CN110258522A - The closed ground-connecting-wall for protruding into basement rock encloses well construction - Google Patents

The closed ground-connecting-wall for protruding into basement rock encloses well construction Download PDF

Info

Publication number
CN110258522A
CN110258522A CN201910562006.0A CN201910562006A CN110258522A CN 110258522 A CN110258522 A CN 110258522A CN 201910562006 A CN201910562006 A CN 201910562006A CN 110258522 A CN110258522 A CN 110258522A
Authority
CN
China
Prior art keywords
wall
ground
well
basement rock
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910562006.0A
Other languages
Chinese (zh)
Inventor
彭文明
王晓东
夏勇
余挺
叶发明
余学明
张琦
何坤
李进元
王党在
张连明
张凤财
周正军
蒋媛媛
李建
傅涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Chengdu Engineering Co Ltd
Original Assignee
PowerChina Chengdu Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Chengdu Engineering Co Ltd filed Critical PowerChina Chengdu Engineering Co Ltd
Priority to CN201910562006.0A priority Critical patent/CN110258522A/en
Publication of CN110258522A publication Critical patent/CN110258522A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ

Abstract

The present invention relates to a kind of closed ground-connecting-walls for protruding into basement rock to enclose well construction, belongs to exploration technical field of construction.The present invention influences the deficiency big, quantity of sampling quantity is few and field test condition is undesirable on deep layer of sand sampling disturbance for conventional surveying techniques, proposes that a kind of closed ground-connecting-wall for protruding into basement rock encloses well construction.The present invention includes ground, ground successively includes coating and basement rock from top to bottom, it further include ground-connecting-wall and grout curtain, ground-connecting-wall is formed using reinforced concrete structure, surrounding enclosed encloses well construction, ground-connecting-wall is arranged in coating and in lower end insertion basement rock, and grout curtain is arranged in the basement rock of ground-connecting-wall bottom.Coating depth is usually more than 30m.Supporting is carried out using Horizontal steelwork bracing inside ground-connecting-wall, has poured earth's surface collar tie beam at the top of ground-connecting-wall, and enclose the shaft bottom in well in ground-connecting-wall and be provided with dewatering well.

