CN102776878A - Construction method for preventing diaphragm wall from streaming - Google Patents

Construction method for preventing diaphragm wall from streaming Download PDF

Info

Publication number
CN102776878A
CN102776878A CN201210292842XA CN201210292842A CN102776878A CN 102776878 A CN102776878 A CN 102776878A CN 201210292842X A CN201210292842X A CN 201210292842XA CN 201210292842 A CN201210292842 A CN 201210292842A CN 102776878 A CN102776878 A CN 102776878A
Authority
CN
China
Prior art keywords
iron
sand
bags
filled
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201210292842XA
Other languages
Chinese (zh)
Inventor
鲍俊捷
索晓华
卢志军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fifth Engineering Co Ltd of CTCE Group
Original Assignee
Fifth Engineering Co Ltd of CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fifth Engineering Co Ltd of CTCE Group filed Critical Fifth Engineering Co Ltd of CTCE Group
Priority to CN201210292842XA priority Critical patent/CN102776878A/en
Publication of CN102776878A publication Critical patent/CN102776878A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

A construction method for preventing diaphragm wall from streaming comprises the following steps of: filling a plurality of sand bags behind an I-beam of a primary slot section, wherein the sand bags are small-volume normal woven bags filled with 1/3 volume of sand, bag mouths are tied firmly and the bags are paved, the sand in the bags are loose, and the bags are arranged behind the I-beam, and beaten and compacted by a steel box hammer so that the sand bags are filled behind the I-beam completely; repeating the operation till the whole process is finished; and taking out the filled sand bags when drilling during a secondary slot section. With the adoption of the method, the purpose of tight connection between the concrete of the secondary slot section and the I-beam joint in the diaphragm wall construction is achieved. The construction method has the characteristics of being convenient in construction and easy in operation, the streaming of concrete is avoided, the concrete of the secondary slot section is tightly combined with the I-beam joint, and the water leakage rate of the underground diaphragm wall is reduced.

Description

A kind of ground-connecting-wall prevents the job practices of streaming
Technical field
This patent relates to a kind of ground-connecting-wall and prevents the job practices of streaming.
Background technology
The city underground deep foundation ditch is under complicated weak soil geological conditions, and space enclosing structure adopts ground-connecting-wall to add the inner supporting structure system more.The ground-connecting-wall joint style is adopted as the fore shaft union more and i iron connects first two.But in rich groundwater and the high zone of artesian water; The ground-connecting-wall joint style adopts the i iron joint more, and the i iron joint welds with reinforcing cage before install reinforcing cage, to the processing of i iron joint area; Great majority all adopt adapter plate now, and the shortcoming of this way construction is:
Generally all can backbreak when (1) grabbing groove, the width of grabbing groove is greater than design width, but the adapter plate width is general identical with groove section design width, can't block concrete fully and flow to the second stage of groove section;
(2) in the work progress, the adapter plate position width of need backbreaking.
If it is not in place that this is managed everywhere; First phase groove section " is streamed " when concreting to not constructing the second stage of groove fragment position; Brush wall device can't brush the foreign material in concrete that streams and the i iron joint totally when causing the second stage of groove section grooving; The concrete of the second stage of groove section is combined closely with the i iron joint, thereby cause ground-connecting-wall joint percolating water, bring hidden danger for follow-up construction quality and foundation ditch safety.
Summary of the invention
Its purpose of the present invention just is to provide a kind of ground-connecting-wall to prevent the job practices of streaming, thereby has solved the concrete and the compact problem of i iron joint of the second stage of groove section in the ground-connecting-wall construction.Have easy construction, easy-operating characteristics, and stopped concrete " streaming ", the concrete of the second stage of groove section is combined closely with the i iron joint, reduce the probability of diaphragm wall percolating water.Can be widely used among the diaphragm wall i iron joint construction technology.
The technical scheme that realizes above-mentioned purpose and take comprises that throw the back-up sand earth bag behind at the i iron of first phase groove section, said sandy soil bag is that little volume is common bag weaved; Adorn the sand of 1/3 volume, the sack colligation is firm, pave; The inside is loose shape, is invested in i iron back, rams closely knit with steel case hammer; Make it be filled in i iron back fully, repeat aforesaid operations, until whole completion; Carrying out the second stage of groove section when grabbing groove, the sandy soil bag that throwing is filled out with cubic metre of earth grab out jointly.
Compared with prior art the present invention has the following advantages.
Throw the construction technology of back-up sand earth bag behind owing to having adopted, thereby solved the concrete and the compact problem of i iron joint of the second stage of groove section in the ground-connecting-wall construction at the i iron of first phase groove section.Have easy construction, easy-operating characteristics, and stopped concrete " streaming ", the concrete of the second stage of groove section is combined closely with the i iron joint, reduce the probability of diaphragm wall percolating water.
Description of drawings
Below in conjunction with accompanying drawing the present invention is made further detailed description.
Fig. 1 is for throwing back-up sand earth bag position view among the present invention.
Fig. 2 is steel element structure schematic front view among the present invention.
Fig. 3 is the vertical view of Fig. 2.
Fig. 4 is the lateral view of Fig. 2.
The specific embodiment
Said job practices comprises, and is as shown in Figure 1, throws back-up sand earth bag 1 behind at the i iron 2 of first phase groove section, and said sandy soil bag 1 is that little volume is common bag weaved; Adorn the sand of 1/3 volume, the sack colligation is firm, pave; The inside is loose shape, is invested in i iron 2 back, rams closely knit with steel case hammer; Make it be filled in i iron back fully, repeat aforesaid operations, until whole completion; Carrying out the second stage of groove section when grabbing groove, the sandy soil bag that throwing is filled out takes out.
Said i iron is provided with the steel member, and like Fig. 2,3, shown in 4, wire rope and snap close are put in the overpunching of said steel member; Draw-in groove 4 is adopted in the bottom, this member is stuck on the i iron of reinforcing cage, is used to confirm to fill out the accurate position of sandbag, prevents that sandbag from inserting in the reinforcing cage 3; Ground-connecting-wall under water concrete build finish after, this steel member is hung out.
Embodiment
I iron in first phase groove section is thrown the back-up sand earth bag behind, utilizes cuboid steel case hammer to ram closely knit then.See that (Fig. 1) throws and fill out sandy soil bag position view.
Because the position that ground-connecting-wall top mark height generally at below ground, is thrown when filling out the sandy soil bag is difficult to control, therefore; Need processing one to have the i iron steel member of draw-in groove; Be connected on the i iron of ground-connecting-wall reinforcing cage 3,, put on wire rope and snap close in this member overpunching; Draw-in groove is adopted in the bottom, and this member is stuck on the reinforcing cage i iron.Ground-connecting-wall under water concrete build finish after, this i iron steel member is taken out.See (Fig. 2,3,4) i iron draw-in groove steel member.
The sandy soil bag adopts little volume common bag weaved, adorns the sand of 1/3 volume, and the sack colligation is firm, paves, and the inside is loose shape, is invested in i iron back.When throwing in for the first time about 2 meters of the degree of depth, ram closely knitly with the crane whereabouts of slinging, make it be filled in i iron back fully with cuboid steel case hammer.Repeat aforesaid operations, until whole completion.Carrying out the second stage of groove section when grabbing groove, the sandy soil bag that throwing is filled out with cubic metre of earth grab out jointly.

Claims (2)

1. the job practices that ground-connecting-wall prevents to stream is characterized in that, said job practices comprises, throws back-up sand earth bag (1) behind at the i iron (2) of first phase groove section; Said sandy soil bag is that little volume is common bag weaved, adorns the sand of 1/3 volume, and the sack colligation is firm, paves; The inside is loose shape, is invested in i iron (2) back, rams closely knit with steel case hammer; Make it be filled in i iron back fully, repeat aforesaid operations, until whole completion; Carrying out the second stage of groove section when grabbing groove, the sandy soil bag that throwing is filled out is grabbed out together with the earthwork.
2. a kind of ground-connecting-wall according to claim 1 prevents the job practices of streaming to it is characterized in that said i iron (2) is provided with the steel member that wire rope and snap close are put in the overpunching of said steel member; Draw-in groove (4) is adopted in the bottom, and this member is stuck on the i iron, is used to confirm to fill out the accurate position of sandbag, prevents that sandbag from inserting in the reinforcing cage; Ground-connecting-wall under water concrete build finish after, this steel member is hung out.
CN201210292842XA 2012-08-17 2012-08-17 Construction method for preventing diaphragm wall from streaming Pending CN102776878A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210292842XA CN102776878A (en) 2012-08-17 2012-08-17 Construction method for preventing diaphragm wall from streaming

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210292842XA CN102776878A (en) 2012-08-17 2012-08-17 Construction method for preventing diaphragm wall from streaming

Publications (1)

Publication Number Publication Date
CN102776878A true CN102776878A (en) 2012-11-14

Family

ID=47121974

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210292842XA Pending CN102776878A (en) 2012-08-17 2012-08-17 Construction method for preventing diaphragm wall from streaming

Country Status (1)

Country Link
CN (1) CN102776878A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103031854A (en) * 2012-12-07 2013-04-10 广东省基础工程公司 Method for reducing concrete diffusion of continuous wall
CN104790430A (en) * 2015-04-13 2015-07-22 上海远方基础工程有限公司 Underground diaphragm wall construction method
CN110258522A (en) * 2019-06-26 2019-09-20 中国电建集团成都勘测设计研究院有限公司 The closed ground-connecting-wall for protruding into basement rock encloses well construction

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07216872A (en) * 1994-02-09 1995-08-15 Kajima Corp Horizontal reinforcement joint structure for underground continuous wall
CN101205717A (en) * 2006-12-18 2008-06-25 上海华瀛建筑科技有限公司 Ultra-deep underground continuous wall connector
CN101858090A (en) * 2010-06-23 2010-10-13 天津深基工程有限公司 Construction method for soft connection of diaphram wall rigid joints
CN102444144A (en) * 2011-09-28 2012-05-09 广东省基础工程公司 Device preventing concrete from streaming for I-shaped steel joint of diaphragm wall
CN102535519A (en) * 2012-03-20 2012-07-04 广州中煤江南基础工程公司 I-shaped steel joint structure for underground continuous wall and construction method for I-shaped steel joint structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07216872A (en) * 1994-02-09 1995-08-15 Kajima Corp Horizontal reinforcement joint structure for underground continuous wall
CN101205717A (en) * 2006-12-18 2008-06-25 上海华瀛建筑科技有限公司 Ultra-deep underground continuous wall connector
CN101858090A (en) * 2010-06-23 2010-10-13 天津深基工程有限公司 Construction method for soft connection of diaphram wall rigid joints
CN102444144A (en) * 2011-09-28 2012-05-09 广东省基础工程公司 Device preventing concrete from streaming for I-shaped steel joint of diaphragm wall
CN102535519A (en) * 2012-03-20 2012-07-04 广州中煤江南基础工程公司 I-shaped steel joint structure for underground continuous wall and construction method for I-shaped steel joint structure

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103031854A (en) * 2012-12-07 2013-04-10 广东省基础工程公司 Method for reducing concrete diffusion of continuous wall
CN104790430A (en) * 2015-04-13 2015-07-22 上海远方基础工程有限公司 Underground diaphragm wall construction method
CN104790430B (en) * 2015-04-13 2016-06-29 上海远方基础工程有限公司 Construction method of underground continuous wall
CN110258522A (en) * 2019-06-26 2019-09-20 中国电建集团成都勘测设计研究院有限公司 The closed ground-connecting-wall for protruding into basement rock encloses well construction

Similar Documents

Publication Publication Date Title
CN106759473B (en) The constructing structure and its construction method of underground pipe gallery and road
AU2018102180A4 (en) Anti-clogging strengthened permeable pile and construction method
CN102505704A (en) Large open caisson construction method in soft geological shaft
CN109487807A (en) A kind of steel pipe pile cofferdam pilot hole altering fill method
CN105239598A (en) Integral sinking construction method for well-type full-automatic stereo garage
CN103696784A (en) Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
CN108316339A (en) A kind of construction method of water penetration geology large size arch bridge base
CN108532586A (en) A kind of construction method of garage parking diaphram wall
CN110318410A (en) A kind of deep basal pit chance artesian water is prominent to gush decompression drought stress construction method
CN103953030B (en) The compacted castinplace pile of screw thread supination joint bar
CN102535490A (en) Method for dewatering foundation pit by using bored cast-in-place pile
CN109519150A (en) One kind being directed to the biggish plugging dewatering well device and method of water yield
CN113174958A (en) Construction method for foundation pit of adjacent road under poor ground condition
CN104532853A (en) Deep foundation pit supporting method and system characterized by steel reinforced cement-soil piles, bolts easy to detach and automatic monitoring and early warning
CN102776878A (en) Construction method for preventing diaphragm wall from streaming
CN104947648A (en) Deep replacement dynamic compaction gravel pile foundation reinforcement method
CN101591906A (en) The method for processing foundation of intubate, multipass vacuum well-point dewatering dynamic consolidation
CN106869153B (en) A kind of method of the quick soft soil foundation treatment of well-points dewatering
CN109441355A (en) Silt or sand bed pipe well high pressure water flushing fast pore-creating construction method
CN203729309U (en) Support system with combined double-row piles combined with vertical prestressed anchor bolts
CN101280561B (en) Method for making composite type pile body suitable for special formation
CN107268603A (en) The karst cave treatment structure and processing method of a kind of diaphram wall
CN111549789A (en) Reinforcing structure for foundation pit support and construction method thereof
CN103015435A (en) Long auger down hole hammer vibration rotary-jet steel reinforced cement-soil pile foundation pit water-resisting and supporting method
CN109778837A (en) Cast-in-place ground-connecting-wall adjacent slot section I-shaped steel joint sand pocket device and its application method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20121114