CN1851490A - Method for realizing single-end fault range finding by utilizing long-line equation - Google Patents
Method for realizing single-end fault range finding by utilizing long-line equation Download PDFInfo
- Publication number
- CN1851490A CN1851490A CN 200610083818 CN200610083818A CN1851490A CN 1851490 A CN1851490 A CN 1851490A CN 200610083818 CN200610083818 CN 200610083818 CN 200610083818 A CN200610083818 A CN 200610083818A CN 1851490 A CN1851490 A CN 1851490A
- Authority
- CN
- China
- Prior art keywords
- reference point
- impedance
- installation place
- distance
- trouble spot
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Emergency Protection Circuit Devices (AREA)
Abstract
The present invention discloses fault range measuring method through single end voltage and current. Said invention first utilizes the end voltage and current to calculate the impedance, if the result is positive, it meaning the protective calculated impedance being greater than the impedance from installation place to reference point, using formula to calculate the real distance, if the result is negative, it meaning the trouble point being the middle place, the reference point should be less than 400k, said method is not influence by circuit distribution capacitance.
Description
Technical field
The present invention relates to field of power, relate more specifically to relay protection and utilize single-ended amount to realize the new method of one-end fault ranging.
Background technology
The ultra-high-tension power transmission line transmission distance is longer, the terrain environment numerous and complicated of road warp, and fault takes place inevitable substantially.When transmission line of electricity breaks down, need find out fault rapidly and in time get rid of or find as early as possible and handled, because directly having influence on, the length of troubleshooting time send electricity to ensure and the safe operation of system.The eliminating time is long more, and the loss that power failure is caused is big more, and is also big more to the impact of total system stable operation.Therefore, get rid of as early as possible or the processing transmission line malfunction, not only reliably power supply is most important with assurance to timely reparation circuit, and the safety and stability and the economical operation of electric system all had crucial meaning.The prerequisite of eliminating or handling failure is to find the definite position of trouble spot.Ultra-high-tension power transmission line geographical environment complexity along the line is crossed rugged mountain forest sometimes, crosses over the network of rivers, river sometimes.And a lot of accident vestiges artificial or transient fault often disappear after fault, can't reappear failure condition.Localization of fault solution just accurately, it has remarkable social benefit and economic benefit.
At present; the electric pressure of China just develops to 1000kV from 500kV; and along with the raising of electric pressure and the increase of line length; cause the increase of capacitance current and the existence of middle shunt reactor, the method for in the past utilizing single-ended amount to carry out localization of fault more and more is difficult to measure accurately the distance of trouble spot apart from the protection installation place.Traditional way mainly contains following way:
Impedance method: the voltage that measures during according to fault, the magnitude of current calculate the impedance of fault loop.Because path length is directly proportional with impedance, therefore just can obtain by the distance of device installing place to the trouble spot.
Traveling wave method: utilize after the capable ripple of high frequency fault transient state current voltage or the fault position with indirect judgement trouble spots such as pulse frequency modulation radar systems.Traveling wave method requires the sampling rate height, at present, can't adopt in the route protection.
At present; the fault localization algorithm is mainly to adopt terminal voltage, electric current to calculate fault impedance in traditional route protection, or adopts vector method, or adopts and separate Differential Equation Algorithm; compare with the reactance of unit kilometer according to the line fault impedance again, the way of fault distance.Computing formula is as follows:
Be the zero sequence compensation coefficient.Z
The a certain single phase impedance that expression calculates,
Be single-phase voltage,
Be single-phase current.
To phase-to phase fault:
Z
The alternate impedance that expression calculates,
Be voltage between phases,
For biphase current poor.
In line length during less than 400km, not too large by the error that traditional computing impedance is directly found range, should satisfy the needs of most of circuits, and for UHV (ultra-high voltage), long transmission line, owing to will increase the natural power of circuit transmission, therefore, need reduce the reactance of circuit, but increased the distributed capacitance of circuit simultaneously, can see by analyzing, on the long line of extra-high voltage, the electric current of the capacitance current of circuit and circuit transmission natural power is compared and can be reached more than 76%, and under the situation of so big capacitance current, must be to terminal voltage, the end electric current is a foundation, the error that with the lumped parameter is the impedance computation fault distance of Model Calculation can be increasing, far can not satisfy the requirement of extra-high voltage long transmission line, and along with the increase of line length, for the capacitance current of compensated line, might increase shunt reactor in the line, this situation is bigger to the error effect that traditional algorithm produces.By following formula (1) as can be known, the impedance that is directly measured by protection is not directly proportional with Route Length, and along with the increase of line length, error is increasing.The present invention is directed to the calculating of fault localization in present extra-high voltage, the long transmission line urgent need solution protection; proposed a kind of new algorithm, this algorithm can solve one-end fault impedance that data are surveyed preferably with the increase of line length and the error that raising brought of electric pressure.Emulation shows, in line length during less than 400km, directly utilize following formula (1) counter push away the fault distance error of surveying also smaller, if suitably select reference point, the error of calculation of fault localization also was greatly improved than originally.
Summary of the invention
For the extra-high voltage long transmission line, because the influence of line distribution capacitance electric current can not be ignored, therefore, traditional is foundation with the lumped parameter, relies on single-ended amount to carry out the fault localization algorithm because error can be increasing, can not use.The result that the present invention at first utilizes terminal voltage, end electric current impedance of calculating and the impedance of protecting the installation place to reference point to compare, if the result is for just, the impedance that the expression protection is calculated is greater than the impedance of protection installation place to reference point, therefore, at first utilize long-line equation that terminal voltage, end electric current are converted reference point, if shunt reactor is arranged, then need cut the electric current of shunt reactor, utilize the traditional algorithm computing impedance in reference point again, utilize the counter distance of releasing reference point to the trouble spot of following formula (1); Last again with the protection installation place to reference point apart from addition, draw the distance of real protection installation place to trouble spot; If the result is for negative; the expression fault is protecting the installation place to reference point; and the selection of reference point can not be greater than 400km; directly utilize counter the pushing away also of following formula (1) can obtain fault distance; because this formula has been considered distributed capacitance; therefore, this location algorithm is not subjected to the influence of line distribution capacitance.
According to the present invention, provide a kind of long-line equation that in the ultra-high-tension power transmission line of electric system, utilizes to calculate the new method that realizes one-end fault ranging, this method comprises the steps:
Line protective devices obtain the current/voltage instantaneous value to the current-voltage waveform sampling of mutual inductor; Obtain the phasor form of each electric parameters by fourier algorithm; Calculate the impedance Z of protection installation place to trouble spot
Mf'; Select reference point k, calculate the impedance Z of protection installation place to reference point k
Mk
If place computing impedance Z is installed in protection
Mf' greater than the impedance Z of protection installation place to reference point
Mk, then utilize long-line equation will protect installation place voltage
Electric current
Calculate reference point voltage
Electric current
Electric current with reference point k
Deduct the electric current of shunt reactor
After obtain
Utilize again
The algorithm computation reference point k of computing impedance is to the impedance Z of trouble spot
Kf, utilize Z
KfCalculate reference point to the trouble spot apart from l
Kf
According to an aspect of the present invention, wherein utilize following formula to calculate the distance of trouble spot:
Z=Z
c1th(γ
1l) (1)
If Z
Mf' less than Z
Mk, then directly by Z
Mf' calculate and protect the distance of installation place far from the trouble spot;
In the formula: Z is the impedance of calculating by lumped parameter for protection, Z
C1Be the positive sequence wave impedance of circuit, γ
1Be the positive sequence propagation coefficient of circuit, l is the protection distance of installation place to trouble spot or the reference point distance to the trouble spot, th (γ
1L) be hyperbolic tangent function;
If Z
Mf' less than Z
Mk, Z is Z
Mf', then directly by Z
Mf' calculate and protect the distance of installation place far from the trouble spot;
If Z
Mf' greater than Z
Mk, Z is for to convert the impedance Z that reference point is calculated by the phasor form
Kf, can calculate reference point to the trouble spot apart from l
Kf, with the l that calculates
KfWith the protection installation place to reference point apart from l
MkAddition obtains by protection the fault distance that the place is surveyed being installed.
According to another aspect of the present invention, wherein when judging Z
Mf' greater than Z
MkThe time, then following formula is as converting formula to reference point with terminal voltage, electric current by phasor, and formula is as follows:
In the formula:
By protection installation place (m end) the vector of survey voltage, electric current,
Be voltage, the electric current of reference point k, γ is the propagation constant of circuit, Z
cBe the wave impedance of circuit, l is that m holds to the distance of reference point k, ch (), and sh () is respectively cosh and hyperbolic sine function; This formula is set up on modulus, i.e. Z
Mf' greater than Z
MkBe with reference to the property condition, otherwise, fault distance directly calculated.
In the present invention, utilize formula (1) to separate atanh function call fault distance or reference point distance to the trouble spot.
According to another aspect of the present invention, wherein the selection of reference point is not more than 400 meters.
According to another aspect again of the present invention, wherein if Z
Mf' greater than Z
Mk, the last actual impedance Z in protection installation place to trouble spot
Mf=Z
Mk+ Z
Kf
Description of drawings
Accompanying drawing 1 is for being provided with the impedance relay of reference point k;
Accompanying drawing 2 is realized the process flow diagram of fault localization for utilizing long-line equation.
Specific embodiments
The present invention relates to the method for relay protection fault localization in the field of power.A kind of way of carrying out fault localization by single ended voltage, electric current is disclosed.If when in the high-tension line shunt reactor being arranged; the installation place that can establish shunt reactor is that a reference point k is (as Fig. 1; with the m end is example; n end computing method are identical); compare with of the impedance of protection installation place by protection being installed the impedance of surveying in the place to reference point k; if institute's impedance of surveying to the impedance of reference point k, then utilizes long-line equation will protect installation place survey voltage greater than the protection installation place
Electric current
Convert to the voltage of reference point k in the mode of phasor calculation
Electric current
, with electric current
Deduct the electric current on the shunt reactor
Utilize
Recomputate impedance again; The impedance that calculated this moment is the impedance Z of reference point k to trouble spot f
Kf, pass through Z
KfBy the counter distance of releasing reference point and trouble spot of long-line equation; at last; with the protection installation place to reference point k apart from addition; draw real method by protection installation place to trouble spot distance; if institute's impedance of surveying less than the protection installation place to the impedance of reference point k, the then direct distance of protecting installation place to trouble spot that calculates by long-line equation.This method comprises the steps: that line protective devices are sampled to voltage, the current waveform of mutual inductor and obtains voltage, current instantaneous value; Obtain the phasor form of each electric parameters by fourier algorithm; Calculate the impedance Z of protection installation place by the method for separating computing impedances such as the differential equation or vector method
Mf'; At first judge the impedance Z of being calculated
Mf' whether greater than the impedance Z of protection installation place to reference point
Mk, if greater than, then utilize long-line equation will protect the voltage of surveying
Electric current
Mode with phasor calculation calculates reference point, utilizes the method computing impedance Z that separates computing impedances such as the differential equation or vector method more again
Kf, utilize Z
KfRelease reference point apart from the trouble spot distance by long-line equation, last, with the protection installation place to reference point apart from addition, must protect and the place is installed surveys fault distance, otherwise, directly by Z
Mf' extrapolate fault distance.This method is to having or not shunt reactor all to be suitable in the middle of the circuit, and the fault distance accuracy height of surveying is reduced to minimum with the distribution parameter capacitance current to the influence of one-end fault ranging, is very beneficial for the eliminating of field accident.
Symbol in below discussing uses as follows: current transformer (being called for short TA, as follows) and voltage transformer (VT) (being called for short TV, as follows).
At first protect according to the TA of protection installation place and the instantaneous value that TV records electric current and voltage.
Secondly obtaining the phasor form of each electric parameters by fourier algorithm, according to selecting the phase result, is foundation with the lumped parameter then, utilizes formula (3), and (4) calculate head end fault impedance Z
Mf', if Z
Mf' greater than Z
Mk, then utilize formula (2) that head end voltage, electric current are converted reference point, if shunt reactor is arranged, then need deduct the electric current of shunt reactor, utilize formula (3) again in reference point, (4) calculating reference point is to the impedance Z of trouble spot
Kf, the reference point of utilizing formula (1) again to the trouble spot apart from l
Kf,, last, the true fault distance l under
Mf=l
Kf+ l
Mk, otherwise, can directly utilize formula (1) by Z
Mf' directly calculate l
MfSimultaneously, if Z
Mf' greater than Z
Mk, can correspondingly draw the last actual impedance Z in protection installation place to trouble spot
Mf=Z
Mk+ Z
Kf
The logic of Xian Shiing with reference to the accompanying drawings, Z
Mf' greater than Z
MkBe the key that adopts long-line equation (2) to convert, otherwise, can not carry out conversion, directly utilize formula (1) to calculate fault localization.
During the actual zone internal fault, above range measurement principle is set up, and when protection opposite direction external area error, because protection can not moved, therefore, can not find range by mistake, and is therefore, also no problem.
For example; if protection is installed the impedance of place calculating greater than the distance of protection installation place to reference point; then utilize long-line equation will protect installation place survey voltage, electric current to convert reference point with the phasor form; after deducting the shunt reactor electric current; calculating reference point is to the impedance of trouble spot; solve the distance of trouble spot again to reference point, and with the protection installation place to reference point apart from addition, obtain real the fault distance that the place is seen being installed by protection.
If protection is installed the impedance of place calculating less than the distance of protection installation place to reference point, then directly extrapolate protection the fault distance that the place is seen is installed;
Be illustrated in figure 1 as the ultra-high-tension power transmission line that is provided with reference point k, for the circuit of shunt reactor is arranged between in the line, then reference point is chosen as the mounting points (k represents with symbol) of shunt reactor among the figure; If no shunt reactor, the then selection of reference point any (k represents with symbol), but protect the installation place can not surpass 400km to the length of reference point, described method is as follows:
If protection is installed the place and is surveyed impedance (with the m end is example, and n end computing method are identical) Z
Mf' greater than the impedance Z of protection installation place to reference point k
Mk, then utilize long-line equation will protect installation place voltage, electric current to convert to reference point k, utilize voltage, the electric current of reference point k to calculate the impedance Z of k point again to f
Kf, more by formula (1) extrapolate the k point to f order apart from l
Kf, last and protection installation place to reference point apart from l
MkAddition gets fault localization l
Mf,, then need deduct the electric current of shunt reactor earlier if shunt reactor is arranged
Computing impedance Z again
Kf, calculate l again
Mf
If protection is installed the place and is surveyed impedance (with the m end is example, and n end computing method are identical) Z
Mf' less than the impedance Z of protection installation place to reference point k
Mk, directly by Z
Mf' calculating l
Mf
Claims (6)
1. one kind is utilized long-line equation to calculate the method that realizes one-end fault ranging in the ultra-high-tension power transmission line of electric system, and this method comprises the steps:
Line protective devices obtain the current/voltage instantaneous value to the current-voltage waveform sampling of mutual inductor;
Obtain the phasor form of each electric parameters by fourier algorithm;
The impedance Z of calculating protection installation place to trouble spot '
Mf
Select reference point k, calculate the impedance Z of protection installation place to reference point k
Mk
If place computing impedance Z ' is installed in protection
MfGreater than the impedance Z of protection installation place to reference point
Mk, then utilize long-line equation will protect installation place voltage
m, electric current
Calculate reference point voltage
k, electric current
Electric current with reference point k
Deduct the electric current of shunt reactor
After obtain
Utilize again
k,
The algorithm computation reference point k of computing impedance is to the impedance Z of trouble spot
Kf, utilize Z
KfCalculate reference point to the trouble spot apart from l
Kf
2. utilize following formula to calculate the distance of protection installation place to trouble spot according to the process of claim 1 wherein:
Z=Z
c1th(γ
1l)
If Z '
MfLess than Z
Mk, then directly by Z '
MfCalculate the distance of protection installation place far from the trouble spot;
In the formula: Z is the impedance of calculating by lumped parameter for protection, Z
C1Be the positive sequence wave impedance of circuit, γ
1Be the positive sequence propagation coefficient of circuit, l is the protection distance of installation place to trouble spot or the reference point distance to the trouble spot, th (γ
1L) be hyperbolic tangent function;
If Z '
MfLess than Z
Mk, Z is Z '
Mf, then directly by Z '
MfCalculate the distance of protection installation place far from the trouble spot;
If Z '
MfGreater than Z
Mk, Z is for to convert the impedance Z that reference point is calculated by the phasor form
Kf, can calculate reference point to the trouble spot apart from l
Kf, with the l that calculates
KfWith the protection installation place to reference point apart from l
MkAddition obtains by protection the fault distance that the place is surveyed being installed.