Description

The closed ground-connecting-wall for protruding into basement rock encloses well construction
Technical field
The present invention relates to a kind of closed ground-connecting-walls for protruding into basement rock to enclose well construction, belongs to exploration technical field of construction.
Background technique
Conventional survey method mainly based on the exploration such as probing, shallow vertical shaft, field test only can be carried out other pressure examination, feeler inspection, The limited experimentations such as vertical and horizontal seismic wave test.Probing is a kind of exploitation method for being largely used to verify sand gravel layer thickness, it can be with Coring identifies geologic structure, divides stratigraphic boundary, while can carry out hydrogeological test, comprehensive logging and deep dynamic consolidation operation, To seek the Penetration Signature on stratum and more intuitively describe geologic feature in hole;Current drilling technique can be accomplished to cover Layer more than 500 meters of depth of drilling, but since drill bit is smaller, drive sampling quantity is few, big to the disturbing influence of soil sample, as drilling is deep Degree increases, and above-mentioned influence is all the more obvious;It on the other hand, is more than field test difficulty increasing in hole after certain depth such as 50m, Test method and evaluation criterion are both needed to further investigate.Shallow shaft depths are generally less than 10m, and prospecting personnel can observe directly geology Structure accurately and reliably, and is convenient for sketch;Original state ground sample can be therefrom taken without restriction and is used as large-scale in-situ test.
The most widely used coating exploration engineering of above two hydraulic and hydroelectric engineering, it is difficult to meet deep coating original state and take Sample and in-situ test.For the hydroelectric project of part southwest, dam foundation coating is deep, and supporting course is based on fine grained, It finds out coating especially deep coating physico mechanical characteristic, water reason characteristic, establishes coating mechanical characteristic and buried depth relationship, it is quasi- Really the problems such as evaluation dam foundation coating sedimentation and deformation, sand liquefaction, stability of dam foundation, leakage and seepage stability, the dam foundation is provided The Structure Calculations parameter indexes such as mechanical strength, bearing capacity, permeability, anti-macroseism and liquefaction performance resistivity energy, are that dam engineering designs Key core basis.
Summary of the invention
The technical problems to be solved by the present invention are: big on deep layer of sand sampling disturbance influence for conventional surveying techniques, The deficiency that quantity of sampling quantity is few and field test condition is undesirable proposes that a kind of closed ground-connecting-wall for protruding into basement rock encloses well construction.
To solve above-mentioned technical problem the technical scheme adopted by the invention is that: the closed ground-connecting-wall for protruding into basement rock encloses well Structure, including ground, ground include successively from top to bottom coating and basement rock, further include ground-connecting-wall and grout curtain, ground-connecting-wall Using reinforced concrete structure, surrounding formed it is enclosed enclose well construction, ground-connecting-wall is arranged in coating and lower end is inserted into In basement rock, grout curtain is arranged in the basement rock of ground-connecting-wall bottom.Coating depth is usually more than 30m.
Further, ground-connecting-wall is the rectangle well surrounded by four sides wall, mutually overlapped between the four sides wall of ground-connecting-wall, And seam injected hole is respectively set in seam crossing.
Further, seam injected hole slip casting is protruded into the wall base rock of ground-connecting-wall.
Further, further including Horizontal steelwork bracing, Horizontal steelwork bracing is from top to bottom stratified and set on quadrangle on ground-connecting-wall, Each layer of Horizontal steelwork bracing is made of four slip casting steel pipes, pre-buried steel of each slip casting steel-pipe welding in two adjacent surfaces ground-connecting-wall On plate, pre-embedded steel slab is welded on the steel reinforcement cage of ground-connecting-wall by embedded bar.
