler device.As inferring from figure, drafting system 1 also has roller to 7, and it and roller constitute preliminary draft district 9 to 3.Also should point out once more: the method for operations according to the instant invention drafting system is not limited to the specific spinning method of all method for open-end rotor spinning as shown here, or the other roller that is not limited to existence is to 7.
Fig. 5 shows that it operates drafting system 1 by the method according to this invention according to controller 19 of the present invention.For this purpose, rear roller has special driver 18 to 4, and front roller has driver 17 equally to 3.As illustrated herein, if drafting system 1 also contains with roller the 3 other rollers that constitute the preliminary draft districts 7, then roller also can drive (or having additional special purpose driver) to 3 driver 17 by roller to 7.When drafting system is devoted oneself to work when middle, controller 19 according to the present invention is corresponding to according to the inventive method control driver 17 and 18.Controller 19 can correspondingly be connected in other monitoring device and the control device of weaving loom (described as a whole weaving loom does not have figure to release).
How to be shut down in advance according to drafting system, the method according to this invention also can comprise: before in drafting system is devoted oneself to work, fibrous composite termination 6 is retracted to 4 jaw line 5 from rear roller.This for example also can utilize controller 19 and driver 17 automatically to carry out.This is particularly suitable for hand of no use and at the preset distance place fibrous composite termination 6 and rear roller is separated 4 jaw line 5.This is to wish that especially wherein drafting system is at first shut down in the method for full-automatic butt joint and device, makes fibrous composite 2 be disconnected 4 jaw line 5 places at rear roller.Exactly, in the case, obtained the fibrous composite termination 6 that limits clearly, it just must be positioned properly before drafting system is devoted oneself to work once more.
The present invention is not limited to possibility and the embodiment that mentions especially.On the contrary, these modification are as being proposed to be used in the technical staff, so that as far as possible advantageously implement inventive concept.Therefore similarly reproduce inventive concept and, can easily derive out from described embodiment by other useful purposes and combination that the application protects.Some disclosed characteristic is described in the combination of this explanation, and has proposed requirement in the combination of each claim below.Yet what also can imagine is each feature in other combination in the application documents of feature in requirement this specification itself or idea of the present invention.Therefore the applicant is retained in the right that other combination is provided in any case especially in the application documents of idea of the present invention.
Label
1 drafting system, 2 fibrous composites
3 front rollers are right to 4 rear rollers
5 jaw lines, 6 fibrous composite terminations
7 rollers are to 8 main drawing areas
9 preliminary draft districts, 10 yarn end
11 fibrous composite 12 spinning units of drawing-off
13 yarns, 14 minor air cells
The right roller of 15 spindles, 16 rear rollers
17 preliminary draft drivers, 18 rear rollers are to driver
19 controllers, 20 aprons
U
4(t) rear roller is to the bent U of 4 velocity of rotation
3(t) front roller is to 3 velocity of rotation song
The line line
U
A, 4Rear roller rotates fast U to 4 butt joint
A, 3Front roller rotates speed to 3 butt joint
The degree degree
t
S, 3Front roller is put t to 3 working time
H, 3Front roller reaches butt joint to 3 and rotates
Speed U
A, 3Week time of (acceleration)
Phase
t
H, 4Rear roller reaches butt joint to 4 and rotates t
EV, 3Front roller finishes by acceleration 3
Speed U
A, 4The stack time cycle that the time of (acceleration) produces
Cycle
t
EV, 4Rear roller finishes by acceleration t 4
KThe time point of butt joint action beginning
Produce the time cycle of stack
t
EThe time point t of butt joint release
AEThe time cycle of butt joint action
t
EVETwo rollers are to finishing the time U of stack
B, 4Rear roller rotates speed to 4 work
Between degree of putting
U
B, 3Front roller rotates speed to 3 work
Degree
Claims (13)
1. operation is used for the method for the drafting system (1) of drawn fiber composite (2), drafting system (1) comprises: front roller to (3) and rear roller with jaw line (5) to (4), and start drafting system (1) and the fibrous composite termination (6) of existence, it is characterized in that: before in drafting system (1) is devoted oneself to work, fibrous composite termination (6) is brought to apart from jaw line (5) the preset distance place of rear roller to (4), this preset distance better is up to 6mm, this distance is 0.1mm-5mm better, this preset distance especially better is 3mm or 4mm, and the action that is brought to a certain distance better is to implement by the fibrous composite termination (6) by cutting to length.
2. operation is used for the method for the drafting system (1) of drawn fiber composite (2), drafting system (1) comprises: front roller to (3) and rear roller with jaw line (5) to (4), and start drafting system (1) and the fibrous composite termination (6) of existence, it is characterized in that: when drafting system (1) is devoted oneself to work when middle, have only when produce by acceleration be superimposed upon front roller to the velocity of rotation curve of (3) in and when in the velocity of rotation curve of rear roller, stopping to (4), fibrous composite termination (6) just enter the jaw line (5) of rear roller to (4); When fibrous composite termination (6) entered rear roller to the jaw line (5) of (4), before and after roller better had constant velocity of rotation value to (3,4).
3. according to the method for claim 2, it is characterized in that: before in drafting system (1) is devoted oneself to work, fibrous composite termination (6) is also brought to apart from jaw line (5) the preset distance place of rear roller to (4), and this preset distance better is 0.1mm-5mm, is more preferably 3mm or 4mm.
4. operation is used for the method for the drafting system (1) of drawn fiber composite (2), drafting system (1) comprises: front roller to (3) and rear roller with jaw line (5) to (4), and start drafting system (1) and the fibrous composite termination (6) of existence, it is characterized in that: before in drafting system (1) is devoted oneself to work, fibrous composite termination (6) is brought to apart from jaw line (5) the preset distance place of rear roller to (4), this preset distance better is up to 6mm, this distance is 0.1mm-5mm better, this distance especially better is 3mm or 4mm, and the action that is brought to a certain distance better is to implement by the fibrous composite termination (6) by cutting to length.
5. according to one the method for operation drafting system (1) in each claim of front, it is characterized in that: drafting system (1) has at least one other roller to (7), in the case, before and after roller better is the main drawing area (8) that constitutes drafting system (1) to (3,4).
6. according to one the method for operation drafting system (1) in each claim of front, it is characterized in that: rear roller is right to the delivery roller that (4) constitute drafting systems (1).
7. according to one the method for operation drafting system (1) in each claim of front, it is characterized in that: when drafting system (1) by in being devoted oneself to work the time or afterwards, the section of the fibrous composite of drawing-off (2) is put up by yarn end (10), and for this purpose, being preferably yarn end (10) moves equally by the jaw line (5) of rear roller to (4).
8. according to one the method for operation drafting system (1) in each claim of front, it is characterized in that: drafting system (1) directly transmits the fibrous composite (11) of drawing-off to spinning unit (12), spinning unit (12) is fibrous composite (2,11) be spun in the yarn (13), and be preferably drafting system (1) and spinning unit (12) is the parts at the spinning station of weaving loom.
9. the method for operation drafting system (1) according to Claim 8, it is characterized in that: spinning unit (12) utilizes open-end spinning process fibrous composite (2,11) be spun in the yarn (13), and, for this purpose, be preferably spinning unit (12) and have minor air cell (14) and spindle (15).
10. according to one the method for operation drafting system (1) in each claim of front, it is characterized in that: when fibrous composite termination (6) enter rear roller to the jaw line (5) of (4), rear roller has the peripheral speed of 300m/min at least to the roller (16) of (4), or fibrous composite (11) is at least 300m/min just leaving the speed that has behind the jaw line (5) of rear roller to (4).
11. according to one the method for operation drafting system (1) in each claim of front, it is characterized in that: fibrous composite termination (6) are to enter the jaw line (5) of rear roller to (4) than the low roller velocity of rotation value of work velocity of rotation value, and enter rear roller afterwards to the jaw line (5) of (4) in fibrous composite termination (6), roller (3,4,16) synchronously accelerate work velocity of rotation to them.
12. be used for the controller (19) of one or more drafting system (1) of weaving loom, it is characterized in that: the controller (19) that is used for operating drafting system (1) or each drafting system is implemented the method according to each claim one of front.
13. have weaving loom according to one or more controller (19) of claim 12.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
EP04002942A EP1564317A1 (en) | 2004-02-10 | 2004-02-10 | Method for obtaining a pieced yarn lenght having constant mass in a vortex Spinning procedure |
EP04002942.3 | 2004-02-10 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN1918331A true CN1918331A (en) | 2007-02-21 |
Family
ID=34684656
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNA2005800045919A Pending CN1918331A (en) | 2004-02-10 | 2005-01-28 | Method for obtaining a pieced yarn lenght having constant mass in a vortex spinning procedure |
Country Status (5)
Country | Link |
---|---|
US (1) | US20070234522A1 (en) |
EP (2) | EP1564317A1 (en) |
JP (1) | JP2007522355A (en) |
CN (1) | CN1918331A (en) |
WO (1) | WO2005075721A2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115210420A (en) * | 2019-12-18 | 2022-10-18 | 卓郎智能技术有限公司 | Method for arranging fibre slivers on spinning device at spinning position |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102017115939A1 (en) | 2017-07-14 | 2019-01-17 | Saurer Spinning Solutions Gmbh & Co. Kg | Method for operating an air-spinning device, yarn guide and air-jet spinning machine comprising such a yarn guide |
Family Cites Families (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB840455A (en) * | 1957-10-22 | 1960-07-06 | British Rayon Res Ass | Improvements in, or relating to the reduction of torsional oscillation in rollers |
DE3413894A1 (en) * | 1983-04-15 | 1984-10-25 | Kabushiki Kaisha Toyoda Jidoshokki Seisakusho, Kariya, Aichi | METHOD FOR MAKING A YARN |
IL90789A0 (en) * | 1988-08-05 | 1990-01-18 | Rieter Ag Maschf | Textile machine with drawframes |
KR100296977B1 (en) * | 1996-01-30 | 2001-11-22 | 무라타 기카이 가부시키가이샤 | Fishing method of spinning machine |
TW341605B (en) * | 1996-05-16 | 1998-10-01 | Murada Kikai Kk | Piecing method for a spinning machine |
JP2002155435A (en) * | 2000-11-15 | 2002-05-31 | Murata Mach Ltd | Piecing method and apparatus therefor in spinning machine |
EP1219737B2 (en) * | 2000-12-22 | 2012-01-18 | Maschinenfabrik Rieter Ag | Procedure for piecing up or joining a yarn created in a spinning station, said spinning station being equiped to carry out the procedure |
EP1375709B1 (en) * | 2002-06-21 | 2014-08-06 | Maschinenfabrik Rieter Ag | Piecing method for, or piecing of, spinning stations in Air vortex spinning machines |
-
2004
- 2004-02-10 EP EP04002942A patent/EP1564317A1/en not_active Withdrawn
-
2005
- 2005-01-28 US US10/587,916 patent/US20070234522A1/en not_active Abandoned
- 2005-01-28 JP JP2006551704A patent/JP2007522355A/en not_active Withdrawn
- 2005-01-28 WO PCT/CH2005/000045 patent/WO2005075721A2/en active Application Filing
- 2005-01-28 EP EP05700340A patent/EP1713963A2/en not_active Withdrawn
- 2005-01-28 CN CNA2005800045919A patent/CN1918331A/en active Pending
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115210420A (en) * | 2019-12-18 | 2022-10-18 | 卓郎智能技术有限公司 | Method for arranging fibre slivers on spinning device at spinning position |
CN115210420B (en) * | 2019-12-18 | 2024-08-27 | 卓郎智能技术有限公司 | Method for arranging fiber slivers on spinning device of spinning position |
Also Published As
Publication number | Publication date |
---|---|
JP2007522355A (en) | 2007-08-09 |
WO2005075721A2 (en) | 2005-08-18 |
EP1564317A1 (en) | 2005-08-17 |
EP1713963A2 (en) | 2006-10-25 |
WO2005075721A3 (en) | 2005-12-22 |
US20070234522A1 (en) | 2007-10-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101333704B (en) | Device for fibre finishing or fibre selection of fibre bundles containing textile fibres | |
US7946000B2 (en) | Apparatus for the fibre-sorting or fibre-selection of a fibre bundle comprising textile fibres, especially for combing | |
CN101078140B (en) | Method and device for producing single yarn on operation unit of rotor spinning machine | |
US6691501B2 (en) | Method of piecing up a yarn formed on a spinning position, or for starting the spinning process, and a spinning position equipped for implementing the method | |
CN100379911C (en) | Joint of spinning of spinning position of pneumatic spinning machine or starting method | |
CN101548037A (en) | Device and method for supplying flames to ring spinning machines | |
CN101044275A (en) | Knitting machine, yarn processing method of knitting machine, yarn processing control device of knitting machine and program thereof | |
ITMI950245A1 (en) | PROCEDURE AND DEVICE FOR CONNECTING AN OPEN END SPINNING DEVICE | |
US7464530B2 (en) | Process for preparing a piecing operation in an air jet spinning arrangement | |
US7941900B2 (en) | Apparatus for the fibre-sorting or fibre-selection of a fibre bundle comprising textile fibres, especially for combing | |
US10570534B2 (en) | Method for the resumption of the spinning process on an air-jet spinning machine, and an air-jet spinning machine for performing the method | |
CN1918331A (en) | Method for obtaining a pieced yarn lenght having constant mass in a vortex spinning procedure | |
CS9000652A2 (en) | Method and device for spinning mechanism spinning-in for break spinning | |
CN101223305B (en) | Method for operating an open-end spinning device | |
KR101957731B1 (en) | Textile machine having a drafting unit and two fibre-material feeds | |
US9771671B2 (en) | Double-folding drafting unit | |
CN116601346A (en) | Combing machine and method for operating a combing machine | |
CN115803485A (en) | Method for operating a combing machine for textile preparation and combing machine | |
EP3178974B1 (en) | Method for preparing a workstation for the resumption of the spinning process on an air-jet spinning machine and an air-jet spinning machine for performing the method | |
CN110359138A (en) | The wiring of rotor spinning equipment for rotor spinning machine is for yarn method and rotor spinning machine | |
WO2001055490A2 (en) | Method for open-end rotor spinning | |
CN113755976B (en) | Yarn splicing method for open-end rotor spinning machine and open-end rotor spinning machine | |
CN1670276A (en) | Method and device for preparing a installation course on a air jetting and spinning equipment | |
CN1752311A (en) | Method and device for preparing lengthening process on jet spinning device | |
US20070151224A1 (en) | Method for producing an effect yarn on an open-end rotor spinning machine, and corresponding effect yarn |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||