3. method as claimed in claim 1 is wherein when judging Z '
MfGreater than Z
MkThe time, then following formula is as converting formula to reference point with terminal voltage, electric current by phasor, and formula is as follows:
In the formula:
m,
By protection installation place (m end) the vector of survey voltage, electric current,
k,
Be voltage, the electric current of reference point k, γ is the propagation constant of circuit, Z
cBe the wave impedance of circuit, l is that m holds to the distance of reference point k, ch (), and sh () is respectively cosh and hyperbolic sine function; This formula is set up on modulus, i.e. Z '
MfGreater than Z
MkBe with reference to the property condition, otherwise, fault distance directly calculated.
4. as method as described in the claim 2: formula is separated atanh function call fault distance or the reference point distance to the trouble spot as described in it is characterized in that utilizing.
5. as the method for claim 1-4, wherein the selection of reference point is not more than 400 meters.
6. as the method for claim 1-4, wherein if Z '
Mf, greater than Z
Mk, the last actual impedance Z in protection installation place to trouble spot
Mf=Z
Mk+ Z
Kf
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB200610083818XA CN100458456C (en) | 2006-06-02 | 2006-06-02 | Method for realizing single-end fault range finding by utilizing long-line equation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB200610083818XA CN100458456C (en) | 2006-06-02 | 2006-06-02 | Method for realizing single-end fault range finding by utilizing long-line equation |
Publications (2)
Publication Number | Publication Date |
---|---|
CN1851490A true CN1851490A (en) | 2006-10-25 |
CN100458456C CN100458456C (en) | 2009-02-04 |
Family
ID=37132973
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNB200610083818XA Active CN100458456C (en) | 2006-06-02 | 2006-06-02 | Method for realizing single-end fault range finding by utilizing long-line equation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN100458456C (en) |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101325332B (en) * | 2008-07-30 | 2010-06-09 | 北京四方继保自动化股份有限公司 | Method for implementing element for measuring earthing distance without relevance to load current and ground resistance |
CN101727524A (en) * | 2009-12-24 | 2010-06-09 | 中国电力科学研究院 | Design method for two-way equivalent arc hyperbolic derivative controller of high-pressure magnetic control type paralleling reactor |
CN102023275A (en) * | 2010-09-27 | 2011-04-20 | 华北电力大学 | Circuit single-end ranging method based on phase aberration characteristic of positioning function |
CN102147443A (en) * | 2011-01-13 | 2011-08-10 | 国网电力科学研究院 | Single-end distance measuring method based on self-adaptive current |
CN103176032A (en) * | 2013-03-06 | 2013-06-26 | 福建省电力有限公司 | Voltage measuring method for single-phase ground fault point of extra-high-voltage alternating-current transmission line |
CN104204824A (en) * | 2011-11-28 | 2014-12-10 | 诺丁汉大学 | Fault location in power distribution systems |
CN105929305A (en) * | 2016-05-16 | 2016-09-07 | 山东大学 | Non-whole-course hybrid-voltage double-circuit fault segment recognition and precise range finding method |
CN106356822A (en) * | 2016-10-10 | 2017-01-25 | 许继集团有限公司 | Underreach combined type protection method and device for semi-wavelength power transmission line |
CN109946562A (en) * | 2017-12-20 | 2019-06-28 | 中国电力科学研究院有限公司 | A kind of electrical power distribution network fault location method and system |
WO2019166903A1 (en) * | 2018-02-28 | 2019-09-06 | Abb Schweiz Ag | Method and device for fault location in a two-terminal transmission system |
CN110470950A (en) * | 2019-08-16 | 2019-11-19 | 深圳供电局有限公司 | Fault positioning method for transmission line |
CN110470949A (en) * | 2019-08-16 | 2019-11-19 | 深圳供电局有限公司 | Fault positioning method for transmission line |
CN113608033A (en) * | 2021-07-22 | 2021-11-05 | 国网河南省电力公司电力科学研究院 | High-precision wide-range power distribution network capacitance current testing method |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110333428A (en) * | 2019-06-25 | 2019-10-15 | 许继集团有限公司 | A kind of mixed power transmission line fault distance-finding method, device and computer storage medium |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1103451C (en) * | 1997-12-04 | 2003-03-19 | 中国人民解放军第二炮兵工程学院技术开发中心 | High-voltage overhead line on-line failure distance finding method and instrument installation |
JP3532182B2 (en) * | 2001-11-27 | 2004-05-31 | 財団法人 関西電気保安協会 | Ground fault detection device for ungrounded electric circuit, ground fault protection relay using the same, and ground fault detection method |
CN1142443C (en) * | 2001-12-28 | 2004-03-17 | 清华大学 | High-accuracy failure wave-recording device and its transmission line combined failure distance-measuring method |
CN1297050C (en) * | 2003-06-11 | 2007-01-24 | 贺家李 | Power transmission line longitudinal linkage protective method |
CN1793995B (en) * | 2006-03-09 | 2010-11-17 | 保定浪拜迪电气股份有限公司 | Measuring method of power transmission line failure distance |
-
2006
- 2006-06-02 CN CNB200610083818XA patent/CN100458456C/en active Active
Cited By (20)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101325332B (en) * | 2008-07-30 | 2010-06-09 | 北京四方继保自动化股份有限公司 | Method for implementing element for measuring earthing distance without relevance to load current and ground resistance |
CN101727524A (en) * | 2009-12-24 | 2010-06-09 | 中国电力科学研究院 | Design method for two-way equivalent arc hyperbolic derivative controller of high-pressure magnetic control type paralleling reactor |
CN101727524B (en) * | 2009-12-24 | 2015-11-25 | 中国电力科学研究院 | The two-way equivalent arc anti-hyperbolic derivative controller method for designing of high-pressure magnetic formula shunt reactor |
CN102023275A (en) * | 2010-09-27 | 2011-04-20 | 华北电力大学 | Circuit single-end ranging method based on phase aberration characteristic of positioning function |
CN102147443A (en) * | 2011-01-13 | 2011-08-10 | 国网电力科学研究院 | Single-end distance measuring method based on self-adaptive current |
CN104204824A (en) * | 2011-11-28 | 2014-12-10 | 诺丁汉大学 | Fault location in power distribution systems |
US10352984B2 (en) | 2011-11-28 | 2019-07-16 | The University Of Nottingham | Fault location in power distribution systems |
CN103176032A (en) * | 2013-03-06 | 2013-06-26 | 福建省电力有限公司 | Voltage measuring method for single-phase ground fault point of extra-high-voltage alternating-current transmission line |
WO2014135089A1 (en) * | 2013-03-06 | 2014-09-12 | 国家电网公司 | Method for measuring voltage at single phase ground fault in ultrahigh voltage alternating current power transmission line |
CN103176032B (en) * | 2013-03-06 | 2015-07-08 | 福建省电力有限公司 | Voltage measuring method for single-phase ground fault point of extra-high-voltage alternating-current transmission line |
CN105929305B (en) * | 2016-05-16 | 2019-02-05 | 山东大学 | The non-whole mixed pressure double line down section identification of one kind and precision ranging method |
CN105929305A (en) * | 2016-05-16 | 2016-09-07 | 山东大学 | Non-whole-course hybrid-voltage double-circuit fault segment recognition and precise range finding method |
CN106356822A (en) * | 2016-10-10 | 2017-01-25 | 许继集团有限公司 | Underreach combined type protection method and device for semi-wavelength power transmission line |
CN106356822B (en) * | 2016-10-10 | 2019-02-05 | 许继集团有限公司 | A kind of deficient range combinations formula guard method of half-wave power transmission route and device |
CN109946562A (en) * | 2017-12-20 | 2019-06-28 | 中国电力科学研究院有限公司 | A kind of electrical power distribution network fault location method and system |
WO2019166903A1 (en) * | 2018-02-28 | 2019-09-06 | Abb Schweiz Ag | Method and device for fault location in a two-terminal transmission system |
CN110470950A (en) * | 2019-08-16 | 2019-11-19 | 深圳供电局有限公司 | Fault positioning method for transmission line |
CN110470949A (en) * | 2019-08-16 | 2019-11-19 | 深圳供电局有限公司 | Fault positioning method for transmission line |
CN113608033A (en) * | 2021-07-22 | 2021-11-05 | 国网河南省电力公司电力科学研究院 | High-precision wide-range power distribution network capacitance current testing method |
CN113608033B (en) * | 2021-07-22 | 2024-01-23 | 国网河南省电力公司电力科学研究院 | High-precision wide-range power distribution network capacitance current testing method |
Also Published As
Publication number | Publication date |
---|---|
CN100458456C (en) | 2009-02-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN1851490A (en) | Method for realizing single-end fault range finding by utilizing long-line equation | |
CN100580470C (en) | Phase amount and zero sequence amount combined realization powerline both-end distance measuring method | |
CN100526895C (en) | Distributing capacitance current and transition resistance influence resisting line one-end fault ranging method | |
CN101074979A (en) | Method for measuring power-transmission circuit double-ended distance by distributing parameter | |
CN103869221B (en) | Based on the double-circuit line singlephase earth fault distance measurement method of SV network samples | |
CN100588066C (en) | Method for realizing line differential protection based on long line equation | |
CN100386637C (en) | Fault line selection method for single-phase-to-ground fault in small ground current distribution network | |
CN101325330B (en) | Method for implementing earthing distance measurement element | |
CN102135571B (en) | Anti-interference measurement method for zero sequence impedance of super-high-voltage/ultrahigh-voltage multi-loop power transmission line | |
CN109901024A (en) | A kind of Fault Locating Method of aerial-cable hybrid line | |
CN107271845A (en) | A kind of online distance-finding method of protection fault information management system | |
CN104049180A (en) | Double-circuit line non-in-phase jumper wire earth fault single-end distance measurement method | |
CN102129014A (en) | Method for realizing line phase-to-phase fault single-end distance measurement by utilizing distribution parameter model | |
CN104062539B (en) | Single-ended distance measuring method for double-circuit line non-same-name phase crossover line ground fault | |
CN105116279A (en) | Method for accurately positioning single-phase earth fault of generator stator | |
CN104090210B (en) | The non-same famous prime minister's cross-line earth fault method of single end distance measurement of double-circuit line | |
CN1793995A (en) | Measuring method of power transmission line failure distance | |
CN104035005B (en) | The non-same famous prime minister's cross-line Earth design method of double-circuit line | |
CN104062552A (en) | Non-same-phase overline ground fault single-ended distance measurement method for double-circuit lines | |
CN105116294A (en) | Traveling wave polarity measure based power distribution network cable fault monitoring method | |
CN102096020B (en) | Relay protection malfunction distance measuring and calibrating method of electric power system | |
CN104090213A (en) | Double-circuit-line non-same-name phase overline ground fault positioning method | |
CN1588737A (en) | Same lever/parallel double loop high resistance earthing protecting method and device | |
CN103296654A (en) | Line single-phase earth fault relay protection method implemented by aid of distributed parameters | |
CN103809078B (en) | The single-phase permanent fault recognition methods of a kind of both-end band shunt reactor transmission line of electricity |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20171226 Address after: 100085 Beijing city on the base of the information industry on the street, No. four, No. 9, Haidian District Co-patentee after: Beijing Sifang Jibao Engineering Technology Co., Ltd. Patentee after: Beijing Sifang Jibao Automation Co., Ltd. Address before: 100085 Beijing city on the base of the information industry on the street, No. four, No. 9, Haidian District Patentee before: Beijing Sifang Jibao Automation Co., Ltd. |
|