CN210216391U - Enclosed type diaphragm wall surrounding well structure extending into bedrock - Google Patents

Enclosed type diaphragm wall surrounding well structure extending into bedrock Download PDF

Info

Publication number
CN210216391U
CN210216391U CN201920973769.XU CN201920973769U CN210216391U CN 210216391 U CN210216391 U CN 210216391U CN 201920973769 U CN201920973769 U CN 201920973769U CN 210216391 U CN210216391 U CN 210216391U
Authority
CN
China
Prior art keywords
wall
diaphragm wall
ground
surrounding well
bedrock
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920973769.XU
Other languages
Chinese (zh)
Inventor
Wenming Peng
彭文明
Xiaodong Wang
王晓东
Yong Xia
夏勇
Ting Yu
余挺
Faming Ye
叶发明
Xueming Yu
余学明
Qi Zhang
张琦
Kun He
何坤
Jinyuan Li
李进元
Dangzai Wang
王党在
Lianming Zhang
张连明
Fengcai Zhang
张凤财
Zhengjun Zhou
周正军
Yuanyuan Jiang
蒋媛媛
Jian Li
李建
Tao Fu
傅涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Chengdu Engineering Co Ltd
Original Assignee
PowerChina Chengdu Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Chengdu Engineering Co Ltd filed Critical PowerChina Chengdu Engineering Co Ltd
Priority to CN201920973769.XU priority Critical patent/CN210216391U/en
Application granted granted Critical
Publication of CN210216391U publication Critical patent/CN210216391U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The utility model relates to a stretch into closed ground of basement rock and link wall surrounding well structure belongs to exploration construction technical field. The utility model discloses to the not ideal not enough of conventional exploration technique to deep sand bed sample disturbance influence big, sample small in quantity and field test condition, provide a closed ground that stretches into basement rock and link wall surrounding well structure. The utility model discloses a ground, ground from top to bottom include overburden and basement rock in proper order, still include ground even wall and curtain grout, and ground even wall adopts reinforced concrete structure, forms closed surrounding well structure all around, and ground even wall sets up in the overburden and in the basement rock was inserted to the lower extreme, the curtain grout sets up in the basement rock of ground even wall bottom. The depth of the cover layer is typically over 30 m. The inside of the diaphragm wall is supported by horizontal steel supports, a ground surface ring beam is poured on the top of the diaphragm wall, and a dewatering well is arranged at the bottom of the diaphragm wall in the surrounding well.

Description

Enclosed type diaphragm wall surrounding well structure extending into bedrock
Technical Field
The utility model relates to a stretch into closed ground of basement rock and link wall surrounding well structure belongs to exploration construction technical field.
Background
The traditional exploration method mainly takes exploration such as drilling and shallow shaft exploration, and limited tests such as side pressure test, penetration test and earthquake longitudinal and transverse wave test can be only carried out in field test. The drilling is an exploration method for detecting the thickness of a gravel layer, which can take core to identify the geological structure, divide the boundary line of the stratum, and simultaneously carry out hydrogeological test, comprehensive well logging and in-hole camera shooting operation to find the permeability characteristic of the stratum and more intuitively describe the geological characteristics in the hole; the existing drilling technology can drill covering layers more than 500 meters deep, but because the drill bit is smaller, the number of drilling samples is small, the disturbance influence on soil samples is large, and the influence is more obvious along with the increase of the drilling depth; on the other hand, after a certain depth, for example, 50m, the difficulty of in-situ in-hole testing is increased, and the testing method and the evaluation standard need to be deeply researched. The depth of the shallow shaft is generally less than 10m, so that the prospecting personnel can directly observe the geological structure, and the method is accurate, reliable and convenient for sketch; from which pristine soil samples can be taken without restriction and used for large in situ testing.
The two water conservancy and hydropower engineering are widely applied to the covering layer exploration technology, and original state sampling and in-situ test of the deep covering layer are difficult to meet. For hydroelectric engineering in partial southwest region, the dam foundation covering layer is deep, the supporting layer mainly comprises fine particles, the physical and mechanical properties and the hydraulic properties of the covering layer, particularly the deep covering layer are found out, the relation between the mechanical properties and the burial depth of the covering layer is established, the problems of sedimentation deformation of the dam foundation covering layer, sandy soil liquefaction, stable sliding resistance, leakage, stable permeation and the like are accurately evaluated, structural calculation parameter indexes such as mechanical strength, bearing capacity, permeability, strong earthquake resistance, liquefaction resistance and the like of the dam foundation are provided, and the dam foundation is a key core foundation for dam engineering design.
SUMMERY OF THE UTILITY MODEL
The utility model discloses the technical problem that will solve is: aiming at the defects of large influence of conventional exploration technology on deep sand layer sampling disturbance, small sampling quantity and unsatisfactory field test conditions, the closed type diaphragm wall surrounding well structure stretching into bedrock is provided.
For solving the technical problem the utility model discloses the technical scheme who adopts is: the closed type diaphragm wall surrounding well structure extending into the bedrock comprises a foundation, wherein the foundation sequentially comprises a covering layer and the bedrock from top to bottom, the diaphragm wall surrounding well structure further comprises a diaphragm wall and curtain grouting, the diaphragm wall is of a reinforced concrete structure and forms a closed type surrounding well structure all around, the diaphragm wall is arranged in the covering layer, the lower end of the diaphragm wall is inserted into the bedrock, and the curtain grouting is arranged in the bedrock at the bottom of the diaphragm wall. The depth of the cover layer is typically over 30 m.
Further, the method comprises the following steps: the underground diaphragm wall is a rectangular surrounding well formed by surrounding four walls, the four walls of the underground diaphragm wall are mutually overlapped, and joint grouting holes are respectively arranged at joints.
Further, the method comprises the following steps: and grouting of the joint grouting holes extends into the basement rock at the bottom of the diaphragm wall.
Further, the method comprises the following steps: the wall structure is characterized by further comprising horizontal steel supports, wherein the horizontal steel supports are arranged at four corners of the wall in a layered mode from top to bottom, each layer of horizontal steel support is composed of four grouting steel pipes, each grouting steel pipe is welded to an embedded steel plate of the adjacent two-side wall, and the embedded steel plates are welded to a reinforcement cage of the wall through embedded steel bars.
Further, the method comprises the following steps: and a ground surface ring beam is poured at the top of the diaphragm wall, and a dewatering well is arranged at the bottom of the well in the diaphragm wall surrounding well. And the ground surface ring beam is poured, so that water and other impurities above the ground can be prevented from falling into the well during the surrounding well excavation supporting construction. The dewatering well is set to provide dry land environment.
The closed type diaphragm wall surrounding well structure extending into the bedrock can be implemented according to the following steps:
completely pouring the underground diaphragm wall and reaching the age of more than 6 months, and grouting the bedrock and the underground diaphragm wall through the embedded grouting pipe to form a closed grouting curtain under the wall;
and excavating a covering layer in a surrounding well formed by the underground diaphragm wall until the covering layer is excavated to the bottom of the well. In order to fully utilize the cover layer in the well for testing and sampling, the bottom of the well is lower than the elevation of the base-cover interface.
The underground continuous wall preferably adopts a rectangular surrounding well formed by surrounding four walls, wherein two oppositely arranged walls are first-stage underground continuous walls, the other two walls are second-stage underground continuous walls, and the underground continuous walls are poured and constructed in two stages, and the method comprises the following steps:
a. constructing a first-stage diaphragm wall groove section;
b. hoisting the reinforcement cages of the diaphragm wall into the groove section of the diaphragm wall in sections by using a crawler crane, and putting the reinforcement cages in place until all the reinforcement cages are installed;
c. placing the joint pipes at two ends of the slotted hole before pouring concrete into the slotted hole of the first-stage diaphragm wall, then pouring the concrete, pulling up the joint pipes after the concrete is initially set, forming a smooth semi-cylindrical surface and two guide holes for construction of the second-stage slotted hole at two ends of the first-stage diaphragm wall, and forming a joint surface after construction of the second-stage slotted hole is finished;
d. performing second-stage underground diaphragm wall slotted hole construction, steel reinforcement cage hoisting and concrete pouring, wherein the construction method is the same as the steps a-c;
e. before the diaphragm wall is poured, embedding grouting pipes in the groove holes and the joint surfaces of the first-stage diaphragm wall and the second-stage diaphragm wall, and enabling the lower ends of the embedded grouting pipes to be located at the bottom of the pouring holes;
f. and (3) completely pouring the diaphragm wall and reaching the age of more than 6 months, grouting the bedrock and the diaphragm wall through the embedded grouting pipes, sealing the joint parts of the first-stage diaphragm wall and the second-stage diaphragm wall, and forming a grouting curtain sealed under the wall.
When the underground diaphragm wall is excavated in the enclosed well formed by the underground diaphragm wall, the underground diaphragm wall is supported in time, the preferable embodiment is that the inner wall of the underground diaphragm wall is provided with horizontal steel supports which are arranged at four corners of the underground diaphragm wall from top to bottom in a layering way, each layer of horizontal steel support is composed of four grouting steel pipes, each grouting steel pipe is welded on the pre-embedded steel plates of the adjacent two-sided underground diaphragm wall, and the pre-embedded steel plates are welded on the reinforcement cages of the underground diaphragm wall through pre-embedded steel bars;
when the underground diaphragm wall is excavated in the enclosed well formed by the underground diaphragm wall, the method comprises the following steps:
h. the covering layer in the surrounding well is manually excavated and layered, constructors can go in and out and slag can be hoisted by using a gantry crane, and meanwhile, emergency safety crawling ladders can be arranged on the wall of the well;
i. the excavation gap is cleaned and accumulated water is pumped and drained according to the field test and the requirement of soil sample extraction;
j. cleaning an embedded steel plate on the inner wall of the excavated diaphragm wall, welding and installing horizontal steel supports, grouting and filling the horizontal steel supports, and performing covering layer excavation and horizontal steel support installation in the surrounding well in a staggered manner;
k. and h-j working procedures are circulated until the well bottom is excavated, and a precipitation well is arranged at the well bottom.
The utility model has the advantages that: the underground diaphragm wall with the reinforced concrete structure is inserted into bedrock, and four walls are mutually lapped to form a stable surrounding well structure, so that safety guarantee is provided for construction and test in the surrounding well; the horizontal steel supports which are timely supported on the underground diaphragm wall are welded with the embedded steel bars of the underground diaphragm wall, so that the stability of the wall body is further enhanced; curtain grouting is arranged at the bottom of the diaphragm wall, joint grouting is carried out at the lap joint part of the diaphragm wall, and the seepage-proofing performance of the surrounding well is enhanced; and a dewatering well is arranged in the foundation pit of the surrounding well excavation to provide a dry land operation environment.
Drawings
Fig. 1 is a schematic cross-sectional view of the present invention.
Fig. 2 is a schematic view a-a of fig. 1.
Fig. 3 is a schematic view B-B of fig. 1.
Parts in the figure are marked: the construction method comprises the following steps of covering layer 1, bedrock 2, ground connecting wall 3, first-stage ground connecting wall 31, second-stage ground connecting wall 32, embedded steel bars 41, embedded steel plates 42, horizontal steel supports 5, joint grouting holes 6, curtain grouting 7, dewatering wells 8, well bottom 9, ground surface ring beams 10, foundation covering interface 11 and ground 12.
Detailed Description
The present invention will be further explained with reference to the drawings and the embodiments.
As shown in fig. 1 to 3, the utility model discloses a ground, ground from top to bottom include overburden 1 and basement rock 2 in proper order, still include ground even wall 3 and curtain grout 7, and ground even wall 3 adopts reinforced concrete structure, forms closed surrounding well structure all around, and ground even wall 3 sets up in overburden 1 and the lower extreme inserts in basement rock 2, and curtain grout 7 sets up in basement rock 2 of 3 bottoms of ground even wall. The depth of the cover layer 1 is typically more than 30 m. When the method is implemented, the underground diaphragm wall 3 is completely poured and reaches the age of more than 6 months, grouting is performed into the bedrock 2 and the underground diaphragm wall 3 through the embedded grouting pipes to form a grouting curtain 7 sealed under the wall, and the depth of the grouting curtain 7 is determined according to seepage calculation; then, in a surrounding well formed by the underground diaphragm wall 3, the covering layer 1 is excavated until the shaft bottom 9 is excavated, and a precipitation well 8 is arranged at the shaft bottom 9. To take full advantage of the well cover 1 for testing and sampling, the bottom of the well 9 is at a level below the bedding interface 11.
For convenient construction and stable structure, the underground diaphragm wall 3 is a rectangular surrounding well surrounded by four walls, the four walls of the underground diaphragm wall 3 are mutually overlapped, and joint grouting holes 6 are respectively arranged at joints. In order to make the structure more stable, the joint grouting holes 6 are grouted to extend into the basement rock 2 of the underground diaphragm wall 3. When the underground diaphragm wall 3 preferably adopts a rectangular surrounding well formed by surrounding four walls, two oppositely arranged walls are first-stage underground diaphragm walls 31, the other two walls are second-stage underground diaphragm walls 32, and the construction of the underground diaphragm wall 3 is carried out in two stages.
When excavating in the enclosing well formed by the diaphragm wall 3, should in time strut, the preferred embodiment is, the diaphragm wall 3 inner wall is provided with horizontal steel support 5, horizontal steel support 5 from top to bottom sets up the four corners on diaphragm wall 3 in layers, each horizontal steel support 5 comprises four slip casting steel pipes, each slip casting steel pipe welds on the pre-buried steel plate 42 of adjacent two sides diaphragm wall 3, pre-buried steel plate 42 welds on the steel reinforcement cage of diaphragm wall 3 through pre-buried reinforcing bar 41. The support type, the support time and the support parameter design adopted in the surrounding well formed by excavation are determined by comprehensive technical and economic demonstration analysis.
In addition, a ground surface ring beam 10 is poured on the top of the diaphragm wall 3, and a dewatering well 8 is arranged at the bottom of the well 9 in the surrounding well of the diaphragm wall 3. The ground surface ring beam 10 is poured, so that water and other impurities above the ground 12 can be prevented from falling into the well during the surrounding well excavation supporting construction. The dewatering well 8 is provided for the purpose of providing a dry working environment.
The utility model discloses it is preferred to implement according to following step:
a. constructing a groove section of the first-stage diaphragm wall 31; drilling equipment and a construction mode are selected according to the characteristics of the covering layer 1 and the bedrock 2;
b. hoisting the reinforcement cages of the underground diaphragm wall 3 into the groove sections of the first-stage underground diaphragm wall 31 section by using crawler cranes in sections, and putting the reinforcement cages in place until all the reinforcement cages are installed;
c. placing the joint pipes at two ends of the slotted hole before pouring concrete into the slotted hole of the first-stage underground diaphragm wall 31, then pouring the concrete, pulling up the joint pipes after the concrete is initially set, forming a smooth semi-cylindrical surface and two guide holes for second-stage slotted hole construction at two ends of the first-stage underground diaphragm wall 31, and forming a joint surface after the second-stage slotted hole construction is finished;
d. performing second-stage underground diaphragm wall 32 slotted hole construction, steel reinforcement cage hoisting and concrete pouring, wherein the construction method is the same as the steps a-c;
e. before the diaphragm wall 3 is poured, grouting pipes are pre-embedded in the groove holes and the joint surfaces of the first-stage diaphragm wall 3 and the second-stage diaphragm wall 3, and the lower ends of the pre-embedded grouting pipes are positioned at the bottom of the pouring holes;
f. the underground diaphragm wall 3 is completely poured and reaches the age of more than 6 months, the foundation rock 2 and the underground diaphragm wall 3 are grouted through the embedded grouting pipes, the joint parts of the first-stage and second-stage underground diaphragm walls 3 are sealed, and a grouting curtain 7 sealed under the walls is formed;
g. pouring a ground surface ring beam 10 on the top of the diaphragm wall 3 to prevent water and other impurities above the ground 12 from falling into the well during the surrounding well excavation supporting construction;
h. the cover layer 1 in the surrounding well is manually excavated and layered, and constructors can go in and out and slag can be hoisted by using a gantry crane;
i. the excavation gap is cleaned and accumulated water is pumped and drained according to the field test and the requirement of soil sample extraction;
j. cleaning an embedded steel plate 42 on the inner wall of the excavated diaphragm wall 3, welding and installing the horizontal steel supports 5, grouting and filling the horizontal steel supports 5, and performing excavation and installation of the horizontal steel supports 5 in the covering layer 1 in the surrounding well in a staggered manner and in a time supporting manner;
k. the h-j working procedures are circulated until the well bottom 9 is excavated, and a dewatering well 8 is arranged at the well bottom 9; to take full advantage of the well cover 1 for testing and sampling, the bottom of the well 9 is at a level below the bedding interface 11.
Example (b):
the depth of the covering layer 1 is about 70m, and in order to find out the mechanics and seepage characteristics of the covering layer 1, the original sampling and the in-situ test of the covering layer 1 are carried out by adopting a closed type underground continuous wall surrounding well structure extending into bedrock. The underground diaphragm wall 3 surrounding well adopts a reinforced concrete structure, the wall thickness is 1.2m, and the net size of the surrounding well is 6.4m multiplied by 6.4 m. The diaphragm wall 3 is controlled to extend into the weakly weathered bedrock, the depth of the diaphragm wall 3 is 10m, and the total depth of the diaphragm wall 3 is 80 m. 32 curtain grouting 7 preformed holes are arranged at the bottom of the diaphragm wall 3, seepage control analysis is carried out according to the seepage characteristics of bedrock, and the average grouting depth in the bedrock 2 is 20 m. In order to ensure the stability of the structure of the underground diaphragm wall 3 surrounding well, 26 layers of horizontal steel supports 5 are arranged on the inner wall of the underground diaphragm wall 3 surrounding well, and through structural calculation, one layer is arranged at intervals of 2-5 m of the height of the horizontal steel supports 5, wherein the upper part of the underground diaphragm wall 3 is stressed in a small mode, the interlayer interval is large, the lower part of the underground diaphragm wall is stressed in a large mode, and the interlayer interval is small. Each layer of horizontal steel support 5 comprises four steel pipes with the diameter of 600mm, the steel pipes are respectively and obliquely supported on the adjacent two ground connecting walls 3, and C35 expanded cement mortar is poured into the steel pipes; an embedded steel plate 42 with the thickness of 30mm and U-shaped anchoring embedded steel bars 41 welded on the steel plate are respectively embedded in the supporting section of the underground diaphragm wall 3, and the embedded steel bars 41 and the embedded steel plates 42 are poured in concrete through welding on a steel bar cage of the underground diaphragm wall 3. In order to ensure the anti-seepage effect of the joints of the groove sections of the diaphragm walls 3, the joints of the groove sections of the diaphragm walls 3 are respectively provided with 2 pre-buried pipes with joint grouting holes 6, and the grouting depth of the joint grouting holes 6 is 5m below the diaphragm walls 3.

Claims (5)

1. Stretch into closed ground of basement rock and link wall surrounding well structure, including the ground, the ground from top to bottom includes overburden (1) and basement rock (2) in proper order, its characterized in that: the underground continuous wall is characterized by further comprising an underground continuous wall (3) and curtain grouting (7), wherein the underground continuous wall (3) is of a reinforced concrete structure, a closed surrounding well structure is formed at the periphery of the underground continuous wall, the underground continuous wall (3) is arranged in the covering layer (1), the lower end of the underground continuous wall is inserted into the bedrock (2), and the curtain grouting (7) is arranged in the bedrock (2) at the bottom of the underground continuous wall (3).
2. A closed type diaphragm wall surrounding well structure extending into bedrock according to claim 1, wherein: the underground diaphragm wall (3) is a rectangular surrounding well formed by surrounding four walls, the four walls of the underground diaphragm wall (3) are mutually overlapped, and joint grouting holes (6) are respectively arranged at joints.
3. A closed type diaphragm wall surrounding well structure extending into bedrock according to claim 2, wherein: the joint grouting holes (6) are used for grouting and extend into the wall bottom bedrock (2) of the diaphragm wall (3).
4. A closed type diaphragm wall surrounding well structure extending into bedrock according to claim 2, wherein: still include horizontal steel shotcrete (5), horizontal steel shotcrete (5) from top to bottom layering sets up four corners on even wall (3) on the ground, and each horizontal steel shotcrete (5) of layer comprises four slip casting steel pipes, and each slip casting steel pipe welding is on pre-buried steel sheet (42) of adjacent two sides ground even wall (3), and pre-buried steel sheet (42) are on the steel reinforcement cage of ground even wall (3) through pre-buried reinforcing bar (41) welding.
5. A closed type diaphragm wall surrounding well structure extending into bedrock according to any one of claims 1 to 4, wherein: the top of the diaphragm wall (3) is poured with a ground surface ring beam (10), and a dewatering well (8) is arranged at the bottom (9) of the well enclosed by the diaphragm wall (3).
CN201920973769.XU 2019-06-26 2019-06-26 Enclosed type diaphragm wall surrounding well structure extending into bedrock Active CN210216391U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920973769.XU CN210216391U (en) 2019-06-26 2019-06-26 Enclosed type diaphragm wall surrounding well structure extending into bedrock

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920973769.XU CN210216391U (en) 2019-06-26 2019-06-26 Enclosed type diaphragm wall surrounding well structure extending into bedrock

Publications (1)

Publication Number Publication Date
CN210216391U true CN210216391U (en) 2020-03-31

Family

ID=69934101

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920973769.XU Active CN210216391U (en) 2019-06-26 2019-06-26 Enclosed type diaphragm wall surrounding well structure extending into bedrock

Country Status (1)

Country Link
CN (1) CN210216391U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110258522A (en) * 2019-06-26 2019-09-20 中国电建集团成都勘测设计研究院有限公司 The closed ground-connecting-wall for protruding into basement rock encloses well construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110258522A (en) * 2019-06-26 2019-09-20 中国电建集团成都勘测设计研究院有限公司 The closed ground-connecting-wall for protruding into basement rock encloses well construction

Similar Documents

Publication Publication Date Title
CN102454167B (en) The construction method of especially big & deep open caisson
CN104612162A (en) Subway station deep foundation pit excavation construction method
CN106638640A (en) Modular coffer construction method for concrete without subsealing in the geologic condition of stratum
CN103938634B (en) A kind of deep foundation pit supporting structure and construction method
CN102383412A (en) Construction method by adopting dewatering and water recharging to control sedimentation surrounding deep foundation pit
CN107227961A (en) Heavy caliber dewatering well construction method in metro built by mining method hole
CN111560958A (en) Construction method of water-rich deep foundation pit in silty clay stratum
CN112576265A (en) Sedimentation control method for old villages penetrated by shield
CN115595993A (en) Replacement pile structure of tunnel-passing slope slide-resistant pile and construction method
CN210263062U (en) Anti construction structures that floats of shallow earthing subway tunnel foundation ditch earthwork excavation in pit bottom
CN110593254A (en) Construction method of cast-in-situ bored pile in stratum with karst cave in joint zone
CN113737780A (en) Underwater rock-socketed concrete pile and construction method thereof
CN210216391U (en) Enclosed type diaphragm wall surrounding well structure extending into bedrock
CN204356780U (en) A kind of prefabricated abnormity stake on an empty stomach for deep foundation pit supporting structure
CN210216392U (en) Underground wall surrounding well structure
CN210658410U (en) Inverted wall hanging surrounding well structure
CN110512594B (en) Simple method for forming hole and pile in cavity of rotary drilling rig
CN209891202U (en) Anti-floating anchor rod
CN110258606A (en) Projecting wall encloses well construction
CN106049413A (en) Hybrid power drainage consolidation system applied to deep saturated soft soil foundation and construction method
CN105484270A (en) Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit
CN114232602A (en) Underground continuous pile construction process
CN113668555A (en) Deep foundation pit supporting construction method for large-pipe-diameter prestressed row piles
CN110258521A (en) Ground-connecting-wall encloses well construction
CN112049105A (en) Construction method for sealing and stopping water of tunnel diaphragm wall by water-rich sand layer mining method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant