CN109441355A - Silt or sand bed pipe well high pressure water flushing fast pore-creating construction method - Google Patents

Silt or sand bed pipe well high pressure water flushing fast pore-creating construction method Download PDF

Info

Publication number
CN109441355A
CN109441355A CN201910005842.9A CN201910005842A CN109441355A CN 109441355 A CN109441355 A CN 109441355A CN 201910005842 A CN201910005842 A CN 201910005842A CN 109441355 A CN109441355 A CN 109441355A
Authority
CN
China
Prior art keywords
well
well casing
water
pipe
casing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910005842.9A
Other languages
Chinese (zh)
Inventor
朱涛
王旭升
宋成功
巩龙龙
戴强
李国海
刘康
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI HYDRAULIC ENGINEERING GROUP Co Ltd
Original Assignee
SHANGHAI HYDRAULIC ENGINEERING GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI HYDRAULIC ENGINEERING GROUP Co Ltd filed Critical SHANGHAI HYDRAULIC ENGINEERING GROUP Co Ltd
Priority to CN201910005842.9A priority Critical patent/CN109441355A/en
Publication of CN109441355A publication Critical patent/CN109441355A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/18Drilling by liquid or gas jets, with or without entrained pellets
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/20Driving or forcing casings or pipes into boreholes, e.g. sinking; Simultaneously drilling and casing boreholes

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

Silt or sand bed pipe well high pressure water flushing fast pore-creating construction method, using high pressure water flushing brush dust sandy soils pore-forming, with punching speed underthrust, pore-forming is synchronous with down tube process to carry out well casing (1);Construction is successively comprising steps of filtrate, shut-in well, well-flushing, lower pump between preparation of construction, construction lofting, excavation sand discharge pond and well head, vertical well casing, turn on pump water spray, well casing underthrust-adapter tube, termination of pumping backfill well casing and hole wall try to draw water;Spray head quantity can be increased or decreased according to pipe well sectional dimension size, be suitable for large, medium and small all kinds of pipe wells.The average 6m achievable per hour of deep-well construction is carried out in silty strata, reduces construction period.Reduce the cost of silty strata deep-well construction.Easy to operate needs manual operation, does not need biggish working face and construction material requested and equipment volume, lighter in weight can manually carry, reduce influence of the place to construction.The construction area being difficult to enter suitable for mechanical equipments such as dell, slopes.Reduce technical management cost.

Description

Silt or sand bed pipe well high pressure water flushing fast pore-creating construction method
Technical field
The present invention relates to IPC classification E21B soil layer or the drilling technology of rock, especially silts or sand bed pipe well high pressure water Rush fast pore-creating construction method.
Background technique
Pipe well is the water intaking for being vertically disposed on underground or the tubulose structures for protecting underground water.Pipe well hole diameter is smaller, well depth It is larger, draw the intake structure of deep layer or phreatic water.The pipe well for squeezing into artesian aquifer, when as above ground level such as head, Also known as artesian well.
Light well point is a kind of dewatering process to be drawn water using vacuum pump, generallys use high pressure water punching method pore-forming, pitch-row Generally 1.2m.It is inserted into light-duty well casing in hole, encloses and fills out filtrate.Light-duty well casing connects vacuum gas bag by water header, leads to Often with 20~30m root for one group.It is limited by the vacuum mechanism that draws water, light well point depth of effectively drawing water is about 5m, be can be used more The mode of grade precipitation increases depth of drawing water.Application of light well point precipitation effect is reliable, but single-stage precipitation depth is restricted, and is chiefly used in slope The excavation slope of excavation is stablized.
Ejector well point is to spray high speed in well casing by pipe-line system using high-pressure hydraulic pump or pressure-air as power source Water flow, high speed water flow form instantaneous vacuum when passing through injector, underground water are sucked out.Ejector well point theory precipitation depth is most Big reachable 20m, in actual application, due to the influence of well damage, ejector well point precipitation depth is usually no more than 15m.Injection After the deficiency of well point is long-time precipitation, nozzle is easily damaged, and ejector well point can not work normally, and high-pressure hydraulic pump is caused to spray High-velocity flow flow backward.
Patents documents disclose less.
The Chinese patent application 201110025209.X that Huizhou Hydropower Construction Co., Ltd. proposes discloses a kind of light Type well-point dewatering construction technique, first using general geology drilling machine after mud off drilling and forming hole, installation screen pipe forms pipe well, It is rinsed in screen pipe using high-pressure water jet again, destroys slurry coat method structure sheaf, and make screen pipe pipe week self-forming filter layer, Then the outlet pipe that front end is equipped with immersible pump is set in screen pipe, finally starts immersible pump and realizes well-points dewatering;Pipe well is straight Diameter is less than or equal to 200mm, and pipe well spacing is 3~10m, is additionally provided with return pipe on outlet pipe.The present invention is light-duty in tradition It is improved on the basis of well-points dewatering, by adjusting drilling machine, the diameter of pipe well and well spacing, pipe well is at well technology, together When combine and adjust flow control and draw water technology, not only obtain good dewatering effect, and conveniently moving, speed of application are fast, shadow Ring range it is small, it is energy saving, be convenient to mount and dismount, the foundation pit for being applicable to the middle or small depth natural discharging slope of weak~highly permeable soil layer is opened It digs.
The Chinese patent application 201210063435.1 that Zhongtian Construction Group Co., Ltd. proposes provides a kind of bath brill Head, including equally distributed four tops the going out equipped with apopore for being located at the steel pipe that catchments in center, being located at steel pipe surrounding of catchmenting Water steel pipe is connected at least one water inlet steel pipe to catchment on steel pipe, described to catchment between steel pipe and water outlet steel pipe by dividing water The fixed connection of steel pipe.It need to only cooperate high-pressure hydraulic pump pressurization to send water, can drill by well is accomplished manually, it is simple to operate, At low cost, speed of fulfiling hole is fast, and flushing drill bit need to only be made of common steel tube, can be made according to the diameter of pipe well, It is convenient and efficient.
The Chinese patent application 201820214184.5 that Hangzhou Municipal Engineering Group Co., Ltd. proposes discloses one kind The fast pore-creating device of sandy soil dewatering well, it includes bracket, connection frame and drill bit, and bracket includes three support rods, three branch The first fixed ring and the second fixed ring are separately connected on strut, drill bit is connect by connecting rod with three support rods, and drill bit is by drill bit Set and water injection head connect and compose, and water injection head upper end connects high-pressure hydraulic pump by water pipe, and connection frame includes connecting rod and connection Head connects and composes, and connecting rod bottom is weldingly fixed on corresponding support rod by connecting rod, attended operation mechanism at the top of connector. The present invention is sprayed by water pipe from water injection head by using above-mentioned technology, high-pressure hydraulic pump water outlet, is impacted using the impact force of water Soil layer realizes fast pore-creating process, and there is structure to be simple and convenient to operate, is time saving and energy saving, and pore-forming efficiency is high, hole quality is good, Cost is reduced, especially suitable for pipe well pore-forming under flour sand geological conditions, and repeatable recycling.
In addition, dewatering project refers to applied hydrogeology principle, by dewatering design and dewatering construction, surface water is excluded The levels of ground water such as perched water, diving, artesian water, basement rock water, karst water in body and reduction stratum, the precipitation for meeting engineering are deep The requirement of degree and precipitation time, and on the inert influence of engineering-environment, it includes construction and body of precipitation work system Operating two parts of system.Its method can be divided into light well point method, ejector well point method, electro-osmosis well point method, pipe well points method and great Kou Well, width penetrate the methods of well, sometimes for the special requirement of engineering, can also build relief well, inverted well etc..This standard only relates to gently Type well-points dewatering and pipe well points precipitation.Wherein, be related to Application of light well point precipitation in pipe well points dewatering construction technical standard to Water punching perforation engineering method, including guide rod type water jetting and casing water jetting are gone out.Wherein, in guide rod type water jetting, one is vibrations Formula guide rod water jetting, one is rotary guide rod water jettings of breaking ground.Guide rod is the steel pipe of diameter 100mm or 150mm, pipe outside weld Two water washing pipes, top are plate vibrator.After water rushes rifle punching to projected depth, guide rod is extracted, well casing is put into.Wherein, it covers Pipe water jetting rushes rifle pore-forming using sleeve water, and casing is made of the common steel tube of 200mm.When pore-forming, casing hydraulic giant is with high pressure water Soil layer is impacted, to select working water pressure, generally 0.8~0.9Mpa according to different soil conditions.
After punching to projected depth, 1mm more deep than planned well or so, a period of time is rinsed in Yao Jixu water supply, makes to return The water clay content come is 5% or so.After reaching requirement, first Xiang Kongzhong fills out a small amount of sand, is put into well casing into casing again, in order to avoid well casing It is inserted into soil.It fills out gravel and should divide and complete several times, in order to avoid pull out casing difficulty.
No matter tube well dewatering is widely used in house construction engineering, hydraulic engineering, municipal works etc..Traditional mechanical hole building Construction technology directly need to make mud off in silt or the construction of sand bed geology and be also easy to produce the quality safeties such as collapse hole, drilling machine inclination Accident and speed of fulfiling hole is slow, hole quality is poor, long construction period, construction investment it is big the disadvantages of.To the duration of project subject construction And safety has large effect.
Summary of the invention
The object of the present invention is to provide silt or sand bed pipe well high pressure water flushing fast pore-creating construction methods, solve traditional machine Tool construction method directly need to make mud off in the construction of silt sand bed geology and be also easy to produce the quality such as collapse hole, drilling machine inclination Safety accident, and the difficult points such as speed of fulfiling hole is slow, hole quality is poor.
The purpose of the present invention will be realized by following technical measures: use high pressure water flushing brush dust sandy soils pore-forming, well casing With punching speed underthrust, pore-forming is synchronous with down tube process to be carried out;Construction method successively includes construction procedure: preparation of construction, construction Setting-out is excavated between sand discharge pond and well head, vertical well casing, turn on pump water spray, well casing underthrust-adapter tube, termination of pumping backfill well casing and hole wall Filtrate, shut-in well, well-flushing, the examination of lower pump are drawn water;Wherein:
Preparation of construction includes: the selection of pipe, well casing back cover, tube wall aperture, Dense mesh screen winding, spray head installation, high-pressure hydraulic pump Pipeline inspection, measuring well location;Excavate sand discharge pond and well head;Vertical well casing;Turn on pump water spray;Well casing underthrust;Adapter tube;Termination of pumping backfills well Gravel packing between pipe and hole wall;Shut-in well;Well-flushing;Lower pump tries dewatering well normal work of drawing water.
Excavate sand discharge pond and well head: sand discharge pond excavation volume should be greater than 5 times of wellhole volume and be not easy apart from well head distance More than 10m, silt easily blocks sand discharge ditch too far in sand discharge pond.
Vertical well casing: well casing is placed on the well head dug in advance vertically, and with two-way vertical line, visual angle is at 90 DEG C of angles, sighting tube Body outer contour pops up center line in pipe shaft in advance, guarantees two-way deviation within specification tolerance.Because of well casing underthrust By manual control, verticality is difficult to control, so using theodolite moment observation pipe shaft verticality and continuous during down tube Correction.
Turn on pump water spray: high-pressure hydraulic pump should be opened after well casing is vertical toward spray head conveying high-pressure water.Original place is answered to spray after spray head water outlet Water 30S, makes silty strata be in saturated-water phase as far as possible, and may be sprayed water according to chiltern difference will voluntarily sink less than 30S well casing.
Well casing underthrust: well casing underthrust should select and appoint 3 workers to be divided into 3 directions and keep pipe shaft verticality and apply downwards to well casing Plus-pressure.It should suitably be downwardly applied to pressure in well casing down process, force well casing with the slow underthrust of speed of sand washing.If in underthrust Well casing can be pulled and pushed up and down by the sufficient flush pipe bottom silt layer of sand of high pressure water by larger resistance until well casing bottom reaches in the process To setting elevation.
Water pump should run without interruption in pore forming process, verified punching water pump stopping water spray in pore forming process on the spot and be more than 30S, silt may back-silt, and lead to 1 wall of well casing and hole wall back-silts closely knit can not continue underthrust.
Adapter tube: the well depth that deep-well precipitation uses is usually more than 8m, and the well casing length of market routine is 6m, and works as well casing length Pipe shaft verticality is manually difficult to keep when more than 6m, so the mode that adapter tube can be used increases well depth.Well casing adapter tube uses socket joint Formula structure, because bell and spigot joint is more weak, for avoid joint flex cause borehole inclination bending even can not the quality such as underthrust ask The bending resistance that intensity biggish bar material such as reinforcing bar, angle bar etc. is attached to bell and spigot joint position enhancing well casing connector can be used in topic Ability.
Termination of pumping backfill well casing and hole wall between gravel packing: when be inserted under well casing set elevation after to avoid Sediment deposit Should suitably lengthen and sit bottom water spraying time, when the sediment content that well head overflows remains unchanged can filtrate under termination of pumping, when lower filtrate Between should be carried out immediately after stopping water spray, avoid hole wall from back-silting and hole wall collapse hole.Filter pipe position is preferable using particle psephicity 4# melon seeds piece sand enclose and fill out, enclose and fill out more than position is upwardly at the top of filter pipe from bottom, each well encloses raising degree according to aqueous Depending on the top depth of layer.
Shut-in well: to prevent mud and surface waste water from flowing into well outside pipe, the thick sticky grave of 2.00m is backfilled below earth's surface Hole.
Well-flushing: this construction method does not cause mud off, and well-flushing need to only clear up remaining a small amount of silt in pipe.
Construction method, comprising the following steps:
A, preparation of construction:
(1) the selection of pipe bellows, steel pipe, without sandpipe and pipe of cement;Wherein bellows selects the biggish pipe of tube wall strength Material;
(2) well casing back cover should using toughness big, permeable impermeable husky material, play and do not returned in hydraulic balance and pipe inside and outside well casing The effect of silt;
(3) bellows is needed in pipe rib aperture, opens 2-3 on each circle rib of well casing directly to reduce well casing buoyancy The hole of diameter 5-8mm;
(4) well casing tube wall end the clamping purse seine that 3 layer of 120 mesh Dense mesh screen is wound behind hole and with plastic ties carry out binding plus Gu.
(5) each steel pipe spray head is intended to individually bundle with well casing, and head of the nozzle will be lower than well casing bottom 20-30cm;
(6) spray head tail portion and water pipe at least overlap 15cm and bind three with iron wire, it is ensured that do not disconnect during down tube.
(7) checked high-pressure hydraulic pump pipeline, route whether safety and stability.
(8) measuring well location;According to dewatering well well location floor plan measuring stake position, when the well point of laying is by ground obstacle Or when execution conditions influence, scene is appropriately adjusted.
B, excavate sand discharge pond and well head: sand discharge pond excavation volume should be greater than 5 times of wellhole volume and apart from well head apart from not Easily more than 10m, silt easily blocks sand discharge ditch too far in sand discharge pond.
C, vertical well casing: well casing is placed on the well head dug in advance vertically, and with two-way vertical line, visual angle is at 90 DEG C of angles, observation Pipe shaft outer contour pops up center line in pipe shaft in advance, guarantees two-way deviation within specification tolerance.Because under well casing It inserts by manual control, verticality is difficult to control, so during down tube not using theodolite moment observation pipe shaft verticality Disconnected correction.
D, turn on pump is sprayed water: high-pressure hydraulic pump should be opened after well casing is vertical toward spray head conveying high-pressure water.Original place is answered after spray head water outlet Spray water 30S, so that silty strata is in saturated-water phase as far as possible, according to chiltern difference may spray water less than 30S well casing will voluntarily under It is heavy.
E, well casing underthrust: well casing underthrust should select and appoint 3 workers to be divided into 3 directions and keep pipe shaft verticalities and downward to well casing Apply pressure.It should suitably be downwardly applied to pressure in well casing down process, force well casing with the slow underthrust of speed of sand washing.If under Well casing can be pulled and pushed up and down by the sufficient flush pipe bottom silt layer of sand of high pressure water until well casing bottom by larger resistance during inserting Reach setting elevation.Water pump should run without interruption in well casing pore forming process, verified punching water pump in pore forming process on the spot and stopped More than 30S, silt may back-silt water spray, and causing well tubular wall and hole wall to back-silt closely knit can not continue underthrust.
F, take over: the well depth that deep-well precipitation uses is usually more than 8m, and the well casing length of market routine is 6m, and when well casing is long It is manually difficult to keep pipe shaft verticality when degree is more than 6m, so the mode that adapter tube can be used increases well depth.Well casing adapter tube, which uses, to be held Formula structure is inserted, because bell and spigot joint is more weak, to avoid joint flex from causing borehole inclination bending even can not the quality such as underthrust Problem can be used intensity biggish bar material such as reinforcing bar, angle bar etc. and be attached to the anti-of bell and spigot joint position enhancing well casing connector Curved ability.
G, the gravel packing between termination of pumping backfill well casing and hole wall: when be inserted under well casing set elevation after to avoid silt time Silt, which should be lengthened suitably, sits bottom water spraying time, can filtrate, lower filtrate under termination of pumping when the sediment content that well head overflows remains unchanged Time should carry out immediately after stopping water spray, and hole wall is avoided to back-silt and hole wall collapse hole.Filter pipe position using particle psephicity compared with Good 4# melon seeds piece sand, which encloses, to be filled out, and is enclosed and is filled out more than position is upwardly at the top of filter pipe from bottom, and each well encloses raising degree according to containing Depending on the top depth of water layer.
H, it shunts in a well: to prevent mud and surface waste water from flowing into well outside pipe, 2.00m thickness cohesive soil is backfilled below earth's surface Sealing of hole.
I, well-flushing: this construction method does not cause mud off, and well-flushing need to only clear up remaining a small amount of silt in pipe.
J, lower pump examination is drawn water dewatering well normal work: every mouthful of deep-well is equipped with an immersible pump, at well construction after, dropping Timely tripping in immersible pump in well, installs drainage pipeline and cable, and cable and pipe-line system are in setting it is noted that avoiding taking out It is not excavated machine during water, crane etc. rolls, damaged in collision.Therefore scene will be identified on devices.Draw water with Drainage system;Examination is carried out after the installation is completed to draw water.
Especially, well casing bottom is blocked using the clamping purse seine Dense mesh screen of layer, and sets up three steel pipe spray heads, spray head bottom end is super To 30cm and with well casing against binding, spray head top tail end connects high-pressure hydraulic pump and water inlet pipe for well casing bottom end 20 out.Pipe well pore-forming High pressure water is delivered to spray head by Shi Caiyong high-pressure hydraulic pump, is gone out hole outside by high pressure water flushing loose powder sand and with water flow, is used simultaneously Manually well casing is applied into pressure down, gradually will be inserted to design altitude under well casing.It should be in well casing socket joint when well casing needs to take over The winding of encryption Dense mesh screen and the bending resistance at even tube wall distribution bar reinforcement well casing bell and spigot at mouthful.
Advantages of the present invention and effect:
(1) for this construction method through practical proof, conventional drilling machine carries out deep-well construction in silty strata averagely per hour can be complete At 2m, this engineering method carries out the average 6m achievable per hour of deep-well construction in silty strata.Greatly reduce construction period.
(2) this construction method is without equipment such as drilling machine, slush pumps.It is only necessary to three high-pressure hydraulic pumps, and it is used High-pressure hydraulic pump can put into construction in later period draining, eliminate mechanical disengaging field, lease, reduce a series of expenses such as electricity consumption, hence it is evident that drop The cost of low silty strata deep-well construction.
(3) construction material requested is market common materials, and tubing is alternative more, bellows, steel pipe can be used, without sand Pipe, pipe of cement etc..It is essentially identical with traditional drilling well pore-forming material requested.It is easy purchase, price transparent.
(4) work post number needed for opposite drilling machine pore-forming, easy to operate slightly train general work of this engineering method can be on duty.Work Kind limits small, advantage of lower cost.
(5) this engineering method only needs manual operation, does not need biggish working face and construction material requested volume, lighter in weight people Work can carry, and reduce influence of the place to construction.The construction area being difficult to enter suitable for mechanical equipments such as dell, slopes Domain.Reduce technical management cost.
Detailed description of the invention
Fig. 1 is construction site schematic diagram in the embodiment of the present invention 1.
Fig. 2 is that 1 mesohigh water of the embodiment of the present invention rushes fast pore-creating apparatus structure schematic diagram.
Appended drawing reference includes:
Well casing 1, water inlet pipe 2, spray head 3, well head 4, water source 5, sand discharge pond 6, sand discharge ditch 7, high-pressure hydraulic pump 8, well casing 9, circle rib 10, open-work 11, clamping purse seine 12, axial stiffness strengthened connection bar 13.
Specific embodiment
The principle of the invention is that, using high pressure water flushing brush dust sandy soils pore-forming, well casing is with punching speed underthrust, and pore-forming is under The synchronous workload for carrying out and eliminating the processes such as mud off, mechanical erection and reduce well-flushing of plumber's sequence.
The present invention is larger suitable for infiltration coefficient, and soil property is powder, sandy soil, and rich groundwater, precipitation is deep, and area is big, applies The case where work working face is narrow, short time limit.Especially suitable effect of constructing under this kind of Complicated Geologic Condition of sand bed with saturated dynamic water Fruit is favourable, within well depth is up to 20m.
Construction method of the present invention successively includes construction procedure: preparation of construction, construction lofting excavate sand discharge pond and well head, erect Filtrate, shut-in well between straight well pipe, turn on pump water spray, well casing underthrust-adapter tube, termination of pumping backfill well casing and hole wall, well-flushing, the examination of lower pump are taken out Water;Wherein:
Preparation of construction includes: the selection of pipe, 9 back cover of well casing, tube wall aperture, Dense mesh screen winding, the installation of spray head 3, high pressure water Pump 8 pipeline inspections, measuring well location;Excavate sand discharge pond 6 and well head 4;Vertical well casing 1;Turn on pump water spray;1 underthrust of well casing;Adapter tube;Stop Gravel packing between blowback well filling pipe and hole wall;Shut-in well;Well-flushing;Lower pump tries dewatering well normal work of drawing water.
Excavate sand discharge pond 6 and well head 4: 6 excavation volume of sand discharge pond should be greater than 5 times of wellhole volume and apart from 4 distance of well head It is not easy more than 10m, silt easily blocks sand discharge ditch 7 too far in sand discharge pond 6.
Vertical well casing 1: well casing 1 is placed on the well head 4 dug in advance vertically, and with two-way vertical line, visual angle is at 90 DEG C of angles, observation Pipe shaft outer contour pops up center line in pipe shaft in advance, guarantees two-way deviation within specification tolerance.Because under well casing 1 It inserts by manual control, verticality is difficult to control, so during down tube not using theodolite moment observation pipe shaft verticality Disconnected correction.
Turn on pump water spray: high-pressure hydraulic pump 8 should be opened toward 3 conveying high-pressure water of spray head after well casing 1 is vertical.Spray head 3 answers original after being discharged Spray water 30S on ground, so that silty strata is in saturated-water phase as far as possible, may be sprayed water according to chiltern difference will voluntarily less than 30S well casing 1 Sink.
1 underthrust of well casing: 1 underthrust of well casing should select and appoint 3 workers be divided into 3 directions keep pipe shaft verticalities and to well casing 1 to Lower application pressure.It should be suitably downwardly applied to pressure in 1 down process of well casing, force well casing 1 with the slow underthrust of speed of sand washing.If Well casing 1 can be pulled and pushed up and down by larger resistance in down process allows the sufficient flush pipe bottom silt layer of sand of high pressure water until well casing 1 bottom reaches setting elevation.
Water pump should run without interruption in pore forming process, verified punching water pump stopping water spray in pore forming process on the spot and be more than 30S, silt may back-silt, and lead to 1 wall of well casing and hole wall back-silts closely knit can not continue underthrust.
Adapter tube: the well depth that deep-well precipitation uses is usually more than 8m, and 1 length of well casing of market routine is 6m, and when well casing 1 is long It is manually difficult to keep pipe shaft verticality when degree is more than 6m, so the mode that adapter tube can be used increases well depth.The adapter tube of well casing 1 uses Socket fitting type structure, because bell and spigot joint is more weak, to avoid joint flex from causing borehole inclination bending even can not the matter such as underthrust Amount problem can be used intensity biggish bar material such as reinforcing bar, angle bar etc. and be attached to bell and spigot joint position enhancing 1 connector of well casing Bending resistance.
Gravel packing between termination of pumping backfill well casing and hole wall: when be inserted under well casing 1 set elevation after to avoid silt time Silt, which should be lengthened suitably, sits bottom water spraying time, can filtrate, lower filtrate under termination of pumping when the sediment content that well head overflows remains unchanged Time should carry out immediately after stopping water spray, and hole wall is avoided to back-silt and hole wall collapse hole.1 position of filter pipe using particle psephicity compared with Good 4# melon seeds piece sand, which encloses, to be filled out, and is enclosed and is filled out more than position is upwardly at the top of filter pipe from bottom, and each well encloses raising degree according to containing Depending on the top depth of water layer.
Shut-in well: to prevent mud and surface waste water from flowing into well outside pipe, the thick sticky grave of 2.00m is backfilled below earth's surface Hole.
Well-flushing: this construction method does not cause mud off, and well-flushing need to only clear up remaining a small amount of silt in pipe.
Present invention will be further explained below with reference to the attached drawings and examples.
Embodiment 1: as shown in Fig. 1, as a kind of preferred operation scheme of practice of construction, as shown in Fig. 1, a kind of powder Soil or sand bed high pressure water flushing method pipe well drilling construction method, comprising the following steps:
A, preparation of construction:
(1) bellows, steel pipe can be selected, without sandpipe and pipe of cement in tubing.Wherein bellows should select tube wall strength larger Tubing 1;
(2) 1 back cover of well casing should using toughness big, permeable impermeable husky material, play inside and outside well casing 1 in hydraulic balance and pipe not The effect back-silted;
(3) hole of 2-3 diameter 5-8mm should be opened on each circle rib 10 of well casing to reduce 1 buoyancy of well casing;
(4) the circle rib 10 of well casing 1 winds the clamping purse seine 12 of 3 layer of 120 mesh Dense mesh screen after ending hole and is carried out with plastic ties Binding is reinforced.
(5) each steel pipe spray head 3 is intended to individually bundle with well casing 1, and 3 bottom of spray head will be lower than 1 bottom 20-30cm of well casing;
(6) 3 tail portion of spray head and water pipe at least overlap 15cm and bind three with iron wire, it is ensured that do not disconnect during down tube.
(7) checked 8 pipeline of high-pressure hydraulic pump, route whether safety and stability.
(8) measuring well location;According to dewatering well well location floor plan measuring stake position, when the well point of laying is by ground obstacle Or when execution conditions influence, scene is appropriately adjusted.
B, excavate sand discharge pond 6 and well head 4: 6 excavation volume of sand discharge pond should be greater than 5 times of wellhole volume and apart from well head 4 away from From being not easy more than 10m, silt easily blocks sand discharge ditch 7 too far in sand discharge pond 6.
C, vertical well casing 1: well casing 1 is placed on the well head 4 dug in advance vertically, and with two-way vertical line, visual angle is seen at 90 DEG C of angles Test tube body outer contour pops up center line in pipe shaft in advance, guarantees two-way deviation within specification tolerance.Because of well casing 1 Underthrust is difficult to control by manual control, verticality, so during down tube simultaneously using theodolite moment observation pipe shaft verticality Constantly correction.
D, turn on pump is sprayed water: should open high-pressure hydraulic pump 8 toward 3 conveying high-pressure water of spray head after well casing 1 is vertical.Spray head 3 is answered after being discharged Spray water 30S in original place, and silty strata is made to be in saturated-water phase as far as possible, and may be sprayed water according to chiltern difference will less than 30S well casing 1 Voluntarily sink.
E, 1 underthrust of well casing: 1 underthrust of well casing should select and appoint 3 workers to be divided into 3 directions and keep pipe shaft verticality and to well casing 1 It is downwardly applied to pressure.It should be suitably downwardly applied to pressure in 1 down process of well casing, force well casing 1 with the slow underthrust of speed of sand washing. Allow the sufficient flush pipe bottom silt layer of sand of high pressure water until well if well casing 1 can be pulled and pushed up and down by larger resistance in down process 1 bottom of pipe reaches setting elevation.Water pump should run without interruption in 9 pore forming process of well casing, be verified punching in pore forming process on the spot Water pump stops water spray more than 30S, and silt may back-silt, and causing 1 wall of well casing and hole wall to back-silt closely knit can not continue underthrust.
F, take over: the well depth that deep-well precipitation uses is usually more than 8m, and 1 length of well casing of market routine is 6m, and works as well casing 1 Length is manually difficult to keep pipe shaft verticality when being more than 6m, so the mode that adapter tube can be used increases well depth.The adapter tube of well casing 1 uses Socket fitting type structure, because bell and spigot joint is more weak, to avoid joint flex from causing borehole inclination bending even can not the matter such as underthrust Amount problem can be used intensity biggish bar material such as reinforcing bar, angle bar etc. and be attached to bell and spigot joint position enhancing 1 connector of well casing Bending resistance.
G, termination of pumping backfill well casing 9 and hole wall between gravel packing: when be inserted under well casing 1 set elevation after to avoid silt It back-silts suitably to lengthen and sits bottom water spraying time, it can filtrate, lower filter under termination of pumping when the sediment content that well head overflows remains unchanged The material time should carry out immediately after stopping water spray, and hole wall is avoided to back-silt and hole wall collapse hole.Filter pipe position uses particle psephicity Preferable 4# melon seeds piece sand, which encloses, to be filled out, and is enclosed and is filled out more than position is upwardly at the top of filter pipe from bottom, each well enclose raising degree according to Depending on the top depth in water-bearing layer.
H, it shunts in a well: to prevent mud and surface waste water from flowing into well outside pipe, 2.00m thickness cohesive soil is backfilled below earth's surface Sealing of hole.
I, well-flushing: this construction method does not cause mud off, and well-flushing need to only clear up remaining a small amount of silt in pipe.
J, lower pump examination is drawn water dewatering well normal work: every mouthful of deep-well is equipped with an immersible pump, at well construction after, dropping Timely tripping in immersible pump in well, installs drainage pipeline and cable, and cable and pipe-line system are in setting it is noted that avoiding taking out It is not excavated machine during water, crane etc. rolls, damaged in collision.Therefore scene will be identified on devices.Draw water with Drainage system;Examination is carried out after the installation is completed to draw water.
In aforementioned, one or many adapter tubes are carried out according to well depth in adapter tube step.
In the embodiment of the present invention, as shown in Fig. 2,1 bottom of well casing, and frame are blocked using 4 layers of clamping 12 Dense mesh screen of purse seine If three steel pipe spray heads, 3 bottom end of spray head is beyond 1 bottom end 20 of well casing to 30cm and with well casing 1 against binding, 3 top tail end of spray head Connect high-pressure hydraulic pump 8 and water inlet pipe 2.High pressure water is delivered to by spray head 3 using high-pressure hydraulic pump 8 when pipe well pore-forming, passes through high pressure water It breaks up silty sand and is gone out outside hole with water flow, while using well casing 1 is manually applied pressure down, will gradually be inserted to and setting under well casing 1 Count elevation.Dense mesh screen should be encrypted at well casing bell and spigot when well casing 1 needs to take over to wind and add in even tube wall distribution bar Bending resistance at 1 bell and spigot of strong well casing.Entire pore forming process should keep 8 continuous water spray of high-pressure hydraulic pump, set until being inserted under well casing 1 Meter elevation and sit bottom spray water 1 minute after can termination of pumping and immediately filling filtrate prevent hole wall from back-silting.
Above embodiments are only used for explanation and illustration of the invention and explanation, understand to help to reading of the invention, but not It limits the invention, those skilled in the art make without creative tribute the present embodiment after reading this specification The modification offered, as long as within the scope of the present invention, belonging to the range of protection of the present invention by Patent Law.

Claims (3)

1. silt or sand bed pipe well high pressure water flushing fast pore-creating construction method, which is characterized in that use high pressure water flushing brush dust sand Layer pore-forming, with punching speed underthrust, pore-forming is synchronous with down tube process to carry out well casing (1);Construction method successively includes construction step Rapid: preparation of construction, construction lofting excavate sand discharge pond and well head, vertical well casing, turn on pump water spray, well casing underthrust-adapter tube, termination of pumping time Filtrate, shut-in well, well-flushing, the examination of lower pump between well filling pipe and hole wall draw water;Wherein:
Preparation of construction includes: the selection of pipe, well casing (9) back cover, Dense mesh screen winding, spray head (3) installation, high-pressure hydraulic pump (8) pipeline It checks, measuring well location;Excavate sand discharge pond (6) and well head (4);Vertical well casing (1);Turn on pump water spray;Well casing (1) underthrust;Adapter tube;Stop Gravel packing between blowback well filling pipe and hole wall;Shut-in well;Well-flushing;Lower pump tries dewatering well normal work of drawing water;
Excavate sand discharge pond (6) and well head (4): sand discharge pond (6) excavation volume should be greater than 5 times of wellhole volume and apart from well head (4) Distance is not easy more than 10m, and sand discharge pond (6) silt easily blocks sand discharge ditch (7) too far;
Vertical well casing (1): well casing (1) is placed on the well head (4) dug in advance vertically, and with two-way vertical line, visual angle is seen at 90 DEG C of angles Test tube body outer contour pops up center line in pipe shaft in advance, guarantees two-way deviation within specification tolerance;Because of well casing (1) underthrust is difficult to control by manual control, verticality, so observing pipe shaft verticality using the theodolite moment during down tube And it constantly rectifies a deviation;
Turn on pump water spray: high-pressure hydraulic pump (8) should be opened after well casing (1) is vertical toward spray head (3) conveying high-pressure water;After spray head (3) water outlet Original place water spray 30S is answered, so that silty strata is in saturated-water phase as far as possible, may be sprayed water according to chiltern difference less than 30S well casing (1) To voluntarily it sink;
Well casing (1) underthrust: well casing (1) underthrust should select and appoint 3 workers to be divided into 3 directions and keep pipe shaft verticality and to well casing (1) It is downwardly applied to pressure;It should be suitably downwardly applied to pressure in well casing (1) down process, force well casing (1) slow with the speed of sand washing Underthrust;If can be pulled and pushed well casing (1) up and down by larger resistance in down process allows the sufficient flush pipe bottom silt sand of high pressure water Layer is until well casing (1) bottom reaches setting elevation;
Water pump should run without interruption in pore forming process;
Adapter tube: the well depth that deep-well precipitation uses is usually more than 8m, and well casing (1) length of market routine is 1m to 6m, and works as well casing (1) it is manually difficult to keep pipe shaft verticality when length is more than 6m, so the mode that adapter tube can be used increases well depth;Well casing (1) connects Pipe uses socket fitting type structure, is attached to bell and spigot joint position enhancing well casing using the biggish bar material of intensity such as reinforcing bar, angle bar (1) bending resistance of connector;
Termination of pumping backfill well casing and hole wall between gravel packing: when be inserted under well casing (1) set elevation after to avoid Sediment deposit Should suitably lengthen and sit bottom water spraying time, when the sediment content that well head overflows remains unchanged can filtrate under termination of pumping, when lower filtrate Between should be carried out immediately after stopping water spray, avoid hole wall from back-silting and hole wall collapse hole;Filter pipe position is preferable using particle psephicity 4# melon seeds piece sand enclose and fill out, enclose and fill out more than position is upwardly at the top of filter pipe from bottom, each well encloses raising degree according to aqueous Depending on the top depth of layer;
Shut-in well: to prevent mud and surface waste water from flowing into well outside pipe, 2.00m thickness cohesive soil sealing of hole is backfilled below earth's surface;
Well-flushing: remaining a small amount of silt in pipe need to only be cleared up.
2. silt as described in claim 1 or sand bed pipe well high pressure water flushing fast pore-creating construction method, which is characterized in that construction Method, comprising the following steps:
A, preparation of construction:
(1) the selection of pipe bellows, steel pipe, without sandpipe and pipe of cement;Wherein bellows should select the biggish tubing of tube wall strength;
(2) well casing (1) back cover should using toughness big, permeable impermeable husky material, play inside and outside well casing (1) in hydraulic balance and pipe not The effect back-silted;
(3) for bellows, the hole of 2-3 diameter 5-8mm is opened on each circle rib (10) of well casing;
(4) the circle rib (10) of well casing (1) end the clamping purse seine (12) that 3 layer of 120 mesh Dense mesh screen is wound behind hole and with plastic ties into Row binding is reinforced;
(5) each steel pipe spray head (3) is intended to individually bundle with well casing (1), and spray head (3) bottom will be lower than well casing (1) bottom 20- 30cm;
(6) spray head (3) tail portion and water pipe at least overlap 15cm and bind three with iron wire, it is ensured that do not disconnect during down tube;
(7) checked high-pressure hydraulic pump (8) pipeline, route whether safety and stability;
(8) measuring well location;According to dewatering well well location floor plan measuring stake position, when the well point of laying by ground obstacle or is applied When work condition influences, scene is appropriately adjusted;
B, excavate sand discharge pond (6) and well head (4): sand discharge pond (6) excavation volume should be greater than 5 times of wellhole volume and apart from well head (4) distance is not easy more than 10m, and sand discharge pond (6) silt easily blocks sand discharge ditch (7) too far;
C, vertical well casing (1): well casing (1) is placed on the well head (4) that has dug in advance vertically, with two-way vertical line, visual angle at 90 DEG C of angles, It observes pipe shaft outer contour or pops up center line in pipe shaft in advance, guarantee two-way deviation within specification tolerance;Under Pipe shaft verticality is observed using the theodolite moment during pipe and is constantly rectified a deviation;
D, turn on pump is sprayed water: high-pressure hydraulic pump (8) should be opened after well casing (1) is vertical toward spray head (3) conveying high-pressure water;Spray head (3) water outlet After answer original place spray water 30S, so that silty strata is in saturated-water phase as far as possible, may be sprayed water according to chiltern difference less than 30S well casing (1) will voluntarily sink;
E, well casing (1) underthrust: well casing (1) underthrust should select and appoint 3 workers to be divided into 3 directions and keep pipe shaft verticality and to well casing (1) it is downwardly applied to pressure;It should be suitably downwardly applied to pressure in well casing (1) down process, force well casing (1) slow with the speed of sand washing Slow underthrust;If can be pulled and pushed well casing (1) up and down by larger resistance in down process allows the sufficient flush pipe bottom silt of high pressure water Layer of sand is until well casing (1) bottom reaches setting elevation;Water pump should run without interruption in well casing (9) pore forming process, be verified on the spot Punching water pump stops water spray more than 30S in pore forming process, and silt may back-silt, and well casing (1) wall and hole wall is caused to back-silt closely knit nothing Method continues underthrust;
F, take over: the well depth that deep-well precipitation uses is usually more than 8m, and well casing (1) length of market routine is 6m, and works as well casing (1) Length is manually difficult to keep pipe shaft verticality when being more than 6m, so the mode that adapter tube can be used increases well depth;Well casing (1) adapter tube is adopted Use socket fitting type structure;
G, it the gravel packing between termination of pumping backfill well casing (9) and hole wall: suitably lengthens and sits after being inserted to setting elevation under well casing (1) Bottom water spraying time, when the sediment content that well head overflows remains unchanged can under termination of pumping filtrate, lower filtrate time should stop spraying It is carried out immediately after water, hole wall is avoided to back-silt and hole wall collapse hole;Filter pipe position uses the preferable 4# melon seeds piece sand of particle psephicity It encloses and fills out, enclose and fill out more than position is upwardly at the top of filter pipe from bottom, each well encloses raising degree according to the top depth in water-bearing layer Depending on;
H, it shunts in a well: backfilling 2.00m thickness cohesive soil sealing of hole below earth's surface;
I, well-flushing: this construction method does not cause mud off, and well-flushing need to only clear up remaining a small amount of silt in pipe;
J, lower pump examination is drawn water dewatering well normal work: every mouthful of deep-well is equipped with an immersible pump, at well construction after, in dewatering well Interior timely tripping in immersible pump, installs drainage pipeline and cable, and cable and pipe-line system are in setting it is noted that avoiding drawing water Machine is not excavated in journey, crane etc. rolls, damaged in collision;Therefore scene will be identified on devices;It draws water and drains System;Examination is carried out after the installation is completed to draw water.
3. silt as described in claim 1 or sand bed pipe well high pressure water flushing fast pore-creating construction method, which is characterized in that use 4 layers of clamping purse seine (12) Dense mesh screen block well casing (1) bottom, and set up at least three steel pipe spray heads (3), and spray head (3) bottom end is super Out well casing (1) bottom end 20 to 30cm and with well casing (1) against binding, spray head (3) top tail end connect high-pressure hydraulic pump (8) and intake It manages (2);High pressure water is delivered to spray head (3) using high-pressure hydraulic pump (8) when pipe well pore-forming, by high pressure water flushing loose powder sand and with water Stream is gone out outside hole, while using well casing (1) is manually applied pressure down, gradually will be inserted to design altitude under well casing (1);Work as well Pipe (1) should encrypt Dense mesh screen winding at well casing bell and spigot and reinforce well casing (1) in even tube wall distribution bar when needing to take over Bending resistance at bell and spigot.
CN201910005842.9A 2019-01-03 2019-01-03 Silt or sand bed pipe well high pressure water flushing fast pore-creating construction method Pending CN109441355A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910005842.9A CN109441355A (en) 2019-01-03 2019-01-03 Silt or sand bed pipe well high pressure water flushing fast pore-creating construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910005842.9A CN109441355A (en) 2019-01-03 2019-01-03 Silt or sand bed pipe well high pressure water flushing fast pore-creating construction method

Publications (1)

Publication Number Publication Date
CN109441355A true CN109441355A (en) 2019-03-08

Family

ID=65542293

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910005842.9A Pending CN109441355A (en) 2019-01-03 2019-01-03 Silt or sand bed pipe well high pressure water flushing fast pore-creating construction method

Country Status (1)

Country Link
CN (1) CN109441355A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110318662A (en) * 2019-07-10 2019-10-11 台州长天能源技术有限公司 Gravity head beats U-shaped well method device product
CN111852327A (en) * 2020-08-14 2020-10-30 安徽铜冠(庐江)矿业有限公司 Water outlet and control method for filling and drilling construction
CN113187381A (en) * 2021-03-19 2021-07-30 中基发展建设工程有限责任公司 High-water-length spiral well forming construction process

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003147758A (en) * 2001-08-27 2003-05-21 Kazuhiko Sakamoto Underground water level lowering device
CN102383731A (en) * 2011-09-15 2012-03-21 中冶交通工程技术有限公司 High-pressure water jet flow pore-forming tool and device and poured pile construction method
CN104060636A (en) * 2014-05-22 2014-09-24 中国建筑第四工程局有限公司 Depressurization and anti-floating method and device thereof for foundation construction in high water level region building
CN205036295U (en) * 2015-10-10 2016-02-17 中国石油集团川庆钻探工程有限公司 Full well section self-suction type reverse circulation gas drilling system
CN105544573A (en) * 2015-12-29 2016-05-04 中国水利水电第十三工程局有限公司 Water pressure jetting type well completion construction method of dewatering tube well
CN106759409A (en) * 2016-11-07 2017-05-31 中铁三局集团广东建设工程有限公司 A kind of water-rich sand layer regional precipitation well construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003147758A (en) * 2001-08-27 2003-05-21 Kazuhiko Sakamoto Underground water level lowering device
CN102383731A (en) * 2011-09-15 2012-03-21 中冶交通工程技术有限公司 High-pressure water jet flow pore-forming tool and device and poured pile construction method
CN104060636A (en) * 2014-05-22 2014-09-24 中国建筑第四工程局有限公司 Depressurization and anti-floating method and device thereof for foundation construction in high water level region building
CN205036295U (en) * 2015-10-10 2016-02-17 中国石油集团川庆钻探工程有限公司 Full well section self-suction type reverse circulation gas drilling system
CN105544573A (en) * 2015-12-29 2016-05-04 中国水利水电第十三工程局有限公司 Water pressure jetting type well completion construction method of dewatering tube well
CN106759409A (en) * 2016-11-07 2017-05-31 中铁三局集团广东建设工程有限公司 A kind of water-rich sand layer regional precipitation well construction method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘辉;蔡金博;范新建;张莹;: "高水位沙土地基全联合角钢构架基础形式研究", 吉林电力, no. 02, pages 5 - 7 *
卢相军;王晓磊;解希华;: "丰水季节深基坑"管井+轻型井点"降水施工", 武汉大学学报(工学版), no. 1 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110318662A (en) * 2019-07-10 2019-10-11 台州长天能源技术有限公司 Gravity head beats U-shaped well method device product
CN110318662B (en) * 2019-07-10 2023-12-19 台州长天能源技术有限公司 Gravity head U-shaped well drilling method and equipment product
CN111852327A (en) * 2020-08-14 2020-10-30 安徽铜冠(庐江)矿业有限公司 Water outlet and control method for filling and drilling construction
CN113187381A (en) * 2021-03-19 2021-07-30 中基发展建设工程有限责任公司 High-water-length spiral well forming construction process
CN113187381B (en) * 2021-03-19 2023-11-21 中基发展建设工程有限责任公司 High-water-level long-spiral well formation construction process

Similar Documents

Publication Publication Date Title
CN100480475C (en) Controllable one-well lamina precipitation construction method
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN101962949B (en) Long spiral double-pipe high-pressure stir-jet grouting pile construction method and device
CN102322058B (en) Construction process and equipment for downhole impacting high-pressure jet grouting pile
CN100464055C (en) Construction method of shallow buried underground excavating tunnel super large section using PBA method
CN112502777B (en) Method for treating tunnel inrush roof collapse and door closing
CN106368224A (en) Graded slope reinforcing reverse construction method for high slope under complicated geology
CN102296630A (en) Construction method of long-screw high-pressure mix jetting cement diaphragm wall
CN109736338A (en) A kind of hydraulic engineering foundation pit pipe well combination light well point Yield rainfall relation method
CN107044128A (en) Supporting and dewatering construction method in Deep Excavation
CN109441355A (en) Silt or sand bed pipe well high pressure water flushing fast pore-creating construction method
CN114233385B (en) Treatment method for mud-bursting water of inclined shaft
CN102383412A (en) Construction method by adopting dewatering and water recharging to control sedimentation surrounding deep foundation pit
CN108316339A (en) A kind of construction method of water penetration geology large size arch bridge base
CN110318410A (en) A kind of deep basal pit chance artesian water is prominent to gush decompression drought stress construction method
CN102561404A (en) Steel reinforced concrete column type joint and construction method of underground diaphragm wall using same
CN108951649B (en) Foundation pit supporting structure
CN111810198A (en) Tunnel earth surface directional large-caliber deep hole grouting device and grouting method
CN104532853A (en) Deep foundation pit supporting method and system characterized by steel reinforced cement-soil piles, bolts easy to detach and automatic monitoring and early warning
CN111852515A (en) Tunnel stratum pre-reinforcement comprehensive grouting method
CN110424430A (en) Deep basal pit powder land floor Deep Pumped Wells construction method and its application
CN105133581A (en) Three-in-one construction method for uplift pile, lattice column and precipitation well in supporting structure
CN108867673A (en) A kind of underwater prevention method in the foundation pit based on the curtain that draws water
CN102995647B (en) Underground water control method used for grouting and seepage insulation of pile hole
CN110685292A (en) Foundation pit drainage system and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190308