CN109958443A - The vertical shaft arranged side by side and its construction method secretly made in a kind of piping lane tunnel - Google Patents

The vertical shaft arranged side by side and its construction method secretly made in a kind of piping lane tunnel Download PDF

Info

Publication number
CN109958443A
CN109958443A CN201910359901.2A CN201910359901A CN109958443A CN 109958443 A CN109958443 A CN 109958443A CN 201910359901 A CN201910359901 A CN 201910359901A CN 109958443 A CN109958443 A CN 109958443A
Authority
CN
China
Prior art keywords
vertical shaft
tunnel
piping lane
pilot
shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910359901.2A
Other languages
Chinese (zh)
Other versions
CN109958443B (en
Inventor
杜建江
殷旭
臧洪全
王海波
祁璇
高东升
陈世会
孙大雷
吕爱华
赵国燕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing General Municipal Engineering Design and Research Institute Co Ltd
Original Assignee
BEIJING WANXING BUILDING GROUP CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING WANXING BUILDING GROUP CO LTD filed Critical BEIJING WANXING BUILDING GROUP CO LTD
Priority to CN201910359901.2A priority Critical patent/CN109958443B/en
Publication of CN109958443A publication Critical patent/CN109958443A/en
Application granted granted Critical
Publication of CN109958443B publication Critical patent/CN109958443B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D1/00Sinking shafts
    • E21D1/08Sinking shafts while moving the lining downwards
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D1/00Sinking shafts
    • E21D1/10Preparation of the ground
    • E21D1/16Preparation of the ground by petrification
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/04Lining shafts; Linings therefor with brick, concrete, stone, or similar building materials
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/06Lining shafts; Linings therefor with iron or steel
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/11Lining shafts; Linings therefor with combinations of different materials, e.g. wood, metal, concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D8/00Shafts not provided for in groups E21D1/00 - E21D7/00
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Abstract

The invention discloses the vertical shaft arranged side by side secretly made in a kind of piping lane tunnel and its construction methods, the vertical shaft arranged side by side secretly made in the piping lane tunnel includes multiple vertical shafts being set side by side, vertical shaft is down-set perpendicular to branch line piping lane tunnel axis from tunnel floor in the biggish water tank tunnel of main line Pipe rack space, including strengthened ring beam, shotcrete supporting steel grating structure and vertical shaft lateral type steel support structure, strengthened ring beam is embedded in advance on the main line piping lane tunnel floor in pit mouth portion.The invention has the following advantages that the vertical shaft for lower layer's branch line piping lane constructing tunnel is secretly made completely, do not need in addition to provide construction site, surrounding enviroment be influenced smaller;Shaft structure is arranged side by side, and the position of shaft excavation is also a part of lower layer's branch line piping lane tunnel structure;Since vertical shaft is located in main line piping lane tunnel, using piping lane tunnel as construction transverse passage-way, and if vertical shaft is individually arranged, need to be arranged construction transverse passage-way connection vertical shaft and branch line piping lane excavated surface.

Description

The vertical shaft arranged side by side and its construction method secretly made in a kind of piping lane tunnel
Technical field
The present invention relates to hypogee technical field of construction, in particular to the vertical shaft arranged side by side secretly made in a kind of piping lane tunnel and Its construction method.
Background technique
Currently, pipe gallery main line tunnel two sides generally require access branch line piping lane tunnel, it is therefore desirable to reserved branch spool Corridor interface.And branch line piping lane tunnel interface section generally all takes the form perpendicular to main line tunnel arrangement, when branch line piping lane tunnel When being arranged vertically below main line piping lane tunnel, need to provide vertical shaft for branch line piping lane constructing tunnel.It is multiple in surrounding enviroment condition In the case where miscellaneous, the position of branch line piping lane constructing tunnel vertical shaft cannot be often provided.
For this purpose, the invention patent proposes: in the main line piping lane water tank tunnel that excavation supporting and two lining constructions are completed, hanging down Block form vertical shaft directly is set in branch line pipe gallery tunnel axis.And it is opened on the side wall of vertical shaft two sides according to branch line piping lane tunnel Dig contour line, pre-buried strengthened ring beam, after carrying out strengthening supporting to well head, using secretly making block form vertical shaft as branch line piping lane tunnel Construction shaft.
Summary of the invention
Technical problem to be solved by the invention is to provide the vertical shafts and its construction party arranged side by side secretly made in a kind of piping lane tunnel Method secretly makees block form vertical shaft, as lower layer's branch twine helad using the upper layer main line piping lane tunnel that excavation supporting is completed in it Close the construction shaft in piping lane tunnel.
The technical problem to be solved by the present invention is to what is be achieved through the following technical solutions:
The vertical shaft arranged side by side secretly made in a kind of piping lane tunnel, including multiple vertical shafts being set side by side, the vertical shaft is in main line pipe It is down-set perpendicular to branch line piping lane tunnel axis from tunnel floor in the biggish water tank tunnel of corridor span, including strengthened ring beam, Shotcrete supporting steel grating structure and vertical shaft lateral type steel support structure, the strengthened ring beam are embedded in the main line pipe in pit mouth portion in advance On corridor tunnel floor.
Preferably, in above-mentioned technical proposal, the shotcrete supporting steel grating structure setting is used between adjacent vertical shaft Supporting.
Preferably, in above-mentioned technical proposal, the vertical shaft lateral type steel support structure is set to each individual vertical shaft It is interior.
Preferably, in above-mentioned technical proposal, the vertical shaft includes the first vertical shaft, third vertical shaft and is set to therebetween The second vertical shaft, shotcrete supporting steel grating structure at left and right sides of second vertical shaft respectively with first vertical shaft, described Three vertical shafts share.
Preferably, in above-mentioned technical proposal, the vertical shaft lateral type steel support structure is I22 α type steel support.
Preferably, in above-mentioned technical proposal, the width of the strengthened ring beam is 1300mm.
A kind of construction method for the vertical shaft arranged side by side secretly made in piping lane tunnel, comprising the following steps:
(1) three vertical shaft contour lines are marked in main line piping lane water tank tunnel floor, shaft structure is arranged side by side, intermediate vertical shaft and two Side vertical shaft shares shotcrete supporting steel grating structure in adjacent wall;
(2) when applying main line piping lane water tank tunnel double-lining, in tunnel floor position along the pre-buried strengthened ring beam of shaft perimeter, add Strong ring beam and the supervisor corridor tunnel double-lining bottom plate on periphery connect;
(3) excavation for first completing the first vertical shaft, third vertical shaft abolishes the supervisor corridor tunnel floor initial stage in two vertical shaft ring beams Supporting construction, the first Pin grid of construction shaft, and connect with main line piping lane water tank tunnel floor preliminary bracing, then adopt downwards Make shotcrete method for constructing construction shaft structure with using inverse;Slip casting ductule, which is set, in shaft wall during shaft excavation reinforces ground Layer, and fashioned iron is set up to support.
(4) after above-mentioned two shaft excavation on earth, ingate is opened in vertical shaft two sidewalls, construction enters branch line piping lane in order Tunnel applies branch line piping lane tunnel excavation support and two lining structures;
(5) after two lining structure concrete of 1-8 pilot tunnel reaches design strength, the second vertical shaft is excavated downwards.Using spray anchor Contrary sequence method excavates downwards the second vertical shaft;
(6) after the second vertical shaft back cover, ingate is opened in vertical shaft two sidewalls, enters the branch line piping lane tunnel of two sides in order Road carries out excavation supporting to branch line piping lane tunnel;
(7) after the 9-16 pilot tunnel of the second vertical shaft two sides all perforation, applying for two lining structures is carried out.
Preferably, in above-mentioned technical proposal, strengthened ring beam is reinforced concrete structure, the width 1300mm of ring beam section, Height is identical as two liner thickness degree of tunnel floor, is 350mm.
Preferably, in above-mentioned technical proposal, in the step (3), shaft wall grid Pin is away from 500-750mm.
Preferably, in above-mentioned technical proposal, the step of the construction in order of the step (4) are as follows:
41) ingate is opened from the first vertical shaft, third vertical shaft to side, excavates 1,2 pilot tunnels, be staggered 4-6m up and down;1, it leads for No. 2 After the perforation of hole, 3, No. 4 pilot tunnels are excavated, be staggered 4-6m up and down;
42) after the perforation of 1-4 pilot tunnel, ingate is opened from the first vertical shaft, third vertical shaft to the other side, 5, No. 6 pilot tunnels are wrong up and down Open 4-6m;After No. 7 pilot tunnels lag No. 5 pilot tunnel 10m, 7, No. 8 pilot tunnels are excavated, be staggered 4-6m up and down;
43) after 1-8 pilot tunnel all perforation, two lining structure of 1-8 pilot tunnel of constructing.
Preferably, in above-mentioned technical proposal, the supporting construction in the step (5) at left and right sides of the second vertical shaft is respectively at One vertical shaft, third vertical shaft share.
Preferably, in above-mentioned technical proposal, the step of the construction in order of the step (6) are as follows:
61) ingate is opened from the second vertical shaft to side, excavates 9,10 pilot tunnels, be staggered 4-6m up and down;9, No. 10 pilot tunnel perforations Afterwards, 11, No. 12 pilot tunnels are excavated, be staggered 4-6m up and down;
62) after the perforation of 9-12 pilot tunnel, ingate is opened from the second vertical shaft to the other side, be staggered 4-6m above and below 13, No. 14 pilot tunnels; After No. 15 pilot tunnels lag No. 13 pilot tunnel 10m, 15, No. 16 pilot tunnels are excavated, be staggered 4-6m up and down;
63) after 9-16 pilot tunnel all perforation, two lining structure of 9-16 pilot tunnel of constructing.
Above-mentioned technical proposal of the present invention, has the following beneficial effects:
(1) secretly make completely for the vertical shaft of lower layer's branch line piping lane constructing tunnel, do not need in addition to provide construction site, to week Surrounding environment influences smaller;
(2) shaft structure is arranged side by side, and the position of shaft excavation is also a part of lower layer's branch line piping lane tunnel structure.That is: Vertical shaft is both the construction channel in branch line piping lane tunnel and some of piping lane tunnel structure, reduces cost;
(3) since vertical shaft is located in main line piping lane tunnel, using piping lane tunnel as construction transverse passage-way, and if vertical shaft Individually arrangement then needs to be arranged construction transverse passage-way connection vertical shaft and branch line piping lane excavated surface.
Detailed description of the invention
Fig. 1 is the plan view for the vertical shaft arranged side by side secretly made in piping lane tunnel of the invention.
Fig. 2 is the vertical shaft lateral type steel support structure schematic diagram for the vertical shaft arranged side by side secretly made in piping lane tunnel of the invention.
Fig. 3 is the skiagraph for the vertical shaft arranged side by side secretly made in piping lane tunnel of the invention.
Fig. 4 is the sequence of excavation schematic diagram secretly made in piping lane tunnel of the invention.
Wherein: 1- strengthened ring beam, 2- shotcrete supporting steel grating structure, 3- vertical shaft lateral type steel support structure, 4- main line pipe Corridor tunnel, the first vertical shaft of 5-, the second vertical shaft of 6-, 7- third vertical shaft.
Specific embodiment
Specific embodiments of the present invention will be described in detail below, in order to further understand the present invention.
A kind of vertical shaft arranged side by side secretly made in piping lane tunnel, including multiple vertical shafts being set side by side, vertical shaft main line piping lane across It spends in biggish water tank tunnel, it is down-set perpendicular to branch line piping lane tunnel axis from tunnel floor, including strengthened ring beam 1, anchor Spray supporting steel grating structure 2 and vertical shaft lateral type steel support structure 3, strengthened ring beam 1 are embedded in the main line piping lane in pit mouth portion in advance On 4 bottom plate of tunnel.
Shotcrete supporting steel grating structure 2 is set between adjacent vertical shaft, is used for supporting.Vertical shaft lateral type steel support structure 3 are set in each individual vertical shaft.
The vertical shaft of the application includes the first vertical shaft 5, the second vertical shaft 6 and third vertical shaft 7, the second vertical shaft left and right sides Shotcrete supporting steel grating structure respectively with first vertical shaft, the third vertical shaft share.Certainly, the present invention not as Limit.
Preferably, vertical shaft lateral type steel support structure is I22 α type steel support.Preferably, the width of the strengthened ring beam is 1300mm。
A kind of construction method for the vertical shaft arranged side by side secretly made in piping lane tunnel, comprising the following steps:
(1) three vertical shaft contour lines are marked in main line piping lane water tank tunnel floor, shaft structure is arranged side by side, intermediate vertical shaft and two Side vertical shaft shares shotcrete supporting steel grating structure (Fig. 1, Fig. 2) in adjacent wall;
(2) when applying main line piping lane water tank tunnel double-lining, in tunnel floor position along the pre-buried strengthened ring beam of shaft perimeter, add Strong ring beam and the supervisor corridor tunnel double-lining bottom plate on periphery connect, and strengthened ring beam is reinforced concrete structure, the width of ring beam section 1300mm, it is highly identical as two liner thickness degree of tunnel floor, be 350mm (Fig. 3);
(3) excavation for first completing the first vertical shaft, third vertical shaft abolishes the supervisor corridor tunnel floor initial stage in two vertical shaft ring beams Supporting construction, the first Pin grid of construction shaft, and connect with main line piping lane water tank tunnel floor preliminary bracing, then adopt downwards Make shotcrete method for constructing construction shaft structure with using inverse, shaft wall grid Pin is away from 500-750mm;Perpendicular during shaft excavation Well side wall sets slip casting ductule strengthening stratum, and sets up fashioned iron to support.
(4) after above-mentioned two shaft excavation on earth, ingate is opened in vertical shaft two sidewalls, construction enters branch line piping lane in order Tunnel applies (Fig. 4) to branch line piping lane tunnel excavation support and two lining structures:
The step of constructing in order are as follows:
41) ingate is opened from the first vertical shaft, third vertical shaft to side, excavates 1,2 pilot tunnels, be staggered 4-6m up and down;1, it leads for No. 2 After the perforation of hole, 3, No. 4 pilot tunnels are excavated, be staggered 4-6m up and down;
42) after the perforation of 1-4 pilot tunnel, ingate is opened from the first vertical shaft, third vertical shaft to the other side, 5, No. 6 pilot tunnels are wrong up and down Open 4-6m;After No. 7 pilot tunnels lag No. 5 pilot tunnel 10m, 7, No. 8 pilot tunnels are excavated, be staggered 4-6m up and down;
43) after 1-8 pilot tunnel all perforation, two lining structure of 1-8 pilot tunnel of constructing;
(5) after two lining structure concrete of 1-8 pilot tunnel reaches design strength, the second vertical shaft is excavated downwards.Using spray anchor Contrary sequence method excavates downwards the second vertical shaft, and wall shares supporting construction respectively at No. 1, No. 3 vertical shafts at left and right sides of the second vertical shaft;
(6) after the second vertical shaft back cover, ingate is opened in vertical shaft two sidewalls, enters the branch line piping lane tunnel of two sides in order Road carries out excavation supporting (Fig. 4) to branch line piping lane tunnel:
The step of constructing in order are as follows:
61) ingate is opened from the second vertical shaft to side, excavates 9,10 pilot tunnels, be staggered 4-6m up and down;9, No. 10 pilot tunnel perforations Afterwards, 11, No. 12 pilot tunnels are excavated, be staggered 4-6m up and down;
62) after the perforation of 9-12 pilot tunnel, ingate is opened from the second vertical shaft to the other side, be staggered 4-6m above and below 13, No. 14 pilot tunnels; After No. 15 pilot tunnels lag No. 13 pilot tunnel 10m, 15, No. 16 pilot tunnels are excavated, be staggered 4-6m up and down;
63) after 9-16 pilot tunnel all perforation, two lining structure of 9-16 pilot tunnel of constructing;
(7) after the 9-16 pilot tunnel of the second vertical shaft two sides all perforation, applying for two lining structures is carried out.
Compared with prior art, the vertical folded vertical shaft knot arranged side by side fallen in tunneling pipe gallery tunnel proposed using invention Structure has the advantage that
(1) secretly make completely for the vertical shaft of lower layer's branch line piping lane constructing tunnel, do not need in addition to provide construction site, to week Surrounding environment influences smaller;
(2) shaft structure is arranged side by side, and the position of shaft excavation is also a part of lower layer's branch line piping lane tunnel structure.That is: Vertical shaft is both the construction channel in branch line piping lane tunnel and some of piping lane tunnel structure, reduces cost;
(3) since vertical shaft is located in main line piping lane tunnel, using piping lane tunnel as construction transverse passage-way, and if vertical shaft Individually arrangement then needs to be arranged construction transverse passage-way connection vertical shaft and branch line piping lane excavated surface.
Although the present invention is disclosed as above with embodiment, so it is not intended to limit the present invention, any those skilled in the art Member, without departing from the spirit and scope of the present invention, can make a variety of different selections and modification, therefore protection model of the invention It encloses and is limited by claims and its equivalents.

Claims (10)

1. the vertical shaft arranged side by side secretly made in a kind of piping lane tunnel, which is characterized in that including multiple vertical shafts being set side by side, the vertical shaft It is down-set perpendicular to branch line piping lane tunnel axis from tunnel floor in the biggish water tank tunnel of main line Pipe rack space, including Strengthened ring beam, shotcrete supporting steel grating structure and vertical shaft lateral type steel support structure, the strengthened ring beam are embedded in pit mouth in advance On the main line piping lane tunnel floor in portion.
2. the vertical shaft arranged side by side secretly made in piping lane tunnel according to claim 1, which is characterized in that the shotcrete steel grating branch Protection structure is set between adjacent vertical shaft, is used for supporting.
3. the vertical shaft arranged side by side secretly made in piping lane tunnel according to claim 1, which is characterized in that the vertical shaft transverse direction fashioned iron Support construction is set in each individual vertical shaft.
4. the construction method for the vertical shaft arranged side by side secretly made in piping lane tunnel according to claim 1, which is characterized in that described perpendicular Well includes the first vertical shaft, third vertical shaft and is set to the second vertical shaft between the two, the anchor at left and right sides of second vertical shaft Supporting steel grating structure is sprayed to share with first vertical shaft, the third vertical shaft respectively.
5. a kind of construction method for the vertical shaft arranged side by side secretly made in piping lane tunnel, which comprises the following steps:
(1) three vertical shaft contour lines are marked in main line piping lane water tank tunnel floor, shaft structure is arranged side by side, and intermediate vertical shaft and two sides are perpendicular Well shares shotcrete supporting steel grating structure in adjacent wall;
(2) when applying main line piping lane water tank tunnel double-lining, in tunnel floor position along the pre-buried strengthened ring beam of shaft perimeter, reinforcing ring Beam and the supervisor corridor tunnel double-lining bottom plate on periphery connect;
(3) excavation for first completing the first vertical shaft, third vertical shaft abolishes the supervisor corridor tunnel floor preliminary bracing in two vertical shaft ring beams Structure, the first Pin grid of construction shaft, and connect with main line piping lane water tank tunnel floor preliminary bracing, then adopt downwards Make shotcrete method for constructing construction shaft structure with inverse;Slip casting ductule strengthening stratum is set in shaft wall during shaft excavation, And fashioned iron is set up to support.
(4) after above-mentioned two shaft excavation on earth, ingate is opened in vertical shaft two sidewalls, construction enters branch line piping lane tunnel in order Road applies branch line piping lane tunnel excavation support and two lining structures;
(5) after two lining structure concrete of 1-8 pilot tunnel reaches design strength, the second vertical shaft is excavated downwards.Make using spray anchor is inverse The second vertical shaft is excavated under normal direction;
(6) after the second vertical shaft back cover, ingate is opened in vertical shaft two sidewalls, enters the branch line piping lane tunnel of two sides in order, it is right Branch line piping lane tunnel carries out excavation supporting;
(7) after the 9-16 pilot tunnel of the second vertical shaft two sides all perforation, applying for two lining structures is carried out.
6. the construction method for the vertical shaft arranged side by side secretly made in piping lane tunnel according to claim 5, which is characterized in that reinforcing ring Beam is reinforced concrete structure, and the width 1300mm of ring beam section is highly identical as two liner thickness degree of tunnel floor, is 350mm.
7. the construction method for the vertical shaft arranged side by side secretly made in piping lane tunnel according to claim 5, which is characterized in that the step Suddenly in (3), shaft wall grid Pin is away from 500-750mm.
8. the construction method for the vertical shaft arranged side by side secretly made in piping lane tunnel according to claim 5, which is characterized in that the step Suddenly the step of construction in order of (4) are as follows:
41) ingate is opened from the first vertical shaft, third vertical shaft to side, excavates 1,2 pilot tunnels, be staggered 4-6m up and down;1, No. 2 pilot tunnels pass through After logical, 3, No. 4 pilot tunnels are excavated, be staggered 4-6m up and down;
42) after the perforation of 1-4 pilot tunnel, ingate is opened from the first vertical shaft, third vertical shaft to the other side, be staggered 4- above and below 5, No. 6 pilot tunnels 6m;After No. 7 pilot tunnels lag No. 5 pilot tunnel 10m, 7, No. 8 pilot tunnels are excavated, be staggered 4-6m up and down;
43) after 1-8 pilot tunnel all perforation, two lining structure of 1-8 pilot tunnel of constructing.
9. the construction method for the vertical shaft arranged side by side secretly made in piping lane tunnel according to claim 5, which is characterized in that the step Suddenly the step of construction in order of (6) are as follows:
61) ingate is opened from the second vertical shaft to side, excavates 9,10 pilot tunnels, be staggered 4-6m up and down;9, it after No. 10 pilot tunnel perforations, opens 11, No. 12 pilot tunnels are dug, be staggered 4-6m up and down;
62) after the perforation of 9-12 pilot tunnel, ingate is opened from the second vertical shaft to the other side, be staggered 4-6m above and below 13, No. 14 pilot tunnels;No. 15 After pilot tunnel lags No. 13 pilot tunnel 10m, 15, No. 16 pilot tunnels are excavated, be staggered 4-6m up and down;
63) after 9-16 pilot tunnel all perforation, two lining structure of 9-16 pilot tunnel of constructing.
10. the construction method for the vertical shaft arranged side by side secretly made in piping lane tunnel according to claim 5, which is characterized in that described Shotcrete supporting steel grating structure at left and right sides of second vertical shaft is shared with first vertical shaft, the third vertical shaft respectively.
CN201910359901.2A 2019-04-30 2019-04-30 Parallel vertical shafts hidden in pipe gallery tunnel and construction method thereof Active CN109958443B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910359901.2A CN109958443B (en) 2019-04-30 2019-04-30 Parallel vertical shafts hidden in pipe gallery tunnel and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910359901.2A CN109958443B (en) 2019-04-30 2019-04-30 Parallel vertical shafts hidden in pipe gallery tunnel and construction method thereof

Publications (2)

Publication Number Publication Date
CN109958443A true CN109958443A (en) 2019-07-02
CN109958443B CN109958443B (en) 2024-04-02

Family

ID=67026792

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910359901.2A Active CN109958443B (en) 2019-04-30 2019-04-30 Parallel vertical shafts hidden in pipe gallery tunnel and construction method thereof

Country Status (1)

Country Link
CN (1) CN109958443B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111997618A (en) * 2020-07-16 2020-11-27 煤炭科学研究总院 Anti-seismic supporting structure of mine shaft

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0414599A (en) * 1990-05-07 1992-01-20 Taisei Corp Construction of branch section of underground level and construction method
JPH05187184A (en) * 1992-01-09 1993-07-27 Tokyo Electric Power Co Inc:The Structure for vertical shaft
JPH10131217A (en) * 1996-11-05 1998-05-19 Kajima Corp Underground structure such as shaft and construction method therefor
JP2001207774A (en) * 2000-01-26 2001-08-03 Mitsui Constr Co Ltd Shaft excavating method
JP2004019099A (en) * 2002-06-12 2004-01-22 Kajima Corp Construction method for intermediate shaft and intermediate shaft
CN103374915A (en) * 2012-04-27 2013-10-30 北京市政建设集团有限责任公司 Continuous closed hanging-upside-down shotcreting supporting system and construction method thereof
CN103939105A (en) * 2014-03-24 2014-07-23 中铁工程设计咨询集团有限公司 Construction method and structure for laying construction shaft above underground engineering
CN105350970A (en) * 2015-09-28 2016-02-24 北京城建道桥建设集团有限公司 Combined vertical shaft and construction method thereof
CN109578014A (en) * 2019-01-28 2019-04-05 中铁第六勘察设计院集团有限公司 Anti- dash forward of one kind gushes back cover structure and construction method
CN209924990U (en) * 2019-04-30 2020-01-10 北京万兴建筑集团有限公司 Concealed parallel vertical shaft in pipe gallery tunnel

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0414599A (en) * 1990-05-07 1992-01-20 Taisei Corp Construction of branch section of underground level and construction method
JPH05187184A (en) * 1992-01-09 1993-07-27 Tokyo Electric Power Co Inc:The Structure for vertical shaft
JPH10131217A (en) * 1996-11-05 1998-05-19 Kajima Corp Underground structure such as shaft and construction method therefor
JP2001207774A (en) * 2000-01-26 2001-08-03 Mitsui Constr Co Ltd Shaft excavating method
JP2004019099A (en) * 2002-06-12 2004-01-22 Kajima Corp Construction method for intermediate shaft and intermediate shaft
CN103374915A (en) * 2012-04-27 2013-10-30 北京市政建设集团有限责任公司 Continuous closed hanging-upside-down shotcreting supporting system and construction method thereof
CN103939105A (en) * 2014-03-24 2014-07-23 中铁工程设计咨询集团有限公司 Construction method and structure for laying construction shaft above underground engineering
CN105350970A (en) * 2015-09-28 2016-02-24 北京城建道桥建设集团有限公司 Combined vertical shaft and construction method thereof
CN109578014A (en) * 2019-01-28 2019-04-05 中铁第六勘察设计院集团有限公司 Anti- dash forward of one kind gushes back cover structure and construction method
CN209924990U (en) * 2019-04-30 2020-01-10 北京万兴建筑集团有限公司 Concealed parallel vertical shaft in pipe gallery tunnel

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
岳林祥;: "地下隧道施工竖井技术探讨", 山西水利, no. 02, pages 50 - 51 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111997618A (en) * 2020-07-16 2020-11-27 煤炭科学研究总院 Anti-seismic supporting structure of mine shaft
CN111997618B (en) * 2020-07-16 2022-03-15 煤炭科学研究总院有限公司 Anti-seismic supporting structure of mine shaft

Also Published As

Publication number Publication date
CN109958443B (en) 2024-04-02

Similar Documents

Publication Publication Date Title
CN210013697U (en) Construction structure of near-penetrating building of underground excavation section of subway station entrance and exit
CN110173267A (en) Building up station construction method is passed through in a kind of metro shield section
CN107905814B (en) Large span loess tunnel top bar CD construction method
CN107288642A (en) PBA construction technologies
CN110159298A (en) A kind of first branch button arch construction method of Underground Subway Station
CN110318418A (en) A kind of open cut underground station strip accessory structure construction method
CN105862930A (en) Protection structure on existing tunnel below new underground engineering
CN110424454A (en) Build together method and the structure of building together of pipe gallery and subway station
CN106758890B (en) Campshed box culvert structure and its construction method
CN108412502A (en) A kind of deep tunnel passes through upper-soft lower-hard ground construction method
CN108756897B (en) A kind of construction method of breaking surrounding rock people's air defense tunnel cross point
CN105862912B (en) A kind of agent on crack resistance of concrete sliding pile panelling construction method
CN109958443A (en) The vertical shaft arranged side by side and its construction method secretly made in a kind of piping lane tunnel
CN107246014A (en) Detachable foundation pit trestle system and its construction method
CN104963693B (en) Rectangular parallel push pipe connection channel construction method
CN109973115A (en) A kind of construction method of karst area tunnel vault draining
CN207033463U (en) Mine shield handing-over tunnel folded type joint design in the middle part of marine site
CN106948350B (en) The rapid constructing method of deep basal pit accessory structure
CN108951647A (en) Construction method for supporting is excavated in hole in the hole of open trench tunnel
CN110359495A (en) Comprehensive pipe gallery structure seam construction and its construction method
CN107574836A (en) Cross the constructing structure and construction method of urban road underpass
CN107558477A (en) The supporting construction and construction method that a kind of foundation ditch is combined with side slope
CN107191206A (en) A kind of step construction method of Shallow-buried Large-span Tunnel Unit two six
CN110005416A (en) A kind of branch line piping lane tunnel interface section constructing method
CN106677795B (en) Border on the sea high hydraulic pressure tunnel single layer steel plate concrete composite lining structure and mounting process

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Zheng Zhibin

Inventor after: Wang Miao

Inventor after: Liu Kai

Inventor after: Yang Mingchao

Inventor after: Zhitanyun

Inventor after: Li Minggan

Inventor after: Yan Chaotao

Inventor after: Qiu Jing

Inventor after: Wang Chenxiao

Inventor after: Gao Biao

Inventor after: Jiang Linlin

Inventor after: Cluster rock

Inventor after: Jiang Naiqian

Inventor before: Du Jianjiang

Inventor before: Zhao Guoyan

Inventor before: Yin Xu

Inventor before: Zang Hongquan

Inventor before: Wang Haibo

Inventor before: Qi Xuan

Inventor before: Gao Dongsheng

Inventor before: Chen Shihui

Inventor before: Sun Dalei

Inventor before: Lv Aihua

TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20211109

Address after: 100082, building 32, No. 3 North Main Street, Haidian District, Beijing, Xizhimen

Applicant after: BEIJING GENERAL MUNICIPAL ENGINEERING DESIGN & RESEARCH INSTITUTE Co.,Ltd.

Address before: 100026 Building 1, yard 5, Jingkai Xingwei West Road (Xingfeng section), Daxing District, Beijing

Applicant before: BEIJING WAN XING BUILDING GROUP Co.,Ltd.

GR01 Patent grant
GR01 Patent grant