CN115354673A - Hole forming method for anti-slide pile in red bed soft rock area and hoisting type manual auxiliary device - Google Patents
Hole forming method for anti-slide pile in red bed soft rock area and hoisting type manual auxiliary device Download PDFInfo
- Publication number
- CN115354673A CN115354673A CN202210996219.6A CN202210996219A CN115354673A CN 115354673 A CN115354673 A CN 115354673A CN 202210996219 A CN202210996219 A CN 202210996219A CN 115354673 A CN115354673 A CN 115354673A
- Authority
- CN
- China
- Prior art keywords
- pile
- hole
- drilling
- plate
- bottom plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B15/00—Supports for the drilling machine, e.g. derricks or masts
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A10/00—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
- Y02A10/23—Dune restoration or creation; Cliff stabilisation
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Environmental & Geological Engineering (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Paleontology (AREA)
- Geology (AREA)
- Mechanical Engineering (AREA)
- Physics & Mathematics (AREA)
- Fluid Mechanics (AREA)
- Geochemistry & Mineralogy (AREA)
- Earth Drilling (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
技术领域technical field
本申请涉及抗滑桩施工技术领域,具体而言,涉及红层软岩区抗滑桩成孔方法及吊装式人工辅助装置。The application relates to the technical field of anti-sliding pile construction, in particular, to a method for forming holes for anti-sliding piles in soft rock areas of red beds and a hoisting artificial auxiliary device.
背景技术Background technique
红层主要是指中生代以来即三叠系、侏罗系、白垩系和新生代古近系的湖相、河流相、河湖交替相或是山麓洪积相等陆相碎屑岩,多以夹层互层出现,从外表来看主要颜色为红色,而名山至天全一带地表水主要发育分布于红层地区,无大的厂矿,一般不受工业污染,水质良好,水化学类型简单,多属千重碳酸钙型水,其次为重碳酸钙钠型水及重碳酸钙镁型水,矿化度一般小于0.5mg/L,硬度10~18,PH值6.8~7.5。The red beds mainly refer to the lacustrine, fluvial, alternate river-lake facies or continental clastic rocks of the Piedmont alluvium since the Mesozoic, namely the Triassic, Jurassic, Cretaceous and Cenozoic Paleogene. Interlayers appear, and the main color is red from the outside, while the surface water from Mingshan to Tianquan is mainly developed and distributed in the red layer area, there are no large factories and mines, generally free from industrial pollution, the water quality is good, the water chemical type is simple, and most of them belong to Calcium bicarbonate type water, followed by calcium bicarbonate sodium type water and calcium magnesium carbonate type water, the salinity is generally less than 0.5mg/L, the hardness is 10-18, and the pH value is 6.8-7.5.
针对该地区的抗滑桩,其桩孔在开挖前,先按照设计标高上调1m进行场地平整,场地确认交接后,进行抗滑桩施工,基本采用旋挖钻机辅以人工剔凿成孔,成孔后经检查孔径、孔深、垂直度等指标合格后立即安装钢筋笼并灌注混凝土,而基于红层软岩区的抗滑桩,尤其针对方形的抗滑桩,使用人工辅助越少,其安全性越高,但是旋挖钻机挖掘时,人工辅助剔凿孔壁凸出部分并清理孔底成渣,保证孔底无沉渣的步骤不可或缺,现有成孔过程方式如图1至图2的方案,除旋挖钻机进行挖掘后,剩余人工剔凿部分依然较多,进而容易导致成孔经济性差,综合钻进效率低。For the anti-slide piles in this area, before the pile holes are excavated, the site shall be leveled up by 1m according to the design elevation. After the site is confirmed and handed over, the construction of the anti-slide piles shall be carried out, basically using rotary drilling rigs supplemented by manual chiseling to form holes. After the holes are inspected, the diameter, hole depth, verticality and other indicators are qualified, and the reinforcement cage is installed immediately and the concrete is poured. However, the anti-slide piles based on the red bed soft rock area, especially for the square anti-slide piles, require less manual assistance. Its safety is higher, but when the rotary drilling rig excavates, the protruding part of the hole wall is manually assisted and the slag at the bottom of the hole is cleaned to ensure that there is no sediment at the bottom of the hole. The existing hole forming process is shown in Figure 1 to In the scheme shown in Figure 2, after the rotary drilling rig is excavated, there are still many remaining manual chiseling parts, which will easily lead to poor economical hole formation and low comprehensive drilling efficiency.
发明内容Contents of the invention
本申请旨在至少解决现有技术中存在的技术问题之一。为此,本申请提出红层软岩区抗滑桩成孔方法及吊装式人工辅助装置,所述红层软岩区抗滑桩成孔方法具有的尺寸保障性好、中间2.1米钻孔钻进效率较高、剩余人工剔凿部分少的效果。This application aims to solve at least one of the technical problems existing in the prior art. For this reason, the application proposes a method for forming anti-slide piles in soft rock areas of red beds and a hoisting type artificial auxiliary device. The efficiency is higher and the remaining manual chisel parts are less.
第一方面,根据本申请实施例的红层软岩区抗滑桩成孔方法,包括:In the first aspect, according to the embodiment of the present application, the anti-sliding pile hole-forming method in the soft rock area of red beds includes:
桩位测量:钻孔桩施工前采用全站仪进行精确测量,并与路基联测,形成闭合三角网后,精确测定钻孔桩位置,并测定、埋设护桩,以此保证位置的准确;Pile position measurement: Before the construction of the bored piles, the total station is used for accurate measurement, and combined with the subgrade to measure, after forming a closed triangular network, the position of the bored piles is accurately measured, and the guard piles are measured and buried to ensure the accuracy of the position;
锁口、孔口护壁制作:为了安全及孔位锁定,钻孔前先根据测量定位进行锁口施工,确保孔口稳固,孔口下1米范围做好护壁,1米以下视地质情况施作护壁;Fabrication of lock mouth and orifice retaining wall: For safety and hole position locking, the lock opening construction should be carried out according to the measurement and positioning before drilling to ensure the stability of the orifice. The retaining wall should be prepared within 1 meter below the orifice, and the construction should be carried out according to the geological conditions below 1 meter. retaining wall;
钻机安装:钻机就位后,调平机座,确保钻头中心与孔位中心在一条铅垂线上,与孔位中心的偏差在规范允许范围之内,调整钻架的垂直度使其满足要求,钻架、钻头等部位连接牢固、运转良好;Drilling rig installation: After the drilling rig is in place, level the machine base to ensure that the center of the drill bit and the center of the hole are on a vertical line, and the deviation from the center of the hole is within the allowable range of the specification, and adjust the verticality of the drill stand to meet the requirements , Drill frame, drill bit and other parts are firmly connected and in good operation;
钻架安装:钻架安装稳定,钻机定位时采用细线挂重锤检测,保证钻头中心与孔位中心偏差不大于2厘米;Drill stand installation: The drill stand is installed stably, and the drilling rig is positioned with a thin wire hanging weight for detection to ensure that the deviation between the center of the drill bit and the center of the hole is not greater than 2 cm;
旋挖施工:开钻后,将钻机调平对准钻孔,把钻头吊起徐徐放入孔内,对正桩位,开始钻进。在钻进过程中,严格控制钻头提高不超过2米,钻进时,需要进行检孔,防止出现偏孔,钻孔作业对钻机、钻头、钢丝绳及卡具进行检查;Rotary excavation construction: After drilling, level the drilling rig and align it with the drilling hole, lift the drill bit and slowly put it into the hole, align the pile position, and start drilling. During the drilling process, strictly control the raising of the drill bit to no more than 2 meters. When drilling, it is necessary to check the hole to prevent the deviation of the hole. During the drilling operation, check the drill rig, drill bit, wire rope and fixture;
旋挖成孔:先在四周用1.2米钻头成4个孔,再在中间用2.1米钻头成1个孔。局部外扩5厘米钻进,保障尺寸性,剩余部分人工剔凿;Rotary digging to form holes: first use a 1.2-meter drill to form 4 holes around, and then use a 2.1-meter drill to form 1 hole in the middle. Partially expanded 5 cm to ensure the size, and the remaining part is manually chiseled;
岩层取样:当钻到岩层时,分层取渣样,在渣样袋中注明标高、尺寸、桩号和日期;Sampling of rock formations: when drilling into rock formations, take slag samples layer by layer, and mark the elevation, size, stake number and date in the slag sample bag;
人工辅助:机械成孔后,安装吊装式人工辅助装置,借助吊篮达到清理位置,打开相应需要剔凿的位置,使用风镐自上而下剔凿孔壁凸出部分并清理孔底成渣,保证孔底无沉渣;Manual assistance: After the mechanical hole is formed, install a hoisting artificial auxiliary device, use the hanging basket to reach the cleaning position, open the corresponding position that needs to be chiseled, and use a pneumatic pick to remove the protruding part of the chiseled hole wall from top to bottom and clean the slag at the bottom of the hole , to ensure that there is no sediment at the bottom of the hole;
成孔验收:采用检孔器对孔深、尺寸、孔位、垂直度进行检查;Hole acceptance: use a hole detector to check the hole depth, size, hole position, and verticality;
吊装钢筋笼:每根桩钢筋笼自重重达10顿,钢筋笼采用孔外单根钢筋连接好,人工配合吊车单机根吊入孔内,人工下井逐一安装而成;Hoisting reinforcement cage: Each pile reinforcement cage weighs 10 tons. The reinforcement cage is connected with a single reinforcement outside the hole, and is manually hoisted into the hole with a single root of a crane, and is manually installed one by one in the well;
桩基声测管的安装:每根桩共布置6根声测管声测管,检查管壁是否有破损,接头处是否合格,确定声测管的分段长度,声测管的长度需要根据钢筋笼的分段长度进行确定,不能过长也不能过短,否则无法对上下两节声测管进行连接;Installation of acoustic tubes for pile foundation: a total of 6 acoustic tubes are arranged for each pile, check whether the tube wall is damaged, whether the joints are qualified, determine the section length of the acoustic tube, and the length of the acoustic tube needs to be determined according to The segmental length of the reinforcement cage shall be determined, neither too long nor too short, otherwise the upper and lower sections of the acoustic tube cannot be connected;
灌注混凝土:在混凝土浇筑前应先抽排孔内积水清除泥浆,桩身混凝土比桩顶设计标高应超灌30至50厘米,确保截除桩头后桩身混凝土质量;Concrete pouring: Before pouring concrete, the accumulated water in the hole should be drained to remove the mud, and the pile body concrete should be 30 to 50 cm higher than the design elevation of the pile top, so as to ensure the quality of the pile body concrete after the pile head is cut off;
处理桩头:桩头采用人工风镐的方式剔除,剔至桩顶标高或桩顶标高以下的均匀混凝土骨料处,针对低于设计标高的桩头应当采取高标号混凝土接桩。Handling of pile heads: The pile heads are removed by means of manual air picks, and removed to the uniform concrete aggregate at or below the pile top elevation, and high-grade concrete piles should be used for pile heads lower than the design elevation.
根据本申请的一些实施例,所述钻机的机座用枕木垫实塞紧,保证固定平稳。According to some embodiments of the present application, the machine base of the drilling rig is tightly plugged with sleepers to ensure stable fixation.
根据本申请的一些实施例,所述声测管出厂长度为12米、9米和3米,根据钢筋笼长度合理搭配声测管型号。According to some embodiments of the present application, the ex-factory lengths of the acoustic tubes are 12 meters, 9 meters and 3 meters, and the models of the acoustic tubes are reasonably matched according to the length of the steel cage.
根据本申请的一些实施例,所述混凝土浇筑采用天泵浇筑,震动棒振动的方式进行。According to some embodiments of the present application, the concrete pouring is carried out by means of sky pump pouring and vibrating rods vibrating.
第二方面,根据本申请实施例的吊装式人工辅助装置,红层软岩区抗滑桩成孔方法的人工辅助使用该吊装式人工辅助装置进行防护,包括:辅助架组件和吊篮组件。In the second aspect, according to the hoisting artificial auxiliary device of the embodiment of the present application, the artificial assistance of the anti-slide pile hole forming method in the red bed soft rock area is protected by the hoisting artificial auxiliary device, including: an auxiliary frame assembly and a hanging basket assembly.
所述辅助架组件包括支撑件、双层连接架、底板件、侧板件、分离式插销机构和吊绳件,所述支撑件固定连接于所述双层连接架四角的上下两侧,由所述支撑件和所述双层连接架组成基本框架,所述底板件转动连接于所述基本框架两端的所述双层连接架,所述侧板件分别转动连接于所述支撑件,同侧的所述侧板件之间通过门销锁定,所述分离式插销机构分别安装于所述双层连接架和所述底板件上,所述分离式插销机构能够将所述底板件上端固定于所述支撑件,所述分离式插销机构能够脱开所述底板件和所述支撑件的连接,所述吊绳件的两端分别挂接于所述底板件和所述支撑件,所述吊篮组件包括吊篮支架和吊篮,所述吊篮支架固定连接于所述基本框架顶端,所述吊篮上四角固定有牵引钢索,所述牵引钢索通过导向轮连接于提升机。The auxiliary frame assembly includes a support, a double-layer connecting frame, a bottom plate, a side plate, a separate latch mechanism and a hanging rope, and the support is fixedly connected to the upper and lower sides of the four corners of the double-layer connecting frame. The support member and the double-layer connecting frame form a basic frame, the bottom plate member is rotatably connected to the two-layer connecting frame at both ends of the basic frame, and the side plate members are respectively rotatably connected to the support member. The side panels on the side are locked by door pins, and the separate latch mechanism is respectively installed on the double-layer connecting frame and the bottom panel, and the separate latch mechanism can fix the upper end of the bottom panel For the supporting part, the separate latch mechanism can disengage the connection between the bottom part and the supporting part, and the two ends of the sling part are respectively hung on the bottom part and the supporting part, so The hanging basket assembly includes a hanging basket bracket and a hanging basket, the hanging basket bracket is fixedly connected to the top of the basic frame, and the four corners of the hanging basket are fixed with traction cables, and the traction cables are connected to the hoist through guide wheels .
根据本申请的一些实施例,所述支撑件包括主支撑杆和辅支撑杆,所述主支撑杆和所述辅支撑杆固定插接于所述双层连接架内外层的四角。According to some embodiments of the present application, the support member includes a main support rod and an auxiliary support rod, and the main support rod and the auxiliary support rod are fixedly inserted into the four corners of the inner and outer layers of the double-layer connecting frame.
根据本申请的一些实施例,所述双层连接架包括外层连接杆、外层固定套筒、内层固定套筒、内层连接杆、护板和挡板,所述外层固定套筒和所述外层连接杆相互固定连接成外层框架,所述内层固定套筒和所述内层连接杆相互固定连接成内层框架,所述外层固定套筒和所述内层固定套筒相互固定连接,所述护板固定连接于所述内层连接杆上下两侧,所述护板固定连接于所述挡板上侧,所述挡板能够挡住所述侧板件,所述侧板件通过所述门销锁定于所述挡板。According to some embodiments of the present application, the double-layer connecting frame includes an outer layer connecting rod, an outer layer fixing sleeve, an inner layer fixing sleeve, an inner layer connecting rod, a guard plate and a baffle plate, and the outer layer fixing sleeve and the outer layer connecting rods are fixedly connected to each other to form an outer layer frame, and the inner layer fixing sleeve and the inner layer connecting rods are fixedly connected to each other to form an inner layer frame, and the outer layer fixing sleeve and the inner layer are fixed The sleeves are fixedly connected to each other, the guard plate is fixedly connected to the upper and lower sides of the inner connecting rod, the guard plate is fixedly connected to the upper side of the baffle, and the baffle can block the side plate, so The side panels are locked to the baffle via the door pins.
根据本申请的一些实施例,所述吊绳件包括第一挂环、支撑钢索和防脱吊钩,所述第一挂环和所述防脱吊钩分别固定连接于所述支撑钢索两端,所述第一挂环套接于所述辅支撑杆,所述防脱吊钩挂接于所述底板件。According to some embodiments of the present application, the sling includes a first hanging ring, a supporting steel cable, and an anti-off hook, and the first hanging ring and the anti-off hook are respectively fixedly connected to the supporting steel cable At both ends, the first hanging ring is sleeved on the auxiliary support rod, and the anti-loosening hook is hooked on the bottom plate.
根据本申请的一些实施例,所述辅支撑杆上设置有第二挂环,所述第一挂环套接于所述第二挂环,所述底板件上固定连接有第三挂环,所述防脱吊钩挂接于所述第三挂环。According to some embodiments of the present application, the auxiliary support rod is provided with a second hanging ring, the first hanging ring is sleeved on the second hanging ring, and the bottom plate is fixedly connected with a third hanging ring, The anti-drop hook is hooked to the third hanging ring.
根据本申请的一些实施例,所述侧板件包括侧板,所述侧板开设有穿绳孔,所述防脱吊钩能够通过所述穿绳孔挂接于所述第三挂环。According to some embodiments of the present application, the side panel includes a side panel, and the side panel is provided with a rope-through hole, and the anti-off hook can be hooked to the third hanging ring through the rope-through hole.
根据本申请的一些实施例,所述底板件包括底板、导绳环和解锁绳,所述导绳环固定连接于所述底板底端的外壁,所述解锁绳上端固定连接于所述底板内侧壁,所述解锁绳穿过所述导绳环,所述底板上开设有过绳孔,所述分离式插销机构包括引导拔锁部、转动拔锁板和弹性插销锁,所述引导拔锁部设置于所述内层连接杆下侧的所述挡板外侧,所述引导拔锁部一侧穿过所述挡板后连接于所述解锁绳,所述转动拔锁板下端转动连接于所述底板内侧壁,所述弹性插销锁固定连接于所述底板外侧,所述弹性插销锁端部能够将所述底板锁紧于所述辅支撑杆,所述弹性插销锁一侧穿过所述底板,所述弹性插销锁穿过所述底板一侧滑动连接于所述转动拔锁板,所述支撑钢索上设置有拉紧环,所述吊篮上固定连接有拉板绳,所述拉板绳穿过上层的所述过绳孔后,所述拉板绳固定连接于下层所述支撑钢索上的所述拉紧环。According to some embodiments of the present application, the bottom plate includes a bottom plate, a rope guide ring and an unlocking rope, the rope guide ring is fixedly connected to the outer wall at the bottom end of the bottom plate, and the upper end of the unlocking rope is fixedly connected to the inner side wall of the bottom plate , the unlocking rope passes through the rope guide ring, and a rope hole is opened on the bottom plate, and the detachable latch mechanism includes a guide puller, a rotating lock plate and an elastic latch lock, and the guide puller It is arranged on the outer side of the baffle on the lower side of the inner layer connecting rod, one side of the guiding lock-pull part passes through the baffle and is connected to the unlocking rope, and the lower end of the rotating lock-pull plate is rotatably connected to the The inner side wall of the bottom plate, the elastic bolt lock is fixedly connected to the outer side of the bottom plate, the end of the elastic bolt lock can lock the bottom plate to the auxiliary support rod, and one side of the elastic bolt lock passes through the The bottom plate, the elastic bolt lock slides through one side of the bottom plate and is connected to the rotating lock plate, the supporting steel cable is provided with a tension ring, and the hanging basket is fixedly connected with a pull plate rope. After the stay rope passes through the rope hole of the upper layer, the stay rope is fixedly connected to the tension ring on the supporting steel cable of the lower layer.
根据本申请的一些实施例,所述引导拔锁部包括缓冲套筒、第一压缩弹簧、支撑耳板、连杆、拔锁杆和施力杆,所述缓冲套筒固定连接于所述挡板外侧,所述第一压缩弹簧设置于所述缓冲套筒内,所述支撑耳板固定连接于所述挡板外侧,所述连杆滑动连接于所述支撑耳板,所述连杆一端分别滑动插接于所述缓冲套筒内部,所述缓冲套筒端部能够挡住所述连杆插入所述缓冲套筒内的一端,所述连杆分别压紧于所述第一压缩弹簧两端,所述拔锁杆和所述施力杆固定连接于所述连杆一侧,所述拔锁杆能够带动所述转动拔锁板上端,所述解锁绳穿过所述导绳环后固定于所述施力杆。According to some embodiments of the present application, the guiding locking part includes a buffer sleeve, a first compression spring, a supporting ear plate, a connecting rod, a locking lever and a force applying rod, and the buffering sleeve is fixedly connected to the locking mechanism. outside the plate, the first compression spring is arranged in the buffer sleeve, the support lug is fixedly connected to the outside of the baffle, the connecting rod is slidably connected to the support lug, and one end of the connecting rod Slidingly inserted into the inside of the buffer sleeve, the end of the buffer sleeve can block the end of the connecting rod inserted into the buffer sleeve, and the connecting rod is respectively pressed against the two ends of the first compression spring. end, the locking lever and the force applying lever are fixedly connected to one side of the connecting rod, the locking lever can drive the upper end of the rotating locking plate, and the unlocking rope passes through the rope guide ring fixed to the force bar.
根据本申请的一些实施例,所述施力杆上固定连接有挂绳环,所述解锁绳穿过所述导绳环固定连接于所述挂绳环。According to some embodiments of the present application, a lanyard ring is fixedly connected to the force applying rod, and the unlocking rope passes through the guide rope ring and is fixedly connected to the lanyard ring.
根据本申请的一些实施例,所述转动拔锁板包括板体和转轴,所述转轴固定连接于所述底板内壁,所述板体下端转动连接于所述转轴,所述板体上开设有滑槽,所述弹性插销锁穿过所述底板一侧滑动连接于所述滑槽,所述拔锁杆能够带动所述板体上端。According to some embodiments of the present application, the rotating locking plate includes a plate body and a rotating shaft, the rotating shaft is fixedly connected to the inner wall of the bottom plate, the lower end of the plate body is rotatably connected to the rotating shaft, and the plate body is provided with The elastic bolt lock is slidably connected to the chute through one side of the bottom plate, and the locking lever can drive the upper end of the board body.
根据本申请的一些实施例,所述弹性插销锁包括锁套、滑动板、滑杆、限位板、第二压缩弹簧、锁舌和拨动杆,所述锁套和所述滑动板固定连接于所述板体外壁,所述滑杆滑动连接于所述滑动板,所述限位板固定连接于所述滑杆一端,所述第二压缩弹簧套接于所述滑杆,所述第二压缩弹簧两端分别压紧于所述限位板和所述滑动板,所述锁舌固定连接于所述限位板一侧,所述锁舌滑动插接于所述锁套,所述锁舌能够锁紧于所述辅支撑杆,所述锁舌能够锁紧于所述内层连接杆,所述拨动杆固定连接于所述滑杆远离所述限位板一端,所述拨动杆上设置有卡槽,所述拨动杆通过所述卡槽滑动连接于所述滑槽。According to some embodiments of the present application, the elastic bolt lock includes a lock sleeve, a sliding plate, a sliding rod, a limit plate, a second compression spring, a dead bolt and a toggle rod, and the lock sleeve is fixedly connected to the sliding plate On the outer wall of the board, the sliding rod is slidably connected to the sliding plate, the limiting plate is fixedly connected to one end of the sliding rod, the second compression spring is sleeved on the sliding rod, and the first Both ends of the two compression springs are respectively pressed against the limiting plate and the sliding plate, the locking bolt is fixedly connected to one side of the limiting plate, the locking tongue is slidably inserted into the lock sleeve, and The lock tongue can be locked to the auxiliary support rod, the lock tongue can be locked to the inner connecting rod, the toggle lever is fixedly connected to the end of the slide bar away from the limit plate, the toggle A slot is provided on the moving rod, and the shifting rod is slidably connected to the sliding groove through the slot.
本申请的有益效果是:上述成孔方法,通过局部外扩5厘米钻进,并配合人工辅助,因人工较机械整体成孔,便于控制挖掘尺寸,进而提高尺寸的保障性,中间部分采用2.1米钻孔钻进,以此提高钻孔钻进的效率,而且剩余部分少,需要人工剔凿部分少,降低劳动强度,成孔经济性好,安装有声测管用作检测通道及取代一部分钢筋截面,声测管还可作为桩底压浆的管道,声测管可作为事故桩缺陷冲洗与压浆处理的管道,这时需采取措施把需压浆的缺陷部位的管道打穿,并可通过声测管进行超声波透射法检测。The beneficial effects of the present application are: the above-mentioned method of forming a hole is drilled through a local expansion of 5 cm, and with manual assistance, because the artificial hole is formed more than the machine as a whole, it is convenient to control the excavation size, and then improve the security of the size. The middle part adopts 2.1 Drilling per meter to improve the efficiency of drilling, and there are few remaining parts, less parts need to be manually chiseled, labor intensity is reduced, and the hole is economical. The acoustic measuring tube is installed as a detection channel and replaces a part of the steel bar section. , the acoustic tube can also be used as a pipeline for grouting at the bottom of the pile, and the acoustic tube can be used as a pipeline for flushing and grouting treatment of accidental pile defects. The acoustic tube is tested by ultrasonic transmission method.
本申请的附加方面和优点将在下面的描述中部分给出,部分将从下面的描述中变得明显,或通过本申请的实践了解到。Additional aspects and advantages of the application will be set forth in part in the description which follows, and in part will be obvious from the description, or may be learned by practice of the application.
附图说明Description of drawings
为了更清楚地说明本申请实施例的技术方案,下面将对本申请实施例中所需要使用的附图作简单地介绍,应当理解,以下附图仅示出了本申请的某些实施例,因此不应被看作是对范围的限定,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他相关的附图。In order to more clearly illustrate the technical solutions of the embodiments of the present application, the accompanying drawings that need to be used in the embodiments of the present application will be briefly introduced below. It should be understood that the following drawings only show some embodiments of the present application, so It should not be regarded as a limitation on the scope, and those skilled in the art can also obtain other related drawings according to these drawings without creative work.
图1是第一种红层软岩区抗滑桩成孔方法的示意图;Fig. 1 is the schematic diagram of the anti-slide pile hole-forming method of the first kind of red bed soft rock area;
图2是第二种红层软岩区抗滑桩成孔方法的示意图;Fig. 2 is the schematic diagram of second kind of anti-slide pile hole-forming method in soft rock area of red beds;
图3是根据本申请实施例的红层软岩区抗滑桩成孔方法的示意图;Fig. 3 is the schematic diagram of the hole-forming method of the anti-slide pile in the soft rock region of the red bed according to the embodiment of the present application;
图4是根据本申请实施例的红层软岩区抗滑桩成孔方法的桩基声测管安装的示意图;Fig. 4 is the schematic diagram of the installation of the pile foundation acoustic tube of the anti-sliding pile hole-forming method in the red bed soft rock area according to the embodiment of the present application;
图5是根据本申请实施例的吊装式人工辅助装置的立体结构示意图;Fig. 5 is a three-dimensional structural schematic diagram of a hoisting artificial assistance device according to an embodiment of the present application;
图6是根据本申请实施例的吊装式人工辅助装置的局部立体结构示意图;Fig. 6 is a schematic diagram of a partial three-dimensional structure of a hoisting artificial assistance device according to an embodiment of the present application;
图7是根据本申请实施例的双层连接架的立体结构示意图;7 is a schematic diagram of a three-dimensional structure of a double-layer connecting frame according to an embodiment of the present application;
图8是根据本申请实施例的吊绳件处的立体结构示意图;Fig. 8 is a schematic diagram of a three-dimensional structure of a hanging rope according to an embodiment of the present application;
图9是根据本申请实施例的底板件的立体结构示意图;FIG. 9 is a schematic diagram of a three-dimensional structure of a floor member according to an embodiment of the present application;
图10是根据本申请实施例的分离式插销机构的立体结构示意图;Fig. 10 is a schematic perspective view of a separate latch mechanism according to an embodiment of the present application;
图11是根据本申请实施例的引导拔锁部的立体结构示意图;Fig. 11 is a schematic perspective view of a three-dimensional structure of a guiding lock pulling part according to an embodiment of the present application;
图12是根据本申请实施例的转动拔锁板的立体结构示意图;Fig. 12 is a schematic diagram of a three-dimensional structure of a rotating lock-pull plate according to an embodiment of the present application;
图13是根据本申请实施例的弹性插销锁的立体结构示意图。Fig. 13 is a schematic perspective view of the three-dimensional structure of the elastic bolt lock according to the embodiment of the present application.
图标:100-辅助架组件;110-支撑件;111-主支撑杆;112-辅支撑杆;120-双层连接架;121-外层连接杆;122-外层固定套筒;123-内层固定套筒;124-内层连接杆;125-护板;126-挡板;130-底板件;131-底板;132-导绳环;133-解锁绳;134-过绳孔;140-侧板件;141-侧板;142-穿绳孔;150-分离式插销机构;151-引导拔锁部;1511-缓冲套筒;1512-第一压缩弹簧;1513-支撑耳板;1514-连杆;1515-拔锁杆;1516-施力杆;1517-挂绳环;152-转动拔锁板;1521-板体;1522-转轴;1523-滑槽;153-弹性插销锁;1531-锁套;1532-滑动板;1533-滑杆;1534-限位板;1535-第二压缩弹簧;1536-锁舌;1537-拨动杆;1538-卡槽;160-吊绳件;161-第一挂环;162-支撑钢索;163-防脱吊钩;164-第二挂环;165-第三挂环;166-拉紧环;200-吊篮组件;210-吊篮支架;220-吊篮。Icon: 100-auxiliary frame assembly; 110-support; 111-main support rod; 112-auxiliary support rod; 120-double-layer connecting frame; 121-outer connecting rod; Layer fixing sleeve; 124-inner layer connecting rod; 125-guard plate; 126-baffle plate; 130-bottom plate; 131-bottom plate; 132-rope guide ring; Side plate; 141- side plate; 142- rope hole; 150- separate latch mechanism; 151- guide lock part; 1511- buffer sleeve; 1512- first compression spring; Connecting rod; 1515-pull lock lever; 1516-force rod; 1517-lanyard ring; 152-rotate lock plate; 1521-plate body; 1522-rotating shaft; 1523-chute; Lock sleeve; 1532-sliding plate; 1533-sliding rod; 1534-limiting plate; 1535-second compression spring; The first hanging ring; 162-supporting steel cable; 163-anti-off hook; 164-the second hanging ring; 165-the third hanging ring; 166-tension ring; 200-hanging basket assembly; 220 - Basket.
具体实施方式Detailed ways
下面将结合本申请实施例中的附图,对本申请实施例中的技术方案进行描述。The technical solutions in the embodiments of the present application will be described below with reference to the drawings in the embodiments of the present application.
为使本申请实施方式的目的、技术方案和优点更加清楚,下面将结合本申请实施方式中的附图,对本申请实施方式中的技术方案进行清楚、完整地描述,显然,所描述的实施方式是本申请一部分实施方式,而不是全部的实施方式。基于本申请中的实施方式,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施方式,都属于本申请保护的范围。In order to make the purpose, technical solutions and advantages of the embodiments of the application clearer, the technical solutions in the embodiments of the application will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the application. Obviously, the described embodiments It is a part of embodiment of this application, and is not all embodiment. Based on the implementation manners in this application, all other implementation manners obtained by persons of ordinary skill in the art without creative efforts fall within the scope of protection of this application.
下面参考附图描述根据本申请实施例的红层软岩区抗滑桩成孔方法及吊装式人工辅助装置。The method for forming holes of anti-sliding piles in soft rock areas in red beds and the hoisting artificial auxiliary device according to the embodiments of the present application will be described below with reference to the accompanying drawings.
请参阅图1至图3,根据本申请实施例的红层软岩区抗滑桩成孔方法,包括:Please refer to Fig. 1 to Fig. 3, according to the embodiment of the present application, the anti-sliding pile hole-forming method in the soft rock area of red beds includes:
桩位测量:钻孔桩施工前采用全站仪进行精确测量,并与路基联测,形成闭合三角网后,精确测定钻孔桩位置,并测定、埋设护桩,以此保证位置的准确;Pile position measurement: Before the construction of the bored piles, the total station is used for accurate measurement, and combined with the subgrade to measure, after forming a closed triangular network, the position of the bored piles is accurately measured, and the guard piles are measured and buried to ensure the accuracy of the position;
锁口、孔口护壁制作:为了安全及孔位锁定,钻孔前先根据测量定位进行锁口施工,确保孔口稳固,孔口下1米范围做好护壁,1米以下视地质情况施作护壁;Fabrication of lock mouth and orifice retaining wall: For safety and hole position locking, the lock opening construction should be carried out according to the measurement and positioning before drilling to ensure the stability of the orifice. The retaining wall should be prepared within 1 meter below the orifice, and the construction should be carried out according to the geological conditions below 1 meter. retaining wall;
钻机安装:钻机就位后,调平机座,确保钻头中心与孔位中心在一条铅垂线上,与孔位中心的偏差在规范允许范围之内,调整钻架的垂直度使其满足要求,钻架、钻头等部位连接牢固、运转良好;Drilling rig installation: After the drilling rig is in place, level the machine base to ensure that the center of the drill bit and the center of the hole are on a vertical line, and the deviation from the center of the hole is within the allowable range of the specification, and adjust the verticality of the drill stand to meet the requirements , Drill frame, drill bit and other parts are firmly connected and in good operation;
钻机的机座用枕木垫实塞紧,保证固定平稳。The machine base of the drilling rig is tightly plugged with a sleeper pad to ensure a stable fixation.
钻架安装:钻架安装稳定,钻机定位时采用细线挂重锤检测,保证钻头中心与孔位中心偏差不大于2厘米;Drill stand installation: The drill stand is installed stably, and the drilling rig is positioned with a thin wire hanging weight for detection to ensure that the deviation between the center of the drill bit and the center of the hole is not greater than 2 cm;
旋挖施工:开钻后,将钻机调平对准钻孔,把钻头吊起徐徐放入孔内,对正桩位,开始钻进。在钻进过程中,严格控制钻头提高不超过2米,钻进时,需要进行检孔,防止出现偏孔,钻孔作业对钻机、钻头、钢丝绳及卡具进行检查;Rotary excavation construction: After drilling, level the drilling rig and align it with the drilling hole, lift the drill bit and slowly put it into the hole, align the pile position, and start drilling. During the drilling process, strictly control the raising of the drill bit to no more than 2 meters. When drilling, it is necessary to check the hole to prevent the deviation of the hole. During the drilling operation, check the drill rig, drill bit, wire rope and fixture;
旋挖成孔:先在四周用1.2米钻头成4个孔,再在中间用2.1米钻头成1个孔。局部外扩5厘米钻进,保障尺寸性,剩余部分人工剔凿;Rotary digging to form holes: first use a 1.2-meter drill to form 4 holes around, and then use a 2.1-meter drill to form 1 hole in the middle. Partially expanded 5 cm to ensure the size, and the remaining part is manually chiseled;
岩层取样:当钻到岩层时,分层取渣样,在渣样袋中注明标高、尺寸、桩号和日期;Sampling of rock formations: when drilling into rock formations, take slag samples layer by layer, and mark the elevation, size, stake number and date in the slag sample bag;
人工辅助:机械成孔后,安装吊装式人工辅助装置,借助吊篮达到清理位置,打开相应需要剔凿的位置,使用风镐自上而下剔凿孔壁凸出部分并清理孔底成渣,保证孔底无沉渣;Manual assistance: After the mechanical hole is formed, install a hoisting artificial auxiliary device, use the hanging basket to reach the cleaning position, open the corresponding position that needs to be chiseled, and use a pneumatic pick to remove the protruding part of the chiseled hole wall from top to bottom and clean the slag at the bottom of the hole , to ensure that there is no sediment at the bottom of the hole;
成孔验收:采用检孔器对孔深、尺寸、孔位、垂直度进行检查;Hole acceptance: use a hole detector to check the hole depth, size, hole position, and verticality;
吊装钢筋笼:每根桩钢筋笼自重重达10顿,钢筋笼采用孔外单根钢筋连接好,人工配合吊车单机根吊入孔内,人工下井逐一安装而成。Hoisting reinforcement cage: Each pile reinforcement cage weighs 10 tons. The reinforcement cage is connected by a single reinforcement outside the hole. The single root is lifted into the hole manually with a crane, and it is manually installed one by one in the well.
请参阅图4,桩基声测管的安装:每根桩共布置6根声测管声测管,检查管壁是否有破损,接头处是否合格,确定声测管的分段长度,声测管的长度需要根据钢筋笼的分段长度进行确定,不能过长也不能过短,否则无法对上下两节声测管进行连接;Please refer to Figure 4, the installation of pile foundation acoustic tubes: a total of 6 acoustic tubes are arranged for each pile, check whether the pipe wall is damaged, whether the joint is qualified, determine the section length of the acoustic tube, The length of the pipe needs to be determined according to the section length of the steel cage, it cannot be too long or too short, otherwise the upper and lower sections of the acoustic measuring pipe cannot be connected;
声测管出厂长度为12米、9米和3米,根据钢筋笼长度合理搭配声测管型号。The ex-factory length of the acoustic tube is 12 meters, 9 meters and 3 meters, and the model of the acoustic tube is reasonably matched according to the length of the steel cage.
灌注混凝土:在混凝土浇筑前应先抽排孔内积水清除泥浆,桩身混凝土比桩顶设计标高应超灌30至50厘米,确保截除桩头后桩身混凝土质量;Concrete pouring: Before pouring concrete, the accumulated water in the hole should be drained to remove the mud, and the pile body concrete should be 30 to 50 cm higher than the design elevation of the pile top, so as to ensure the quality of the pile body concrete after the pile head is cut off;
混凝土浇筑采用天泵浇筑,震动棒振动的方式进行。Concrete pouring is carried out by sky pump pouring and vibrating rod vibration.
处理桩头:桩头采用人工风镐的方式剔除,剔至桩顶标高或桩顶标高以下的均匀混凝土骨料处,针对低于设计标高的桩头应当采取高标号混凝土接桩。Handling of pile heads: The pile heads are removed by means of manual air picks, and removed to the uniform concrete aggregate at or below the pile top elevation, and high-grade concrete piles should be used for pile heads lower than the design elevation.
上成孔方法,通过局部外扩5厘米钻进,并配合人工辅助,因人工较机械整体成孔,便于控制挖掘尺寸,进而提高尺寸的保障性,中间部分采用2.1米钻孔钻进,以此提高钻孔钻进的效率,而且剩余部分少,需要人工剔凿部分少,降低劳动强度,成孔经济性好,安装有声测管用作检测通道及取代一部分钢筋截面,声测管还可作为桩底压浆的管道,声测管可作为事故桩缺陷冲洗与压浆处理的管道,这时需采取措施把需压浆的缺陷部位的管道打穿,并可通过声测管进行超声波透射法检测。The upper hole forming method is to drill through local expansion of 5 cm and cooperate with manual assistance. Because manual drilling is better than mechanical overall hole forming, it is convenient to control the excavation size, thereby improving the guarantee of size. The middle part is drilled with a 2.1-meter drill hole to This improves the efficiency of drilling, and there are few remaining parts, less parts that need to be manually chiseled, reducing labor intensity, and the hole is economical. The acoustic measuring tube is installed as a detection channel and replaces a part of the steel bar section. The acoustic measuring tube can also be used as The pipeline for grouting at the bottom of the pile and the acoustic tube can be used as a pipeline for flushing and grouting treatment of accidental pile defects. At this time, measures need to be taken to penetrate the pipeline at the defect part that needs to be grouted, and the ultrasonic transmission method can be carried out through the acoustic tube detection.
请参阅图5至图13,相关技术中红层软岩区抗滑桩成孔过程中,在人工辅助成孔时,采用阶段式挖掘的方式进行剩余部分的人工剔凿(既旋挖机挖一段,人工辅助挖掘一段方式),以此减少桩孔坍塌对人员的人身安全造成影响的情况,在人工辅助剔凿的过程中,采用吊篮带动人员进行升降,再使用风镐剔凿剩余部分的方式,但是该种方式,人员裸露于桩孔内,如果桩孔坍塌依然会造成事故,影响人员的人身安全。Please refer to Fig. 5 to Fig. 13, in the process of forming anti-slide piles in the soft rock area of red beds in the related art, when artificially assisting in forming holes, the remaining part is artificially chiseled by means of staged excavation (that is, rotary excavator excavation One section, manual assisted excavation for one section), so as to reduce the impact of pile hole collapse on the personal safety of personnel. In the process of manual assisted chiseling, the hanging basket is used to drive the personnel to lift, and then the remaining part is chiseled with a pneumatic pick However, in this way, the personnel are exposed in the pile hole, and if the pile hole collapses, an accident will still be caused and the personal safety of the personnel will be affected.
为此,发明人经过长期的实践研究,解决了该技术问题。具体地,该吊装式人工辅助装置,红层软岩区抗滑桩成孔方法的人工辅助使用该吊装式人工辅助装置进行防护,包括:辅助架组件100和吊篮组件200。For this reason, the inventor has solved this technical problem through long-term practical research. Specifically, the hoisting artificial auxiliary device, the artificial assistance of the method of forming anti-slide piles in the soft rock area of the red bed uses the hoisting artificial auxiliary device for protection, including: an
请参阅图6,辅助架组件100包括支撑件110、双层连接架120、底板件130、侧板件140、分离式插销机构150和吊绳件160,支撑件110固定连接于双层连接架120四角的上下两侧,由支撑件110和双层连接架120组成基本框架,底板件130转动连接于基本框架两端的双层连接架120,侧板件140分别转动连接于支撑件110,同侧的侧板件140之间通过门销锁定,分离式插销机构150分别安装于双层连接架120和底板件130上,分离式插销机构150能够将底板件130上端固定于支撑件110,分离式插销机构150能够脱开底板件130和支撑件110的连接,吊绳件160的两端分别挂接于底板件130和支撑件110。Please refer to FIG. 6 , the
在本实施例中,吊篮组件200包括吊篮支架210和吊篮220,吊篮支架210固定连接于基本框架顶端,吊篮220上四角固定有牵引钢索,牵引钢索通过导向轮连接于提升机。使用时,人员通过吊篮220下到需要人工剔凿的位置,操作分离式插销机构150,解除分离式插销机构150对底板件130的锁定,底板件130在重力作用下翻转落下,由两个底板件130相互叠起构成人员站立的支撑结构,吊绳件160形成防护型拉紧支撑底板件130,而双层连接架120能够支撑住分离式插销机构150,此时,人员可站立于支撑结构上,剔凿基本框架两端的剩余部分土壤,解除侧板件140上锁定的门销,解除吊绳件160,翻转打开侧板件140,吊绳件160穿过侧板件140再进行连接,此时人员可剔凿基本框架两侧的剩余部分土壤,人工操作区域的上方和下方,均有未打开的底板件130和侧板件140进行防护,即使遭遇坍塌底板件130和侧板件140可抵抗该部分土壤,减少坍塌对人员的人身安全造成影响的情况发生。In this embodiment, the hanging
请参阅图7,支撑件110包括主支撑杆111和辅支撑杆112,主支撑杆111和辅支撑杆112固定插接于双层连接架120内外层的四角。基本框架采用主支撑杆111和辅支撑杆112双层支撑,提高基本框架的整体强度,提高其抵抗变形的能力,同时辅支撑杆112位于主支撑杆111内侧,减少辅支撑杆112接触外部土壤,影响底板件130和侧板件140翻转的情况发生。双层连接架120包括外层连接杆121、外层固定套筒122、内层固定套筒123、内层连接杆124、护板125和挡板126,外层固定套筒122和外层连接杆121相互固定连接成外层框架,内层固定套筒123和内层连接杆124相互固定连接成内层框架,外层固定套筒122和内层固定套筒123相互固定连接,在本实施例中,主支撑杆111螺纹连接于上层和下层的外层固定套筒122内,辅支撑杆112螺纹连接于上层和下层的内层固定套筒123内,便于基本框架的拼装。护板125固定连接于内层连接杆124上下两侧,护板125固定连接于挡板126上侧,挡板126能够挡住侧板件140,侧板件140通过门销锁定于挡板126。侧板件140闭合时,挡板126挡住侧板件140,减少侧板件140向外翻转过度的情况发生,底板件130翻起时,内层连接杆124下侧的护板125能够挡住底板件130,限定底板件130翻起的位置,便于分离式插销机构150的锁定底板件130。Please refer to FIG. 7 , the supporting
请参阅图8,吊绳件160包括第一挂环161、支撑钢索162和防脱吊钩163,第一挂环161和防脱吊钩163分别固定连接于支撑钢索162两端,第一挂环161套接于辅支撑杆112,防脱吊钩163挂接于底板件130。辅支撑杆112上设置有第二挂环164,第一挂环161套接于第二挂环164,底板件130上固定连接有第三挂环165,防脱吊钩163挂接于第三挂环165。侧板件140包括侧板141,侧板141开设有穿绳孔142,防脱吊钩163能够通过穿绳孔142挂接于第三挂环165。侧板件140打开前,解除防脱吊钩163和第三挂环165的挂接,翻转打开侧板141,防脱吊钩163穿过穿绳孔142后重新挂接于第三挂环165,通过支撑钢索162可作为底板件130的拉紧绳系,以减少分离式插销机构150因意外脱离双层连接架120,导致底板件130失去支撑的情况发生。Please refer to FIG. 8 , the
请参阅图9和图10,相关技术中红层软岩区抗滑桩成孔过程中,采用人工辅助装置防护人员,但是通过人员人力开启和关闭底板外力消耗较大,并且人员处于吊篮中,不便于进行操作,人员开启的过程中,吊篮会干涉底板和侧板141的开启,如何利用吊篮的牵引力控制底板的开合以及减少吊篮对底板和侧板141开启的影响成为需要解决的技术问题。Please refer to Figures 9 and 10. In the related art, during the process of forming anti-slide piles in the soft rock area of red beds, artificial auxiliary devices are used to protect personnel, but the external force consumption of opening and closing the bottom plate by personnel is relatively large, and the personnel are in the hanging basket. , it is inconvenient to operate, during the process of personnel opening, the hanging basket will interfere with the opening of the bottom plate and
为解决上技术问题,本发明进一步采用的技术方案是:底板件130包括底板131、导绳环132和解锁绳133,导绳环132固定连接于底板131底端的外壁,解锁绳133上端固定连接于底板131内侧壁,解锁绳133穿过导绳环132,底板131上开设有过绳孔134,分离式插销机构150包括引导拔锁部151、转动拔锁板152和弹性插销锁153,引导拔锁部151设置于内层连接杆124下侧的挡板126外侧,引导拔锁部151一侧穿过挡板126后连接于解锁绳133,转动拔锁板152下端转动连接于底板131内侧壁,弹性插销锁153固定连接于底板131外侧,弹性插销锁153端部能够将底板131锁紧于辅支撑杆112,弹性插销锁153一侧穿过底板131,弹性插销锁153穿过底板131一侧滑动连接于转动拔锁板152,支撑钢索162上设置有拉紧环166,吊篮220上固定连接有拉板绳,拉板绳穿过上层的过绳孔134后,拉板绳固定连接于下层支撑钢索162上的拉紧环166。当需要打开底板131时,人员通过吊篮220下到需要打开位置的上一层位置,人员拉动解锁绳133或者通过吊篮220上的拉板绳牵引解锁绳133,解锁绳133下端沿导绳环132滑动,解锁绳133下端拉动引导拔锁部151运动,引导拔锁部151推动转动拔锁板152上端,转动拔锁板152绕下端转动,转动拔锁板152牵引弹性插销锁153的端部缩回,解除弹性插销锁153对底板131的锁定,底板131可在重力作用下翻下,转动拔锁板152和弹性插销锁153脱离。弹性插销锁153的端部在弹力作用下弹出,弹性插销锁153的端部能够将底板131锁紧于辅支撑杆112,再配合支撑钢索162形成防护型拉紧支撑,通过底板131配合弹性插销锁153的支撑以及支撑钢索162的防护拉紧支撑,提高人员站立于底板131上的安全性,此时人员在上层便可控制下层的底板131展开,形成人员的支撑结构,人员再通过吊篮220落于底板131上,人员站立于支撑结构上,此时可升起吊篮220,再打开侧板141,减少吊篮220对底板131和侧板141打开的干涉,关闭底板131和侧板141时,先关闭侧板141,拉板绳穿过上层的过绳孔134后连接于拉紧环166,吊篮220升起,拉动拉板绳,拉板绳牵引拉紧环166,通过拉紧环166拉起底板131,利用吊篮220上升和下落提供底板131关闭的外力,减少人员关闭,人力消耗较大的情况。In order to solve the above technical problems, the technical solution further adopted by the present invention is: the
请参阅图11,引导拔锁部151包括缓冲套筒1511、第一压缩弹簧1512、支撑耳板1513、连杆1514、拔锁杆1515和施力杆1516,缓冲套筒1511固定连接于挡板126外侧,第一压缩弹簧1512设置于缓冲套筒1511内,支撑耳板1513固定连接于挡板126外侧,连杆1514滑动连接于支撑耳板1513,连杆1514一端分别滑动插接于缓冲套筒1511内部,缓冲套筒1511端部能够挡住连杆1514插入缓冲套筒1511内的一端,连杆1514分别压紧于第一压缩弹簧1512两端,拔锁杆1515和施力杆1516固定连接于连杆1514一侧,拔锁杆1515能够带动转动拔锁板152上端,解锁绳133穿过导绳环132后固定于施力杆1516。施力杆1516上固定连接有挂绳环1517,解锁绳133穿过导绳环132固定连接于挂绳环1517。解锁绳133通过挂绳环1517拉动施力杆1516,施力杆1516带动连杆1514向缓冲套筒1511内移动,连杆1514压紧第一压缩弹簧1512,连杆1514带动拔锁杆1515,拔锁杆1515拨动转动拔锁板152,松开解锁绳133,第一压缩弹簧1512推动连杆1514回复原位。Please refer to Fig. 11, the guiding
请参阅图12,转动拔锁板152包括板体1521和转轴1522,转轴1522固定连接于底板131内壁,板体1521下端转动连接于转轴1522,板体1521上开设有滑槽1523,弹性插销锁153穿过底板131一侧滑动连接于滑槽1523,拔锁杆1515能够带动板体1521上端。Please refer to Fig. 12, the
请参阅图13,弹性插销锁153包括锁套1531、滑动板1532、滑杆1533、限位板1534、第二压缩弹簧1535、锁舌1536和拨动杆1537,锁套1531和滑动板1532固定连接于板体1521外壁,滑杆1533滑动连接于滑动板1532,限位板1534固定连接于滑杆1533一端,第二压缩弹簧1535套接于滑杆1533,第二压缩弹簧1535两端分别压紧于限位板1534和滑动板1532,锁舌1536固定连接于限位板1534一侧,锁舌1536滑动插接于锁套1531,锁舌1536能够锁紧于辅支撑杆112,锁舌1536能够锁紧于内层连接杆124,拨动杆1537固定连接于滑杆1533远离限位板1534一端,拨动杆1537上设置有卡槽1538,拨动杆1537通过卡槽1538滑动连接于滑槽1523。板体1521转动,板体1521带动拨动杆1537,拨动杆1537带动滑杆1533沿滑动板1532滑动,同时锁舌1536沿锁套1531滑动缩回,限位板1534随滑杆1533移动,限位板1534带动第二压缩弹簧1535压缩,第二压缩弹簧1535的弹力增加,板体1521和拔锁杆1515脱离后,锁舌1536在第二压缩弹簧1535的弹力作用下回复原位。Referring to Fig. 13, the
具体的,该红层软岩区抗滑桩成孔方法及吊装式人工辅助装置的工作原理:上成孔方法,通过局部外扩5厘米钻进,并配合人工辅助,因人工较机械整体成孔,便于控制挖掘尺寸,进而提高尺寸的保障性,中间部分采用2.1米钻孔钻进,以此提高钻孔钻进的效率,而且剩余部分少,需要人工剔凿部分少,降低劳动强度,成孔经济性好,安装有声测管用作检测通道及取代一部分钢筋截面,声测管还可作为桩底压浆的管道,声测管可作为事故桩缺陷冲洗与压浆处理的管道,这时需采取措施把需压浆的缺陷部位的管道打穿,并可通过声测管进行超声波透射法检测。Specifically, the working principle of the hole-forming method of the anti-slide pile in the soft rock area of the red bed and the hoisting artificial auxiliary device: the hole-forming method, drilling through a local expansion of 5 cm, and with manual assistance, because the artificial is more complex than the mechanical one. The hole is easy to control the excavation size, thereby improving the security of the size. The middle part is drilled with a 2.1-meter hole to improve the efficiency of the drilling, and the remaining part is small, and the part that needs to be manually chiseled is less, reducing labor intensity. The hole forming is economical, and the acoustic measuring tube is installed as a detection channel and replaces a part of the steel bar section. The acoustic measuring tube can also be used as a pipeline for grouting at the bottom of the pile. The acoustic measuring tube can be used as a pipeline for flushing and grouting treatment of accident pile defects. At this time Measures need to be taken to break through the pipes in the defective parts that need to be grouted, and the ultrasonic transmission method can be used for detection through the acoustic tube.
使用时,人员通过吊篮220下到需要人工剔凿的位置,操作分离式插销机构150,解除分离式插销机构150对底板件130的锁定,底板件130在重力作用下翻转落下,由两个底板件130相互叠起构成人员站立的支撑结构,支撑钢索162形成防护型拉紧支撑底板件130,而双层连接架120能够支撑住分离式插销机构150,此时,人员可站立于支撑结构上,剔凿基本框架两端的剩余部分土壤,解除防脱吊钩163和第三挂环165的挂接,翻转打开侧板141,防脱吊钩163穿过穿绳孔142后重新挂接于第三挂环165,通过支撑钢索162可作为底板件130的拉紧绳系,以减少分离式插销机构150因意外脱离双层连接架120,导致底板件130失去支撑的情况发生,此时人员可剔凿基本框架两侧的剩余部分土壤,人工操作区域的上方和下方,均有未打开的底板件130和侧板件140进行防护,即使遭遇坍塌底板件130和侧板件140可抵抗该部分土壤,减少坍塌对人员的人身安全造成影响的情况发生,基本框架采用主支撑杆111和辅支撑杆112双层支撑,提高基本框架的整体强度,提高其抵抗变形的能力,同时辅支撑杆112位于主支撑杆111内侧,减少辅支撑杆112接触外部土壤,影响底板件130和侧板件140翻转的情况发生。During use, the personnel go down to the position that needs to be manually chiseled through the
当需要打开底板131时,人员通过吊篮220下到需要打开位置的上一层位置,人员拉动解锁绳133或者通过吊篮220上的拉板绳牵引解锁绳133,解锁绳133下端沿导绳环132滑动,解锁绳133通过挂绳环1517拉动施力杆1516,施力杆1516带动连杆1514向缓冲套筒1511内移动,连杆1514压紧第一压缩弹簧1512,连杆1514带动拔锁杆1515,拔锁杆1515拨动板体1521,板体1521带动拨动杆1537,拨动杆1537带动滑杆1533沿滑动板1532滑动,同时锁舌1536沿锁套1531滑动缩回,限位板1534随滑杆1533移动,限位板1534带动第二压缩弹簧1535压缩,第二压缩弹簧1535的弹力增加,解除弹性插销锁153对底板131的锁定,底板131可在重力作用下翻下,板体1521和拔锁杆1515脱离后,锁舌1536在第二压缩弹簧1535的弹力作用下回复原位,弹性插销锁153的锁舌1536能够将底板131锁紧于辅支撑杆112,再配合支撑钢索162形成防护型拉紧支撑,通过底板131配合弹性插销锁153的支撑以及支撑钢索162的防护拉紧支撑,提高人员站立于底板131上的安全性,此时人员在上层便可控制下层的底板131展开,形成人员的支撑结构,松开解锁绳133,第一压缩弹簧1512推动连杆1514回复原位,人员再通过吊篮220落于底板131上,人员站立于支撑结构上,此时可升起吊篮220,再打开侧板141,减少吊篮220对底板131和侧板141打开的干涉,关闭底板131和侧板141时,先关闭侧板141,拉板绳穿过上层的过绳孔134后连接于拉紧环166,吊篮220升起,拉动拉板绳,拉板绳牵引拉紧环166,通过拉紧环166拉起底板131,利用吊篮220上升和下落提供底板131关闭的外力,减少人员关闭,人力消耗较大的情况。When the
需要说明的是,提升机具体的型号规格需根据该装置的实际规格等进行选型确定,具体选型计算方法采用本领域现有技术,故不再详细赘。It should be noted that the specific model specification of the hoist needs to be selected according to the actual specification of the device, and the specific model selection calculation method adopts the existing technology in the field, so it will not be described in detail.
提升机的供电及其原理对本领域技术人员来说是清楚的,在此不予详细说明。The power supply of the hoist and its principle are clear to those skilled in the art, and will not be described in detail here.
以上仅为本申请的实施例而已,并不用于限制本申请的保护范围,对于本领域的技术人员来说,本申请可以有各种更改和变化。凡在本申请的精神和原则之内,作的任何修改、等同替换、改进等,均应包含在本申请的保护范围之内。应注意到:相似的标号和字母在下面的附图中表示类似项,因此,一旦某一项在一个附图中被定义,则在随后的附图中不需要对其进行进一步定义和解释。The above are only examples of the present application, and are not intended to limit the protection scope of the present application. For those skilled in the art, the present application may have various modifications and changes. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of this application shall be included within the protection scope of this application. It should be noted that like numerals and letters denote similar items in the following figures, therefore, once an item is defined in one figure, it does not require further definition and explanation in subsequent figures.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210996219.6A CN115354673B (en) | 2022-08-19 | 2022-08-19 | Anti-slide pile pore-forming method for red-layer soft rock area and hoisting type artificial auxiliary device |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210996219.6A CN115354673B (en) | 2022-08-19 | 2022-08-19 | Anti-slide pile pore-forming method for red-layer soft rock area and hoisting type artificial auxiliary device |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN115354673A true CN115354673A (en) | 2022-11-18 |
| CN115354673B CN115354673B (en) | 2023-09-05 |
Family
ID=84003257
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202210996219.6A Expired - Fee Related CN115354673B (en) | 2022-08-19 | 2022-08-19 | Anti-slide pile pore-forming method for red-layer soft rock area and hoisting type artificial auxiliary device |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN115354673B (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116291200A (en) * | 2023-05-25 | 2023-06-23 | 四川省公路规划勘察设计研究院有限公司 | Basalt fiber anchor rod drilling device for high polymer grouting |
| CN117071544A (en) * | 2023-08-16 | 2023-11-17 | 中交二航局建筑工程有限公司 | A semi-automatic large-diameter pile broken pile processing device and method |
Citations (14)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103243740A (en) * | 2013-05-20 | 2013-08-14 | 马春根 | Construction method of rotary excavating and long spiral combination bored concrete pressure grouting secant pile continuous wall |
| CN103835661A (en) * | 2013-11-06 | 2014-06-04 | 北京中煤矿山工程有限公司 | Local excavation pre-supporting raise boring technology |
| CN106192995A (en) * | 2016-07-11 | 2016-12-07 | 中铁上海工程局集团有限公司 | A kind of apparatus for work about caisson mechanical hole building and construction method thereof |
| CN108468334A (en) * | 2018-03-09 | 2018-08-31 | 中交公局桥隧工程有限公司 | Sandy pear variety is dry to dig clay dado pore-creating filling pile constructing device |
| KR20190127507A (en) * | 2018-05-03 | 2019-11-13 | 백기원 | lifting device for PHC pile and piling method of PHC pile using the same |
| CN210562179U (en) * | 2019-06-18 | 2020-05-19 | 中交第二航务工程局有限公司 | Safety protection device for construction at bottom of anti-slide pile hole |
| CN111691408A (en) * | 2020-06-22 | 2020-09-22 | 福建省华策建设集团有限公司 | Soft rock stratum rectangular slide-resistant pile construction method |
| CN213897093U (en) * | 2020-12-03 | 2021-08-06 | 安徽省路桥工程集团有限责任公司 | Anti-sliding pile construction system in landslide zone |
| CN113266358A (en) * | 2021-06-04 | 2021-08-17 | 北京中煤矿山工程有限公司 | Mechanical rock breaking drilling process of vertical shaft heading machine for breaking stratum |
| CN214195634U (en) * | 2020-12-11 | 2021-09-14 | 中交路桥华东工程有限公司 | Manual hole digging pile construction protection device |
| CN113832958A (en) * | 2021-09-08 | 2021-12-24 | 中交二公局第三工程有限公司 | Anti-slide pile construction method with mechanical cooperation with manual excavation |
| CN215562597U (en) * | 2020-12-22 | 2022-01-18 | 中电建路桥集团有限公司 | Platform for assisting pile foundation construction |
| CN215669599U (en) * | 2021-09-10 | 2022-01-28 | 重庆一零七市政建设工程有限公司 | Landslide is administered and is used friction pile |
| CN114855774A (en) * | 2022-04-24 | 2022-08-05 | 四川省公路规划勘察设计研究院有限公司 | Frame type anti-slide pile and pouring device thereof |
-
2022
- 2022-08-19 CN CN202210996219.6A patent/CN115354673B/en not_active Expired - Fee Related
Patent Citations (14)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103243740A (en) * | 2013-05-20 | 2013-08-14 | 马春根 | Construction method of rotary excavating and long spiral combination bored concrete pressure grouting secant pile continuous wall |
| CN103835661A (en) * | 2013-11-06 | 2014-06-04 | 北京中煤矿山工程有限公司 | Local excavation pre-supporting raise boring technology |
| CN106192995A (en) * | 2016-07-11 | 2016-12-07 | 中铁上海工程局集团有限公司 | A kind of apparatus for work about caisson mechanical hole building and construction method thereof |
| CN108468334A (en) * | 2018-03-09 | 2018-08-31 | 中交公局桥隧工程有限公司 | Sandy pear variety is dry to dig clay dado pore-creating filling pile constructing device |
| KR20190127507A (en) * | 2018-05-03 | 2019-11-13 | 백기원 | lifting device for PHC pile and piling method of PHC pile using the same |
| CN210562179U (en) * | 2019-06-18 | 2020-05-19 | 中交第二航务工程局有限公司 | Safety protection device for construction at bottom of anti-slide pile hole |
| CN111691408A (en) * | 2020-06-22 | 2020-09-22 | 福建省华策建设集团有限公司 | Soft rock stratum rectangular slide-resistant pile construction method |
| CN213897093U (en) * | 2020-12-03 | 2021-08-06 | 安徽省路桥工程集团有限责任公司 | Anti-sliding pile construction system in landslide zone |
| CN214195634U (en) * | 2020-12-11 | 2021-09-14 | 中交路桥华东工程有限公司 | Manual hole digging pile construction protection device |
| CN215562597U (en) * | 2020-12-22 | 2022-01-18 | 中电建路桥集团有限公司 | Platform for assisting pile foundation construction |
| CN113266358A (en) * | 2021-06-04 | 2021-08-17 | 北京中煤矿山工程有限公司 | Mechanical rock breaking drilling process of vertical shaft heading machine for breaking stratum |
| CN113832958A (en) * | 2021-09-08 | 2021-12-24 | 中交二公局第三工程有限公司 | Anti-slide pile construction method with mechanical cooperation with manual excavation |
| CN215669599U (en) * | 2021-09-10 | 2022-01-28 | 重庆一零七市政建设工程有限公司 | Landslide is administered and is used friction pile |
| CN114855774A (en) * | 2022-04-24 | 2022-08-05 | 四川省公路规划勘察设计研究院有限公司 | Frame type anti-slide pile and pouring device thereof |
Non-Patent Citations (2)
| Title |
|---|
| 杨昌梅;: "人机结合旋挖桩施工技术应用", 中国住宅设施, no. 07 * |
| 贾小斌;刘可嘉;刁开达;高万象;范毅;: "旋挖钻机钻孔、人工辅助清孔干作业桩成孔施工技术应用", 甘肃科技, no. 06 * |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116291200A (en) * | 2023-05-25 | 2023-06-23 | 四川省公路规划勘察设计研究院有限公司 | Basalt fiber anchor rod drilling device for high polymer grouting |
| CN116291200B (en) * | 2023-05-25 | 2023-09-05 | 四川省公路规划勘察设计研究院有限公司 | Basalt fiber anchor rod drilling device for high polymer grouting |
| CN117071544A (en) * | 2023-08-16 | 2023-11-17 | 中交二航局建筑工程有限公司 | A semi-automatic large-diameter pile broken pile processing device and method |
Also Published As
| Publication number | Publication date |
|---|---|
| CN115354673B (en) | 2023-09-05 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN110424381A (en) | A kind of process for rotary digging drilling hole stake | |
| WO2022096024A1 (en) | Construction method for super-long small-diameter hole bored pile | |
| CN203846485U (en) | Long pile percussion drill hole forming construction device | |
| CN108894214B (en) | Karst cave geological environment cast-in-place pile and pile-forming construction method thereof | |
| CN115354673B (en) | Anti-slide pile pore-forming method for red-layer soft rock area and hoisting type artificial auxiliary device | |
| CN103526747B (en) | Morning and evening tides environmental impact pore-creating filling pile construction | |
| CN109098170A (en) | Diaphram wall enters the comprehensive construction method of hard rock grooving | |
| CN106836206A (en) | Casing rotary digging bore forming method | |
| CN107227961A (en) | Heavy caliber dewatering well construction method in metro built by mining method hole | |
| CN112411530A (en) | A construction method for verticality control of casing occlusal piles in reclamation strata | |
| CN110805029A (en) | Subway underground-excavated station drilling and grouting fender post construction method | |
| CN110593254A (en) | Construction method of cast-in-situ bored pile in stratum with karst cave in joint zone | |
| CN116220546A (en) | A construction method for combining large-diameter and long piles into holes in ultra-thick hard rock conditions | |
| CN109915021A (en) | A kind of aquatic pile foundation construction drill method | |
| CN206570811U (en) | Existing bridge pile pulling device is passed through in weak soil shield driving area | |
| CN115596453A (en) | "Micro brush slope" entry method for long-distance side of tunnel passing through accumulation | |
| CN113981958A (en) | Method for plugging karst cave of mechanical pore-forming cast-in-place pile | |
| CN105649010A (en) | Grouting pile construction technology | |
| CN113322942A (en) | Construction method of soft stratum squeezing and expanding support disc cast-in-place pile | |
| CN110725163B (en) | Composite roadbed device based on existing rail transit roadbed and pile construction method | |
| CN113107368B (en) | A full-casing construction method for geological survey | |
| CN109056709A (en) | A method of using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation | |
| CN110409474B (en) | Tube well dewatering well placed at the bottom of underground diaphragm wall | |
| CN115369906A (en) | Construction method for beaded karst cave pile foundation in karst development area | |
| CN110374664A (en) | Reverse drilling construction method for high gas and outburst coal seam fresh air well |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20230905 |