Further, having poured earth's surface collar tie beam at the top of ground-connecting-wall, and the shaft bottom in well is enclosed in ground-connecting-wall and is provided with precipitation Well.Earth's surface collar tie beam is poured, when can prevent from enclosing the construction of well excavation supporting, more than ground water and other sundries are fallen into well.Setting The purpose of dewatering well is to provide dry ground operating environment.
Well construction is enclosed for the above-mentioned closed ground-connecting-wall for protruding into basement rock, can be implemented as follows:
It is all poured in ground-connecting-wall and completes and reach age 6 months or more, by pre-embedment grouting pipe to basement rock and ground-connecting-wall Interior grouting forms closed grout curtain under wall;
It is enclosed in well what ground-connecting-wall was formed later, excavates coating, until being excavated to shaft bottom.It is covered to make full use of in well Layer is tested and is sampled, and interface elevation is covered lower than base in shaft bottom.
Wherein ground-connecting-wall is preferably using the rectangle well surrounded by four sides wall, wherein being a phase in two face walls positioned opposite Ground-connecting-wall, in addition two face walls are the second stage of ground-connecting-wall, and ground-connecting-wall, which pours, was divided to for two phases constructed, and are included the following steps:
A, a phase ground-connecting-wall slot section is constructed;
B, the steel reinforcement cage merogenesis of ground-connecting-wall is hung in a phase ground-connecting-wall slot section with crawler crane, decentralization is in place, until all Steel reinforcement cage installs;
C, slot both ends are placed in using junction block before a phase ground-connecting-wall slot casting concrete, then casting concrete, to After concrete initial set, junction block is pulled up, form smooth semi-cylindrical at the both ends of a phase ground-connecting-wall and is applied for the second stage of slot Two guide holes of work form a joint face after the completion of the second stage of slot construction herein;
D, the second stage of ground-connecting-wall slot construction, reinforcing bar cage hoisting, concreting, construction method and step a~c phase are carried out Together;
E, before ground-connecting-wall pours, pre-embedment grouting pipe in slot and on one, the second stage of ground-connecting-wall joint face, and make pre-buried grouting The lower end of pipe is in the bottom of pouring hole;
F, ground-connecting-wall, which all pours, completes and reaches age 6 months or more, by above-mentioned pre-embedment grouting pipe to basement rock and ground Company is in the milk within the walls, closing one, the second stage of ground-connecting-wall seam areas, and forms closed grout curtain under wall.
Ground-connecting-wall formed enclose excavated in well when, supporting should be carried out in time, preferred embodiment is that ground-connecting-wall inner wall is set It is equipped with Horizontal steelwork bracing, Horizontal steelwork bracing is from top to bottom stratified and set on quadrangle on ground-connecting-wall, and each layer of Horizontal steelwork bracing is by four Root slip casting steel pipe is constituted, and on the pre-embedded steel slab of two adjacent surfaces ground-connecting-wall, pre-embedded steel slab passes through pre- each slip casting steel-pipe welding Reinforcement welding is buried on the steel reinforcement cage of ground-connecting-wall;
Ground-connecting-wall formed enclose excavated in well when, include the following steps:
H, well inner covering layer is enclosed using hand excavation, layering carries out, and construction personnel enters and leaves and slags tap using gantry crane handling, Emergency safety climbing ladder can be also installed on the borehole wall simultaneously;
I, it excavates gap and prune job face, pump drainage ponding is required according to field test, extraction soil sample;
J, pre-embedded steel slab is cleaned out on the ground-connecting-wall inner wall excavated out, Horizontal steelwork bracing is welded and is installed, and to level Bracing members carry out slip casting and enrich, and enclose well inner covering layer excavation and staggeredly carry out with Horizontal steelwork bracing installation;
K, h~j process is recycled, until being excavated to shaft bottom, and dewatering well is set in shaft bottom.
The beneficial effects of the present invention are: the ground-connecting-wall of reinforced concrete structure is inserted into basement rock, four sides wall is mutually overlapped, and is formed Stable encloses well construction, provides safety guarantee to enclose construction in well, testing;The Horizontal steelwork bracing of immediate support on ground-connecting-wall, with The welding of ground-connecting-wall embedded bar, further strengthens wall stability;Grout curtain is set in ground-connecting-wall bottom, in ground-connecting-wall clinch Position carries out joint grouting, and well barrier performance is enclosed in enhancing;It encloses well excavation pit setting dewatering well and dry ground operating environment is provided.
Detailed description of the invention
Fig. 1 is diagrammatic cross-section of the invention.
Fig. 2 is the A-A schematic diagram of Fig. 1.
Fig. 3 is the B-B schematic diagram of Fig. 1.
Component marks in figure: coating 1, basement rock 2, ground-connecting-wall 3, a phase ground-connecting-wall 31, the second stage of ground-connecting-wall 32, embedded bar 41, pre-embedded steel slab 42, Horizontal steelwork bracing 5, seam injected hole 6, grout curtain 7, dewatering well 8, shaft bottom 9, earth's surface collar tie beam 10, base cover Interface 11, ground 12.
Specific embodiment
Below in conjunction with the accompanying drawings and embodiment the invention will be further described.
As shown in Figure 1 to Figure 3, the present invention includes ground, and ground includes successively from top to bottom coating 1 and basement rock 2, is also wrapped Include ground-connecting-wall 3 and grout curtain 7, ground-connecting-wall 3 using reinforced concrete structure, surrounding formed it is enclosed enclose well construction, ground connects Wall 3 is arranged in coating 1 and in lower end insertion basement rock 2, and grout curtain 7 is arranged in the basement rock 2 of 3 bottom of ground-connecting-wall.It covers 1 depth of cap rock is usually more than 30m.When implementation, is all poured in ground-connecting-wall 3 and complete and reach age 6 months or more, by pre-buried Grout pipe is in the milk into basement rock 2 and ground-connecting-wall 3, forms closed grout curtain 7 under wall, the depth of grout curtain 7 should be according to infiltration Stream calculation determines;It is enclosed in well what ground-connecting-wall 3 was formed later, excavates coating 1, until being excavated to shaft bottom 9, and set in shaft bottom 9 Set dewatering well 8.To make full use of well inner covering layer 1 to be tested and sampled, 11 elevation of interface is covered lower than base in shaft bottom 9.
For convenience of construction, and guaranteeing stable structure, ground-connecting-wall 3 is the rectangle well surrounded by four sides wall, the four of ground-connecting-wall 3 It is mutually overlapped between face wall and seam injected hole 6 is respectively set in seam crossing.To make structure more stable, seam slip casting 6 slip casting of hole is protruded into the wall base rock 2 of ground-connecting-wall 3.When ground-connecting-wall 3 preferably uses the rectangle well surrounded by four sides wall, wherein Be a phase ground-connecting-wall 31 in two face walls positioned opposite, in addition two face walls are the second stage of ground-connecting-wall 32, ground-connecting-wall 3 pour be divided to two phases into Row construction.
Ground-connecting-wall 3 formed enclose excavated in well when, supporting should be carried out in time, preferred embodiment is 3 inner wall of ground-connecting-wall It is provided with Horizontal steelwork bracing 5, Horizontal steelwork bracing 5 is from top to bottom stratified and set on quadrangle on ground-connecting-wall 3, each layer of Horizontal steelwork bracing 5 are made of four slip casting steel pipes, and each slip casting steel-pipe welding is on the pre-embedded steel slab 42 of two adjacent surfaces ground-connecting-wall 3, pre-buried steel Plate 42 is welded on the steel reinforcement cage of ground-connecting-wall 3 by embedded bar 41.The supporting type taken in well, branch are enclosed what excavation was formed Shield opportunity and supporting parameter design should all carry out the comprehensive argument and analysis of Technological Economy and determine.
In addition, having poured earth's surface collar tie beam 10 at the top of ground-connecting-wall 3, and the shaft bottom 9 in well is enclosed in ground-connecting-wall 3 and is provided with dewatering well 8.Earth's surface collar tie beam 10 is poured, when can prevent from enclosing the construction of well excavation supporting, the water and other sundries on 12 or more ground are fallen into well.If The purpose for setting dewatering well 8 is to provide dry ground operating environment.
The present invention is preferably implemented as follows:
A, 31 slot section of a phase ground-connecting-wall is constructed;Drilling equipment and form of construction work are chosen according to coating 1 and 2 characteristic of basement rock;
B, the steel reinforcement cage merogenesis of ground-connecting-wall 3 is hung in 31 slot section of a phase ground-connecting-wall with crawler crane, decentralization is in place, until complete Portion's steel reinforcement cage installs;
C, slot both ends are placed in using junction block before 31 slot casting concrete of a phase ground-connecting-wall, then casting concrete, After concrete initial set, junction block is pulled up, forms smooth semi-cylindrical at the both ends of a phase ground-connecting-wall 31 and for the second stage of slot Two guide holes of hole construction form a joint face after the completion of the second stage of slot construction herein;
D, the 32 slot construction of the second stage of ground-connecting-wall, reinforcing bar cage hoisting, concreting, construction method and step a~c phase are carried out Together;
E, before ground-connecting-wall 3 pours, pre-embedment grouting pipe in slot and on one, 3 joint face of the second stage of ground-connecting-wall, and make pre-buried filling The lower end of slurry pipe is in the bottom of pouring hole;
F, ground-connecting-wall 3, which all pours, completes and reaches age 6 months or more, by above-mentioned pre-embedment grouting pipe to 2 He of basement rock Grouting in ground-connecting-wall 3, closing one, 3 seam areas of the second stage of ground-connecting-wall, and form closed grout curtain 7 under wall;
G, earth's surface collar tie beam 10 is poured at the top of ground-connecting-wall 3, when preventing from enclosing the construction of well excavation supporting, the water on 12 or more ground and Other sundries are fallen into well;
H, well inner covering layer 1 is enclosed using hand excavation, and layering carries out, and construction personnel is entered and left and slagged tap and hung using gantry crane Fortune;
I, it excavates gap and prune job face, pump drainage ponding is required according to field test, extraction soil sample;
J, pre-embedded steel slab 42 is cleaned out on 3 inner wall of ground-connecting-wall excavated out, Horizontal steelwork bracing 5 is welded and is installed, and is right Horizontal steelwork bracing 5 carries out slip casting and enriches, and encloses the excavation of well inner covering layer 1 and staggeredly carries out with the installation of Horizontal steelwork bracing 5, with immediate support For principle;
K, h~j process is recycled, until being excavated to shaft bottom 9, and dewatering well 8 is set in shaft bottom 9;It is covered to make full use of in well Cap rock 1 is tested and is sampled, and 11 elevation of interface is covered lower than base in shaft bottom 9.
Embodiment:
Coating 1 depth about 70m, for the mechanics and seepage characteristic for investigating thoroughly coating 1, using protrude into basement rock closedly Even walled well construction carries out the original state sampling and in-situ test of coating 1.Ground-connecting-wall 3 encloses well using reinforced concrete structure, wall Thick 1.2m encloses well dead size 6.4m × 6.4m.Ground-connecting-wall 3 is inserted into 2 depth 10m of basement rock, ground to protrude into weak weathered rocks as control Even 3 total depth 80m of wall.3 bottom of ground-connecting-wall sets 32 7 preformed holes of grout curtain, is carried out seeping control analysis according to basement rock seepage characteristic, The average grout penetration 20m in basement rock 2.To guarantee that ground-connecting-wall 3 encloses the stabilization of well construction, well inner wall is enclosed in ground-connecting-wall 3 and sets 26 layers Horizontal steelwork bracing 5, by Structure Calculation, Horizontal steelwork bracing 5 sets one layer every 2m~5m height, wherein 3 top stress of ground-connecting-wall Small, interlayer interval is big, and lower part stress is big, and interlayer interval is small.Every layer of Horizontal steelwork bracing 5 includes the steel pipe of four diameter 600mm, point C35 expansive cement mortar is perfused on two adjacent surfaces ground-connecting-wall 3 in other diagonal brace in steel pipe;It is each pre-buried on the support section of ground-connecting-wall 3 The pre-embedded steel slab 42 of one piece of 30mm thickness and the U-shaped anchoring embedded bar 41 being welded on steel plate, embedded bar 41 and pre-embedded steel slab It is cast in concrete on 42 steel reinforcement cage by being welded on ground-connecting-wall 3.To guarantee 3 slot section seam seepage control effect of ground-connecting-wall, respectively A 3 slot section seam crossing of ground-connecting-wall sets the built-in pipe of 2 seam injected holes 6,6 slip casting depth of seam injected hole to ground-connecting-wall 3 respectively Following 5m.

Claims (9)

1. the closed ground-connecting-wall for protruding into basement rock encloses well construction, including ground, ground successively include from top to bottom coating (1) and Basement rock (2), it is characterised in that: further include ground-connecting-wall (3) and grout curtain (7), ground-connecting-wall (3) using reinforced concrete structure, Surrounding formed it is enclosed enclose well construction, ground-connecting-wall (3) setting is in coating (1) and in lower end insertion basement rock (2), curtain Curtain grouting (7) setting is in the basement rock (2) of ground-connecting-wall (3) bottom.
2. protruding into the closed ground-connecting-wall of basement rock as described in claim 1 encloses well construction, it is characterised in that: ground-connecting-wall (3) is The rectangle well surrounded by four sides wall, mutually overlaps between the four sides wall of ground-connecting-wall (3) and is respectively arranged in seam crossing and connect It stitches injected hole (6).
3. the closed ground-connecting-wall for protruding into basement rock as claimed in claim 2 encloses well construction, it is characterised in that: seam injected hole (6) slip casting is protruded into the wall base rock (2) of ground-connecting-wall (3).
4. the closed ground-connecting-wall for protruding into basement rock as claimed in claim 2 encloses well construction, it is characterised in that: further include horizontal steel Support (5), Horizontal steelwork bracing (5) is from top to bottom stratified and set on quadrangle on ground-connecting-wall (3), each layer of Horizontal steelwork bracing (5) by Four slip casting steel pipes are constituted, and each slip casting steel-pipe welding is on the pre-embedded steel slab (42) of two adjacent surfaces ground-connecting-wall (3), pre-buried steel Plate (42) is welded on the steel reinforcement cage of ground-connecting-wall (3) by embedded bar (41).
5. the closed ground-connecting-wall for protruding into basement rock as described in claim 1 encloses well construction, it is characterised in that: ground-connecting-wall (3) top Portion has poured earth's surface collar tie beam (10), and encloses the shaft bottom (9) in well in ground-connecting-wall (3) and be provided with dewatering well (8).
6. the closed ground-connecting-wall for protruding into basement rock as described in any one of claim 1 to 5 encloses the implementation method of well construction, It is characterized by comprising the following steps:
It is all poured in ground-connecting-wall (3) and completes and reach age 6 months or more, by pre-embedment grouting pipe to basement rock (2) He Dilian Grouting in wall (3), forms closed grout curtain (7) under wall;
It encloses in well, excavates coating (1) what ground-connecting-wall (3) were formed later, until being excavated to shaft bottom (9).
7. the implementation method that the closed ground-connecting-wall for protruding into basement rock as claimed in claim 6 encloses well construction, which is characterized in that ground Even wall (3) be the rectangle well surrounded by four sides wall, wherein in two face walls positioned opposite for a phase ground-connecting-wall (31), in addition two Face wall is the second stage of ground-connecting-wall (32), and ground-connecting-wall (3), which pours, was divided to for two phases constructed, and is included the following steps:
A, phase ground-connecting-wall (31) slot section is constructed;
B, the steel reinforcement cage merogenesis of ground-connecting-wall (3) is hung in phase ground-connecting-wall (31) slot section with crawler crane, decentralization is in place, until complete Portion's steel reinforcement cage installs;
C, slot both ends are placed in using junction block before phase ground-connecting-wall (31) slot casting concrete, then casting concrete, to After concrete initial set, junction block is pulled up, forms smooth semi-cylindrical at the both ends of a phase ground-connecting-wall (31) and for the second stage of slot Two guide holes of hole construction form a joint face after the completion of the second stage of slot construction herein;
D, the second stage of ground-connecting-wall (32) slot construction, reinforcing bar cage hoisting, concreting, construction method and step a~c phase are carried out Together;
E, before ground-connecting-wall (3) pours, pre-embedment grouting pipe in slot and on one, the second stage of ground-connecting-wall (3) joint face, and make pre-buried filling The lower end of slurry pipe is in the bottom of pouring hole;
F, ground-connecting-wall (3), which all pours, completes and reaches age 6 months or more, by above-mentioned pre-embedment grouting pipe to basement rock (2) and Grouting in ground-connecting-wall (3), closing one, the second stage of ground-connecting-wall (3) seam areas, and form closed grout curtain (7) under wall.
8. the implementation method that the closed ground-connecting-wall for protruding into basement rock as claimed in claim 7 encloses well construction, which is characterized in that ground Even wall (3) inner wall is provided with Horizontal steelwork bracing (5), and Horizontal steelwork bracing (5) is from top to bottom stratified and set on four on ground-connecting-wall (3) Angle, each layer of Horizontal steelwork bracing (5) You Sigen slip casting steel pipe are constituted, and each slip casting steel-pipe welding is in two adjacent surfaces ground-connecting-wall (3) on pre-embedded steel slab (42), pre-embedded steel slab (42) is welded on the steel reinforcement cage of ground-connecting-wall (3) by embedded bar (41);
When enclosing excavation in well, include the following steps: in ground-connecting-wall (3) formation
H, well inner covering layer (1) is enclosed using hand excavation, and layering carries out, and construction personnel enters and leaves and slags tap using gantry crane handling;
I, it excavates gap and prune job face, pump drainage ponding is required according to field test, extraction soil sample;
J, pre-embedded steel slab (42) are cleaned out on ground-connecting-wall (3) inner wall excavated out, Horizontal steelwork bracing (5) is welded and are installed, and Slip casting is carried out to Horizontal steelwork bracing (5) to enrich, and is enclosed well inner covering layer (1) excavation and is staggeredly carried out with Horizontal steelwork bracing (5) installation;
K, h~j process is recycled, until being excavated to shaft bottom (9), and dewatering well (8) are set in shaft bottom (9).
9. the implementation method that the closed ground-connecting-wall for protruding into basement rock as claimed in claim 6 encloses well construction, it is characterised in that: well Interface (11) elevation is covered lower than base in bottom (9).
CN201910562006.0A 2019-06-26 2019-06-26 The closed ground-connecting-wall for protruding into basement rock encloses well construction Pending CN110258522A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910562006.0A CN110258522A (en) 2019-06-26 2019-06-26 The closed ground-connecting-wall for protruding into basement rock encloses well construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910562006.0A CN110258522A (en) 2019-06-26 2019-06-26 The closed ground-connecting-wall for protruding into basement rock encloses well construction

Publications (1)

Publication Number Publication Date
CN110258522A true CN110258522A (en) 2019-09-20

Family

ID=67921867

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910562006.0A Pending CN110258522A (en) 2019-06-26 2019-06-26 The closed ground-connecting-wall for protruding into basement rock encloses well construction

Country Status (1)

Country Link
CN (1) CN110258522A (en)

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101560767A (en) * 2009-05-12 2009-10-21 广东省长大公路工程有限公司 Method for connecting slotted sections in underground construction of diaphragm wall
CN101824821A (en) * 2010-05-17 2010-09-08 中国葛洲坝集团股份有限公司 Method for building concrete underground continuous wall in bedrock
CN102776878A (en) * 2012-08-17 2012-11-14 中铁四局集团第五工程有限公司 Construction method for preventing diaphragm wall from streaming
CN202989931U (en) * 2012-12-27 2013-06-12 中船第九设计研究院工程有限公司 Super-large-diameter round square combining deep foundation pit structure
CN203200745U (en) * 2013-05-06 2013-09-18 中建保华建筑有限责任公司 Strengthening support of underground diaphragm wall in inverse construction method
CN103741725A (en) * 2014-01-17 2014-04-23 天津市市政工程设计研究院 Immersed tunnel final joint and shoreside dry-work construction method thereof
JP2014098238A (en) * 2012-11-13 2014-05-29 Raito Kogyo Co Ltd Subgrade exploration device, subgrade improvement device, construction device of continuous wall, and construction method of continuous wall
CN103898900A (en) * 2014-03-25 2014-07-02 东南大学 Concrete-filled steel tube composite structure underground diaphragm wall with pull rods and construction method of underground diaphragm wall
CN105735348A (en) * 2016-04-26 2016-07-06 国电大渡河沙坪水电建设有限公司 Sand blocking ridge and construction method thereof
CN206052741U (en) * 2016-06-14 2017-03-29 江苏燕宁建设工程有限公司 A kind of steel sheet-pile cofferdam for supporting cushion cap foundation ditch
CN206189436U (en) * 2016-11-18 2017-05-24 中国电建集团成都勘测设计研究院有限公司 Cut -pff wall construction structures
CN107119691A (en) * 2017-06-22 2017-09-01 中交二航局第四工程有限公司 One kind is applied to the square deep basal pit of the high pressure-bearing of rich water sand gravel layer and its excavation method
CN208235542U (en) * 2018-03-27 2018-12-14 中国电建集团华东勘测设计研究院有限公司 A kind of fixed anti-drop structure of steel pipe support
CN210216391U (en) * 2019-06-26 2020-03-31 中国电建集团成都勘测设计研究院有限公司 Enclosed type diaphragm wall surrounding well structure extending into bedrock

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101560767A (en) * 2009-05-12 2009-10-21 广东省长大公路工程有限公司 Method for connecting slotted sections in underground construction of diaphragm wall
CN101824821A (en) * 2010-05-17 2010-09-08 中国葛洲坝集团股份有限公司 Method for building concrete underground continuous wall in bedrock
CN102776878A (en) * 2012-08-17 2012-11-14 中铁四局集团第五工程有限公司 Construction method for preventing diaphragm wall from streaming
JP2014098238A (en) * 2012-11-13 2014-05-29 Raito Kogyo Co Ltd Subgrade exploration device, subgrade improvement device, construction device of continuous wall, and construction method of continuous wall
CN202989931U (en) * 2012-12-27 2013-06-12 中船第九设计研究院工程有限公司 Super-large-diameter round square combining deep foundation pit structure
CN203200745U (en) * 2013-05-06 2013-09-18 中建保华建筑有限责任公司 Strengthening support of underground diaphragm wall in inverse construction method
CN103741725A (en) * 2014-01-17 2014-04-23 天津市市政工程设计研究院 Immersed tunnel final joint and shoreside dry-work construction method thereof
CN103898900A (en) * 2014-03-25 2014-07-02 东南大学 Concrete-filled steel tube composite structure underground diaphragm wall with pull rods and construction method of underground diaphragm wall
CN105735348A (en) * 2016-04-26 2016-07-06 国电大渡河沙坪水电建设有限公司 Sand blocking ridge and construction method thereof
CN206052741U (en) * 2016-06-14 2017-03-29 江苏燕宁建设工程有限公司 A kind of steel sheet-pile cofferdam for supporting cushion cap foundation ditch
CN206189436U (en) * 2016-11-18 2017-05-24 中国电建集团成都勘测设计研究院有限公司 Cut -pff wall construction structures
CN107119691A (en) * 2017-06-22 2017-09-01 中交二航局第四工程有限公司 One kind is applied to the square deep basal pit of the high pressure-bearing of rich water sand gravel layer and its excavation method
CN208235542U (en) * 2018-03-27 2018-12-14 中国电建集团华东勘测设计研究院有限公司 A kind of fixed anti-drop structure of steel pipe support
CN210216391U (en) * 2019-06-26 2020-03-31 中国电建集团成都勘测设计研究院有限公司 Enclosed type diaphragm wall surrounding well structure extending into bedrock

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
宋玉国: ""复杂底层混凝土防渗墙施工技术研究"", 《中国优秀硕士学位论文全文数据库》, pages 326 *

Similar Documents

Publication Publication Date Title
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN104631470B (en) The large particle diameter sand gravel of high water level geology deep basal pit combination supporting construction method
CN102277867B (en) Construction method for collapsible loess foundation
CN104846829B (en) Shield-reserved penetration composite type foundation pit support wall and construction method thereof
CN109026064B (en) Construction method for large-span multi-arch tunnel with semi-bright and semi-dark
CN108035335A (en) A kind of construction freezing method well shaft type underground parking garage method
CN108797598A (en) The construction technology of pre-loaded support struts in a kind of deep basal pit
CN109538246A (en) Ledge method tunneling subway station arch springing ruggedized construction and construction method
CN102363961A (en) Deepwater single-wall steel plate pile cofferdam structure with low buried depth and construction method thereof
CN106638640A (en) Modular coffer construction method for concrete without subsealing in the geologic condition of stratum
CN106437726A (en) Ground fracture crushed zone passing construction method for shallow-buried tunnel excavation
CN106150506A (en) A kind of gateway open excavation section inverted side-wall construction method
CN106049195A (en) Method for strengthening subgrade basement of existing high speed railway line
CN106087997A (en) A kind of high latitude, high and cold Permafrost Area drilled pile construction engineering method
CN106522235A (en) Narrow site deep foundation pit excavation supporting construction method
CN105155550A (en) Construction method for digging deep foundation pit in large-thickness highly weathered sandstone stratum in combined supporting mode
CN109778869A (en) Foundation ditch construction method
CN108316339A (en) A kind of construction method of water penetration geology large size arch bridge base
CN110042842A (en) A kind of open cut construction method of deep foundation ditch for wearing river
CN110439590A (en) Method for tunnel construction
CN103015429A (en) Long auger rotary-jet mixing steel reinforced cement-soil pile foundation pit water-resisting and supporting method
CN110042843A (en) A kind of large deep foundation pit construction method of complex condition
CN109706945A (en) Come down fracture belt tunnel construction method
CN109578014A (en) Anti- dash forward of one kind gushes back cover structure and construction method
CN207331740U (en) A kind of heightening and consolidation structure of in-service reinforced concrete retaining wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination