CN109578014A - Anti- dash forward of one kind gushes back cover structure and construction method - Google Patents

Anti- dash forward of one kind gushes back cover structure and construction method Download PDF

Info

Publication number
CN109578014A
CN109578014A CN201910078063.1A CN201910078063A CN109578014A CN 109578014 A CN109578014 A CN 109578014A CN 201910078063 A CN201910078063 A CN 201910078063A CN 109578014 A CN109578014 A CN 109578014A
Authority
CN
China
Prior art keywords
construction
curtain
upper layer
crown
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910078063.1A
Other languages
Chinese (zh)
Other versions
CN109578014B (en
Inventor
吕剑英
李明磊
石广银
胡志耀
王又莹
宋贺月
郑飞
郭骏伟
张斌
郑冉
赵建峰
崔潇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Liuyuan Group Co Ltd
Original Assignee
China Railway Liuyuan Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Liuyuan Group Co Ltd filed Critical China Railway Liuyuan Group Co Ltd
Priority to CN201910078063.1A priority Critical patent/CN109578014B/en
Publication of CN109578014A publication Critical patent/CN109578014A/en
Application granted granted Critical
Publication of CN109578014B publication Critical patent/CN109578014B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/04Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Environmental & Geological Engineering (AREA)
  • Civil Engineering (AREA)
  • Soil Sciences (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The present invention discloses anti-dash forward of one kind and gushes back cover structure and construction method, and the two sides of top beam are respectively equipped with the small pilot tunnel in upper layer;It is connected between top beam and by two lining structure of crown between the small pilot tunnel of top beam and upper layer;The top of two lining structure of crown is fixed with crown end bay and just props up one, crown end bay just branch two.Construction temporary construction vertical shaft and upper layer occasional passage, lower layer's occasional passage;The small pilot tunnel in upper layer is set in the occasional passage of upper layer;Big pipe curtain, tubule curtain are set along set contour line in lower layer's occasional passage.The present invention can avoid depressurizing underground water artificial rainmaking when hidden digging structure is constructed, and destroy water resource, and can realize anhydrous operation when station construction to guarantee safe construction, it can be achieved that the advance support effect of hidden digging structure construction, is effective against the prominent of artesian water and gushes risk.

Description

Anti- dash forward of one kind gushes back cover structure and construction method
Technical field
The invention belongs to construction of underground structure technical field, in particular to a kind of anti-dash forward gushes back cover structure and construction method.
Background technique
With the fast development of China's urban construction, the construction of Underground Rail Transit system is to solve big and medium-sized cities traffic to ask The important means of topic, with the development of Metro Construction, subway foundation pit develops to deep, big direction, and underground water is to foundation pit work The influence of journey becomes the major issue of control Station Project construction safety.
When surface condition is by limited time, cavern-pile method is that have using more construction to periphery in metro station construction Environment influences the advantages that small, highly-safe, wide adaptability, but with traditional shallow burial hidden digging on structural shape and construction technology Premised on anhydrous operation, need to take to diving artificial rainmaking, the measure of artesian water precipitation decompression, large volume before excavating operation Precipitation undoubtedly will cause water resource waste, if can also surrounding enviroment be impacted by dealing with improperly.As environmental consciousness enhances, city City's ground water protection is increasingly stringenter, in constructing underground building, in water rich strata and under conditions of do not allow precipitation, with precipitation Premised on traditional cavern-pile method will no longer be applicable in.
The new challenge proposed to traditional design and construction method is increased in face of buried depth, effectively controlling underground water is buriedly Ironworker's journey matter of utmost importance to be solved.
Summary of the invention
The present invention for the technical problems in the prior art, provides anti-dash forward of one kind and gushes back cover structure and construction method, It can avoid depressurizing underground water artificial rainmaking when hidden digging structure is constructed, destroy water resource, and can realize anhydrous when station construction Operation is to guarantee safe construction, it can be achieved that the advance support effect of hidden digging structure construction, is effective against the prominent of artesian water and gushes risk.
In order to solve the above technical problems, the technical solution adopted by the present invention is that: anti-dash forward of one kind gushes back cover structure, including lateral Building enclosure (9), top beam (12), two lining structure of crown (14), in hardened structure (15), floor structure (16);
The two sides of the top beam (12) are respectively equipped with the small pilot tunnel in upper layer (4);Between the top beam (12) and top beam (12) it is connect between the small pilot tunnel in upper layer (4) by two lining structure of crown (14);The top of two lining structure of crown (14) is solid Surely it is equipped with crown end bay and just props up one (11), crown end bay just two (13) of branch;
Hardened structure (15), floor structure (16) in being successively arranged below two lining structure of crown (14), the bottom plate knot The bottom end of structure (16) is equipped with multiple big pipe curtains (5);
The bottom end of the top beam (12) is equipped with steel pipe column (10);One end and top beam (12) of the steel pipe column (10) Be fixedly connected, the other end sequentially pass through in hardened structure (15), floor structure (16) and be fixedly installed in big pipe curtain (5);
The bottom end of the small pilot tunnel in upper layer (4) is equipped with building enclosure (9);The both ends of the building enclosure (9) respectively with enclose Protection structure (9), big pipe curtain (5) are fixedly connected;
It is equipped with multiple tubule curtains (6) between the adjacent big pipe curtain (5), is equipped in each tubule curtain (6) Freezing pipe (7).
Preferably, equal fill concrete in the big pipe curtain (5), tubule curtain (6).
Preferably, passing through connection bolt (17) connection between multiple tubule curtains (6).
Anti- dash forward of one kind gushes back cover construction method, comprising the following steps:
Before the construction of water rich strata main body stage excavation, combined ground surrounding enviroment and station main structure, accessory structure Form, construct temporary construction vertical shaft (1) and upper layer occasional passage (2), lower layer's occasional passage (3);Occasional passage (2) on upper layer Inside set the small pilot tunnel in upper layer (4);Big pipe curtain (5), tubule curtain (6) are set along set contour line in lower layer's occasional passage (3);
Freezing pipe (7) are laid in tubule curtain (6), actively freeze to form Frozen Soil Cylinder (8);In Frozen Soil Cylinder (8) supporting Under, pipe interlude connection bolt (17) is set in tubule curtain (6) internal openings, big pipe curtain (5) is fixedly connected with, pipe curtain is made to form entirety Encircle bearing structure, guarantees arch back cover bearing structure globality;Fill concrete forms back cover structure in pipe curtain, increases pipe curtain knot Structure overall stiffness and counterweight are effective against in foundation soil counter-force and water rich strata and exist in conjunction with the Frozen Soil Cylinder (8) of pipe interlude High artesian jacking force, guarantee anti-prominent during structural excavation to gush stability;
Along the set contour line construction lateral building enclosure of tunneling (9) and steel pipe column (10) in the small pilot tunnel in upper layer (4);Wait open Big pipe curtain (5) top mark eminence is dug, in the internal artificial aperture of big pipe curtain (5);In the big interior pouring construction bed course of pipe curtain (5), lifting It places lateral building enclosure (9), and timely casting concrete;Big pipe curtain (5) also serves as hidden digging structure as arch structure fulcrum Lateral building enclosure (9) and steel pipe column (10) strip footing, make arch tube curtain structure form complete stress system with hidden digging structure;
Construction skirt piles crown beam, the crown end bay for erecting the small pilot tunnel in upper layer (4) interior main arch just prop up one (11);Upper layer is small leads for backfill The upper space in hole (4);Slurry coat method in extraction in stake, manually installed steel pipe column locator, and according to design merogenesis lifting, Steel reinforcement cage in steel pipe column and steel pipe column is installed;It is closely knit using coarse sand backfill between steel pipe column and steel pile casting;Construction top beam (12), and the splice that main arch two serves as a contrast is reserved, is laid with waterproof layer;
The main arch soil body is excavated, crown end bay is performed and just props up two (13);The small pilot tunnel in upper layer (4) abutment wall is removed paragraph by paragraph, is laid with anti- Water layer, formwork erection pour two lining structure of crown (14);
Continue to excavate soil layer board bottom absolute altitude into negative one layer downwards, entirely mould, is laid with waterproof layer, pours in negative one layer Plate, central sill and in hardened structure (15), station hall layer closing cyclization;Reserved reinforcing bar of plugging into bottom side wall;
Soil layer plate absolute altitude on earth is excavated downwards, is laid with bed course, waterproof layer, is poured side wall and floor structure (16);Work car It stands internal structure, station main body civil construction is completed.
Compared with prior art, the present invention has the beneficial effects that the present invention realizes water rich strata shallow mining method Shi Wushui operating condition to underground water artificial rainmaking pressure relief rupture water resource when can avoid constructing, and can be evaded in excavation project The prominent construction risk gushed of the artesian water faced, guarantees construction safety.
It avoids depressurizing underground water artificial rainmaking when hidden digging structure is constructed, destroys water resource, and can realize station construction Shi Wushui operation guarantees safe construction, at the same time it can also realize the advance support effect of hidden digging structure construction, is effective against and holds Pressure the prominent of water gushes risk, has stronger engineering exploitativeness and promotional value.
Detailed description of the invention
Fig. 1-7 is construction procedure schematic diagram of the invention;
Fig. 8 is the schematic cross section of structure of the invention;
Fig. 9 is pipe curtain type of attachment schematic diagram of the invention;
Figure 10 is construction process figure of the invention.
1- temporary construction vertical shaft in figure, the upper layer 2- occasional passage, 3- lower layer occasional passage, the small pilot tunnel in the upper layer 4-, the big pipe of 5- Curtain, 6- tubule curtain, 7- freezing pipe, 8- Frozen Soil Cylinder, the side 9- just prop up one to building enclosure, 10- steel pipe column, 11- crown end bay, 12- top beam, 13- crown end bay just prop up two, 14- crown, two lining structure, hardened structure in 15-, 16- floor structure, 17- connection spiral shell Bolt.
Specific embodiment
Technical solution in order to enable those skilled in the art to better understand the present invention, in the following with reference to the drawings and specific embodiments It elaborates to the present invention.
One kind is anti-prominent to gush back cover structure, including lateral building enclosure (9), top beam (12), two lining structure of crown (14), in Hardened structure (15), floor structure (16);
The two sides of top beam (12) are respectively equipped with the small pilot tunnel in upper layer (4);Between top beam (12) and top beam (12) with it is upper It is connected between the small pilot tunnel (4) of layer by two lining structure of crown (14);The top of two lining structure of crown (14) is fixed with crown side Two (13) are just propped up across one (11) of first branch, crown end bay;
Hardened structure (15), floor structure (16) in being successively arranged below two lining structure of crown (14), floor structure (16) Bottom end is equipped with multiple big pipe curtains (5);
The bottom end of top beam (12) is equipped with steel pipe column (10);One end and top beam (12) of steel pipe column (10) are fixed to be connected Connect, the other end sequentially pass through in hardened structure (15), floor structure (16) and be fixedly installed in big pipe curtain (5);
The bottom end of the small pilot tunnel in upper layer (4) is equipped with building enclosure (9);The both ends of building enclosure (9) respectively with building enclosure (9), big pipe curtain (5) is fixedly connected;
It is equipped with multiple tubule curtains (6) between adjacent big pipe curtain (5), is equipped with freezing pipe in each tubule curtain (6) (7)。
In the present embodiment, equal fill concrete in big pipe curtain (5), tubule curtain (6).
In the present embodiment, pass through connection bolt (17) connection between multiple tubule curtains (6).
Anti- dash forward of one kind gushes back cover construction method, comprising the following steps:
Referring to figure 1: before the construction of water rich strata main body stage excavation, combined ground surrounding enviroment and station main body Structure, accessory structure form, construct temporary construction vertical shaft (1) and upper layer occasional passage (2), lower layer's occasional passage (3);Upper The small pilot tunnel in upper layer (4) is set in layer occasional passage (2);Big pipe curtain is set along set contour line in lower layer's occasional passage (3) (5), tubule curtain (6);
Referring to shown in attached drawing 2: laying freezing pipe (7) in tubule curtain (6), actively freeze to form Frozen Soil Cylinder (8);Freezing Under native curtain (8) supporting, pipe interlude connection bolt (17) is set in tubule curtain (6) internal openings, is fixedly connected with big pipe curtain (5), So that pipe curtain is formed whole arch bearing structure, guarantees arch back cover bearing structure globality;Fill concrete forms back cover in pipe curtain Structure increases pipe curtain structure overall stiffness and counterweight in conjunction with the Frozen Soil Cylinder (8) of pipe interlude and is effective against foundation soil counter-force And high artesian jacking force present in water rich strata, anti-dash forward gushes stability during guaranteeing structural excavation;
Referring to shown in attached drawing 3: in the small pilot tunnel in upper layer (4) along the set contour line construction lateral building enclosure of tunneling (9) and Steel pipe column (10);Wait excavate big pipe curtain (5) top mark eminence, in the internal artificial aperture of big pipe curtain (5);It is poured in big pipe curtain (5) Construction cushion coat is built, lateral building enclosure (9), and timely casting concrete are placed in lifting;Big pipe curtain (5) is same as arch structure fulcrum When also serve as the lateral building enclosure of hidden digging structure (9) and steel pipe column (10) strip footing, make arch tube curtain structure with hidden digging structure shape At complete stress system;
Referring to shown in attached drawing 4: construction skirt piles crown beam, the crown end bay for erecting the small pilot tunnel in upper layer (4) interior main arch just prop up one (11);Backfill the upper space of the small pilot tunnel in upper layer (4);Slurry coat method in extraction in stake, manually installed steel pipe column locator, and According to the steel reinforcement cage in the lifting of design merogenesis, installation steel pipe column and steel pipe column;It is returned between steel pipe column and steel pile casting using coarse sand Packing is real;It constructs top beam (12), and the splice that reserved main arch two serves as a contrast, is laid with waterproof layer;
Referring to shown in attached drawing 5: excavating the main arch soil body, perform crown end bay and just prop up two (13);The small pilot tunnel in upper layer is removed paragraph by paragraph (4) abutment wall, is laid with waterproof layer, and formwork erection pours two lining structure of crown (14);
Referring to shown in attached drawing 6: continue to excavate soil layer board bottom absolute altitude into negative one layer downwards, entirely mould, laying waterproof layer, Pour plate in negative one layer, central sill and in hardened structure (15), station hall layer closing cyclization;Reserved reinforcing bar of plugging into bottom side wall;
Referring to shown in attached drawing 7: excavating soil layer plate absolute altitude on earth downwards, be laid with bed course, waterproof layer, pour side wall and bottom plate knot Structure (16);Construction station internal structure, station main body civil construction are completed.
In the present embodiment, temporary construction vertical shaft and transverse passage-way can be excavated with construction site on ground, in the transverse passage-way of upper layer The small pilot tunnel in station is set, arch tube curtain (being divided into big pipe curtain tubule curtain by internal diameter difference) structure is set in lower layer's transverse passage-way, Laying freezing pipe forms the Frozen Soil Cylinder being used cooperatively with pipe curtain structure in pipe curtain.
In the present embodiment, this method is suitable for building for the buried Station of water rich strata, the tunneling vehicle in water rich strata It stands in construction process, can avoid influence of the Underground Construction to traffic above-ground and pipeline, while avoiding traditional subsurface excavation method station The larger bring groundwater treatment problem of buried depth.
In the present embodiment, big pipe curtain (5), tubule curtain (6) and Frozen Soil Cylinder (8) form domes can to resist foundation soil anti- Power and water buoyancy form closing water-stop curtain with water barrier and the lateral building enclosure of hidden digging structure (9), guarantee anhydrous job execution Condition.
In the present embodiment, it is not necessarily to ground artificial precipitation, by arranging freezing pipe (7) in pipe curtain, to pipe curtain week in construction Side rich water soil layer, which actively freezes, forms Frozen Soil Cylinder (8), forms closing water-stop curtain with the lateral building enclosure of hidden digging structure (9).
In the present embodiment, the small pilot tunnel in upper layer (4) is for the structures such as the lateral building enclosure in station (9), steel pipe column (10) of constructing; When the small pilot tunnel in upper layer (4) is located at water level line or less and is unable to dewatering construction, according to Practical Project using slip casting or freezing sealing Measure.
In the present embodiment, tubule curtain (6) is mainly arranged in arch structure span centre position, plays connection and intermal force, and diameter Meet construction personnel's working space requirement;Big pipe curtain (5) is used as arch structure fulcrum force, and also serve as hidden digging structure vertical applied force Member base, it is ensured that arch tube curtain structure forms complete structure stress system with tunneling main structure, guarantees structure safety, Its diameter need to meet foundation bearing capacity and construction personnel's working space requirement.
In the present embodiment, big pipe curtain (5) is used as vertical applied force member base, when foundation bearing capacity is unsatisfactory for requiring, in advance Injected hole is stayed, grouting and reinforcing is carried out to ground, improves foundation bearing capacity.
In the present embodiment, big pipe curtain (5) also serves as lateral building enclosure (9) strip footing and steel pipe as arch structure fulcrum again Strip footing under column (10) guarantees structural system integrality, while realizing underwater operating machine and melting digging.
It is described the invention in detail above by embodiment, but the content is only exemplary implementation of the invention Example, should not be considered as limiting the scope of the invention.Protection scope of the present invention is defined by the claims.All utilizations Technical solutions according to the invention or those skilled in the art are under the inspiration of technical solution of the present invention, in reality of the invention In matter and protection scope, designs similar technical solution and reach above-mentioned technical effect, or to made by application range All the changes and improvements etc. should still belong to patent of the invention and cover within protection scope.It should be noted that in order to clear It is stated, part and protection scope of the present invention is omitted in explanation of the invention without being directly significantly associated with but this field skill The statement of component known to art personnel and processing.

Claims (4)

1. anti-dash forward of one kind gushes back cover structure, which is characterized in that including lateral building enclosure (9), top beam (12), the lining knot of crown two Structure (14), in hardened structure (15), floor structure (16);
The two sides of the top beam (12) are respectively equipped with the small pilot tunnel in upper layer (4);Between the top beam (12) and top beam (12) It is connect between the small pilot tunnel in upper layer (4) by two lining structure of crown (14);The top fixation of two lining structure of crown (14) is set There is crown end bay just to prop up one (11), crown end bay just two (13) of branch;
Hardened structure (15), floor structure (16) in being successively arranged below two lining structure of crown (14), the floor structure (16) bottom end is equipped with multiple big pipe curtains (5);
The bottom end of the top beam (12) is equipped with steel pipe column (10);One end and top beam (12) of the steel pipe column (10) are fixed Connection, the other end sequentially pass through in hardened structure (15), floor structure (16) and be fixedly installed in big pipe curtain (5);
The bottom end of the small pilot tunnel in upper layer (4) is equipped with building enclosure (9);The both ends of the building enclosure (9) respectively with go along with sb. to guard him knot Structure (9), big pipe curtain (5) are fixedly connected;
It is equipped with multiple tubule curtains (6) between the adjacent big pipe curtain (5), is equipped with and freezes in each tubule curtain (6) It manages (7).
2. a kind of anti-dash forward according to claim 1 gushes back cover structure, which is characterized in that the big pipe curtain (5), tubule curtain (6) equal fill concrete in.
3. a kind of anti-dash forward according to claim 1 gushes back cover structure, which is characterized in that between multiple tubule curtains (6) Pass through connection bolt (17) connection.
4. anti-dash forward of one kind gushes back cover construction method, comprising the following steps:
Before the construction of water rich strata main body stage excavation, combined ground surrounding enviroment and station main structure, accessory structure form, Construction temporary construction vertical shaft (1) and upper layer occasional passage (2), lower layer's occasional passage (3);It is beaten in occasional passage (2) on upper layer If the small pilot tunnel in upper layer (4);Big pipe curtain (5), tubule curtain (6) are set along set contour line in lower layer's occasional passage (3);
Freezing pipe (7) are laid in tubule curtain (6), actively freeze to form Frozen Soil Cylinder (8);Under Frozen Soil Cylinder (8) supporting, Tubule curtain (6) internal openings set pipe interlude connection bolt (17), are fixedly connected with big pipe curtain (5);
Along the set contour line construction lateral building enclosure of tunneling (9) and steel pipe column (10) in the small pilot tunnel in upper layer (4);Wait excavate Big pipe curtain (5) top mark eminence, in the internal artificial aperture of big pipe curtain (5);In the big interior pouring construction bed course of pipe curtain (5), lifting is placed Lateral building enclosure (9), and timely casting concrete;
Construction skirt piles crown beam, the crown end bay for erecting the small pilot tunnel in upper layer (4) interior main arch just prop up one (11);Backfill the small pilot tunnel in upper layer (4) upper space;Slurry coat method in extraction in stake, manually installed steel pipe column locator, and according to the lifting of design merogenesis, peace Steel reinforcement cage in steel loading tubing string and steel pipe column;It is closely knit using coarse sand backfill between steel pipe column and steel pile casting;Construction top beam (12), and the splice that main arch two serves as a contrast is reserved, is laid with waterproof layer;
The main arch soil body is excavated, crown end bay is performed and just props up two (13);The small pilot tunnel in upper layer (4) abutment wall is removed paragraph by paragraph, is laid with waterproof layer, Formwork erection pours two lining structure of crown (14);
Continue to excavate soil layer board bottom absolute altitude into negative one layer downwards, entirely mould, be laid with waterproof layer, pour plate in negative one layer, in Beam hardened structure (15) in, station hall layer closing cyclization;Reserved reinforcing bar of plugging into bottom side wall;
Soil layer plate absolute altitude on earth is excavated downwards, is laid with bed course, waterproof layer, is poured side wall and floor structure (16);It constructs in station Portion's structure, station main body civil construction are completed.
CN201910078063.1A 2019-01-28 2019-01-28 Anti-surging bottom sealing structure and construction method Active CN109578014B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910078063.1A CN109578014B (en) 2019-01-28 2019-01-28 Anti-surging bottom sealing structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910078063.1A CN109578014B (en) 2019-01-28 2019-01-28 Anti-surging bottom sealing structure and construction method

Publications (2)

Publication Number Publication Date
CN109578014A true CN109578014A (en) 2019-04-05
CN109578014B CN109578014B (en) 2024-02-09

Family

ID=65917664

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910078063.1A Active CN109578014B (en) 2019-01-28 2019-01-28 Anti-surging bottom sealing structure and construction method

Country Status (1)

Country Link
CN (1) CN109578014B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109958443A (en) * 2019-04-30 2019-07-02 北京万兴建筑集团有限公司 The vertical shaft arranged side by side and its construction method secretly made in a kind of piping lane tunnel
CN110608047A (en) * 2019-08-30 2019-12-24 同济大学建筑设计研究院(集团)有限公司 Underpass subway supporting structure and manufacturing method thereof
CN113847040A (en) * 2021-12-02 2021-12-28 中国铁路设计集团有限公司 Large-span non-column underground station underground excavation construction method
CN114263215A (en) * 2021-12-21 2022-04-01 中铁十四局集团隧道工程有限公司 Construction method for building waterproof structure at storey-adding joint of subway station by combining open excavation and underground excavation

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102644466A (en) * 2012-04-27 2012-08-22 北京城建设计研究总院有限责任公司 Joist arching method for constructing ultra-shallow buried large-span underground excavated subway station in rocky stratum
CN204729099U (en) * 2015-07-13 2015-10-28 中铁第六勘察设计院集团有限公司 Rock quality layer tunneling three layers of subway station canopy structure
CN204941545U (en) * 2015-09-19 2016-01-06 中铁二十二局集团第一工程有限公司 Station boring construction system
WO2016095629A1 (en) * 2014-12-15 2016-06-23 中铁第四勘察设计院集团有限公司 Advanced support structure for oversized variable-cross-section tunnel
CN106337686A (en) * 2015-07-13 2017-01-18 中铁第六勘察设计院集团有限公司 Rock stratum underground excavation three-story subway station umbrella cover structure and construction method thereof
CN106703814A (en) * 2015-07-30 2017-05-24 宏润建设集团股份有限公司 Mined metro station hole pile construction method
CN106703828A (en) * 2017-01-22 2017-05-24 济南轨道交通集团有限公司 The construction method of building subway station with fabricated lining combination PBA
CN107218046A (en) * 2017-07-31 2017-09-29 北京市市政工程设计研究总院有限公司 Mechanical assistance sealing Station structure and construction method in a kind of pilot tunnel
CN108005664A (en) * 2018-02-02 2018-05-08 北京市政建设集团有限责任公司 A kind of hole pile construction method of platform structure
CN209430204U (en) * 2019-01-28 2019-09-24 中铁第六勘察设计院集团有限公司 Anti- dash forward of one kind gushes back cover structure

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102644466A (en) * 2012-04-27 2012-08-22 北京城建设计研究总院有限责任公司 Joist arching method for constructing ultra-shallow buried large-span underground excavated subway station in rocky stratum
WO2016095629A1 (en) * 2014-12-15 2016-06-23 中铁第四勘察设计院集团有限公司 Advanced support structure for oversized variable-cross-section tunnel
CN204729099U (en) * 2015-07-13 2015-10-28 中铁第六勘察设计院集团有限公司 Rock quality layer tunneling three layers of subway station canopy structure
CN106337686A (en) * 2015-07-13 2017-01-18 中铁第六勘察设计院集团有限公司 Rock stratum underground excavation three-story subway station umbrella cover structure and construction method thereof
CN106703814A (en) * 2015-07-30 2017-05-24 宏润建设集团股份有限公司 Mined metro station hole pile construction method
CN204941545U (en) * 2015-09-19 2016-01-06 中铁二十二局集团第一工程有限公司 Station boring construction system
CN106703828A (en) * 2017-01-22 2017-05-24 济南轨道交通集团有限公司 The construction method of building subway station with fabricated lining combination PBA
CN107218046A (en) * 2017-07-31 2017-09-29 北京市市政工程设计研究总院有限公司 Mechanical assistance sealing Station structure and construction method in a kind of pilot tunnel
CN108005664A (en) * 2018-02-02 2018-05-08 北京市政建设集团有限责任公司 A kind of hole pile construction method of platform structure
CN209430204U (en) * 2019-01-28 2019-09-24 中铁第六勘察设计院集团有限公司 Anti- dash forward of one kind gushes back cover structure

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109958443A (en) * 2019-04-30 2019-07-02 北京万兴建筑集团有限公司 The vertical shaft arranged side by side and its construction method secretly made in a kind of piping lane tunnel
CN109958443B (en) * 2019-04-30 2024-04-02 北京市市政工程设计研究总院有限公司 Parallel vertical shafts hidden in pipe gallery tunnel and construction method thereof
CN110608047A (en) * 2019-08-30 2019-12-24 同济大学建筑设计研究院(集团)有限公司 Underpass subway supporting structure and manufacturing method thereof
CN113847040A (en) * 2021-12-02 2021-12-28 中国铁路设计集团有限公司 Large-span non-column underground station underground excavation construction method
CN114263215A (en) * 2021-12-21 2022-04-01 中铁十四局集团隧道工程有限公司 Construction method for building waterproof structure at storey-adding joint of subway station by combining open excavation and underground excavation
CN114263215B (en) * 2021-12-21 2023-05-02 中铁十四局集团隧道工程有限公司 Construction method for building waterproof structure at storey-added connection part of subway station by combined excavation and excavation

Also Published As

Publication number Publication date
CN109578014B (en) 2024-02-09

Similar Documents

Publication Publication Date Title
CN102704957B (en) Shed-frame method for shallowly burying large-sized underground structure construction
CN101139838B (en) Construction method for high artesian area ultra-deep foundation pit
CN109578014A (en) Anti- dash forward of one kind gushes back cover structure and construction method
CN106150506B (en) A kind of entrance open excavation section inverted side-wall construction method
CN106907159A (en) A kind of Shallow Covered Metro Station separates open type structure and its construction method
CN106703828A (en) The construction method of building subway station with fabricated lining combination PBA
CN102363961A (en) Deepwater single-wall steel plate pile cofferdam structure with low buried depth and construction method thereof
CN110043264A (en) A kind of construction method of jacking prefabricated rectangle shaft structure pattern
CN106812542B (en) It is a kind of using prefabricated components and preceding slotting shield builds the construction method of subway station
CN106436720A (en) Small-size deep foundation pit supporting structure for pipe jacking construction
CN106988750A (en) The embodiment at existing station is worn under a kind of large span running tunnel super close distance
CN207063982U (en) Mechanical assistance sealing Station structure in a kind of pilot tunnel
CN108589771A (en) One kind having runed underground station increasing layer transfer node construction method
CN106049195A (en) Method for strengthening subgrade basement of existing high speed railway line
CN206888990U (en) A kind of Shallow Covered Metro Station separates open type structure
CN202401462U (en) Deep-water single-wall steel sheet pile cofferdam structure with small soil penetration depth
JP3908464B2 (en) Construction method of underwater tunnel
CN107829747B (en) Construction method suitable for shallow-buried underground excavation tunnel in expansive soil area
CN109339079A (en) A kind of foundation pit water-stopping system and its construction technology close to river permeable stratum
CN209430204U (en) Anti- dash forward of one kind gushes back cover structure
CN111101540B (en) Construction method for passing existing electric power tunnel on open cut tunnel
CN110486062B (en) Method for mechanically underground excavating multi-layer multi-span underground engineering in soft soil
CN209260739U (en) A kind of foundation pit water-stopping system close to river permeable stratum
CN206917655U (en) Pile foundation type bored tunnel in deep backfill
CN215165817U (en) Semi-covered excavation sequential city tunnel structure next to subway

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant